Professional Documents
Culture Documents
Application of Last Planner System To Improve Labour Productivity at Construction Site
Application of Last Planner System To Improve Labour Productivity at Construction Site
Application of Last Planner System To Improve Labour Productivity at Construction Site
2
INTRODUCTION
Lean: The core idea is to maximize customer value while minimizing waste.
Simply lean means creating more value for customers within limited resources.
Last planner system: Is the collaborative, commitment based system that integrates pull
planning , make ready plan, look-ahead plan with constraint analysis, weekly work planning
based upon reliable promises, analysis of Percentage of plan completed and reasons for variance.
AIM –
• To study about Application of Lean Construction tool ( L.P.S ) to improve labor productivity .
OBJECTIVE –
• By identify Importance of Lean Construction.
4
[3]
5
LAST PLANNER SYSTEM
A non-technical person can also use L.P.S at site and users such as owners, client or
construction company can use L.P.S to achieve better performance in design and
construction through increased schedule predictability.
(Fig. Ref. 1)
Step1. Collaborative Programming:
. The goal of this process is that all the main participants and specialist contractors are engaged right
from the start in developing and signing up to the master scheduling and the scheduling for each phase.
. Prepare each team member for action together from starting of project.
. Sorts out sequencing as well as issues or difficulty to make smooth work flow.
Each last planner leader proposes a construction program for his team In P.E.P meeting and they
identifies if any inter-dependencies between their proposals like resources, equipment and reduce
the burden of over-committing by distributing each task to the team member.
. Learning together is all about improving project, planning and production process.
. At the end of the task executed at site by measurement we can get to know the reason for variance
and they try to reduce in next activity and this is called continual improvement.
• PLANNING ERROR
• TECHNOLOGY UNAWARENESS
• WASTAGE
• PROJECT DELAY
• Quality
12
LITERATURE SURVEY
Sr. No Title and Publication Author Description
13
Sr. No Title and Publication Author Description
14
Tools / Principle of lean construction
3. A3 Process Design
6. Continues Improvement
EMPLOYEE NAME WORK MON TUES WED THUR FRI SAT SUN HOURS
ASSIGNED 3/4/17 4/4/17 5/4/17 6/4/17 7/4/17 8/4/17 9/4/17
(Fig. Ref. 1)
WORK DONE
• Apply Last Planner System ( LPS ) at Site.
20
Site Name – Suvarana Rekha
Location – Prabhat Road
Type of Building – Commercial (7 Floor)
Project Duration – Feb 2012 to Dec 2016
Contractors / Consultancy – Project Management Consultancy.
Execution Consultancy.
Plumbing / Electrical / Water Proofing Consultancy.
Design ( Architecture / RCC / P.T Drawing )
21
22
Productivity of labour after applying L.P.S
Calculation
(Data. Ref. 3)
23
1. For plastering work
Per day work done by the labour = 10 m2 (quantity of material)
(8 hour)
Area covered = 100 ft2
No. of person = 1 skilled labour + 1 unskilled labour + 1 helper
Cost for 1 day = 500 + 350 + 300
= 1150
a. Labour productivity = 100 / 1150 = 0.086 ft2/Rs.
After applying L.P.S = 110 /1150 = 0.095 ft2 / Rs.
a. Labour productivity = 100/ 8 = 12.5 work/hr
After applying L.P.S = 110/8 = 13.75 work/hr
24
2. Brick work in foundation and Plinth level with cement mortar
25
For For
plasteri Brick
ng work
work
About Before After
About Before After L.P.S L.P.S
L.P.S L.P.S
By Labour 0.04 0.043
By Labour 0.086 0.095 equati product m3/Rs. m3/Rs
equatio productivity ft2/Rs. ft2/Rs on A. ivity
n A. By Labour 5.62 6.25
By Labour 12.5 13.75 equati product m3/hr. m3/hr
equatio productivity ft2/hr. ft2/hr on B. ivity
n B. By Labour 25.6 23
By Labour 11.5 10.45 equati product Rs./m3 Rs./m3
equatio productivity Rs./ft2 Rs./ft on C. ivity
n C. 2
By Perform 0.9 1
By Performanc 0.9 1 equati ance
equatio e factor on D. factor
n D. 26
Chart Title
14
12
10
0
Labour Productivity for Performance Factor Labour Productivity for Performance Factor
Plastering Work Brick Work
REDUCE WASTE
BETTER
MONITRING
LEAN CONSTRUCTION
+ LAST PLANNER
SYSTEM
OPTIMUM USE
OF RESOURCES
(Fig. Ref. 2)
Barriers in Lean Construction
• Managerial – Lack of management
• Medium and short construction sectors are not interested to perform L.P.S at their site.
• Last planner system do not feasible to apply each activity of construction site.
29
Traditional Construction Management Lean Construction Management
Customer is not involving in planning stage Customer, Client, Owner, Contractor, Project Manager everyone
involve from starting.
This is Push Techniques focus to increase productivity of This is Pull Techniques, main focus is on the proper flow of
each activity even if this may be causes of rework, activities with reduce error or rework and consideration of
reduce customer satisfaction. customer’s requirement and satisfaction.
It does not consider adjustment because of the isolated This system’s capacity absorb the variation, because of feedback
environment and only Project Manager Work as a boss, loop, learning and continual improvement and rapid system
so there are no suggestion or ideas come from the response.
participants.
Traditional construction management does not pay And this approach tries to make continuous improvements.
. It does not consider transparency in between the It tries to increase transparency between the customers,
customers, managers and labors. managers and labors.
(Fig. Ref. 2)
Project Objectives
(Fig. Ref. 1)
Project Objectives
People
Last Planner Engagement &
Can Will
Process Continuous
Improvement
(Fig. Ref. 1)
Result
By applying lean construction tool (L.P.S) at site, the labour productivity observed by 10 to 20% as
compared to previous. Exp. For plastering it improves 12.5 ft2/hr to 13.75 ft2/hr and performance factor
0.9 to 1. Same as for brick work and other construction work. So it is practically beneficial for the
optimizing resources.
Limitations
1. Participants: Large construction companies are ready to implement after giving training or small workshop, but the
small and medium companies are not much interested to use it.
1. No – one – size – fit – to – all: All firms are not fit in the guidelines or the way of Toyota production system, so all
firms operate their works differently that’s why all firms do not accept easily.
1. Takes time: it is not gives result in short term basis, implementation and then result takes time, overall it requires
time, efforts, engagement of employees to make planning and get together within a week or month.
33
References
1. Mossman Alan, 2013 paper “Last Planner 5+1 crucial and collaborative conversations for predictable design and
construction delivery.”
2. Amit Shankar Murje, 2014, why Iean construction techniques is better than the traditional project management
approach.
3. Thomas & Maloney has been published in ASCE journal paper “Modelling Construction Labor Productivity”
4. Howell, Gregory A. (1999). "What is Lean Construction" (pdf). Proceedings IGLC-7. Lean Construction Institute. pp.
1–10. Retrieved 31 March 2013.
5. Ballard, Glenn (2000). Last Planner™ System of Production Control (pdf) (Ph.D.). UK: University of Birmingham.
Retrieved 29 March 2013.
7. 2005 Mr. O.Salem and J. Salomom, implemented and assessed lean at construction site of Honda U.K
34
THANK You
35