ID Task Name Duration Start Finish 26 Oct Predecessors

'20 2 Nov '20 9 Nov '20 16 Nov '20


S M T W T F S S M T W T F S S M T W T F S S
1 TLP Safety Induction 1.5 hrs Tue 3/11/20 Tue 3/11/20
2 Site Visit 1 day Wed 4/11/20 Wed 4/11/20 1
3 Modification of Pig 12 days Thu 5/11/20 Fri 20/11/20 2
Launcher 2 Unit
4 Prepare Material 1 day Thu 5/11/20 Thu 5/11/20 2
5 Cut Existing Launcher 2 days Fri 6/11/20 Mon 9/11/20 4
6 Fitup Pig Launcher 1 day Tue 10/11/20 Tue 10/11/20 5
7 Weld Pig Launcher 2 days Wed 11/11/20 Thu 12/11/20 6
8 Hydrostatic Testing 1 day Fri 13/11/20 Fri 13/11/20 7
9 Radigraphy Testing 1 day Mon 16/11/20 Mon 16/11/20 8
10 Blasting & Painting 4 days Tue 17/11/20 Fri 20/11/20 9

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Launcher Modification
Summary Manual Summary Rollup Progress
Date: Mon 2/11/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only