The document outlines a project plan to modify a pig launcher unit over 12 days from November 5th to November 20th. It involves 10 main tasks: a site visit, preparing materials, cutting the existing launcher, fitting up the new pig launcher, welding it, hydrostatic and radiography testing, and finally blasting and painting it. Each task has a scheduled duration and relies on the completion of preceding tasks in the project plan.
The document outlines a project plan to modify a pig launcher unit over 12 days from November 5th to November 20th. It involves 10 main tasks: a site visit, preparing materials, cutting the existing launcher, fitting up the new pig launcher, welding it, hydrostatic and radiography testing, and finally blasting and painting it. Each task has a scheduled duration and relies on the completion of preceding tasks in the project plan.
The document outlines a project plan to modify a pig launcher unit over 12 days from November 5th to November 20th. It involves 10 main tasks: a site visit, preparing materials, cutting the existing launcher, fitting up the new pig launcher, welding it, hydrostatic and radiography testing, and finally blasting and painting it. Each task has a scheduled duration and relies on the completion of preceding tasks in the project plan.
ID Task Name Duration Start Finish 26 Oct Predecessors
'20 2 Nov '20 9 Nov '20 16 Nov '20
S M T W T F S S M T W T F S S M T W T F S S 1 TLP Safety Induction 1.5 hrs Tue 3/11/20 Tue 3/11/20 2 Site Visit 1 day Wed 4/11/20 Wed 4/11/20 1 3 Modification of Pig 12 days Thu 5/11/20 Fri 20/11/20 2 Launcher 2 Unit 4 Prepare Material 1 day Thu 5/11/20 Thu 5/11/20 2 5 Cut Existing Launcher 2 days Fri 6/11/20 Mon 9/11/20 4 6 Fitup Pig Launcher 1 day Tue 10/11/20 Tue 10/11/20 5 7 Weld Pig Launcher 2 days Wed 11/11/20 Thu 12/11/20 6 8 Hydrostatic Testing 1 day Fri 13/11/20 Fri 13/11/20 7 9 Radigraphy Testing 1 day Mon 16/11/20 Mon 16/11/20 8 10 Blasting & Painting 4 days Tue 17/11/20 Fri 20/11/20 9