REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

Start KP : KP 5+954.64 to KP 5+765.44

PIPE IDENTITY TOTAL LENGTH KP NO. BEND


REMARK
ITEM SIZE PIPE NO. ACTUAL LOC. VERT' HORIZ.
KP 5+954.64
21421
1 28'' 11.96 KP 5+564.74 SB 9.5° N/A
G04518
KP.05
20881
2 28'' 11.11 KP 5+588.66 OB 11° N/A
G04603
KP.05
21337
3 28'' 11.96 KP 5+552.78 OB 9.5° N/A
G04518
KP.05
21571
4 28'' 11.96 N/A N/A N/A
G04442
KP.05
20397
5 28'' 11.96 N/A N/A N/A
G04516
KP.05
20106
6 28'' 11.96 N/A N/A N/A
G04516
KP.05
21518
7 28'' 11.95 N/A N/A N/A
G04440
KP.05
21174
8 28'' 11.96 N/A N/A N/A
G04515
KP.05
21375
9 28'' 11.96 N/A N/A N/A
G04438
KP.05
20688
10 28'' 11.90 N/A N/A N/A
G04603
KP.05
21268
11 28'' 11.96 N/A N/A N/A
G04603
KP.05
20664
12 28'' 11.58 N/A N/A N/A
G04603
KP.05
20839
13 28'' 11.96 N/A N/A N/A
G04603
KP.05
20520
14 28'' G04515 11.96 N/A N/A N/A
KP.05
21638
15 28'' 11.10 N/A N/A N/A
G04442
KP.05
20039
16 28'' 11.96 N/A N/A N/A
G04441
KP.05
TOTAL 189.2 N/A N/A N/A

CONTRACTOR'S INSPECTOR CLIENT'S INSPECTOR

NAME : NAME :

DATE : DATE :

LEGEND : OB : Over Bend, SAG : Sag Bend, SBL : Side Bend, SBR : Side Right, C : Combination, Vert' : Vertical, Horiz : Horinzontal
Loc. : Location

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

Start KP : KP 5+765.44 to KP 5+575.01

PIPE IDENTITY TOTAL LENGTH KP NO. BEND


REMARK
ITEM SIZE PIPE NO. ACTUAL LOC. VERT' HORIZ.
KP.05
21715
17 28'' 11.58 N/A N/A N/A
G04439
KP.05
21480
18 28'' 11.96 N/A N/A N/A
G04440
KP.05
20538
19 28'' 11.46 N/A N/A N/A
G04516
KP.05
20674
20 28'' 11.96 N/A N/A N/A
G04441
KP.05
20452
21 28'' 11.96 N/A N/A N/A
G04442
KP.05
21070
22 28'' 11.96 N/A N/A N/A
G04440
KP.05
21366
23 28'' 11.95 N/A N/A N/A
G04608
KP.05
20668
24 28'' 11.96 N/A N/A N/A
G04603
KP.05
20646
25 28'' 11.96 N/A N/A N/A
G04608
KP.05
21202
26 28'' 11.96 N/A N/A N/A
G04441
KP.05
21120
27 28'' 11.96 N/A N/A N/A
G04518
KP.05
20896
28 28'' 11.96 N/A N/A N/A
G04439
KP.05
20898
29 28'' 11.96 N/A N/A N/A
G04605
KP.05
20915
30 28'' G04438 11.96 N/A N/A N/A
KP.05
21154
31 28'' 11.96 N/A N/A N/A
G04441
KP.05
21241
32 28'' 11.92 N/A N/A N/A
G04441
KP.05
TOTAL 190.43

CONTRACTOR'S INSPECTOR CLIENT'S INSPECTOR

NAME : NAME :

DATE : DATE :

LEGEND : OB : Over Bend, SAG : Sag Bend, SBL : Side Bend, SBR : Side Right, C : Combination, Vert' : Vertical, Horiz : Horinzontal
Loc. : Location

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

Start KP : KP 5+575.01 to KP 5+393.26

PIPE IDENTITY TOTAL LENGTH KP NO. BEND


REMARK
ITEM SIZE PIPE NO. ACTUAL LOC. VERT' HORIZ.
KP.05
21074
33 28'' 11.96 N/A N/A N/A
G04438
KP.05
21090
34 28'' 11.10 N/A N/A N/A
G04438
KP.05
21004
35 28'' 11.96 N/A N/A N/A
G04438
KP.05
21379
36 28'' 11.96 N/A N/A N/A
G04440
KP.05
20591
37 28'' 11.96 N/A N/A N/A
G04439
KP.05
20738
38 28'' 11.58 N/A N/A N/A
G04608
KP.05
20870
39 28'' 11.96 N/A N/A N/A
G04439
KP.05
20302
40 28'' 11.79 N/A N/A N/A
G04441
KP.05
21252
41 28'' 11.95 N/A N/A N/A
G04442
KP.05
20312
42 28'' 11.96 N/A N/A N/A
G04519
KP.05
20450
43 28'' 11.96 KP 5+018.56 N/A RB 16°
G04441
KP.05
21081
44 28'' 11.96 KP 5+054.43 CMB 16°
G04441
KP.05
21061
45 28'' 11.91 KP 5+030.51 OB 9° N/A
G04439
KP.05
21329
46 28'' G04605 11.96 N/A N/A N/A
KP.05
10028
47 28'' 3.82 N/A HOT BEND 30°
G04521
KP.05
20622
48 28'' 11.96 N/A N/A N/A
G04605
KP.05
TOTAL 181.75 N/A N/A N/A

CONTRACTOR'S INSPECTOR CLIENT'S INSPECTOR

NAME : NAME :

DATE : DATE :

LEGEND : OB : Over Bend, SAG : Sag Bend, SBL : Side Bend, SBR : Side Right, C : Combination, Vert' : Vertical, Horiz : Horinzontal
Loc. : Location

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

Start KP : KP 5+393.26 to KP 5+202.53

PIPE IDENTITY TOTAL LENGTH KP NO. BEND


REMARK
ITEM SIZE PIPE NO. ACTUAL LOC. VERT' HORIZ.
KP.05
21253
49 28'' 11.57 N/A N/A N/A
G04441
KP.05
20841
50 28'' 11.96 N/A N/A N/A
G04519
KP.05
20545
51 28'' 11.96 N/A N/A N/A
G04608
KP.05
20540
52 28'' 11.96 N/A N/A N/A
G04440
KP.05
20504
53 28'' 11.96 N/A N/A N/A
G04440
KP.05
20166
54 28'' 11.96 N/A N/A N/A
G04516
KP.05
20756
55 28'' 11.96 N/A N/A N/A
G04441
KP.05
20431
56 28'' 11.96 N/A N/A N/A
G04605
KP.05
21486
57 28'' 11.96 N/A N/A N/A
G04440
KP.05
20749
58 28'' 11.96 N/A N/A N/A
G04605
KP.05
21328
59 28'' 11.96 N/A N/A N/A
G04605
KP.05
21354
60 28'' 11.72 N/A N/A N/A
G04518
KP.05
20001
61 28'' 11.96 N/A N/A N/A
G04441
KP.05
21471
62 28'' G04518 11.96 N/A N/A N/A
KP.05
20350
63 28'' 11.96 N/A N/A N/A
G04605
KP.05
20624
64 28'' 11.96 N/A N/A N/A
G04605
KP.05
TOTAL 190.73

CONTRACTOR'S INSPECTOR CLIENT'S INSPECTOR

NAME : NAME :

DATE : DATE :

LEGEND : OB : Over Bend, SAG : Sag Bend, SBL : Side Bend, SBR : Side Right, C : Combination, Vert' : Vertical, Horiz : Horinzontal
Loc. : Location

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

Start KP : KP 5+202.53 to KP 5+012.04

PIPE IDENTITY TOTAL LENGTH KP NO. BEND


REMARK
ITEM SIZE PIPE NO. ACTUAL LOC. VERT' HORIZ.
KP.05
20903
65 28'' 11.96 N/A N/A N/A
G04603
KP.05
20460
66 28'' 11.96 N/A N/A N/A
G04442
KP.05
21070
67 28'' 11.96 N/A N/A N/A
G04438
KP.05
20943
686 28'' 11.95 N/A N/A N/A
G04438
KP.05
21006
69 28'' 11.10 N/A N/A N/A
G04519
KP.05
20784
70 28'' 11.96 N/A N/A N/A
G04605
KP.05
20144
71 28'' 11.96 N/A N/A N/A
G04516
KP.05
20629
72 28'' 11.96 N/A N/A N/A
G04438
KP.05
20783
73 28'' 11.96 N/A N/A N/A
G04608
KP.05
20713
74 28'' 11.96 N/A N/A N/A
G04519
KP.05
20842
75 28'' 11.96 KP 4+635.14 SB 16° N/A
G04516
KP.05
21242
76 28'' 11.96 KP 4+671.02 OB 12° N/A
G04516
KP.05
20831
77 28'' 11.96 KP 4+647.10 SB 16° N/A
G04608
KP.05
21116
78 28'' G04441 11.96 KP 4+623.18 SB 8.5° N/A
KP.05
20830
79 28'' 11.96 KP 4+360.43 SB 16° N/A
G04603
KP.05
21013
80 28'' 11.96 KP 4+250.55 OB 7° N/A
G04518
KP.05
TOTAL 190.49

CONTRACTOR'S INSPECTOR CLIENT'S INSPECTOR

NAME : NAME :

DATE : DATE :

LEGEND : OB : Over Bend, SAG : Sag Bend, SBL : Side Bend, SBR : Side Right, C : Combination, Vert' : Vertical, Horiz : Horinzontal
Loc. : Location

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

Start KP : KP 5+012.04 to KP 4+857.88

PIPE IDENTITY TOTAL LENGTH KP NO. BEND


REMARK
ITEM SIZE PIPE NO. ACTUAL LOC. VERT' HORIZ.
KP.05
20970
81 28'' 11.96 N/A N/A N/A
G04439
KP.05
21606
82 28'' 11.96 N/A N/A N/A
G04442
KP.05
20065
83 28'' 11.96 N/A N/A N/A
G04441
KP.05
20349
84 28'' 11.96 N/A N/A N/A
G04609
KP.05
20824
85 28'' 11.96 N/A N/A N/A
G04603
KP.05
20115
86 28'' 11.96 N/A N/A N/A
G04438
KP.05
21703
87 28'' 11.50 N/A N/A N/A
G04439
KP.05
21662
88 28'' 11.10 N/A N/A N/A
G04440
KP.04
21001
89 28'' 11.96 KP 4+475.80 OB 9° N/A
G04439
KP.04
21056
90 28'' 11.96 KP 4+451.96 OB 7.5° N/A
G04438
KP.04
21022
91 28'' 11.96 KP 4+348.47 SB 5° N/A
G04440
KP.04
20676
92 28'' 11.96 KP 4+428.12 OB 6° N/A
G04603
KP.04
21129
93 28'' 11.96 KP 4+300.49 OB 7.5° N/A
G04440

TOTAL 154.16

CONTRACTOR'S INSPECTOR CLIENT'S INSPECTOR

NAME : NAME :

DATE : DATE :

LEGEND : OB : Over Bend, SAG : Sag Bend, SBL : Side Bend, SBR : Side Right, C : Combination, Vert' : Vertical, Horiz : Horinzontal
Loc. : Location

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00
REPORT NO :

DATE : 5-Mar-18
PIPE STRINGING REPORT INSPECTION Gr :

WORK/JOB NO : 1710J-86
CLIENT : PETRONAS GAS BERHAD
PROJECT NAME : EPCC OF TELOK GONG LOOP PIPELINE PROJECT,
MELAKA (TUAH)

LEGEND: ACC : ACCEPT, REJ : REJECT, N.A : NOT APPLICABLE DOCUMENT NO.: SOP02_F26_R00