Professional Documents
Culture Documents
Sleepers and Fasteners - Work On Asset PDF
Sleepers and Fasteners - Work On Asset PDF
Fastenings – Work
on Asset:
Specification
Track Access
Authorised By:
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
List of Amendments
Issue Date Clause Description of Amendment
2.1 30 Jan 98 Installation of New Track Clause written
2.1 30 Jan 98 Attachment 1 Concrete Sleeper and fastening details
provided
2.2 May 1998 All Specifications put into alphabetical
order
2.2 May 1998 All IMS Data Listed As Appropriate
2.2 May 1998 Interspersing of Sleeper Types Compatible depth dimension defined
and last paragraph added
2.2 May 1998 Regauging Timber Sleepers Last sentence added
2.2 May 1998 Regauging Timber Bearers Last sentence added
2.2 May 1998 Concrete Sleeper and Bearer Clause Wriiten
Manufacture
Authorised By:
Page 2 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
1. SCOPE
This document specifies requirements for the work to be carried out on and with sleepers and
their fastening assemblies.
It includes timber, steel and concrete sleepers and bearers, and timber bridge transoms,
together with their associated fastening assemblies between the sleeper and rail, the points
and crossings set and the bearer, and the transom and rail and transom and bridge girder.
2. SPECIFICATIONS
Authorised By:
Page 3 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Authorised By:
Page 4 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
2.12.1 General
The installation of new track (including the reinstatement of track on existing formation) shall
be to one of the following classes:
Concrete sleepered track (main line or crossing loop)
Timber sleepered track (crossing loops or other sidings)
Authorised By:
Page 5 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
The class of track to be constructed shall be as directed by Track Access.
The Contractor shall provide details of the procedures to be used in the installation of new
tracks of both the above types, including the following:
Method(s) of handling and placing sleepers.
Method(s) of laying ballast.
Method(s) of handling and placing rail
Method(s) of applying fastenings, including specialist equipment to be used.
Method(s) of tamping track, including equipment to be used.
Specialised track laying plant (if any) to be employed.
Such procedures must meet the requirements below and be approved by Track Access prior
to commencement of work.
2.12.2 Drainage
Drainage systems for new installation sites shall be specified by the Contractor and approved
by Track Access prior to commencement of work.
Surface runoff shall be directed away from the new and any adjacent track structure.
Where free drainage of the ballast can not be achieved (for example through geometric
restrictions), the drainage shall be assisted through the use of pipe drains designed and
installed in accordance with Waterways and Drainage – Work on Asset.
2.12.3 Formation
Where required, the formation shall be constructed or overhauled in accordance with
Earthworks – Work on Asset – Construct Formation and Earthworks – Work on Asset –
Overhaul Track Formation.
2.12.4 Ballast
Ballast used for this activity shall comply with Ballast – Work on Asset - Supply.
Ballast profiles for the track shall be in accordance with Ballast – Design and Rating- Profile
and Ballast – Design and Rating- Depth.
2.12.6 Tamping
Tamping shall be installed in accordance with Track Geometry – Work on Asset.
2.12.7 Rail
Rail shall be installed in accordance with the following:
Rail – Design and Rating - Acceptance of New rail
Rail – Design and Rating - Acceptance of Part worn rail
Rail – Design and Rating - Locations and Types of Mechanical Joints
Rail – Design and Rating - Rail Size
Rail – Design and Rating - Insulated Joints
Rail – Design and Rating - Temporary joints
Rail - Work on Asset - Bonding of Mechanical Joints for Track Circuits
Rail - Work on Asset - Closure Rail Selection
Authorised By:
Page 6 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Rail - Work on Asset - Cutting of Rail
Rail - Work on Asset - Drilling holes in rail
Rail - Work on Asset - Flashbutt Welding
Rail - Work on Asset - Grinding in High Fire Risk Areas
Rail - Work on Asset - Installation of Insulated Joints
Rail - Work on Asset - Installation of Mechanical Joint Components
Rail - Work on Asset - Installation of Temporary Joints
Rail - Work on Asset - Lifting and Handling of rail
Rail - Work on Asset - Locations of Restricted Grinding
Rail - Work on Asset - Other Rail and Track Mounted Equipment
Rail - Work on Asset - Part Worn Rail Use
Rail - Work on Asset - Post Weld Grinding
Rail - Work on Asset - Rail Insertion into track
Rail - Work on Asset - Rail Rake Loading and Unloading
Rail - Work on Asset - Releasing rail from Fastenings
Rail - Work on Asset - Stress Adjustment Maintenance whilst installing
inserts
Rail <14m
- Work on Asset - Stress Adjustment on Continuously Welded Rail
Rail - Work on Asset - Stress Adjustment on Long Welded Rail
Rail - Work on Asset - Stress Adjustment on Short Jointed Rail
Rail - Work on Asset - Track Circuit Bond Welding
Rail - Work on Asset - Weld Types
Rail - Work on Asset - Welding of New Rail in Track
Rail - Work on Asset - Welding Part worn Rails
IMS Data
Base Data
Track Structure Description
Authorised By:
Page 7 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Nil
Authorised By:
Page 8 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Authorised By:
Page 9 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
In general, the following shall apply
Design Life of a minimum of 25 years or 400 million gross tonnes under present
and projected traffic and environmental conditions.
Dimensions to ensure the efficient and effective holding of the specified track
gauge
Compatibility with the existing fastening assembly system
Compatibility with adjacent sleeper spacer systems
Where required for electrical insulation with a minimum electrical resistivity of
107 ohm m.
IMS Data
Base Data
Spacer Type
Authorised By:
Page 10 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Nil
Authorised By:
Page 11 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
For standard gauge tracks Sawn timber of dimensions of 2,450 X 230 X 115
mm
For broad and mixed gauge tracks, Sawn timber of dimensions of 2,600 X 260 X
125 mm
Grade and performance requirements shall be in accordance with
Redgum sleepers to AS O97-1963 Rail Track Sleepers, Lead or Crossing
Timbers, Bridge Transoms, Grade 1
Sleepers to AS O10 – 1948, Jarrah, Karri and Wandoo Railway Sleepers.
IMS Data
Base Data
Sleeper Type (including Species, Grade and Dimensions)
Authorised By:
Page 12 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Base Data
Transom Type
Authorised By:
Page 13 of 14
Track Access
Sleepers and Fastenings – Work on Asset
Issue 2.2 May 1998
Attachment 1
Table of Sleeper and Fastening Components
To be completed
Authorised By:
Page 14 of 14