Unit = Each
Taking out put = one typical board
(i) Excavation for foundations
As per Item No. 11.1 of Chapter 11 cum 0.270 115.770 31.26
(ii) PCC grade M15
As per Item No. 11.4 of Chapter 11 cum 0.270 5798.874 1565.70
(iii)
Painting on MS Steel tubes with primer and two coats of epoxy
paint
2 x 2.45 x 0.30 = 1.47
2 x 1.00 x 0.30 = 0.60
As per Item No. 10.6 of Chapter 10 sqm 2.070 137.868 285.39
(iv) Painting new letters and figures of any shade with synthetic
enamel
Top Plate :
Heading Band=90x1x10=900 per cm height per letter
Figure 7x10 = 70 per cm height per letter
Side Border 2x65x1.5=195 per cm height per letter
Lower Border 1x90x1.5=135 per cm height per letter
Words (57x2.5+245x1.7) = 559 per cm height per letter
Figure 65x20 = 1300 per cm height per letter
Bottom Plate :
Border (2x75x1.5+2x90x1.5) = 495 per cm height per letter
Words 565x1.7 = 96..50 per cm height per letter
Total 4614.50 per cm height per letter
As per Item No. 10.1 of Chapter 10 per
cm
height
per
letter 4614.500 1.0442 4818.46
a) Labour (for fixing at site)
Mate day 0.060 404.7978 24.29
Mazdoor (Unskilled) day 1.000 277.5756 277.58
b) Materials
MS tubes 75mmx75mm of 12 SWG sheet 8400mm long kg 100.090 94.2050 9428.98
5mm steel plate kg 14.600 39.8953 582.47
1.6mm thick MS sheet strengthening by 25mm x 5 MS flat iron
on painting with stove enameled paint on both sides as per
MORD specifications. sqm 1.350 6020.040 8127.05
Add 3% cost of MS tube and steel plate towards the cost of
fabrications, drilling holes, nuts, bolts etc. 544.16
c) Machinery
Tractor with trolley hour 0.300 464.215 139.26
d) Overheads & Contractor's profit @ 15.5% on (a+b+c) 2390.47
Cost for one Board = (i+ii+iii+iv+a+b+c+d) 28215.06
Note : Printing and lettering for blank spaces on the plates will be written
as required and paid separately.
Annexure I
Analysis for RCC Guide post of 250mm dia
Diameter = 250 mm
Analysis for 1 No. RCC Guide post
Amount
Sl No. Description Nos. Length(m)Breadth(m)Height(m) unit Quantity Rate (Rs.)
Excavation
1
1 0.79 0.25 0.30 0.01 115.77 1.70
RCC M-15
2
1 0.79 0.25 1.050 Cum 0.05 5772.16 297.51
Reinforcement
10 mm bars 4 1.15 2.852
3
8 mm Stirrus @ 150 c/c 8 0.6983185 2.179
Total Ton 0.005 62528.26 314.56
5 Painting 1 7.50 1.90 0.075 1.06875 74.18 79.28
TOTAL = 693.06
Say Rs. 693.06