Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

THOHOYANDOU BOTANICAL GARDEN AND NZG CONSTRUCTION/RENOVATION BASELINE RISK ASSESSMENT

1. INTRODUCTION AND OVERVIEW

The Occupational Health and Safety Act of 1993, and its relevant regulations, require employers to do baseline risk assessment for planned construction work and
provide the risk assessment and specific health and safety specification to the principal contractor. The objective of this this baseline risk assessment is to inform the
Principal contractor of the occupational health and safety risk factors to which persons will be exposed when renovating / demolition of structures/building.
Measurements must be taken and the identified problems addressed by the employer. Improved conditions ensure better worker morale, loyalty and greater
productivity.

All construction and maintenance activities can subject workers to levels of environmental stressors and safety factors, e.g. noise, fumes and hazardous substances,
revolving machinery, tools, moving vehicles, electricity, etc., which permanently harm the health and physical wellbeing of persons at work and greatly reduce
productivity

2. SITE DESCRIPTION

Main administration block, staff ablutions and education centre in the Thohoyandou Botanical Garden. The site has offices which will be in operation during
construction work. The following are possible hazards which are related to construction and renovation work;

1. Physical hazards
2. Biological hazards
3. Chemical hazards

Other possible risks includes:

 Collision with plant, equipment and other vehicles.


 Collision with pedestrians and visitors
 Injury to public from falling objects
 Because of high density of people, noise and dust.
 Special attention and consideration should be prearranged regarding the continued use of surrounding area for parking purposes and normal work during
Construction period.
4. STATUTORY REQUIREMENTS

Section 8 of the OCCCUPATIONAL HEALTH and SAFETY ACT 1993 (Act no. 85 of 1993), requires inter alia that the employer shall establish as far as is
reasonably practicable, what the hazards to the health and safety of persons are attached to any work which is performed, further establish what precautionary
measures should be taken with respect to such work and he shall provide the necessary means to apply such precautionary measures. The construction regulations
2014 further requires that a baseline risk assessment for an intended construction work project be compiled and a suitable, sufficiently documented and coherent
site specific health and safety specification for the intended construction work based on the baseline risk assessment to be prepared.

5. Hazards identification.

Based on the nature of work to be undertaken and the risks attached to it, the following must be complied with in order to ensure health and
safety of both SANBI employees and visitors.

 Agreed programme of work with clear completion time per phase to allow employees to organise alternative accommodation.
 Clearly defined designated access route to and from work area/offices
 Ensure all debris is removed from walkways and disposed of safely.
 Daily inspection to be carried out by contractors.
 Clear signage for visitors to main entrance / other services
 Advise employees of restricted access to construction areas during team information sharing.
 Contractors instructed not to engage in conversation with staff but to report to Centre manager if staff breach area.
 Adequate supervision in the vicinity of the work area.
 Contractors’ vehicles not permitted into grounds.
 Pedestrian walkways maintained
 Obtain Permission from SANBI Centre manager for Construction work undertaken out of normal working hours.
 Hot work permit to be obtained first for any welding activities inside the building.
 Adhere to emergency and evacuation procedures.
 All construction employees must wear hard hat, coveralls, safety boots, high visibility vests and any other PPE as determined
by risks attached to their activities.

NB/ Below is baseline risk assessment (not exhaustive) which must be supplemented by your activities risk assessment.
BASELINE RISK ASSESSMENT Centre Name: THOHOYANDOU BG/NZG
STEP 1.
RENOVATION AND CONSTRUCTION PROJECT Year: 2018
Operation Name: Area:

Activity / Task Construction and renovation


Description:

S
T S
E ST T
STEP 2. STEP 3. STEP 4. P EP STEP 7. STEP 8. E
6. P
5 9
.
C RISK RANKING RESIDUAL
L RISK CONTROL MEASURES RISK
A  Hierarchy of Control –
S

Actioner / Initials
Re Elimination, Substitution,
IDENTIFIED S
f SPECIFIC TASK / ACTIVITY Isolation, Engineering,
POTENTIAL RISK

Risk Rating
No STEPS Administration, Personal

Consequen

Consequen
Likelihood

Likelihood
HAZARDS S
. Protection.

Residual
H  Additional information can

Risk
be attached.

ce

ce
E
Tools/machinery Injuries due to S 3 4 12 Full safety plan for the entire project 2 3 6
Noise, Dust improper use of Communication
Site clearing & and
tools. Hearing Use proper PPE
establishment -manual labour
impairment, H Develop WSWP
& small tools.

The disregard of S 4 4 16 The principal contractor will 3 3 9


the public’s responsible for ensuring that non-
health and employees affected by the
safety could construction work are made aware of
result in injuries the dangers likely to arise from said
or even fatalities construction work as well as the
with associated precautionary measures to be
claims and observed to avoid or minimise those
reputation risks dangers. This includes among others:
a. Non- employees entering the site for
Construction whatever reason;
activities b. The surrounding community; and
c. Passers-by the site.

Appropriate signage must be posted to


this effect and all employees on site
must be instructed to ensure that non-
employees are protected at all times.
All non-employees entering the site
must receive site applicable induction
into the hazards and risks and the
control measures for these

Tools, Underground Injuries, S 3 3 9 Do task risk assessment before 2 3 6


services Damages to Develop WSWP
underground Do toolbox talks
cables and All excavation work to comply with the
Excavations - using manual pipelines, following:
labour &motorised plan electrocution, a. Excavation work must be carried out
Engulfment under the supervision of a competent
Excavations - working inside > person with at least two years practical
1.5 metres experience in excavation work who
has been appointed in writing.
b. Before excavation work begins the
stability of the ground must be
evaluated.

Loadings and Stuck Injuries S 3 4 12 2 3 6


unsafe maintenance due to falling Detailed consideration to be given to
condition material all batching plant to ensure that it is
properly planned to meet the working
Batching plants - erection /
requirements, designed to carry the
dismantle and general working necessary loadings and maintained in
a sound condition. It must also be
ensured that there is sufficient
material

Concrete mixing - using Noise, Dust Inhalation H 3 4 12 WSWP 2 3 6


manual labour and using Slippery surfaces Hearing
mechanical means impairment

Concrete pours - using lifting Falling objects Injuries due hit S 3 4 12 WSWP 2 3 6
machinery (Cranes etc) by falling
objects
Concrete pours - using Falling objects, Injuries due to S 3 4 12 WSWP 2 3 6
motorised plant (dumpers etc) Concrete, slips and hit by
and mechanical pumps Slippery surfaces, objects
Noise
Tools, working at Injuries S 4 4 16 Use trained operators 2 4 8
height Inspect and test cranes as required
Lifting Equipment - Tower Load WSWP
crane erection / operation and
Every lifting machine operator must be
dismantle trained specifically for the type of
lifting machine that he or she is
operating.

Noise, Hearing S 3 4 12 Use trained operators 2 3 6


Lifting Equipment - Forklift Load impairment, H Develop WSWP
operation and lifting tackle Collision and Regular tests and inspection
falling load
Injuries
Formwork - general erection / Tools, working at Injuries due to S 3 4 12 Use trained erectors 2 3 6
dismantling and lifting and height, load, falling tools and H Develop and follow WSWP
placing large panels, work on unsecured deck load or deck
collapse
support decks

Tools, working at Injuries due to S 3 4 12 Only skilled employees to be 2 3 6


height, load, falling tools and allowed to erect structures and
unsecured deck load or deck that the skills of these employees
collapse are being verified at regular
Scaffolding - erect / dismantle
intervals.
small scaffolds < 2 m Steps to be taken to ensure that
no structure becomes unstable
or collapses due to construction
work

Develop and follow WSWP


Demolition - using small Noise, Inhalation, S 4 4 16 Risk assessment 3 3 9
electric breakers, compressed electrocution, dust, Hearing H Use trained employees
air breakers, motorised falling objects impairment and Develop WSWP
mechanical means, Asbestos injuries Communication
explosives/blasting
Demolition work to be carried out
under the supervision of a competent
person who has been appointed in
writing.
A detailed structural engineering
survey of the structure to be
demolished to be carried out and a
method statement on the procedure to
be followed in demolishing the
structure to be developed by a
competent person, before any
demolition to be commenced.

Cement dust, Skin damages, S 4 4 16 Risk assessment 3 3 9


Trades - Brickwork operations
Bricks, tools, Inhalation and H Training
and plastering operation Working at height injuries due to Develop WSWP
falling objects Toolbox talks
Working at height, Inhalation, S 4 4 16 Risk assessment 3 3 9
Trades - Painting operations
paint Falling H WSWP and toolbox talk
Training
Trades - Ceiling operations Working at height, Injuries due to S 3 4 12 Risk assessment 2 3 6
Tools slips and fall WSWP and toolbox talk
Working at height Injuries due to S 4 4 16 Risk assessment 3 3 9
falls Fall protection plan
Where work on roofs is
carried out, the risk
Trades - Roofing installations assessment must take into
account the possibility of
persons falling through fragile
material, i.e. skylights and
openings in the roof.

Trades - glazing installations Working at height, Injuries due to S 3 4 12 Risk assessment 2 3 6


Tools slips and fall WSWP and toolbox talk
Tools, talon Skin damage, S 3 3 9 Risk assessment
Trades - Tiling operations
Muscular pain WSWP
due to bending
Trades - Metal work (Doors / Noise, Hearing S 4 4 16 Risk assessment 2 3 6
Tools, cutting impairment, H WSWP
windows) and steel erection machines, Eye damage due
Welders, to glare
Working at height Falling injuries

Trades - plumbing Tools, Muscular pain, S 3 3 9 Risk assessment 2 2 4


Manual handling Injuries WSWP
Large plant - Earthmoving
equipment

Large plant - Material handling


equipment
The unsafe use S 4 4 16 3 3 9
of welding and H 1. A competent person to be appointed
flame cutting to supervise welding, flame cutting or
equipment similar operations on site.
could result in 2. The following rules to govern all
employees and welding and flame cutting or similar
other persons operations:
suffering from a. The welder will be trained regarding
burns or even the safe use/operation of the
General site operations - result in fires equipment.
Welding that could cause b. The welder and his assistant will be
injuries and provided with effective and
fatalities as well appropriate personal protective
as damage to equipment and/or clothing.
property with c. Cables and electrode holders will be
subsequent effectively insulated.
claims and d. The workplace will be effectively
costs screened off to prevent bystanders
from being affected by the welding
rays

General site operations - Noise, flying Eye injuries, S 3 4 12 Risk assessment 2 3 6


Grinding objects Hearing H WSWP
impairement
General site operations - Flame and fumes Burns S 3 4 12 Risk assessment 2 3 6
Flame cutting Fumes H WSWP
inhalation
General site operations - Noise, drill, dust Inhalation, S 3 4 12 Risk assessment 2 3 6
Drilling hearing H WSWP
impairment
Noise, vibration Muscular pains, S 3 3 9 WSWP 2 2 4
General site operations -
damage to
Compaction equipment property like
glasses
Steel material, Falling, S 3 4 12 Risk assessment 2 3 6
General site operations - Steel Electricity Injuries due to WSWP
fixing Working at height improper PPE
handling of
materials
Unsecured material Unsafe stacking S 3 4 12 The principal contractor to ensure 2 3 6
and storage that:
practices may
result in stacked a. A competent person is appointed in
items collapsing writing to supervise all stacking and
with subsequent storage on a construction site;
injuries or even b. Adequate storage areas are
fatalities as well as asset provided and demarcated;
damage with c. The storage areas are kept neat and
associated losses and under control;
costs.
General site operations - d. The height of any stack does not
Stacking and storage exceed 3 times the base unless
stepped back at least half the depth of
a single container at least every fifth
tier or the approval of an inspector of
the Department of Labour has been
obtained to build the stacks higher
with the aid of a machine. (The
operator of the machine must be
protected against items falling from
overhead or off the stack and no items
may overhang);

Poor S 3 4 12 The principal contractor to ensure 2 3 6


housekeeping that:
may impact a. Housekeeping is continuously
General site operations - negatively on implemented and maintained;
Housekeeping productivity, b. Materials and equipment is properly
result in stored;
employees/pers c. Scrap, waste and debris is removed
ons tripping and off site regularly;
falling or even d. Materials placed for use are placed
cause a fire with safely and not allowed to accumulate
subsequent or cause obstruction to the free-flow of
asset damage pedestrians and vehicular traffic;
and cost/claims e. Where practicable, construction
as well as sites are fenced off to prevent entry of
reputation unauthorised persons;
exposures. f. An unimpeded work space is
maintained for every employee

General site operations - Electricity Electrocution S 3 4 12 Risk asessment 2 3 6


Working under power lines WSWP

General site operations - Dry Tools, Inhalation S 3 4 12 Risk assessment 2 3 6


wall partitioning Dust Hearing WSWP
Noise impairment

Unsafe electrical S 4 4 16 Any electrical work undertaken as part 3 3 9


installations of the project, including the
could result in installation of temporary electricity for
employees and construction use shall be in
other persons accordance with Construction
General site operations -
being Regulation and the Electrical
electrical installation and electrocuted Installation Regulations.
Electricity with subsequent The principal contractor to ensure
injuries or even that:
fatalities as well 1. Existing services are to be
Electrical and mechanical
as asset located and clearly marked
lockout damage due to before construction
fire with commences and during the
subsequent progress thereof;
costs and 2. All contractors on site must be
reputation risks. informed of and adhere to this
lockout procedure.

General site operations - Bricks, tools, Injuries due to S 3 4 12 Risk assessment, 2 3 6


paving Surface preparation tools handling, WSWP
Muscular pains
General site operations - Machinery Struck injuries S 3 4 12 Risk assessment
landscaping Noise, Tools Dust WSWP
Muscular strains
Flammable liquids The unsafe use S 3 4 12 The principal contractor to ensure 2 3 6
and/or storage H that:
of flammables a. The risk of fire is avoided;
could result in b. Sufficient and suitable storage of
fires or flammables is provided;
explosions with c. All employees are instructed in the
subsequent use of the firefighting equipment and
injuries or even know how to attempt to extinguish a
fatalities as well fire;
as asset d. A sufficient number of employees
HCS - flammable liquid
damage due to are appointed and trained to act as an
storage and use fire with emergency team to deal with fires and
subsequent other emergencies;
costs and e. Employees are informed regarding
reputation risks. emergency evacuation procedures and
escape routes;
f. Emergency escape routes are kept
clear at all times and clearly marked;
g. Evacuation assembly points are
demarcated and made known to
employees;

HCS - Diesel tanks storage


and use

Chemicals The unsafe use H 4 4 16 The principal contractor to ensure 3 3 9


of hazardous that:
chemical a. Employees receive the necessary
substances information and training to be able to
could result in use, handle and store hazardous
fires with chemical substances safely;
HCS - Hazardous Chemical
subsequent b. The risk assessments required in
substance storage / use injuries or even terms of Construction Regulation 9
fatalities as well include employee exposure to
as asset hazardous chemical substances and
damage due to that the necessary measures be taken
fire with to protect persons from being
subsequent detrimentally affected by hazardous
costs/claims. chemical substances present or used
Spilled chemical in the workplace;
substances may
also impact
negatively on
the health of
employees and
other persons or
negative
implications for
the environment
including legal
and claim
exposures.

Tools/machinery Injuries due to S 3 4 12 Risk assessment 2 3 6


Construction of car parking
Material material WSWP
Unsafe access handling
Tools, materials Muscular strain S 3 4 12 Risk assessment 2 3 6
Trenches due manual WSWP
handling PPE
Install irrigation system
Injuries due to
improper
handling of
materials

STEP 5
Highest Remaining Residual Risk
10.
STEP 11.
Risk assessment trained Mulaudzi Tshavheni Edward
Risk person =
assessment Date: 11/06/2018
prepared by: Other participant names =

Affected South African National Biodiversity Institute employees WSWP to be


Consultation conducted with: Yes / No
developed?
Residual Approval Approval
APPROVAL REQUIRED TO PROCEED
Risk Signature Date:
Extreme
Stop Activity and seek approval from the SANBI OHS responsible person/Project manage
(E)
High (H) Approval must be obtained from Responsible site manager and when all control measures are in place.
Moderate
Work can commence after supervisors’ approval and all control measures are in place
(M)
Work can commence when the supervisor/SHE rep has approved this risk assessment, & all identified
Low (L)
control measures are in place.
Responsible site manager must approve Risk Assessment if it is used to develop a WSWP.

* Discretion for OHS/Project manager to approve Extreme / High risk work to proceed only applies where there is a risk to production loss/plant. This
discretion does not apply to work if the Ext/High residual risk relates to the potential for personal injury or environment risk. In this case work
should stop and seek professional safety advice.

RISK CALCULATOR (Risk Rating = Consequences x Likelihood)


CONSEQUENCE
LIKELIHOOD Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Almost Certain (5) M (11) H (13) E (20) E (23) E (25)
Likely (4) M (7) H (12) H (17) E (21) E (24)
Possible (3) L (4) M (8) H 16) E (18) E (22)
Unlikely (2) L (2) L (5) M (9) H (15) E (19)
Rare (1) L (1) L (3) M (6) M (10) H (14)
QUICK GUIDE OF WHAT
STEP MORE DETAILED INFORMATION ON EACH PROJECT/TASK RISK ASSESSMENT STEP
TO DO
 At the top of the risk assessment record the task name, a brief description of the task, and the relevant work area and
Complete a description of the section. Keep as simple as possible, but with enough information to identify the task.
1.
Activity / Task  If the Risk Assessment is being used to develop a Safe Work Procedure (WSWP), the risk assessment task name
should correspond with the title of the WSWP.
 In the first column “Ref No.” write the step no. starting from 1. Up until however many steps/tasks there are in the task. If
2. Detail specific task steps applicable, these should align with any associated WSWP to enable cross referencing.
 List each of the specific tasks, activities and/or steps associated with the activity/task that will be undertaken.
 In the column next to listed tasks/activities, identify all potential hazards relevant to each item. Record each hazard on a
Identify potential Hazards for separate line.
each Task/Activity in Step 2.  A common mistake is to refer to a hazard as the actual harm or the health effects it caused rather than the hazard. E.g.
3.
 Use Hazard Prompt Sheet If the task was hosing down an area, the hazard is the wet floor not the potential harm caused e.g. fall / cut knee.
(Appendix 2) for help.  If no hazards are found for a task/step or the risk has been addressed in a previous hazard, the task still needs to be
listed to show it has been considered, and to keep the steps/tasks in line with any associated WSWP.
Evaluate the possible  Simply put if someone was exposed to the hazard, what would be the reasonable consequence? It is not always the
Consequence of the Hazard “worst” case scenario; e.g. if you fell 1m off a ladder you could be killed as an extreme (e.g. land on your head), but the
4.
 Use Risk Calculator most likely consequence would be you might sprain your wrist or break a leg. Therefore the consequence is more likely
above to be moderate rather than catastrophic.
Evaluate the Likelihood of  Ask yourself will it ever happen; if so what factors are needed for it to happen, and how often would those factors be
that Consequence around. Then ask yourself what you think the reasonable frequency would be, before determining the Likelihood.
5.
 Use Risk Calculator
above
Determine Risk Ratings of  Determine each hazard’s risk rating by intersecting the “Consequence” and “Likelihood” levels on the Risk Calculator
hazards table.
6.
 Use Risk Calculator
above
 Control measures need to reduce hazard risk ratings to an acceptable level if the current risk level is unacceptable; aim
Identify Controls to reduce
7. for a low risk.
hazard risk
 Apply the Hierarchy of Control when determining control measures
Evaluate the Residual Risk  After control measures have been identified, you need to reassess each hazards risk rating to determine what the
8. (risk rating with controls in remaining risk would be with the controls in place from Step 7 (follow the principles in Steps 4 & 5 above).
place)  The aim is to achieve a Low Risk; if not achieved review controls again and/or ask for help.
 If the highest residual risk on the risk assessment is a Low Risk, or a Moderate Risk the task/project can commence
once all control measures are in place and the risk assessment has been reviewed and approved.
 If a High or Extreme risk still remains, then the task/project must not commence and further review must be undertaken
involving the Budget Centre manager/ Senior Management Team such as SHEQ (an Elected Safety Representative
Determine highest remaining
9. should also be involved).
residual risk
Exemption: In exceptional circumstances, if the “Ext” or “High” risk rating does not apply to personal injury or
environmental damage (e.g. potential for property damage only), and project/site manager in consultation with the OHS
believe it is an acceptable risk for the Company, the task may be approved. This does not apply for Personal injury or
Environmental risks; an “M” (Moderate) risk is the highest ranking allowable.
 Once the risk assessment is complete, all participants should record their name at the bottom of the sheet, document
any consultation that was had (e.g. tabled at SHE Committee) and the project/site manager or delegate should sign off
Approval / WSWP
10. the task for approval.
development
 Specify if a safe work procedure (SWP) is required to be developed (e.g. for routine / regular tasks). If yes, this should
be done in accordance with the Minimum Standard - Safe Work Procedure Development.
 All persons involved in a project/task must acknowledge they have read and understood a risk assessment and agree
11. Sign on / off
to comply with all steps and control measures.
 Reference the initials of the person responsible for ensuring a particular control is implemented before progressing with
12. Document Actioners
the task/project.
APPENDIX 2 Example Hazard Prompt Sheet Centre Name: General
ACTIVITY / TASK PREPARATION CONSIDERATIONS INCLUDE:
 Safety glasses  1st aid equipment/Trained first  High risk licenses
 Double eye / Face shield aiders  Certificates of competency
Emergency
 Earplugs (Specify class:  Fire equipment Training /  Experience
Response /
Minimum ___________)  Other emergency response Competency  Induction training required
Plant /
PPE  Helmet  Chemicals approved for job /  Project / Area Supervisor
Equipment /
 High-visibility  Chemical/Oil spill kit Compliance  Any relevant legislation
Access
 Safety boots  Vehicular type / access / parking  Consultation / Notifications
 Long sleeves/trousers  Amenities / Facilities / Hours of  Any literacy issues
 Coveralls work
 Respirator (Specify type:  Signage / Barricades
__________)  Communication equipment
 UV protection (Hat, glasses, etc)  Registered plant
 Gloves (Specify type:
_____________)
 Other:
POTENTIAL HAZARDS ASSOCIATED WITH THE ACTIVITY/TASK RESULTING FROM (but not limited to):
CATEGORY CONSIDER CATEGORY CONSIDER CATEGORY CONSIDER
 A chain brake  Repetition / Overuse  Unguarded moving parts (e.g.
 A chain catcher  High / Low reach crush)
Manual
 A throttle lock  High force / Heavy loads  Drawing in / cutting points (e.g.
Handling
 A rear hand guard
Chainsaw (Ergonomic)  Awkward / Unbalanced loads nips)
 Anti-vibration rubbers.  Pushing / Pulling / Twisting  Impact and crushing areas
/ Human /
 An exhaust muffler  Carrying & walking  Uncontrolled movement
Muscular
 An anti-kickback chain.  Over exertion (e.g. fatigue)  Tearing / Shearing (e.g.
 Design / Layout abrasions)
Mechanical
Emergency  Working alone / Remote work  Personal characteristics e.g.  Unsafe access
height  Auto-start equipment
 Inadequate isolation points
 Hand & power tool condition
 Inappropriate chemical storage/use Thermal  Steam / Condensate
Fire /  Stored energy (e.g. vessels)
 Self-ignition combustibles (e.g. dust)  Hot or cold materials/surfaces
Explosion  Failure of plant (e.g. loss of
 Fire (e.g. burns)  Heat stress / Cold
load, plant ejection, collapse,
fragmentation)
 Hazardous Subs/Dangerous Pressure  Compressed gases
Goods  Hydraulic / Vacuum
 Inadequate  HP steam / Water
 Working at height / Unguarded edge
Chemical / storage/bunds/labelling  Time of day and
Gravitational  Struck by falling/lowering object
 Rolling/Sliding objects Environment  Gas / Dust / Fumes (e.g. illumination/glare
explosion)  Wet / Slippery / Uneven
 Ascending/Descending stairs / ramp /
 Poor ventilation surfaces
ladders / platform / mobile equipment
 Inhalation / Absorption / Skin General  Weather & outdoors e.g. wind,
 Lifting equipment (e.g. crane, sling)
Injured by contact Work Area UV, fog
 Holes/Gaps or Slip/Trip hazards
people or  Waste/Contamination e.g.  Unauthorised personnel entry
 Scaffolding
objects soil/water/air  Noise / Vibration
 Unbalanced ladders
falling  Inadequate training / experience  Biological – fluids, sharps,
 Structural failure / Exceeding load
Procedural  Incorrect equipment selection / insects
ratings
use  Inadequate
Kinetic  Traffic / pedestrian interaction maintenance/inspections
Energy /  Vehicle instability e.g. rollover  Restricted work area
Mobile Plant  Exceeding rated capacity  Any foreseeable abnormal
Hazards resulting in electrocution / /  Obstructed / Poor Visibility conditions?
Electrical burns; E.g. Pedestrians  Being hit by the activities of  Any other hazardous
 Cables: Unsafe condition/location another person, moving vehicle conditions?
 No earth leakage protection or object  Dead trees
 High voltage / Switch rooms  Sharp slash points

You might also like