Recovery boiler Shut Down and Start

S. No Description
1 Black Liquor Firing to be Reduced
2 Put oil burner one by one
3 Stopped Black Liquor Firing
4 Smelting Down
Stopped all air fans including ID Fan after cut the air
5
heating steam
6 Water/ WWL Boiling of complete system

Start up vent valve to be open and open all air vents when
7
boiler pressure come at 4/5 kg/cm2 Pressure

Empty out MDT and hand over to maintaince team for


8
man hole

Secondery air fan to be started in full mode with ID Fan


9
and ID Fan speed to be kept (- 30 mmwc )

MDT Inside cleaning and all inside stub to be clean with


10 High Pressure pump and special care of Explosion door
and MDT Vent and again box up

11 Dummy to be removed in furnace wash pump line


12 Trial taken of wash pump with SB No 16 and 17
13 Start Water Washing
14 Water Washing to be complete
15 Hearth Cleaning
Cleaning Jobs time Frame ( 9 am to

Inside Cleaning of all DTPA Valves and checking of full


1
open and close
Inside Cleaning of all Gullotine dampers and checking of
2
full open and close
Silensor and air heater cleaning of all fans with HPP
3
including Impeller
4 Inside cleaning and Impeller checking of ID Fan
5 Demister Cleaning at ( + 18.50 M ) With HPP Jet
6 Spout Shettring system to be checked or clean
7 Spout Hydraulic
8 Expansion and Resviour tank cleaning
Boiler Start up activity
1 Start Air Heating
2 Start oil Burner
3 Start Black Liquor Firing
4 Boiler in Line
own and Start up Time Frame
Time Frame Resposibilty
7.30 PM Process Shift Incharge
8:00 PM Process Shift Incharge
9:30 PM Process Shift Incharge
10:30 PM Process Shift Incharge
Process Shift Incharge
9:30 pm to 6:30 am Process Shift Incharge

Process Shift Incharge

11:30 PM Process Shift Incharge

Process Shift Incharge

11:30 pm to 7:30 am Process/ Mech SI

7:30 AM Mech SI
8:30 AM Process Shift Incharge
9:00 AM Neeraj
4:00 AM Neeraj
7:00 PM Neeraj
me Frame ( 9 am to 8 pm )

9 AM TO 8 PM Process Shift Incharge


9 AM TO 8 PM Process Shift Incharge

Start up activity
6:00 AM Process Shift Incharge
10:00 AM Process Shift Incharge
2:00 PM Process Shift Incharge
7:00 PM Process Shift Incharge
Recovery boiler Shut Down and Sta
S. No
1

5
6
7
8
9
S. No

2
3
4

5
6
7
8
9

10
11

12

13

14
15
16
17

18

19

20

21
22
23

24

IBR Joints
1
2
3
4
5
6
7
Start up Procedure
Start up Procedure

9
Recovery boiler Shut Down and Start up Time Frame
Description
MDT Man hole to be open and Box up

Primary and Secondery air port to be open for cooling

Recovery Boiler all peep hole and Manhole to be open

Boiler bank and Economiser area manhole to be open only in


between ( 6:30 am to 8:00 am )
MDT Vent ( + 18.50 M ) Manhole to be open and all demister
to be removed
Spout Shettring system to be open
Green Liquor Circulation system to be open including fish
nozzle and header
Furnace wash pump dummy to be removed
Fans air heater manhole to be open
Description

Connecting pipe in between primary and secondery air


ducting with 300 NB Valve and Flange and spectable dummy

Primary and Secondery air port NRV to be attended


All Six Firing gun shaddle to be set right
Cascade inlet pipe ( 150 NB ) to be extended up to cascade
bottom
Cascade no 2 Leakage from Bottom
Oil to be poured in Gear box and Fluid Drive
ID Fan coupling to be changed
Bird Screen to be provide in all fan silensor
Secondery air fan silensor to be modified
Furnace door to be repaired or chandef with new one at + 4.50
M Floor
Indirect Heater no 2 ( 50 NB ) Gate valve to be changed with
new one

Two 40 NB NRV to be provide in Feed Pump Sealing System

FV 1026A Feed Pump Control valve Body Change over job

Flange leakage in top of dearator it to be change but only


spiral gasket
LP and MP Main header gasket to be chanded
LP and MP Orifice gasket leakage
Indiect heater condensate out let line leakage from bend
( Bend to be change )
Two 25 NB Valve to be provide in indirect heater condensate
out let line

Both air heater condensate out let system to be checked

All Six Firing gun Shattering to be cut clean and again fitted
back and if required to be change with new one

Spout Shower connecting pipe to be cut , cleaned and fitted


back
Condensate transfer line leakage at (+4.50 M)
Two Valve 40 NB and 80 NB to be provide in Condensate
Header at + 4.50 M

Boiler firing door no 2 and 5 Side plate is in damaged


condition it to be changed with Specific MOC

IBR Joints
Modifaction in RWLI
Riser air vent line leakage
RHS and LHS Side Gauge Glass Air ports leakage
Two 15 NB Valve to be provide in Condensate tank
TV 1075 25 NB Valve is Pass to be Changed

Start up Procedure
Start up Procedure

Start Boiler Box up

Oil burner to be make ready


wn and Start up Time Frame
Time Frame Resposibilty
Mech SI

Mech SI

Mech SI

Mech SI
10:30 PM TO 9:00 AM
Mech SI
Mech SI
Mech SI
Mech SI
Mech SI
Time Frame Resposibilty

Mech SI

Mech SI
Mech SI
Mech SI

Mech SI
Mech SI
Mech SI
Mech SI
Mech SI

Mech SI

9:00 am to
Mech SI

9:00 am to Mech SI

3:00 am Mech SI

Mech SI
Mech SI
Mech SI
Mech SI

Mech SI

Mech SI

Mech SI

Mech SI
Mech SI
Mech SI

Mech SI

R Joints
Mech SI
Mech SI
9:00 am to Mech SI
Mech SI
3:00 am Mech SI
Mech SI
Mech SI
p Procedure
p Procedure

3:00 AM Mech SI

6:00 AM Mech SI
Evaporator Shut Down and Start
S. No
1

4
5

Evaporator Shut Down


1

2
3
4
5
6
7
8
Evaporator Shut Down and Start up Time Frame
Description
Water Boiling of Evaporator

Hand over to maintaince

Surface condenser tube cleaning job

Surface condenser to be box up

Water Boiling of Evaporator and Surface condenser trial

Black Liquor taken and SCBL Production


Finisher White Liquor Boiling

Evaporator Shut Down jobs


Effect no 7 to be bypassed

Leval transmitter to be provide in cooling tower


Cooling tower inside cleaning
Cooling tower spray nozzle to be checked
Secondery Condensate line to be connected with wash liquor
line
Effect 1 C Vapor out let manual valve to be checked
Vaccum pump sealing system to be checked
Acid Circulation of both vaccum pump
n and Start up Time Frame
Time Frame Resposibilty
3am to 6am Process Shift Incharge

6:00 AM Process Shift Incharge

8 am to 8 am == 24 Hrs Process Shift Incharge

8 am to 11 am == 3 Hrs Mech SI

11 am to 2 pm == 3 Hrs Process Shift Incharge

2 pm to 6 pm == 4 Hrs Process Shift Incharge


8am to 10 pm == 14 Hrs Neeraj

Shut Down jobs


Mech SI

Mech SI
Process Shift Incharge
8 AM TO 8AM == 24 Hrs Mech SI
Mech SI
Mech SI
Mech SI
Process Shift Incharge