Professional Documents
Culture Documents
Daily Co-Ordination Meeting: HPL, CPP Site
Daily Co-Ordination Meeting: HPL, CPP Site
Sl. No EQUIPMENT LOAD (MW)/STEAM GENERATION (TPH) REASONS / REMARKS (If any)
C. Water Chemistry:
Boiler Water Parameters Cooling Water Parameters
pH Conductivity(µS/cm)
Dated 21.10.2020
Parameters
Range Actual Range Actual
Parameters Range Actual
DM Water(at B/L) (6.5 – 7.0) * 8.1 <0.20 1.21 pH 7.2 –8.5 7.30
Main Steam sample (8.5 - 9.5) 8.65 <5.0 2.65 Conductivity
< 6000 1690
AB-1 (9.0 - 10.0) 9.70 <50 62 Chloride <1600 247
Drum Sample
AB-2 (9.0 - 10.0) 9.7 <50 61 FRC 0.20 - 0.5 0.60
HRSG1 (SHP) (9.0 - 10.0) 9.2 <50 35 COC based on MgH. 3.0-6.0 5.73
HRSG2 (SHP) (9.0 - 10.0) 9.7 <50 76 Remarks if any:
Drum Sample
HRSG1 (MP) (9.8 - 10.6) 10.4 <3000 275
HRSG2 (MP) (9.8 - 10.6) 10.2 <3000 144
Condensate CSTG (8.5-9.5) 8.8 <5.0 2.53
*DM water pH at DM plant O/L is 6.5 to 7.0. However morpholine is dosed to elevate pH & pH parameter at CPP B/L is 6.5 to 9.0&
Conductivity at CPP B/L is 0 to 2.0.
C. Safety Observations:
1. GT-2 turbine compartment & LGB compartment temperature is very high: Continuous monitoring is to be done to see the further
deterioration of temperature profile, new exhaust plenum will be delivered in August’20, then it will be replaced in next opportunity.
2. Turbine compartment overall exhaust temp near BT fan suction is 123degC, Highest is 323degC & LGB compartment exhaust tunnel
area max temp is 250degC.
D. Current Issues:
Sl. Issue Initiation Estimated date of completion or plans Resp.
E. Yesterday’s works:
*(Managers should come prepared to answer the status of previous day job status. Status to be filled up in the work request register on the
same day of completion by both Maintenance & operation)
PM/
Description Dept. Status Trial OK, defect closed. If not status
D No
72/73 HRSG#01, SHP CBD line elbow joint leakage arrested. M Completed -
132 Spare BPST & CST rotor rotation to 180 degree. M Completed -
- EDP# B servicing job M U/P -
- Erection of scaffolding at HRSG-2 chimney is being done. M U/P Work progress is slow
One rack has been prepared out of 6.
Rest will be done after material
- Fabrication of Store rack is being done. M Hold
availability.
Material (0.6T) is available.
F. Pending Issues (to shift from current issues which are more than a month old, to be discussed on first Monday of every month):
Initiation
No Issue Plans EDC Resp.
date
Mass flow meter:
- Installation technical limit needs to be Naphtha B/L mass flow meter is available,
verified from manual. scaffolding done; it will be replaced on 22.11.2020.
1. - Raise New PR for procurement of 12-11-19 - Inst
mass flow meter (Naphtha, CBFS, and PR raised for Mass flow meter for fuel flow
RFG). measurement (PR No-1067561).
- Raise a service PR for calibration.
Communication started with Woodward for onsite
GT-2 SRV & GCV both are having Inst/
2. 08-5-2019 services & to identify the spares of repair kit. -
passing. Mech
E-mail to be sent by 20.10.2020.
PO placed for servo motors on 17.09.2019 (No-
3. CSTG CV hunting 09-5-2019 3046478), follow up is being done for material Oct’2020 Inst
dispatch.
New Feed Control valve for AB/HRSGs PR to be raised after receiving technical budgetary Inst/
4. 22.11.2019 -
to be procured. offer. Mech
Spare shaft is to be made ready for
5. 29.06.2020 PR for critical motor is to be raised. - M/E
critical motor during overhauling.
PO NO: 3046926, Delivery date is over. Follow up is
6. AB-2 soot blower MOV is not working. 20.07.2020 - I
being done. Delivery Date: 19.03.2020
SHP BFP-C is tripping before reaching
BFP-C CAG34 (differential relay) & VAJH-13 (Master
the starting current without any alarm
7. 20.07.2020 trip relay) was replaced. - E
during 1st manual start, needs to be
Problem still persists.
studied.
0 0 0 3
I. Reminder:
PR Status, Pending Material Inspection, Critical system study related to GT, Pending TBA Status, and Status of rejected material,
Emergency procurement issues.