Professional Documents
Culture Documents
Is 5822 1994 PDF
Is 5822 1994 PDF
Is 5822 1994 PDF
REAFFiRMED
'J1T"x-rft"lJ -qT-rrcf)
Indian Standard
CODE OF PRACTICE FOR LAYING OF
ELECTRICALLY WELDED STEEL PIPES FOR
WATER SUPPLY
( Second Revision)
© BIS 1994
FOREWORD
This Indian Standard ( Second Revision) was adopted by the Bureau of Indian Standards, after the draft
finalized by the Water Supply and Sanitation Sectional Committee had been approved by the Civil
Engineering Division Council.
The selection of a pipeline for any particular application depends on the service and environmental
conditions to be satisfied. With the development of new materials and jointing methods, changes in the
application and in design can be expected. but it is the responsibility of every authority to ensure that
the type of the pipeline selected is suitable and safe for the duty envisaged. The earlier disadvantages
of steel pipelines ( liability to deteriorate by corrosion) have been largely overcome in recent years due
to development of protective coatings, and steel pipelines may now be safely used for carrying certain
fluids. This standard was first published in 1970 and subsequently revised in 1986. The present revision
incorporates the following major changes:
a) Inclusion of 168'3 mm outside diameter pipe,
b) Criteria for calculating the nominal thickness has been modified, and
c) Criteria for selecting protective coatings has been modified,
In the formulation of this code due weightage has been given to international co-ordination among
standards and practices prevailing in different countries in addition to relating it to the practices in the
field in thls country. This has been met by deriving assistance from the following standards:
BS CP 8010-1981 'Code of practice for pipelines' British Standards Institution.
BS CP 2010 ( Part 2 ) 'Pipelines: Part 2 Design and construction of steel pipelines in land' British
Standards Institution.
The Committee responsible for the preparation of this standard is given in Annex C.
IS 5822 : 1994
Indian Standard
CODE OF PRACTICE FOR LAYING OF
ELECTRICALLY WELDED STEEL PIPES FOR
WATER SUPPLY
( Second Revision)
1 SCOl)E is recommended, but it may be modified to suit local
conditions by taking necessary precautions. The trench
1.1 This code covers the methods of laying electrical1y
shaH be shored, wherever necessary, and kept dry so
welded mild steel pipes of outside diameters 168.3 mIll
that the workman may work therein safely, and effi-
102 032mm (as covered in IS 3589: 199i), laid either
ciently. The discharge of the trench dewatering pumps
above ground or underground for water supply.
shall be conveyed either to drainage chalUlels or to
1.2 For the purpose of this code, electrically welded I.latuml drains, and shall not be allowed to be spread in
steel pipes shall conform to IS 3589': 1991; mild steel the vicinity of the worksite.
plates to [S 2062 :1992 and welding electrodes to IS
814: 1991. 4.2.1 Trenching
2 I{EFJ~RENCES Trenching includes all excavation which is carried out
by hand or by machine. The width of the trench shall
2.1 The Indian Standards listed in Almex A are neccs- be kept to a minimum consistent with the working space
sary adjuncts to this standard. required. At the bottom between the faces, it shall be
3 CLEARING THE SITE such as to provide not less than 200 nun clearance on
either side of the pipe. Each (.'ase should, however, be
3.1 Preliminary work required to be done bcfore pipe
considered on its merits, having regard to the safety of
laying is st:trted, includes pegging out, dearing and
the trench, the method of laying and jointing the pipe
disposal of all shmb, grass, large cllld small hushes,
and the need to avoid damage to pipe, coating. The
trees, hedges, fences, gates, portions of old masonry
bottom of the trench shall be properly trimmed to
a nd debris from the route.
permit even bedding of the pipeline. For pipes larger
3.2 Where trees have bcen felled, the resulting timber than I 200 mm diameter in earth and murulll the curva-
shall be stilcked properly and disposed off, as dire(~ted ture of the bottom of the trench should match the
by the fluthority. Tree roots within a distance of about curvature of the pipe as far as possible, subtending an
half metre from the side of the pipeline shall be angle of about 1200 at the centre of the pipe, as shown
removed or killed. in Fig. 1A. Where rock or boulders are encountered, the
3.3 All othcr serviceable materials, such as wood work, trench shall be trimmed to a depth ofat least 100 mm
bricks and masonry, recovered during the operation of below the level at which the bottom of the barrel of the
clearing the site shall be separately stacked and dis- pipe is to be laid and filled to a like depth with lean
posed off, as directed by the authority. cement concrete orwith non-compressible material like
NOTE - For the purpose of this code, authority may be sand of adequate depth to give the curved seating, as
an individual, an official, a board, a department or an shown in Fig. 1B and Fig. 1C. '
agency established and authorized by the Union or State
Government or any statutory body created by law who 4.2.2 Pits for Joints
undertakes to admi nister and enforce the provisions of
When welding is to be carried out with the pipe in the
Ihis code as ndopted or nmended.
trench, additional excavation of not more than 600 nun
4 FORMATION in depth and 900 mm in length should he provided all
4.1 GelleR"al round the pipe at th~ position of the joints for facilities
of welding.
Before pipeline is laid, proper fortliation shall be
prepared. For buried pipeline, suitable trenches should 4.2.3 Special Foundations in Poor Soil
be excavated, pipeline above ground may be laid in
<lutting or on embankments or be supported by pillars Where the bottom of the trench at subgrade is found to
as the case may be. consist of material which is un:;table to such a degree
that,; in the opinion of the authority, it cannot be
4.2 Excavation and Preparation of Trenches for removed and replaced with an approved material
Laying Underground Pipeline thoroughly compacted in place to support the pipe
The trench shall be so dug that the pipe may he laid to properly, a suitable foundation for the pipe, consisting
the required aligmnent and at required depth. When the of piling, timbers or other matcri<t Is, in ac<,'ordan(~c with
pipeline is under a roadway, a minimum cover of 1.0 m plans prepared by the authority, shall he constructed.
IS 5822 : 1994
100mm
2
IS S822 : 1994
be dosed in such a manner that it causes the least 4.3 Preparation of Formation for Pipeline Above
interruption to the traffic. Where it is necessary for Ground
traffic to cross open trenches, suitable bridges shall be
Formation should be prepared by cutting high grounds
provided.
and filling in low areas. Care shall be taken while fixing
4.2.10.1 Suitable signs indicating that a'street is closed the a ligmnent and gradient of the pipeline, to balance
shall be placed and necessary detour signs for the the cutting and filJing quantities, as far as possible, with
proper maintenance of traffic shall be provided. minimum of lead. Care should also be taken to ensure
that the pipe rests fully either on cutting or on bank.
4.2.11 Structure Protection
4.3.1 Cutting High Grounds
Temporary support, adequate protection and main-
tenance of all underground and surface structures, Excavation for the formation in cutting should be done
drains, sewers and other obstruction encountered in the iR"such a manner as to obtain sufficient width at the
progress of the work shall be furnished under the direc- bollom to accommodate the pipeline, itfi supports, a
tion of the authority. The structures which may have service passage and side drains. The sides of the cutting
been disturbed shall be restored upon completion of the should generally have the following slopes:
work. a) Earth MURUM and boulders 1: 1
b) Hard MURUM and soft rocks 1/2: 1
4.2.12 Protection of Property
c) Hard rock 1/4 :1
Tress, shrubbery fences, poles and all other property
All excavated material shall be the property of the
shall be protected unless their removal is shown on the
authority and shall be stacked or disposed off as
drawings or authorized by the authority. When it is
directed under 4.2 above. Typical sections in cuttings
necessary to cut roots and tree branches; such cutting
are shown in Fig. 2 and 3.
shall be done under the supervision apd direction of the
authority. 4.3.2 Preparation of Embankment
Material used for embankment shall be spread in
4.2.13 Avoidance of the Existing Service
horizontal layers not more than 300 mm thick. Each
As far as possible, the pipeline shall be laid below layer shaH be consolidated by watering, ramming and
existing services, such as water and gas pipes, cables, rolJing before the next layer is laid. Mechanical con-
cable ducts and drains but not below sewers, which are solidation is recommended. The consolidation obtained
usually laid at great depth; if it is unavoidable pipeline shall not be less than 90 percent of the proctor density
should he suitably protet'ted. A minimum clearance of [ see IS 2720 (Part 7) : 1980 ]. Any wash-outs during
150 mm shall be provided between the pipeline and rains shall be replaced with suitable material. The em-
such other services. Where thrust or auger boring is bankment shall be finished to the correct dimensions
used for laying pipeline across roads, railways or other and gradient prescribed by the authority. If banking is
utilities, larger clearance as required by the authority to be done on the sloping ground or on elilbankment, it
shall be provided. Adequate arrangements shall be shan be cut in steps of not less than 300 mm deep and
made to protect and support the other services during 450 mm wide to give a proper bond. Side slopes of the
laying operations. The pipeJine shall be so laid as not embankment shall be steeper than 1 1/2 horizontal to 1 .
to obstruct access to the other services for inspection, vertical. The slopes of emba nkment should be protected
repair and replacement. When such utilities are met by pitching or any other method, if so required by the
with during excavation, the authority concerned shall authority.
be intimated and arrangements made to support the 4.3.2.1 Width of embankment
utilities in consultation with them.
The width of the embankment at top shall be such as to
ORIGINAL GROUND
3
IS 5822 : 1994
accommodate the pipeline and the service passage. menced, some preliminary work described in 5.2.1
Typkal section of the bank is shownin Fig. 4. to 5.2.5 sha II be done.
4
IS 5822 : 1994
6 WELDING to be done in the trench, the pipe may be lowered in the
trench on supports sufficiently high so as to facilitate
6.1 General
out-coating. The pipe should bc lowered progressively
The welding of pipes in the field should comply with with the help of shear legs or cranes using wide belts or
IS 816 : 1969. Electrodes used for welding should slings. In case of coated pipes, extra (.'a re sha II be taken
comply with IS ~n4: 1991. to preserve the cOIlting while lowering. Slings may be
6.2 Testing or Welded Joints removed progressively without the necessity of digging
under the pipe. Where the trench is sheeted, the pipes
The welded joints shall be tested in accordance with shaH be lowered into the trench by removing at a time,
procedure laid down in IS 3600 (Part 1 ): 1985. One one or two struts only, care being taken to see that no
test specimen taken [rom at least one field joint out of part of the shoring is disturbed or damaged. If neces-
any to shall be subjected to test. sary, additional struts may be fixed during lowering.
6.2.1 If the results of the tensile test do not confonn to Mter the pipe is lowered, it shall be laid in correct line
the rcquirements specified, retests of two additional and level by use of leveJling instruments, sight rails,
specilllcn from the same section shall be made, each of theodolites, etc. Care shall be taken to see that the
which shall conform to the required spedfications. In longitudinal joints of the consecutive pipes are stag-
cflse of railure of olle ortwo, extensive gouging (scoop- gered by at least 30° and should be kept in upper third
ing out) illld repairing shall be carried out as directed of the pipeline, if there are two longitudinal joints they
by the authority. should be on the sides. While assembling, the pipe faces
6.2.2 If internal pressures exceed 1.5 N/mm 2, special shall be brought close enough to leave a unifonn gap
attention should he given to the assembly of the pipe not exceeding 3 mm. The spiders from inside and
and first run of weld. Non-destructive testing of the tightening rings from outside or other suitable equip-
completed weld may be carried out on pipelines by ment should be used to keep the two faces in shape and
rtldiognlphic (see IS 4853: 1982 )or ultrasonic method position till at least one run of weld ing is ca rried out.
( see IS 4260 : 19~6 ) as agreed upon between the user 8.1.2.1 The pipe faces shaH first be t?ck-weJded alter-
and the manufacturer. ' natelyat one or more diametrically opposite pairs of
points. After completing tack-welding, fuJI welding
6.3 Welding of Closure Gaps
shaH be carried out in suitable runs following a se-
Final welding of closure gaps should be carried out quence of welding portions of segments diametrically
wi,thin fI temperature range of average air tempenlture opposite.
± 8°C; For huried pipelines final welding may hest be 8.2 Backfilling
done after intennediate pipes have been backfilled.
Backfilling should closely follow the welding of joints
7 BlANK FLANGES of the pipe so that the prc)lrl'live coating should not be
subsequently damaged. Material hannful to the pipe-
7.1 Blank flanges shall be uscd at all ends left unat-
line shall not be used for backfilling. Refilling shall be
tended al the tempomry closure ofwork.,BJank flanges
done in layers not exceeding 300 mm. Each layer shaH
may ;t1so he necessary for commissioning a section of
be consolidated hy watering and ramming, care being
the pipeline or for testing the pipelille laid. For telll-
taken to prevent damage to the pipeline. The filling on
pom ry closures, non-pressure blank 11a nges consisting
the two sides of lhe pipeline should be carried out
of mild steel pliltcs tack-welded at the pipe ends may
simultaneously.
he used. For pipes subjected to pressu~s, the blank
n(lngcs should be suitably designed. To prevent the 8.2.1 The spiders provided during assembly and weld-
floating of pipes, care should be taken to see that empty ing shall be retained until the trench is refilled and
pipes wilh ends blank flanged should not be left in consolidated. Where timbers are pJaceu under the
uncovered trenches, where water is iikely to accumu- pipeline to aid alignment, these shall be remove.tI before
laic. hackfilling. For further precautions and use of material
in backfilling, reference should be made to IS 3114 :
8 IllitE LAYING 1994.
8.1 Lnying ()f Pipes Underground 8.3 Layi'ng of Pipes Ahove Ground
8.1.1 General 8.3.1 General
The procedure for trenching as described in 4.2 The procedure for handling the pipes as described in 5
and 4.2.1 shall be carefully foHowed. Before the pipe and for lowering and assembling the pipes underground
is lowered, the trench shall be carefully examined to as descrihed in 8.1.2 should be followed for lifting and
determinc that an even bedding is provided for the laying the pipes on supports or on ground. The pipeline
pipeline (lnd that the pipe may be lowered into itwithout may be allowed to rest on ground· if the soil is
damaging the coating. non-aggressive. The ground should, however, be
8.1.2 Lowering and Assembling of Pipes and Specials dressed to match the curvature of the pipe shell for an
arch length subtending an angle of 1200 at the centre
The procedure for lowering varies with the method of pipes. Alternatively, the pipeline should be laid either
adopted for. coating the pipeline. Where the coating is on saddle or roller and rocker supports as specified by
5
IS 5822 : 1994
the authority. Figures 5 and 6 show supports general1y railway or a river shan be determined so as to satisfy
adopted on steel pipelines. the requirements of the authority concerned.
10 BRANCH CONNECTIONS, SPECIALS, ETC
10.1 Complicated specials, such as 'V' pieces, com-
posite bends and tapcrs~ shaH be fabricated in
worklihop. SmalJ branches, single piece bends, etc, may
be fabricated at site, care being taken to ensure that the
fabricated fittings have at least the same strength as the
pipeJine to which these are to be joined.
10.2 Appurtenances
The spacing of the isolating sluice valves along a
pipe line depends upon the type of terrain through which
GL
the pipeline passes and the operational flexibility re-
quired. Valves may be positioned as follows:
FIG. 5 SADDLE SUPPORT a) At the beginning and at the end of the pipeline;
8.3.2 Expansion Joints b) To facilitate hydraulic testing of sections or the
For aU pipelines laid above ground, provision for pipeline;
expansion and contraction on account of temperature c) For long pipelines, isolating valves should be
va riation should be made either by providing expansion provided at intervals not exceeding 6 km; and
joints at predetermined intervals or by providing loops d) On either side of a major crossing.
where leakage through expansion joints cannot be per- Valves may be located either above ground or below
mitted. Where expansion joints are provided, it is ground, but should be' easily accessible (see IS 780 :
necessary to create restraining points on the pipeline to 1984 a nd IS 2906 : 1984).
ensure proper functioning of these joints. The pipe
laying work should preferably start from the restrained 10.2.1 Control valves should be provided on all
points on either side working towards centre where the branches. Similarly, air valves at all humps and scour
expansionjointshould be fitted last. Spacingofexpan- valves at all dips are necessary. For inspection pur-
sion joint depends on local conditions. Provision· of poses, man-holes may be provi,ded on either side of
expansion joint at intervals of 300 m'onexposed steel isolating valve and at other suitable places.
pipeline is generally recommended. Expansion joints 10.2.2 Protective devices, such as relief valves, surge
should always be provided between two fixed supports or break pressure stations, may be provided to ensure
or anchorages (see 8.3.3). that the internal pressure at any point in the pipeline
8.3· A.nchorages does not exceed the design pressure.
The pipe shall be anchored by concrete anchor blocks 10.2.3 Pressure indicating the flow recording instru-
orother means to resist unbalanced water pressures and ments and burst alarms should also be provided at
temperature stresses. Provision should be made to suitable places.
anchor the main during construction and in service 11 TESTING OF PIPELINE
where floatation could occur.
H.l General
9 ROAD, RAIL AND RIVER CROSSING
Before putting it into commission, the welded pipeline
9.1 The mode of laying the pipeline crossing, rop-d, shall be tested both for its strength and leakage.
STOOL
ROLLER OR
ROCkER
GL
7
IS 5822 : 1994
interiors, both before and during construction each of flushing and commissioning, reliable communication
Ihem should he inspected and, if necessary, cleaned system between both ends of the section of the
before i nsltl lIatioll. pipeline being dealt with as well as .between the field
13.1.3 After pressure testing the main, it should be partics in between these sections should be established.
n~lshed with water of sufficient velocity to remove a1l
15 REMOVAL, RESTORATION AND MAIN-
dirt and other foreign materials. When this process has TENANCE OF PAVED.~OOTJ-ATHS, AFTER
hec~l l'omplet~d, disinfection (using liquid chlorine,
sodium orcalclUm hypol'hlorite)shouJd proceed byone
LAYING OFPU-E
of the recommended methods as described in 13.2 15.1 Allowable Removal of I)avement
and 13.3.
Pavement and road surfaces may he removed as a part
13.2 Continuous I;'eed of the trench eXl'avatioll, andthe amount removed shall
In this method, water from the distribution system or depend upon the width of trench specified for the
other approved source and the chlorine is fed at consta nt instalJation of the pipe and the width and length of the
rate into the Hew main at a concentration of at least 20 pavement area required to be removed for the installa-
mg/1. A properly adjusted hypochlorite solution in· tion of gate valves, specials, man-holes or other struc-
fllrcs. The width of pavement removed along the
jectc~ in~o .the m~in with a ~yp()~h)orinator, or liquid
chJonne IllJected mlo the mam through a solution·feed nonnal trench for the installation of the pipe shaH not
chlorinator (Illd booster pump may be used. The exceed the width of the trench specified by more than
chlorine residua) should be checked at intervals to 150 mm on eal~h side of the trench. The width and
ensure that the proper level is maintained. Chlorine lengths of the area of pavement removed for the insta I·
applkfltion should continue until the entire main is lation of gate valves, specials, man-holes or other struc-
filled. All valves, hydrants, etc, along the main should tures shaJlnot exceed the maximum linear dimensions
be operated to ensure their proper disinfection. The of such structures by more than 150 nun on each side.
~~erever in the opinion of the authority, existing con·
water should remain in the main fora minimum of
24 h. ~ollm,~ing the 24 hours period no less than 10 lUg/I dltlOllS make it necessary or advisable to remove addi-
chJonne reSidual should remain in the main. tional pavement, it shall be removed as dirccted by the
authority.
13.3 Slug Method
15.2 Replacement of Pavements and Stnlctures
In this method a continuous flow of water is fed with a
l'onsta!lt dose of l~hlorj~le (as in the previous method) AJI pavements, paved footpaths, curbing, gutters,
hut With rates proportioned to give a chlorine can· shrubbery, fenccs, poles, sods or other property and
cent~alion of at least 3?O mgtl. The chlorine is applied
surface structures removed or distllrhed as a part of the
contmuously for a period of time to provide a column work shall be restored to a condition equal to that before
of chlorinated water that contacts all interior surfaces the work began, furnishing a1l lalxlUr and materials
of the main for a period or at least3 h. A'i the slug passes incidental thereto. In restoring the pavement, sound
tees, crosses, etc, proper valves shall be operated to granite hloc.ks, sound brick or asphalt paving bloc.ks
ensure their di~il1.fection. !his method is lIsed principal· may he re·lIsed. No permanent pavement shall be res-
Iy for large. dIameter maills where continuous fced is tored unless and until in the opinion of the authority, the
illlpmcticai. condition of the backfill is such as to properly support
the pavement.
13.4 Regilf~less of the method used, it is necessary to
ma ke ccrtaJll that backflow of the strong chlorine solu· 15.3 Cleaning-Up
lion into t~e supplying line does not occur. Following
the presl'fJbed contact period, the chlorinated water AJI surplus water main materials and aJJ tools and
should be flushed to waste until the remaining water temporary stmctures shall be removed from the site as
has a chloril~e ·residual approximating that throughout directed by the authority. AI) dirt, rubbish, and excess
the r~st of the system. Bacteri(llogical tests as earth from th~ exc~vati~n sha II be hauled to a dump and
p.r:esl~ribed by the authorities should be taken and if the
the ('onstructlon site left dean to the satisfaction of the
·results fail to meet minimulll standards, the disinfecting authority.
procedure should be repeated and the results again 16 HESIGN REQUIREMENTS
tested before placing the main in sl'rvil'e.
16.1 General Design Re(luirements
14 COMMUNICATIONS
~ner~J requirements. f()r the design of steel pipes are
14.1 During all phases of deaning, testing, disinfecting, given III Annex B for mformation.
8
IS 5822 : 1994
ANNEXA
( Clause 2.1 )
ANNEXB
(Clause 16.1 )
to
IS 5822 : 1994
sunrdYS, undergoes variation in length as well as in 12 = maximum or minimum operating tempera-
diameters. The diametrical expansion or contraction of • ture in °c,
the pipe is generally small and it may be neglected for
the purposes of design. The linear ex'pansion in a pipe 11 temperatl1re at the time of installation in
line is given by the expression: °c,
dl = I . oc • L m = Poisson's ratio, and
where fll = hoop stress due to water in N/nllu2.
dl = variation in.1ength in mm, B·12 DESIGN REQUIREMENTS FOR
temperature variation, in °C, FLEXIBILITY AND BENDING
oc = linear coefficient of expansion in B-12.1 The physical constants for the steel for pipeline
mm/ nuu/oC, and shaU be as follows:
L length between fixed point and free end in a) Coefficient of Expansion - The linear coefficient
mm. of thennal expam~iol\ for mild steel may be taken
as 12 x 10-6/°C forte,mperature up to 120 oC.
U-U.1.1 Expansion joint'i are generally provided on
the above ground pipeline which absorb the elongation b) Modulus of elasticity as 0.2 x 106 N/mm 2, and
or contraction of the pipe by telescopic movement of c) Poisson's rtltio as 0.3 for steel.
ilmcr and outcr gland of the expansion joint. Provision
of expansion joint thus releases the pipeline of thermal B·IJI)IPE SUPPORTS
stresses. The relief is not, however, complete as some
amount of restraint on the free movement of the pipe B-IJ.l General
line is always present due to frictional force developed The stresses transmitted to the connected equipment,
within the expansion joint'proper and at tbe supporting ]ike valves' should be kept within safe limits.
system of the pipeline, which depends UpOR the type of
support adopted. The frictional force developed within 8·1J.2 Supports
the expansion joints is given by the expression. Supports should be designed to support the pipeline
F e =mx3.14xdxBxp without causing excessive local stresses. Due al-
(Skoctiich expression) ]owance shall be made for the weight of water, hydros-
where tatic head, frictional resistance at the supports, etc.
Proper bearing surface, such as flat base, roller and
Fe = axial force in N, rocker, should be provided where controJled move-
m = coefficient of friction =n.3, ments are required.
d = diameter of pipe in mm,
8·14 USE OF ANCHORS BLOCKS ON THE
B = width of packing in mm, and
PIPELINE
P internal pressure in N/nlln2.
8-14.1 Anchorages
OR
Fe = P X F + A.p ......... (American practice) Anchors a re provided on the pipeline at the position of
]ine valves or sectionalizing valves, at the blank flange,
where at the t,apers and at the mid-point between two consecu-
Fe axial force in N, tive ~xpansion joints, in the case of above ground
P 3t X a = circumference of pipe shell in nun, pipeline. These anchors are generaJly of gravity type
F 7.43 N/mm of circumferencl-, and should be designed to resist the axial forces due·to
maximum design hydraulic pressure, frictional resis-'
A :: cross-sectional area of shell in mm2 , and tance setup atthe expansion joint, and atJhe supporting
p = internal pressure in N/nuu 2. system, for their worst combination S6 that the pipe
shell is completely relieved of stresses resulted from the
U-U.2 Restrained )ipelille a hove forces.
InpipeJille laid'above ground where the movement due
to ,temperature variation, calmot be accommodated B-14.1.1 The anchors provided at the mid-point be-
either in expansionjoint'i or loops, full provision for the tween the two consecutive expa nsion joints, fixity
longitudinal compression stress due to axial force points may be frame type in which case an
the axial
caused by temperature rise should be made in accord- forces acting on the pipeline are carried hy the frame
ancewith the expression: consisting of one or more pair of supports and the
pipeline, by shear and bending.
Fe = E xL (/ 2 - 11) - m .171
where B-14.2 Anchor Blocks
E = n~odulus of elasticity in Nlmm ,
2
Anchor blocks shall be designed in aCl~ordance will
L = linear coefficient of expansion, IS 5330 : 1984.
11
IS 5822 : 1994
ANNEXC
(Foreword)
COMMITTEE COMJ)OSITION
Water Supply and Sanitation Sectiollal Committee, CED 24
Chairman Representing
StlRI V. H. PATH, In personal capacity (J 28 M(lnakbag Society, Ambawadi, Ahmedabad)
Members
ADVISER (PI-IE) Central Public Health & Environmental Engineering Organization, Ministry
of Urban Development, New Delhi
DEI'lffY ADVISER (PI-IE) (Alternate)
:;1IR1 M. S. AsNANI Public Works Department, Delhi Administration
SURVBYOROF WORKS III (Alternale)
~1IR1 AVAOHESH KUMAR Tata Consulting Engineers, Bombay
S. GAONKAR (Alternate)
DR
511RII. S. BAWEJA Public Health Engineering Department, Madhya Pradesh
SURd. N. OmsE (Alternate)
CIIIF.F ENGINEER (PPRD) U. P. Jal Nigam, Lucknow
SIIRI V. K. GUPTA (Alfernale)
SIIRI J. D. Owz In personal capacity (B/5BA Gangotri Enclave, Alaknanda, New Dellll)
SURI S. G. DEOLAUKER In personal capacity (Flat No. 403, Savitri Cinema Commercial Complex,
New Delhi)
SURI DBVENDRA SINGH In personal C<1pacity (Anne\"e Building, 2nd Floor, DD-J, Kalkaji Extension,
New Delhi)
SURI H. G. GAR(i Haryaila Public Works Department, Chandigarh
SURI S. S. BOLA (Alternate)
HYDRAULIC ENGINEER Municipal Corporation of Greater Bombay
CHIEF EN(iINEER (Si-wERMiE PROJECTS)
( Alternate- )
SURI F. LAL KANSAL Public Works Department, Public Health, Patiala (Punjab)
SHRI M. M. KApOOR Engineers India Limited, New Delhi
SHRI RANA PRATAP (Alternate)
SHRI LALlAN PRASAD The Institution of Engineers India, Calcutta
SIIRI B. A. MALLVA Northern Railway Headquarters, New Delhi
MANAOING DIRECIOR Punjab Water Supply & Sewerage Board, Chandigarh
DR V. A. MIIAISALKAR National Environmental Engineering Research Institute (CSIR), Maharashtra
SIIR' A. K. SEnl (Alternate)
SI-tRi S. R. MUKHERJEE Metropolitan Development Authority, Calcutta (West Bengal)
SUR) A. K.
DU1TA (Alternate)
SHRI R. NATARAJAN Hindustan Dore, Oliver (India) Ltd, New Delhi
SURI B. P. MISHRA (Allernate )
PROF K. J. NAnt All India Institute of Hygiene and Public Health, Calcutta
SHRI D. GUIN (Alternale)
SIIRI SISIR K. NEAGI Institutional Public He-11th Engineers, C,1Icutt:1
SURd. P. GUPTA (Alternate)
COL H. S. PAUL Directorate of Designs, Engineer-in-Chief's Branch, Army Headquarters,
MAJ B. DAS (Alternate) New Delhi
SURI T. RAMACHANDRAN Madras Metropolitan Water Supply and Sewage Board, Tamil Nadu
SIIRI K. NAGRAJAN (Alternate)
SIIRI S. PRAKASH Delhi Water Supply & Sewage Disposal Undertaking, Delhi
SIIR) S. S. ClIADHA ( Alternate)
SECRE1J\RY India Water Works Association, Bombay
SUR! L. R. SEUGAL L. R. Sehgal & C-o, New Delhi
SIIR! S. K. SHARMA Central Building Research Institute (CSIR), Roorkee
SIIR! S. S. SRIVASTAVA U. P. Jal Nigam, Lucknow
SHRI V. K. GUPTA ( Alternate)
( Continued on page 13 )
12
IS 5822 : 1994
Members Representing
SUPERINTENDING ENGINEER (DCC) IV Central Public Works Department, New De!hi
SURVEYOROFWORKS (DCC) IV
(Alternate)
SIIRI B. N. TAVAGARAJA Bangalore Water Supply & Sewage Board, Karnataka
SIIRI H. S. PlnTAKEMPANNA (Alternate)
SIIR! S. V. WAGH Maharashtra Water Supply & Sewage Project, Thane, Maharashtra
SURI S. V. SHELKlKAR (Alternate)
SHRIJ. VENKATARAMAN, Director General, BlS (Ex-officio Member)
Director ( Civ Engg )
Member Secretary
HEMANT KUMAR
Joint Director ( Civ Engg ). HIS
13
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
,
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1