Professional Documents
Culture Documents
Loss Expense CPD Slides PDF
Loss Expense CPD Slides PDF
Introduction
Loss & Expense Procedures and Causes
Parties obligations relating to the subject
Why is it paid?
➢ It is paid by the client in order to put the Contractor’s
cash position back to where it would have been if the
Breach of Contract did not arise.
Extension of Time
➢ Relevant Events:
➢ Neutral Relevant events
Relevant events:
Relevant matters:
How is it calculated?
Procedures
Reference
The
to
Relevant
documents
Matter
and records
Supporting
The Cause
information
and Effect
(if available)
Loss & Expense – Top Tip
Why is it paid?
Typically Heads of Claim include:
➢ Acceleration Procedures
➢ Increased Costs
➢ Disruption Costs
➢ Finance Charges
➢ Subcontractor Claims
Loss & Expense
Acceleration Procedures
➢ Client fault
➢ Contractor fault
➢ Critical path analysis
Loss & Expense
Critical path analysis
Loss & Expense
Preliminaries are:
People and facilities required to carry out the works
➢ Site Manager
➢ Site Huts
➢ Tower Crane
➢ Temporary Electrics
➢ Welfare Facilities
For example:
Delay of 6 weeks =
➢ Site Manager x 6 weeks
Etc, etc…
Loss & Expense
For example :-
► Architect issues 100 variations for finishes in 2 week period
► Major changes
► Therefore additional Site Manager brought in to manage that
process and those changes
Cause & Effect Schedules are ideal for demonstrating Loss & Expense
Loss & Expense
► Emden ► Eichleay
Loss & Expense
Emden Formula
h x c x pd = Claim Amount
100 cp
► cp = Contract Period
► pd = Period of Delay
Loss & Expense
Hudson Formula
Eichleay Formula
Top Tip
Contractor can do this by producing invitations
to tender and letters declining the tenders, as
there was not enough resources available.
Loss & Expense
Increased Costs
► He would have purchased an item in 2015 for £10 and then due
to delays he purchased it in 2016 for £11.
Disruption Costs
► Out of sequence working
► Return visits
► Trade congestion
Finance Charges
► Bank charges,
► loss of bank interest etc.
How can the subcontractor
prove cause and effect?
Subcontractor Claims
Records
Loss & Expense
Demonstration
Thanks for
attending!
Please visit academy.rics.org to find out what else RICS Training can offer you