UTMN-2094 04JUNE Progress Report

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

UTMN-2094 FLOW LINE WEEKLY UPDATE

P.O ISSUE DATE : MCC DATE : CUT OF DATE : 04-JUNE-2020


TOTAL
TOTAL PREVIOUS WEEK THIS WEEK COMPLETED
SL.NO ACTIVITY QUANTITY UNIT QTY QUANTITY QUANTITY

1 RIGHT OF WAY 3398 LM 3200

2 FLOW LINE EXCAVATION 3398 LM 130 3360

3 FLOW LINE WELDING 283 JOINTS 3 239

4 EXTERNAL GIRTH WELD COATING 283 JOINTS 49 61 110

5 MARL ROAD CROSSINGS 5 EACH 20% 20%

6 ASPHALT ROAD CROSSING 1 EACH

7 UNDER GROUND P/L CROSSINGS 4 EACH Excavation 100%

8 POD CROSSINGS 5 EACH Excavation 100% Excavation 100%

9 PIPE LOWERING 3398 LM 1060 1060

10 CP SINGLE PIN TERMINALS 3 EACH

11 CP BONDING BOX INSTALLATION 5 EACH

12 KM MARKER INSTALLATION 3 EACH

13 PIPE MOVEMENT MARKER 4 EACH

14 WARNING BOARD 10 EACH

15 BACK FILLING 3398 LM 200 200

16 BERMING 3398 LM

REQUIREMENT NOTIFICATION

QTY CONFIRM QTY APPROVED


BY SITE BY ENGINEERING
SL.NO ITEMS REQUIRED DATE SIZE QUANTITY ENGINEER HEAD

SUB CONTRACTOR INCHARGE