CALCULATION SHEET

Sub: Name of Work: Detail design, 3D monitoring, Geo Technical Investigation and construction
supervision including Instrumentation of single line BG Tunnel No-1 to 4 (approx. length 1000m)
between Gouripur to Abhayapuri in connection with construction of New line between NMX-JPZ.

Agency: M/s. Beaver Infra Consultants Pvt.Ltd.,


CA No:CON/NMX-JPZ/2338 dtd. 03.05.2017.

Schedule-C
1. At Sl.No:1 – 1. Tunnel Construction Engineer, Local
At Tunnel-1 = 1x1months = 1
At Tunnel-2 = 1x3 months = 3
At Tunnel-4 = 1x3 months = 3
Total = 7 nos.
3. At Sl.No:3 – Resident Geologist, Local,
At Tunnel-2 = 1x2 months = 2
At Tunnel-4 = 1x2 months = 2
Total = 4 nos

5. At Sl.No:5 – Senior Survey & Instrumentation Engineer.


At Tunnel-1 = 1x1months = 1
At Tunnel-2 = 1x3 months = 3
At Tunnel-4 = 1x3 months = 3
Total = 7 nos.

Schedule-E

5. Sl.No:5 – Monitoring, observing and recording the measurements


At Tunnel-1 = 1 faces x 1 months = 1
At Tunnel-2 = 2 faces x 3 months = 6
At Tunnel-4 = 2 faces x 3 months = 6
Total = 13.

Schedule-F
2. Sl.No:2 – Monitoring /Installation Engineer for Instruments
At Tunnel-1 = 1x1 month = 1
At Tunnel-2 = 1x3 months = 3
At Tunnel-4 = 1x3 months = 3
Total = 7 nos

5. Sl.No:5 – Site Assistant


(1 site assistant for Surveyor team and 1 site assistant for Instrumentation team)
At Tunnel-1 = 2x1months = 2
At Tunnel-2 = 2x3 months = 6
At Tunnel-4 = 2x3 months = 6
Total = 14 nos.

6. Sl.No: 6 – Transportation of Survey team


At Tunnel-2 = 1x2 months = 2
At Tunnel-4 = 1x2 months = 2
Total = 4 nos

SSE/W/CON/JPZ XEN/CON/JPZ Dy.CE/CON/JPZ