plants
Presented by:
Lucy Wanjiku M. (B. Tech Production Engineering)
Grad. Engineer IEK; EBK
Engineering Director
ECOCYCLE LTD, Kenya
www.ecocycle.co.ke
WWTP layout
SBR(Sequential Batch Reactor)Treatment process
• Sludge is enriched with oxygen to set in motion a biological process. The plant
features a pre-treatment coarse catch tank , a buffer tank, the reactor and an optional
storage tank. The plate diffusers, sludge- and Clearwater disposal are driven by an air
pressure system.
Treatment Phase:
Settling Phase: Clear Water
The effluent is
Loading Phase: The settling phase Disposal Phase:
intermittently
From the pre- takes about 75 min. In this phase the
enriched with oxygen
treatment chamber During this time the treated water is
which leads to a high
the effluent devoid activated sludge pumped out
concentration of
of coarse materials begins to settle at the into storage tank or
micro
is pumped into the bottom of the tank. nature e.g. into an
organisms. These
reactor. Treated, clear water infiltration bed, a
form the basis for
remains above the Canal or stream.
the biological
settled sludge.
treatment.
Biological Oxygen Demand
• Dissolved or suspended oxidizable organic material in wastewater is a food source for
micro-organisms.
• Digestion of this food requires oxygen. The oxygen content of the water will ultimately
be decreased by the amount required to digest the dissolved or suspended food.
• The so-called 5-day BOD measures the amount of oxygen consumed by biochemical
oxidation of waste contaminants in a 5-day period.
• The BOD value is expressed in milligrams of oxygen consumed per litre of sample during
5 days of incubation at 20 °C .
Rating ranges between 80 Watts -380 watts , Rating ranges between 0.55 Kw – 7.8 Kw, 3-Phase at
Single phase at 50Hz; depending on the liters of 50Hz; depending on the liters of sewage to be treated per
sewage to be treated per day day
Air Lift Pumping- no submersible pumps
NO PUMPS…
Air Lift pumping Mechanism_ filling
AERATION PROCESS
Excavation
Klaermax WWTP Tank Construction –
Small scale
WWTP layout & Control cabinet Location –
small scale
Control panel Mounting & finishing:-
• Boundary wall
• Free standing pillar
• House Wall.
• Creeping plants
• Encasing
WWTP layout & Control cabinet Location-
Large scale
Klaermax WWTP Monthly Power Costs _
Residential unit
Rating: 80- 360 watts.
Take an average home with 16 People; Blower rating is 120 watts.
Due to the PLC controls, only 10 hours in a day actively consume power.
Daily power consumption = 120 watts x 10 hours = 1200 watts i.e. =1.2Kwh
Irrigation
Firefighting
Dust suppression
A R
C
System installed at a home
System installed at a gated community–
Fair acres villas Nairobi
Why Recycle?
To avoid this…..