Accomplishment Report - MAR16-21,2020

You might also like

Download as rtf, pdf, or txt
Download as rtf, pdf, or txt
You are on page 1of 1

Digee Glass and Aluminum Co.

STRUCTURAL DESIGN DEPARTMENT


ACCOMPLISHMENT REPORT
for the 3rd week of MARCH
(March 16-21, 2020)
CHECK IF APPROVED
REMARKS
DATE SUBMITTED
DATE RECEIVED
SUBMISSION DATE
TASK
PROJECT NAME
1

Delay was caused because task was initially finished on March 17, 2020 in the evening, then correction and revision was made in the morning of March 18, 2020.
March 18, 2020
March 16, 2020
March 17, 2020
3-TORRE Lorenzo
Design of Interior Glass Partition due to revision
2

Delayed because of the delay made by the first task and confirmation from the Engineering of the profile to be used.
March 20, 2020
March 16, 2020
March 18, 2020
BELMONT HOTEL - Iloilo
Summary Report - for Bidding
3

-
March 19, 2020
March 19, 2020
March 19, 2020
AGS
Checking the Shop Drawing of AGS - Curtain Wall and Sliding Door for PMU
Prepared by:
Date Submitted:
LEMUEL D. GULTIANO
March 21, 2020
Jr. Structural Engineer
Noted and Approved by:
KIMBERLY BAYHON HENSON
Structural Design Manager

You might also like