DETAILS IN SUPPORTS OF DO NO 1

CA No :- CWE (M) -31 of 2016-2017


Name of Work :- Special repairs to toilet and bathrooms at Bldg No P-3 of BI line at Colaba under GE (W) Colaba, Mumbai
Name of Contractor :- M/s Ashok Construction.
Brief Description of DO :- Addition of certain new items under Schedule 'A' Part -I

Add Portion
Ser Description of Items Unit Qty Ser Item Rate per Amount Remarks
No Unit
1 S&F for mild steel work medium weight of any Kg 1802.92 Sr No 1 74.43 134191.3356 Star Rate
section equal/ unequal MS angle or MS Flats No-1
including fabrication and errection complete in
purlins and rafter fixed to existing wooden trusses
for making arrangemnt to receive self tapping
screws of roof sheeting complete all as specified.

Total Rs 134191.34

OMIT Portion
Ser Description of Items Unit Qty Ser Item Rate per Amount Remarks
No Unit

1 S & F for steel work of grade-3 as per IS 10748 in Kg 300.00 Sch 'A' 70.00 21000.00
tubular trusses including special shaped washer Item No
etc. complete using ERW or HRIW welded tubes -43
confirming to IS 1161: 2014 (Yst 240 Grade)
including painting complete all as specified and
directed.

Total Rs 21000.00

SUMMARY

Total Add Rs 134191.34


Total Omit Rs 21000.00
Financial Effect of Change 113191.34

Signature of Contractor JE Civil Engineer-in-Charge


STAR RATE NO-1

Contract No :- CWE (M) -31 of 2016-2017


Name of Work :- Special repairs to toilet and bathrooms at Bldg No P-3 of BI line at Colaba under GE (W) Colaba, Mumbai
Name of Contractor :- M/s Ashok Construction.

Ser No Description of Items Unit Rate Remarks


Rs Ps
1 S&F for mild steel work medium weight of any section Kg 74 43 Total Financial
square/ rectangular MS angle or MS Flats including effect is
fabrication and errection complete in purlins and rafter Rs113191.34
fixed to existing wooden trusses for making arrangemnt to
receive self tapping screws of roof sheeting complete all
as specified.

Recommended Date
GE (West)
Mumbai
Checked Date
DCWE (Contracts)
Checked Date
Director
(Contracts)
Approved Date
CWE (Army)
Mumbai

Accepted by M/s Ashok Construction.

Signature of Contractor --------------- Date---------


STAR RATE NO-1

Contract No :- CWE (M) -31 of 2016-2017


Name of Work :- Special repairs to toilet and bathrooms at Bldg No P-3 of BI line at Colaba under GE (W) Colaba, Mumbai
Name of Contractor :- M/s Ashok Construction.

Description :
S&F for mild steel work medium weight of any section square/ rectangular MS angle or MS Flats including
fabrication and errection complete in purlins and rafter fixed to existing wooden trusses for making arrangemnt
to receive self tapping screws of roof sheeting complete all as specified.
Unit KG

Ser No Description Unit Quantity Rate Amount

(A) Materials
(i) Mild Steel angle Iron Kg 1.02 42 42.84
Including 2% wastage (Purchase Voucher Attached)
(ii) Transportation LS 0.77

(B) Labour
(i) Black Smith (Fabrication,erection & fixing) Day 0.0045 448 2.02
(ii) Fitter/Welder (Fabrication,erection & fixing) Day 0.0160 448 7.17
(iii) Helper/Semi Skilled Labour Day 0.0075 407 3.05
(iv) Mazddor Day 0.0190 368 6.99
(As per minmum fair wages)
Total Material and Labour 62.84
(C) 15% for OH and Profit (as per condition 62 (G) of IAFW 9.43
2249)
Sub Total 72.26
(D) 2% Work Contract Tax 1.445
(E) 1% Labour Cess 0.723
Total 74.43
Total Cost Rs 74.43
Per Kg
Rate Rs 74.43
Per Kg

Prepared by me AGE (Contracts)

Certified that rates of materials including discount have been verified from market and labour contents applied are actually observed
at site of work.

Engineer- in-Charge

Accepted subjected to approval by Competent Authority


Contractor : M/s Ashok Construction.
Appx 'B'
(Refer to Para 7 of HQ CE Pune Zone letter No 80000/A-
10/10/E8 dated 03 Jul 2014

STATEMENT OF PROPOSED DEVIATIONS FOR APPROVAL IN PRINCIPLE

1 Contract No :- CWE (M) -31 of 2016-2017


2 Name of Work :- Special repairs to toilet and bathrooms at Bldg No P-3 of BI line at Colaba under GE (W) Colaba, Mumbai
3 Name of Contractor :- M/s Ashok Construction.
4 Value of contract as accepted 609864.00
5 Cumulative effect of all Wos/Dos already initiated
6 Contract Amount PLUS/MINUS the algebric sum of all 609864.00
Dos initiated
7 Original date of Completion 4-Oct-16
8 Extended date of Completion 31-Jan-17
9 Deviation limit of the Contract 10% (To be enhanced to 20%)

Ser No Bldg or Items affected Description of proposed Reasons for Wether the work (a) awaits Approx financial effect of the Whether the proposed Whether sufficient funds to
(Give reference to deviation proposed approval (b) is in progress (c) proposed deviation (Plus/Minus) deviation exceeds or does meet the proposed deviation
Schedule 'A' Items) devations completed not exceed the amount of are available
A/A (If exceeds,action taken
for revised A/A)

1 2 3 4 5 6 7 8
1 Sch 'A' Part-I Addition of certain new Site Work in Progress 113191.34 Within Limits Yes
items under Schedule 'A' requirement
Part -I
Engineer-in-Charge

Garrison Engineer (West)


f HQ CE Pune Zone letter No 80000/A-
3 Jul 2014

Time effect, If Remarks


any

9 10
NIL
ge

r (West)