Professional Documents
Culture Documents
Details in Supports of Do No 1
Details in Supports of Do No 1
Add Portion
Ser Description of Items Unit Qty Ser Item Rate per Amount Remarks
No Unit
1 S&F for mild steel work medium weight of any Kg 1802.92 Sr No 1 74.43 134191.3356 Star Rate
section equal/ unequal MS angle or MS Flats No-1
including fabrication and errection complete in
purlins and rafter fixed to existing wooden trusses
for making arrangemnt to receive self tapping
screws of roof sheeting complete all as specified.
Total Rs 134191.34
OMIT Portion
Ser Description of Items Unit Qty Ser Item Rate per Amount Remarks
No Unit
1 S & F for steel work of grade-3 as per IS 10748 in Kg 300.00 Sch 'A' 70.00 21000.00
tubular trusses including special shaped washer Item No
etc. complete using ERW or HRIW welded tubes -43
confirming to IS 1161: 2014 (Yst 240 Grade)
including painting complete all as specified and
directed.
Total Rs 21000.00
SUMMARY
Recommended Date
GE (West)
Mumbai
Checked Date
DCWE (Contracts)
Checked Date
Director
(Contracts)
Approved Date
CWE (Army)
Mumbai
Description :
S&F for mild steel work medium weight of any section square/ rectangular MS angle or MS Flats including
fabrication and errection complete in purlins and rafter fixed to existing wooden trusses for making arrangemnt
to receive self tapping screws of roof sheeting complete all as specified.
Unit KG
(A) Materials
(i) Mild Steel angle Iron Kg 1.02 42 42.84
Including 2% wastage (Purchase Voucher Attached)
(ii) Transportation LS 0.77
(B) Labour
(i) Black Smith (Fabrication,erection & fixing) Day 0.0045 448 2.02
(ii) Fitter/Welder (Fabrication,erection & fixing) Day 0.0160 448 7.17
(iii) Helper/Semi Skilled Labour Day 0.0075 407 3.05
(iv) Mazddor Day 0.0190 368 6.99
(As per minmum fair wages)
Total Material and Labour 62.84
(C) 15% for OH and Profit (as per condition 62 (G) of IAFW 9.43
2249)
Sub Total 72.26
(D) 2% Work Contract Tax 1.445
(E) 1% Labour Cess 0.723
Total 74.43
Total Cost Rs 74.43
Per Kg
Rate Rs 74.43
Per Kg
Certified that rates of materials including discount have been verified from market and labour contents applied are actually observed
at site of work.
Engineer- in-Charge
Ser No Bldg or Items affected Description of proposed Reasons for Wether the work (a) awaits Approx financial effect of the Whether the proposed Whether sufficient funds to
(Give reference to deviation proposed approval (b) is in progress (c) proposed deviation (Plus/Minus) deviation exceeds or does meet the proposed deviation
Schedule 'A' Items) devations completed not exceed the amount of are available
A/A (If exceeds,action taken
for revised A/A)
1 2 3 4 5 6 7 8
1 Sch 'A' Part-I Addition of certain new Site Work in Progress 113191.34 Within Limits Yes
items under Schedule 'A' requirement
Part -I
Engineer-in-Charge
9 10
NIL
ge
r (West)