Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Hindawi

Advances in Operations Research


Volume 2018, Article ID 6721912, 15 pages
https://doi.org/10.1155/2018/6721912

Research Article
The Behavior of Procurement Process as Described by
Using System Dynamics Methodology

Mohd Izhan Mohd Yusoff


Telekom Research & Development Sdn Bhd, TM Innovation Center, Lingkaran Teknokrat Timur, 63000 Cyberjaya,
Selangor Darul Ehsan, Malaysia

Correspondence should be addressed to Mohd Izhan Mohd Yusoff; izhan@tmrnd.com.my

Received 19 December 2017; Revised 22 February 2018; Accepted 4 March 2018; Published 22 April 2018

Academic Editor: Viliam Makis

Copyright © 2018 Mohd Izhan Mohd Yusoff. This is an open access article distributed under the Creative Commons Attribution
License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly
cited.

System dynamics methodology has been used in many fields of study which include supply chain, project management and
performance, and procurement process. The said methodology enables the researchers to identify and study the impact of the
variables or factors on the outcome of the model they developed. In this paper, we showed the use of system dynamics methodology
in studying the behavior of procurement process that is totally different from those mentioned in previous studies. By using a typical
procurement process employed by a telecommunication company as a case study, we proposed a new one (i.e., procurement process)
and developed a procurement model where we discovered that the number of days involved in completing the whole procurement
process depends heavily upon the scenarios we created (especially those that exceed two months), and suggested future research
undertakings.

1. Introduction reports by technical and commercial evaluation committee


and the approval of the reports (submitted by technical and
Procurement process plays a vital or important role in commercial evaluation committee) by approval committee.
ensuring that a telecommunication company gets its supplies Recently, new “gates” are introduced to evaluate the reports
(for projects) in timely manner, at the best price (offered submitted by technical and commercial evaluation commit-
by the wining vendor), and free from all elements of foul tee before they are presented to approval committee, with the
play (or bribery). At the beginning, the procurement process aim or purpose of expediting the approval process, as well as
activities employed by a telecommunication company were to eliminate all elements of foul play (or bribery).
done manually; for example, the vendors involved in call for No (scientific) study was done or conducted to evalu-
quotation exercise were required to (apart from registering ate the performance of the existing and new procurement
themselves to the telecommunication company) submit their processes especially before the deployment of the latter. The
quotations (in hardcopy format) by placing them in labelled introduction of online procurement process system did not
boxes located at the said company’s finance or procurement solve all the problems faced by the existing procurement
department. The labels were stated, for example, the supply process. For example, the number of papers that the approval
and installation of hardware or software (with technical spec- committee could handle or manage at any given time is
ifications as required by the telecommunication company). limited. The meeting would normally be held during working
Then online procurement process system was introduced. days, once a month, and for a specific number of hours
The vendors involved in call for quotation exercise were only. More and more reports from the existing meeting are
required to upload their quotations (in softcopy format) forwarded to the next meeting due to either time constraint
into the said system. The following are procurement process or lack of quorum. More and more reports are rejected by
activities that did not change (over time) and are done approval committee due to failing to meet the criteria fixed
manually: the evaluation of quotations and preparation of by approval committee.
2 Advances in Operations Research

Our research undertakings are focused on solving the in multiunit maintenance program (emphasizing resource
problems as mentioned above via the introduction of a new strategy involving human and procurement). The model is
procurement process. They are solved in stages where the divided into several submodels, namely, human resource
new procurement process is updated or expanded on each submodel, which focuses on policies related to provision and
stage. On the first stage and the main highlight of this paper, management, and procurement submodel, which emphasizes
the problem we wish to solve is the frequency of approval the procurement process and inventory system. The model
committee meetings. The rest of the problems are solved in showed the impact of one decision in a certain maintenance
future research undertakings. We performed the following resourcing system on the other maintenance resourcing
steps for the first stage: firstly, we studied the procurement system and will lead to an optimum policy for maintenance
process of a telecommunication company (via Standard resource provision system. Sadreddin et al. [6] used a large
Operating Procedure, or SOP, documents supplied by them). Canadian construction company as case study to develop the
Secondly, we collected (one year) real data, which include cost of quality (coq) model for the procurement process of the
the number of days required for an applicant to complete the construction industry and establish a general course of action
whole procurement process. Thirdly, we designed and built for minimizing quality costs. The use of the prevention-
the procurement model using system dynamics methodology appraisal-failure approach for the coq model of the procure-
and a portion of (or all) real data collected from previous ment process, the internal quality costs within the company,
step. Finally, we studied the performance of the procurement and costs of its suppliers were considered. Several different
model, which includes comparing the (procurement) model’s policies were designed and their effects on quality costs
results with the real data collected from previous step. were investigated via system dynamics methodology. Their
findings suggested that prevention costs should be increased
2. Literature Survey to minimize failures, and they also found that appraisal cost is
quite high in the procurement process and should be reduced
Supply chain, which manages the flow of finished products or in order to minimize overall coq. However this strategy could
services, is part and parcel of product development cycle and increase failure occurrences thereby damaging company’s
it is normally invoked when the product is completed (i.e., reputation. The possible reductions of appraisal cost in the
when the product has gone through all tests related to quality construction companies should thus be carefully considered.
with flying colors). Asgari and Hoque [1] demonstrated the Ross-Smith and Yearworth [7] listed several weaknesses
use of system dynamics methodology to understand the which include traditional independent project performance
behavior of all variables involved in Ready-Made-Garment evaluations which are time consuming and disruptive to
(RMG) industry (such as enablers, performance or results, business as usual and used system dynamics methodology to
and inhibitors), especially those related to supply chain, combine performance evaluation and continual tracking into
so that top management could make effective decisions one performance auditing method, thus allowing a model
to improve the supply chain of the said industry. They of a system to be continually updated and internally and
conducted a survey and individual interviews with senior independently analyzed as required. Using the Bernard gray
management personnel, supply chain professionals, and mer- report of defense procurement as a test case, they found
chandisers of RMG industry. Kussainov [2] on the other hand that qualitative system dynamics has utility in creating an
modeled and analyzed vaccine supply chain management in enterprise performance audit.
view of significant (or important) contribution of immuniza- Croom and Johnston [8] addressed the issues relating to
tion programs to public health advancement. The contri- the impact of e-business developments on internal customer
butions of the said programs are, among others, increasing service with a focus on electronic procurement introduction.
longevity, reducing child mortality rates, economic growth, In other words, it concentrates on the intraorganizational
development, and prosperity across the board for most of the system dynamics of e-business. Marquez and Blanchar [9]
world. presented simulation study to extend current methods for
Malik and Cheng [3] used system dynamics methodology real options strategies in the management of strategic com-
to understand the factors that alter the project as well as modity type parts. They simulated 3 generic types of supplier
the relationship between different knowledge areas in a contracts to accomplish varying degrees of security and
construction project. They believed the model they devel- flexibility and simulated a portfolio of these contracts applied
oped, apart from improving project performance, addressed to secure a single part, with the purpose of extending and
the weaknesses displayed by Project Management Body of refining portfolio valuation. Mula et al. [10] used Vensim
Knowledge, or PMOK, which introduced ten knowledge simulation tool to propose a simulation approach based on
areas. Latorre et al. [4] identified obstacles which prevent system dynamics for operational procurement and trans-
achievement of the overall performance desired for the port planning in a two-level, multiproduct and multiperiod
UK’s construction industry (especially how project managers’ supply chain. The results are compared with spreadsheet
decisions impact such performance). The model visualizes based simulation, fuzzy multiobjective programming, and
the interactions of all relevant goals and elements, presents system dynamics based simulation models. Marinkovic [11]
the need for increased efficiency in the construction indus- concentrated on a specific antihail public service provider
try, and presents the role that KPIs have in driving these in Siberia, exploring not only the outcome of the public
required efficiencies. Using system dynamics methodology, provider’s procurement practices, but also outputs of such
Cahyo et al. [5] modeled the resource provision policy actions on the territory level, and built a model of corruption
Advances in Operations Research 3

$1000, two quotations are collected from authorized vendors


via call for quotation process (the duration for the said
Level_1 process is 14 days). They (i.e., quotations) are evaluated and
only one is selected by technical and commercial evalua-
Rate_1
tion committee. Approval committee chaired by Manager
of Procurement studies the reports submitted by technical
Link and commercial evaluation committee and approves the
purchasing of hardware from selected vendor. If the price of
hardware is greater than say $100,000, more quotations are
required by technical and commercial evaluation committee
from authorized vendors, and approval committee is chaired
Auxiliary_1 by Chief Executive Officer. Figure 2 shows a normal or typical
procurement process where the blue arrow lines represent
Figure 1: An example of a model developed using system dynamics first path taken by user or applicant whilst the red arrow
methodology.
lines represent second path, which is taken when approval
committee rejects the recommendation from technical and
commercial evaluation committee (in this paper, we are
based on Dynamics Performance Management approach in focusing on readvertisement because this action clearly adds
order to extend their understanding of corruption and its more days to the whole procurement process). The rejection
background as well as to provide an input to future policy- might be due to several reasons; one of them is that the
making on corruption issues. number of quotations submitted by vendors did not meet
In this paper, which is divided into Methodology, The the criteria fixed by approval committee. The details of the
Procurement Model, Results, and Conclusion sections, we procurement process used by a telecommunication company
will show the use of system dynamics methodology in will not be revealed in this paper and they will be treated as
studying the behavior of procurement process that is totally confidential information.
different from those mentioned in the above studies. The procurement model, as shown in Figures 4 and 5
(using an algorithm as shown in Figure 3), which represent
3. Methodology two (2) scenarios, used random numbers between zero and
one (to create application date and chances and add realism
System dynamics methodology is defined as a field for to the simulation), fixed 30 days for each month, ignored
understanding how things change through time. It deals with Saturday and Sunday as well as official (or unofficial) holidays,
how the internal feedback loops within the structure of a fixed the 10th and 20th of each month for approval committee
system create behavior and focuses on the feedback behavior to convene or meet (i.e., twice for each month) (in real data,
of variables within the closed loop of the system. The strength approval committee meets once a month on working days
of SD is its way of analyzing the impact of information where they reserved time, date, and venue to discuss the
feedback on decision making of a complex system. The submitted reports, (the reservation depends heavily upon the
following are some of the common symbols used in system availability of committee members), and the measurement
dynamics methodology. used to represent cycle time is working days), and fixed
Stock, represented by Level 1 in Figure 1, is an element either the 3rd or 13th of each month for the (technical
that accumulates and depletes over time. Flow, represented and commercial evaluation committee) reports to reach the
by Rate 1, is the rate of change in a stock. Link defines secretariat (of the approval committee). If the reports reached
dependency between elements of a stock and flow diagram; on the 3rd or 13th, they are tabled (or presented) on the
and Auxiliary, represented by Auxiliary 1, is used to define 10th or 20th, respectively. Call for quotation process starts
some intermediate concepts. Positive feedback loops enhance on the same day as the applicant submits his or her form to
or amplify changes, which tends to move a system away from the relevant authority. The price of hardware or software to
its equilibrium state and make it more unstable. Negative be procured was not considered in the said model (further
feedback loops dampen or buffer changes, which tends to hold clarification on the assumptions used: (1) if there are at least 7
a system to some equilibrium state making it more stable [12]; days to complete 10 items in the reports, 7 of them are not
practical example is given in the Appendix. met with less than 7 days leading to postponement of the
Note that Powersim Studio Enterprise 2005 is the applica- submission date. There are cases where 10 items are met in
tion used to develop procurement model. less than 7 days; (2) if there are 10 criteria fixed by approval
committee, 7 of them are not met leading to an extension of
4. The Procurement Model procurement process; (3) the fixing of date of submission and
date of convene (for approval committee) could only be done
The purchasing of hardware and software for projects under- or achieved if online (process) system (replacing manual
taken by a telecommunication company must go through process) is used. Reports can be uploaded into online system
procurement process involving call for quotation, technical by the applicant where approval committee could study and
and commercial evaluation committee, and approval com- approve them via the same system (on the stipulated or agreed
mittee. For example, if the price of hardware is less than say date)).
4 Advances in Operations Research

Start
User/Applicant User/Applicant:
Technical/
Commercial
Evaluation
Committee
Procurement
department

Close Request for


Quotation

Approval
Committee

Advertisement

No
Approve?
Submit quotation
Yes

Letter Of
Acceptance/
Vendor Purchasing Order/
Delivery Order

Figure 2: Flow diagram shows a normal (or typical) procurement process employed by a telecommunication company.

Scenario 1. Figure 4 is best described via the following evaluation of the quotations submitted by the authorized
example: the applicant submits his or her form to the relevant vendors) are not complete (or ready) for submission (to the
authority say in January and, based on the information given secretariat of approval committee) on the 3rd of February. The
in the form, the relevant authority calls for quotations from reports are submitted to the secretariat of approval committee
authorized vendors for a period of 14 days. Once completed, on the 13th of February instead and presented before the
that is, before the 30th of January, in terms of call for said committee on the 20th of February. When the reports
quotation process, the technical and commercial evaluation are presented before the approval committee on the 20th of
committee (where the applicant is also a member) reports February and due to the fact that, among others, the number
(which include evaluation of the quotations submitted by of quotations received (from the first call for quotation
the authorized vendors) are submitted to the secretariat process) did not meet the targeted value (or criteria), there
(of approval committee) on the 3rd of February where the are more than 70% chances that the (approval) committee will
(approval) committee meets on the 10th of February. request the applicant to repeat the call for quotation process
When the reports are presented (or tabled) before the for (an additional) seven days. The updated technical and
approval committee on the 10th of February and due to the commercial evaluation committee reports (which include
fact that, among others, the number of quotations received evaluation of the quotations submitted by the authorized ven-
(from the first call for quotation process) did not meet the dors) are submitted to the secretariat (of approval committee)
targeted value (or criteria), there are more than 70% chances on the 3rd of March to be presented and approved by the
that the (approval) committee will request the applicant to approval committee seven days later, that is, on the 10th of
repeat the call for quotation process for (an additional) seven March. Otherwise, the reports are approved by the approval
days. The updated technical and commercial evaluation com- committee on the 20th of February.
mittee reports (which include evaluation of the quotations
submitted by the authorized vendors) are submitted to the Scenario 2. Figure 5 is best described thru the following
secretariat (of approval committee) on the 3rd of March to example: the applicant submits his or her form to the relevant
be presented and approved by the approval committee seven authority say in January and, based on the information given
days later, that is, on the 10th of March. Otherwise, the in the form, the relevant authority call for quotations from
reports are approved by the approval committee on the 10th authorized vendors for a period of 14 days. Once completed,
of February. This scenario assumes that the number of days to that is, well after the 30th of January, in terms of call for
complete the reports is greater than (or equal to) seven days. quotation process, the complete technical and commercial
If the number of days to complete the reports (after 14 evaluation committee reports (which include evaluation of
days of call for quotation process) is less than seven days, the quotations submitted by the authorized vendors) are
there are more than 70% chances that the technical and submitted to the secretariat (of approval committee) on either
commercial evaluation committee reports (which include the 3rd of February, 13th of February, or 3rd of March,
Advances in Operations Research 5

User/Applicant
User/Applicant:
(date of submission) Technical/
Commercial
Evaluation
Committee

Yes Status of No
Procurement the report,
department Ready?
Close Request for
Quotation
(+14 days from date of
submission)
Secretariat Secretariat
Approval Approval
Committee, 3rd Committee, 13th
Advertisement (mm-yyyy) (mm-yyyy)

Submit quotation

Vendor Approval Approval


A Committee, Committee,
No No
10th 20th
(mm-yyyy), (mm-yyyy),
Approve? Approve?
B

Yes Yes

Letter Of
Acceptance/
Purchasing Order/
Delivery Order

User/Applicant:
User/Applicant
Technical/
(date of rejection)
Commercial
Evaluation
Committee

Procurement
department

Secretariat
Close Request for
Approval
Quotation
Committee, 3rd
(+7 days from date of
((mm+1)-yyyy)
rejection)

Advertisement

Approval
Submit quotation Committee 10th
((mm+1)-yyyy)
Approve

Vendor

Letter Of
Acceptance/
Purchasing Order/
Delivery Order

User/Applicant:
User/Applicant Technical/
(date of rejection) Commercial
Evaluation
Committee

Status of
Procurement Yes No
the report,
department Ready?
Close Request for
Quotation
(+7 days from date of
rejection) Secretariat Secretariat
Approval Approval
Committee, 3rd Committee, 13th
((mm+1)-yyyy) ((mm+1)-yyyy)
Advertisement

Submit quotation
Approval Approval
Committee 10th Committee 20th
((mm+1)-yyyy) ((mm+1)-yyyy)
Vendor Approve Approve

Letter Of
Acceptance/
Purchasing Order/
Delivery Order

Figure 3: Due to its size, only a portion of the algorithm used in developing the procurement model is presented in this paper, and in the
form of the above flow diagram.
6 Advances in Operations Research

Auxiliary_15 Auxiliary_18
Auxiliary_21
Rate_18
Auxiliary_36

Auxiliary_17
Auxiliary_19 Level_4
Auxiliary_44 Rate_8 Rate_9
Auxiliary_4

Auxiliary_15 Auxiliary_41 Auxiliary_15


Auxiliary_16 Auxiliary_20

Level_3
Rate_6 Rate_7 Level_10 Level_11
Rate_19 Rate_20 Rate_21 Rate_22
Auxiliary_15
Auxiliary_5
Auxiliary_32 Auxiliary_43

Auxiliary_38
Auxiliary_42

Auxiliary_39
Auxiliary_29 Level_9
Auxiliary_40
Auxiliary_16 Rate_17 Rate_18

Level_3

Auxiliary_15

Copy of Auxiliary_15 Copy of Auxiliary_18


Copy of Auxiliary_21
Copy of Rate_18
Copy of Auxiliary_36

Copy of Auxiliary_17
Copy of Auxiliary_19 Copy 2 of Level_4
Copy of Auxiliary_44 Copy 2 of Rate_8 Copy 2 of Rate_9
Auxiliary_4
Copy of Auxiliary_15 Copy of Auxiliary_15
Copy of Auxiliary_16 Copy of Auxiliary_41
Copy of Auxiliary_20

Copy 2 of Level_3
Copy 2 of Rate_6 Copy 2 of Rate_7 Copy of Level_10 Copy of Level_11
Copy of Rate_19 Copy of Rate_20 Copy of Rate_21 Copy of Rate_22
Copy of Auxiliary_15
Auxiliary_5 Copy of Auxiliary_43
Auxiliary_32

Copy of Auxiliary_38
Copy of Auxiliary_42
Auxiliary_29 Copy of Auxiliary_39
Copy of Auxiliary_29 Copy of Level_9
Copy of Auxiliary_16 Copy of Rate_17 Copy of Rate_18
Copy of Auxiliary_40
Copy 2 of Level_3

Copy of Auxiliary_15

Figure 4: The procurement model developed using system dynamics methodology (Scenario 1).

where the (approval) committee meets on either the 10th of approval committee on either the 10th of February, 20th of
February, 20th of February, or 10th of March, respectively. February, or 10th of March. This scenario assumes that the
When the reports are presented (or tabled) before the number of days to complete the reports is greater than (or
approval committee on either the 10th of February, 20th equal to) seven days.
of February, or 10th of March and due to the fact that, If the number of days to complete the reports (after 14
among others, the number of quotations received (from the days of call for quotation process) is less than seven days,
first call for quotation process) did not meet the targeted there are more than 70% chances that the technical and
value (or criteria), there are more than 70% chances that commercial evaluation committee reports (which include
the (approval) committee will request the applicant to repeat evaluation of the quotations submitted by the authorized
the call for quotation process for (an additional) seven days. vendors) are not complete (or ready) for submission (to the
The updated technical and commercial evaluation committee secretariat of approval committee) on either the 3rd or 13th
reports (which include evaluation of the quotations submit- of February. The reports are submitted to the secretariat of
ted by the authorized vendors) are submitted to the secretariat approval committee on either the 13th of February or 3rd
(of approval committee) on either the 3rd of March or of March instead and presented before the said committee
3rd of April to be presented and approved by the approval on either the 20th of February or 10th of March. When
committee seven days later, that is, on the 10th of March or the reports are presented before the approval committee on
the 10th of April. Otherwise, the reports are approved by the either the 20th of February or 10th of March and due to the
Advances in Operations Research 7

Auxiliary_4 Auxiliary_51
Auxiliary_25
Auxiliary_24 Auxiliary_15 Auxiliary_52 Copy of Level_4
Copy of Rate_8 Copy of Rate_9
Auxiliary_35
Auxiliary_31 Auxiliary_34 Auxiliary_35
Auxiliary_15
Copy of Level_3 Copy of Rate_7
Copy of Rate_7 Auxiliary_28
Auxiliary_32 Copy of Rate_6
Auxiliary_26 Auxiliary_15
Auxiliary_15
Auxiliary_16 Copy of Level_3
Level_6
Copy of Auxiliary_8 Rate_10 Rate_11
Auxiliary_56 Auxiliary_57
Auxiliary_5 Auxiliary_30 Copy of Auxiliary_10

Copy of Auxiliary_7 Auxiliary_49


Copy of Auxiliary_9 Level_12 Level_14
Rate_23 Rate_24 Rate_28 Rate_29
Auxiliary_50
Auxiliary_34 Auxiliary_53
Copy of Rate_7 Rate_24
Auxiliary_33
Auxiliary_45
Auxiliary_47 Level_13 Level_15
Rate_25 Rate_26 Rate_27 Rate_30
Auxiliary_51
Auxiliary_15
Auxiliary_46
Auxiliary_48 Auxiliary_15

Auxiliary_55
Auxiliary_54

Rate_24

Copy of Auxiliary_51
Auxiliary_4
Copy of Auxiliary_25 Copy of Auxiliary_52
Copy of Auxiliary_24 Auxiliary_15 Copy of Copy of
Copy of Copy of Level_4 Copy of Copy of
Copy 2 of Rate_8 Rate_9
Copy of Auxiliary_31 Auxiliary_35 Copy 2 of Copy 2 of
Auxiliary_15 Auxiliary_34 Auxiliary_35
Copy of Copy of Copy of Copy of
Level_3 Copy of Copy of Copy of Auxiliary_28
Auxiliary_32 Copy of Copy of Copy of Auxiliary_26 Rate_7 Auxiliary_15
Rate_6 Rate_7
Auxiliary_15
Auxiliary_16 Copy of Copy of
Level_3 Copy 2 of Level_6
Copy of Copy of Copy 2 of Rate_10 Copy 2 of Rate_11
Auxiliary_8 Auxiliary_58 Auxiliary_59
Auxiliary_5 Copy of Auxiliary_30
Copy of Copy of
Auxiliary_10
Copy of Copy of Copy of Auxiliary_49
Auxiliary_30 Copy of Level_12 Copy of Level_14
Auxiliary_7 Copy of Copy of Copy of Rate_24 Copy of Rate_28 Copy of Rate_29
Auxiliary_9 Copy of Auxiliary_51 Copy of Rate_23
Copy of Auxiliary_50
Copy 2 of Copy of Auxiliary_53
Copy of Copy of Copy of Rate_24
Auxiliary_34 Rate_7
Copy 2 of
Auxiliary_33
Copy of Auxiliary_45
Copy of Auxiliary_46 Copy of Level_13 Copy of Level_15
Copy of Auxiliary_47
Copy of Rate_25 Copy of Rate_26 Copy of Rate_27 Copy of Rate_30
Auxiliary_15
Copy of Auxiliary_48 Auxiliary_15

Copy of Auxiliary_55
Copy of Auxiliary_54

Copy of Rate_24

Figure 5: The procurement model developed using system dynamics methodology (Scenario 2).

fact that, among others, the number of quotations received 5. Results


(from the first call for quotation process) did not meet the
We performed 100 runs (which produced at most 1,200
targeted value (or criteria), there are more than 70% chances
observations) and some of them (i.e., results) are given in this
that the (approval) committee will request the applicant to
paper. Example of one (1) run is shown in Figures 6, 7, 8, and
repeat the call for quotation process for (an additional) seven
9 where each procurement process is represented by three
days. The updated technical and commercial evaluation com- spikes of different colors, namely, green (representing the date
mittee reports (which include evaluation of the quotations of submission), yellow (representing the date when call for
submitted by the authorized vendors) are submitted to the quotation process is completed), and red (representing the
secretariat (of approval committee) on either the 3rd of March date when approval committee approved the reports). All
or 3rd of April to be presented and approved by the approval submissions are randomly made; hence they are independent
committee seven days later, that is, on the 10th of March or of each other.
10th of April. Otherwise, the reports are approved by the The first three spikes in Figure 6 represent the following
approval committee on either the 20th of February or 10th behavior: the application was submitted on the 15th of
of March. January and call for quotation process was completed on the
8 Advances in Operations Research

1 1

0 0

1-1-2016
19-1-2016
7-2-2016
25-2-2016
13-3-2016
1-4-2016
19-4-2016
7-5-2016
25-5-2016
13-6-2016
1-7-2016
19-7-2016
7-8-2016
25-8-2016
13-9-2016
1-10-2016
19-10-2016
7-11-2016
25-11-2016
13-12-2016
1-1-2016
19-1-2016
7-2-2016
25-2-2016
13-3-2016
1-4-2016
19-4-2016
7-5-2016
25-5-2016
13-6-2016
1-7-2016
19-7-2016
7-8-2016
25-8-2016
13-9-2016
1-10-2016
19-10-2016
7-11-2016
25-11-2016
13-12-2016
Auxiliary_17 Auxiliary_21 Auxiliary_31 Auxiliary_28
Auxiliary_18 Auxiliary_42 Auxiliary_25 Auxiliary_56
Auxiliary_20 Auxiliary_43 Auxiliary_26 Auxiliary_57

Figure 6: Behavior produced from the procurement model’s Sce- Figure 8: Behavior produced from the procurement model’s Sce-
nario 1. nario 2.

1 1

0 0
1-1-2016
21-1-2016
11-2-2016
1-3-2016
21-3-2016
11-4-2016
1-5-2016
21-5-2016
11-6-2016
1-7-2016
21-7-2016
11-8-2016
1-9-2016
21-9-2016
11-10-2016
1-11-2016
21-11-2016
11-12-2016
1-1-2016
21-1-2016
11-2-2016
1-3-2016
21-3-2016
11-4-2016
1-5-2016
21-5-2016
11-6-2016
1-7-2016
21-7-2016
11-8-2016
1-9-2016
21-9-2016
11-10-2016
1-11-2016
21-11-2016
11-12-2016

Copy of Auxiliary_17 Copy of Auxiliary_21 Copy of Auxiliary_31 Copy of Auxiliary_28


Copy of Auxiliary_18 Copy of Auxiliary_42 Copy of Auxiliary_25 Auxiliary_58
Copy of Auxiliary_20 Copy of Auxiliary_43 Copy of Auxiliary_26 Auxiliary_59

Figure 7: Behavior produced from the procurement model’s Sce- Figure 9: Behavior produced from the procurement model’s Sce-
nario 1 (continued). nario 2 (continued).

29th of January. The applicant cum technical and commercial completed on the 28th of September. The applicant did
evaluation committee (henceforth, the applicant) managed not manage to complete the reports on the 3rd of October
to complete the reports and submitted them on the 3rd of and submitted them on the 13th of October instead. The
February. The approval committee approved the reports on approval committee did not approve the reports on the 20th
the 10th of February. The total number of days involved is of October. The applicant submitted the updated reports on
25. The second three spikes (in the same figure) represent the 3rd of November. The approval committee approved the
the following behavior: the application was submitted on the reports on the 10th of November. The total number of days
13th of May and call for quotation process was completed involved is 56. The fourth (final) three spikes represent the
on the 27th of May. The applicant managed to complete the following behavior: the application was submitted on the 15th
reports and submitted them on the 3rd of June. The approval of November and call for quotation process was completed on
committee approved the reports on the 10th of June. The total the 29th of November. The applicant managed to complete
number of days involved is 27. The third three spikes represent the reports and submitted them on the 3rd of December.
the following behavior: the application was submitted on The approval committee approved the reports on the 10th of
the 14th of September and call for quotation process was December. The total number of days involved is 25.
Advances in Operations Research 9

Figure 7’s first three spikes represent the following behav- (related to total number of days involved) are 36.1, 17.6, 22,
ior: the application was submitted on the 11th of February and 72, respectively.
and call for quotation process was completed on the 25th of Results for the rest of the (100) runs (especially related to
February. The applicant completed and submitted the reports total number of days involved) are presented in the form of
on the 3rd of March. The approval committee did not approve summary (or standard) statistics average, standard deviation,
the reports on the 10th of March. The applicant submitted the minimum, and maximum, which were produced using four
updated reports on the 3rd of April. The approval committee (4) specially designed (system dynamics) models; one of
approved the reports on the 10th of April. The total number them is shown in Figure 10. Summary (or standard) statistics
of days involved is 59. The second three spikes (in the same average, standard deviation, minimum, and maximum for
figure) represent the following behavior: the application was Figure 11’s 1052 observations (related to total number of days
submitted on the 6th of October and call for quotation involved) are 37.25, 13.58, 21, and 77, respectively. “SimData”
process was completed on the 20th of October. The applicant in Figure 11(a) refers to total number of days involved
managed to complete the reports and submitted them on in completing the procurement process. Two humps are
the 3rd of November. The approval committee approved (vividly) observed: first hump lies between 21 days and 47
the reports on the 10th of November. The number of days days (for the procurement process to complete) and second
involved is 34. The third (final) three spikes represent the hump between 52 days and 77 days. If number of days for
following behavior: the application was submitted on the 6th each month is fixed at 30, there are quite a considerable
of December and call for quotation process was completed number of cases/runs where the procurement process would
on the 20th of December. The rest of the (procurement) take approximately 29 days as well as 63 days (more than two
processes were brought forward to the next year. The total months) to complete; refer to Figure 11(b) [13].
number of days involved is not calculated. Figure 11 is dissected into Scenario 1, represented by
The first three spikes in Figure 8 represent the following Figures 12(a) and 12(b). Summary (or standard) statistics
behavior: the application was submitted on the 20th of March average, standard deviation, minimum, and maximum for
and call for quotation process was completed on the 4th of Figure 12’s 570 observations (related to total number of days
April. The applicant managed to complete the reports and involved) are 40.49, 13.94, 24, and 69, respectively. Similar
submitted them on the 13th of April. The approval committee to the previous figure, “SimData” refers to total number of
approved the reports on the 20th of April. The total number days involved in completing the procurement process. Two
of days involved is 30. The second three spikes (in the same humps are observed: first hump lies between 24 days and 56
figure) represent the following behavior: the application was days (for the procurement process to complete) and second
submitted on the 18th of June and call for quotation process hump between 57 days and 69 days. If number of days for
was completed on the 2nd of July. The applicant managed to each month is fixed at 30, there are quite a considerable
complete the reports and submitted them on the 3rd of July. number of cases/runs where the procurement process would
The approval committee approved the reports on the 10th of take approximately 33 days (more than one month) as well
July. The total number of days involved is 22. The third (last) as 62 days (more than two months) to complete; refer to
three spikes represent the following behavior: the application Figure 12(b).
was submitted on the 25th of August and call for quotation Scenario 2, represented by Figures 13(a) and 13(b), is
process was completed on the 9th of September. The applicant the final output from Figure 11’s dissection. Summary (or
managed to complete the reports and submitted them on standard) statistics average, standard deviation, minimum,
the 13th of September. The approval committee approved the and maximum for Figure 13’s 482 observations (related to
reports on the 20th of September. The total number of days total number of days involved) are 33.43, 12.08, 21, and
involved is 25. 77, respectively. Three humps are observed: first hump lies
Figure 9’s first three spikes represent the following behav- between 21 days and 35 days (for the procurement process to
ior: the application was submitted on the 28th of April and complete), second hump between 36 days and 63 days, and
call for quotation process was completed on the 12th of May.
third hump between 71 days and 77 days. If number of days
The applicant did not complete and submit the reports on the
for each month is fixed at 30, there are quite a considerable
13th of May. The applicant submitted them on the 3rd of June
number of cases/runs where the procurement process would
instead. The approval committee did not approve the reports
take approximately 24 days, 42 days (more than one month),
on the 10th of June. The applicant submitted the updated
reports on the 3rd of July that approval committee approved and 75 days (more than two months) to complete; refer to
on the 10th of July. The total number of days involved is Figure 13(b).
72. The second (final) three spikes represent the following The procurement model (simulated) data of 1052 observa-
behavior: the application was submitted on the 28th of July tions (refer to Figure 11) are compared with the real data of 59
and call for quotation process was completed on the 12th observations (refer to Figure 14) to see if the former “behaves”
of August. The applicant managed to complete the reports in the same manner as the latter (if their “behavior” is the
and submitted them on the 13th of August. The approval same, it is as though, or if, the new procurement process is
committee approved the reports on the 20th of August. The deployed “live”). Note that summary (or standard) statistics
total number of days involved is 22. averages, standard deviation, minimum, and maximum for
Summary (or standard) statistics average, standard devi- Figure 14 (representing real data) are 33.42, 10.35, 13, and 60,
ation, minimum, and maximum for the above observations respectively.
10 Advances in Operations Research

Auxiliary_37 Auxiliary_61

Level_8
Rate_14

Rate_15

Level_7
Rate_12 Rate_13

Auxiliary_60
Auxiliary_61

Auxiliary_37

Auxiliary_43

Auxiliary_27
Auxiliary_11
Auxiliary_42

Auxiliary_21

Auxiliary_17
Auxiliary_15
Auxiliary_20

Figure 10: Specially designed system dynamics model used to calculate total number of days involved.

Two statistical nonparametric tests are chosen; they are as As mentioned above, Mann–Whitney 𝑈 test and
follows: Kolmogorov-Smirnov two-sample test statistics are used to
(a) Mann–Whitney 𝑈 test is a nonparametric test of test that the distributions of both populations are equal and
the null hypothesis where it is equally likely that a two samples come from a common distribution, respectively.
randomly selected value from one sample is less than The two populations and samples are referring to Figures 11
or greater than a randomly selected value from a and 14. Table 1 shows especially the 𝑝 value corresponding
second sample. It does not require the assumption of to Asymptotic Significance (2-tailed) where both of them are
normal distributions. greater than 0.05, the distributions of both populations are
equal (Mann–Whitney 𝑈 test), and two samples come from
(b) Kolmogorov-Smirnov two-sample test statistics is a a common distribution (Kolmogorov-Smirnov two-sample
nonparametric test of the equality of continuous, one- test statistics) (if Asymptotic Significance (2-tailed) is less
dimensional probability distributions that can be used than (<) 0.05, the distributions of both populations are not
to compare a sample with a reference probability equal (Mann–Whitney U test) and two samples come from
(one-sample 𝑘-𝑠 test) or to compare two samples different distribution (Kolmogorov-Smirnov two-sample
(two-sample 𝑘-𝑠 test). test statistics)). In other words, their (i.e., Figures 11 and 14)
Details can be found in Sachs [14]. “behavior” is the same.
Advances in Operations Research 11

4.50E − 02
60 4.00E − 02
50 3.50E − 02
3.00E − 02
40
2.50E − 02
Frequency

30 2.00E − 02
1.50E − 02
20
1.00E − 02
10 5.00E − 03
0 0.00E + 00
21
23
25
27
29
31
33
35
37
39
41
43
45
47
52
54
56
58
60
62
64
66
68
71
73
75
77

10.97958258
15.13806573
19.29654889
23.45503204
27.6135152
31.77199835
35.93048151
40.08896467
44.24744782
48.40593098
52.56441413
56.72289729
60.88138045
65.0398636
69.19834676
73.35682991
77.51531307
81.67379622
85.83227938
SimData

f(t(k))
(a) (b)

Figure 11: One thousand and fifty-two (1052) observations representing 100 runs are displayed in the form of (a) bar chart and (b) probability
density function (pdf).

6.00E − 02
50
45 5.00E − 02
40
35 4.00E − 02
Frequency

30
3.00E − 02
25
20 2.00E − 02
15
10 1.00E − 02
5
0 0.00E + 00
24
26
28
30
32
34
36
38
54
56
58
60
62
64
66
68

9.891363036
13.8954327
17.89950237
21.90357204
25.90764171
29.91171138
33.91578104
37.91985071
41.92392038
45.92799005
49.93205972
53.93612938
57.94019905
61.94426872
65.94833839
69.95240805
73.95647772
77.96054739
81.96461706
SimData

f(t(k))
(a) (b)

Figure 12: Scenario 1’s five hundred and seventy (570) observations are displayed in the form of (a) bar chart and (b) probability density
function (pdf).

Table 1: Asymptotic Significance (2-tailed) for both Mann–Whitney process normally employed by a telecommunication com-
𝑈 test and Kolmogorov-Smirnov two-sample test. pany and introduced new procurement process via procure-
ment model (Scenarios 1 and 2) using system dynamics
Kolmogorov-Smirnov
Mann–Whitney 𝑈 test methodology. In the said model, several assumptions were
two-sample test
made (which include (1) using random numbers between
Asymp. Sig.
0.181 0.230 zero and one to create application date and chances, (2) fixing
(2-tailed)
30 days for each month, ignoring Saturday and Sunday as well
as official or unofficial holidays, (3) fixing the 10th and 20th
of each month for approval committee to convene or meet,
6. Conclusion and (4) fixing either the 3rd or 13th of each month for the
technical and commercial evaluation committee reports to
In the previous sections, we listed several studies related reach the secretariat of the approval committee) and it was
to supply chain, project management and performance, and executed for 100 runs. The results from the said execution
procurement process. We also highlighted a procurement showed the procurement process could be less than 30
12 Advances in Operations Research

5.00E − 02
60 4.50E − 02
4.00E − 02
50
3.50E − 02
40 3.00E − 02
Frequency

2.50E − 02
30
2.00E − 02
20 1.50E − 02
1.00E − 02
10 5.00E − 03
0 0.00E + 00

8.362755728
12.80745432
17.25215291
21.6968515
26.1415501
30.58624869
35.03094728
39.47564587
43.92034447
48.36504306
52.80974165
57.25444024
61.69913883
66.14383743
70.58853602
75.03323461
79.4779332
83.9226318
88.36733039
21
23
25
27
29
31
33
35
37
39
41
43
45
47
52
63
72
74
76
SimData

f(t(k))
(a) (b)

Figure 13: Scenario 2’s four hundred and eighty-two (482) observations are displayed in the form of (a) bar chart and (b) probability density
function (pdf).

6 in approval committee are approved by the said committee


5 (i.e., to ensure all criteria are met), and building several
models for different price of hardware and software to
4 be procured, the above model could also be incorporated
Frequency

3 into the model as shown in Figure 15 for future research


undertakings (especially to visualize the benefits such that
2 more reports could be handled or managed by approval com-
1 mittee). Figure 15 uses the following assumptions (subjected
to changes): (1) 30 days are fixed for every month; (2) Saturday
0 and Sunday as well as official holidays are not considered in
13
17
18
21
23
24
25
27
28
29
30
31
32
34
35
36
37
38
39
40
41
43
44
45
51
52
53
55
60

the model; (3) applications submitted per month come from 4


RealData
projects, namely, A, B, C, and D. They are selected at random
Figure 14: Fifty-nine (59) observations of real data are displayed in (to add realism to the simulation); (4) the applications are
the form of bar chart. generated between the 1st and 30th of each month; (5) 3
applications are generated from 3 different projects selected at
random from 4 projects; (6) 2 applications are generated from
days (or one month) if technical and commercial evaluation 2 different projects selected at random from 4 projects; (7)
committee reports satisfied approval committee’s criteria and 1 application is generated from a project selected at random
more than two months if they did not. The number of runs from 4 projects; (8) standard cycle time is 3 days and several
for scenario one is greater than scenario two especially when days are added at random; (9) next model (or Model 2)
the number of days involved for procurement process to focuses on each application especially on the cycle time. The
complete is greater than two months. In other words, it is cycle time depends on when the application is submitted that
most likely (or probable) for procurement process to exceed is either before or after the 15th of each month (15th is the
two months for scenario one as compared to scenario two. date the committee holds its meeting) plus the number of days
The said model is useful if the company’s main business needed to complete the process.
involved procuring hardware and software for executing (or
completing) its projects. If procuring hardware and software Appendix
was not done properly (or in timely manner), the projects
may suffer (significant) delays and require more monies to Two scenarios are considered for water tank model as shown
complete (as well as negative impact on key performance in Figure 16; they are as follows.
indicators of those who are involved in the projects). Note
that the “behavior” of procurement model data and real data Scenario A.1. The following are the equations used in water
is the same when tested using statistical nonparametric tests. tank model: Rate 1 = 10 Liter/Hour; Level 1 = 0 Liter (at
Apart from building approval committee model using the beginning); Rate 2 = Level 1 Liter/Hour if Level 1 ≥ 100
system dynamics methodology (which includes listing all Liters; Rate 2 = 0 Liter if otherwise. Over a period of 24 hours
of the variables or factors affecting approval committee’s where the water tank is empty at the beginning, water flows
decision making), adding “gates” to ensure all reports tabled into the tank at the rate of 10 Liters per hour. If water in the
Advances in Operations Research 13

Probability Level_1
Rate_1

Level_2
Rate_2 Rate_3
standard cycle time Additional Time
Level_3
Rate_4

standard plus
additional Auxiliary_12 Auxiliary_15 Auxiliary_10

Level_4
Rate_5
Auxiliary_134
Auxiliary_89

Level_8
Auxiliary_153 Rate_11
Auxiliary_115
Level_5
Rate_6
Auxiliary_102
Auxiliary_173 Auxiliary_16 Level_7 Auxiliary_23
Rate_9 Rate_10

Auxiliary_175 Auxiliary_17
Auxiliary_9 Auxiliary_13
Auxiliary_1
Auxiliary_21
Auxiliary_18
Auxiliary_3
Auxiliary_19

Level_9
Level_6 Rate_12
Auxiliary_8
Rate_7 Rate_8 Auxiliary_25
Auxiliary_22 Auxiliary_20

Level_12 Counter
Rate_15 Rate_16

Auxiliary_2 Auxiliary_24

Auxiliary_12 Auxiliary_11
Auxiliary_117
Level_10
Rate_13 Auxiliary_27
Auxiliary_5 Auxiliary_14
Auxiliary_4
Auxiliary_6
Auxiliary_33
Auxiliary_123 Auxiliary_35

Auxiliary_7 Level_13
Auxiliary_30
Rate_17 Rate_18
Auxiliary_34 Auxiliary_38
Bulan
Auxiliary_26
Auxiliary_31 Auxiliary_78
Tahun
Auxiliary_32
Level_11
Auxiliary_79 Rate_14 Auxiliary_29
Auxiliary_77 Auxiliary_84

Auxiliary_47 Auxiliary_81
Level_15 Auxiliary_86 Auxiliary_80
Auxiliary_89
Rate_21 Auxiliary_40 Level_14
Auxiliary_46 Rate_19 Rate_20
Auxiliary_82
Auxiliary_87
Auxiliary_41 Auxiliary_44 Auxiliary_85
Auxiliary_39
Auxiliary_45 Auxiliary_28
Auxiliary_42 Auxiliary_83
Auxiliary_88
Auxiliary_111 Auxiliary_107
Auxiliary_43 Auxiliary_58 Auxiliary_103
Auxiliary_54
Auxiliary_65 Auxiliary_68
Auxiliary_52 Auxiliary_112
Auxiliary_108
Auxiliary_55 Auxiliary_59 Auxiliary_104
Auxiliary_69 Auxiliary_115
Auxiliary_53 Auxiliary_62 Auxiliary_64 Auxiliary_66 Auxiliary_71 Auxiliary_72 Auxiliary_74
Auxiliary_113
Auxiliary_109
Auxiliary_60 Auxiliary_76 Auxiliary_105
Auxiliary_56
Auxiliary_51
Auxiliary_67 Auxiliary_70
Auxiliary_73 Auxiliary_75 Auxiliary_114
Auxiliary_63
Auxiliary_57 Auxiliary_61
Auxiliary_118 standard cycle time Auxiliary_106 Auxiliary_110

The higher the complexity, more time is


needed to complete the process.
Auxiliary_133
Auxiliary_120 Complexity impacting cycle time
Auxiliary_121 Probability
Auxiliary_98
Auxiliary_90 Auxiliary_94
Auxiliary_12
Auxiliary_134
Auxiliary_123
Auxiliary_49 Auxiliary_99
Auxiliary_91 Auxiliary_95
Auxiliary_122
Auxiliary_119 Auxiliary_102
Auxiliary_50
Auxiliary_92 Auxiliary_100 Auxiliary_96
Auxiliary_132 Auxiliary_123 Auxiliary_128 Auxiliary_130 Auxiliary_131

Auxiliary_48
standard plus
additional
Auxiliary_93 Auxiliary_101 Auxiliary_97
standard cycle time
Copy of Auxiliary_54 Copy of Auxiliary_58

Copy of Auxiliary_68
Copy of Auxiliary_52
Copy of Auxiliary_65 Auxiliary_127
Copy of Auxiliary_59 Copy of Auxiliary_72 Auxiliary_125
Copy of Auxiliary_64
Copy of Auxiliary_71 Copy of Auxiliary_74 Auxiliary_128
Copy of Auxiliary_55
Copy of Auxiliary_62 Copy of Auxiliary_66 Copy of Auxiliary_69
Copy of Auxiliary_53
Auxiliary_126
Copy of Auxiliary_76
Copy of Auxiliary_56 Copy of Auxiliary_60
Auxiliary_124
standard plus
Copy of Auxiliary_67 additional
Copy of Auxiliary_51 Copy of Auxiliary_63 Auxiliary_12
Copy of Auxiliary_75
Copy of Auxiliary_73
Copy of Auxiliary_57 Copy of Auxiliary_61 Copy of Auxiliary_70

standard cycle time

Auxiliary_129

Auxiliary_12 Auxiliary_132
Auxiliary_12 Auxiliary_131
Auxiliary_130

standard plus
additional
Auxiliary_12

Copy of The higher the complexity, more time is


Auxiliary_135 Auxiliary_139 Copy of Auxiliary_154
Auxiliary_139 needed to complete the process.
Auxiliary_135 Complexity impacting cycle time
Auxiliary_36
Probability
Auxiliary_140 Copy of
Auxiliary_136 Copy of Auxiliary_140
Auxiliary_89 Auxiliary_89 Auxiliary_136 Auxiliary_153
Auxiliary_143 Copy of
Auxiliary_35 Auxiliary_143

Auxiliary_89
Auxiliary_141 Copy of Copy of
Auxiliary_137
Auxiliary_137 Auxiliary_141

Copy 3 of Auxiliary_152 Copy of Copy 2 of


Auxiliary_152 Auxiliary_152 Auxiliary_152
Auxiliary_138 Copy of
Auxiliary_142 Copy of
Auxiliary_138
Auxiliary_142

Auxiliary_146 Auxiliary_149
Copy of Copy of
Copy of Auxiliary_146
Auxiliary_144 Auxiliary_149
Auxiliary_143 Copy of
Copy of Auxiliary_143
Auxiliary_147
Auxiliary_152 Auxiliary_144 Copy of
Auxiliary_150 Copy of
Auxiliary_147 Copy of Auxiliary_152
Auxiliary_150
Auxiliary_143 Auxiliary_145 Auxiliary_148
Auxiliary_151 Auxiliary_143 Copy of Copy of standard cycle time
Auxiliary_145 Auxiliary_148
Copy of
standard cycle time Auxiliary_151
Copy 3 of
Auxiliary_149 standard plus
Copy 2 of Copy 2 of Copy 3 of
additional
Auxiliary_146 Auxiliary_149 Auxiliary_146
standard plus Copy of Copy of
additional Auxiliary_143 Auxiliary_143
Copy 2 of Copy 3 of
Copy 2 of Copy 3 of
Auxiliary_147 Copy 2 of Auxiliary_147 Copy 3 of
Auxiliary_152 Auxiliary_152
Auxiliary_150 Auxiliary_150

Copy 2 of Copy 3 of
Copy 2 of Auxiliary_143 Copy 3 of
Auxiliary_143 Auxiliary_145
Auxiliary_145 Auxiliary_148
Auxiliary_148 Copy 2 of Copy 3 of
Auxiliary_151 Auxiliary_151

The higher the complexity, more time is


needed to complete the process.
Complexity impacting cycle time
Auxiliary_159
Copy of
Auxiliary_159 Auxiliary_174
Auxiliary_160 Copy of
Auxiliary_160
Auxiliary_173

Auxiliary_161 Copy of Probability


Auxiliary_155 Copy of
Auxiliary_161
Auxiliary_155
Auxiliary_165 Copy of
Auxiliary_156 Auxiliary_165
Auxiliary_115 Copy of
Auxiliary_162 Auxiliary_115
Auxiliary_156 Copy of
Auxiliary_162 Copy of Auxiliary_38 Auxiliary_38
Auxiliary_172
Auxiliary_157 Copy of
Auxiliary_157
Auxiliary_163 Copy of
Auxiliary_163
Auxiliary_158 Copy of
Auxiliary_158
Auxiliary_164
Copy of
Auxiliary_164

Copy of Auxiliary_168 Auxiliary_170


Auxiliary_165 Auxiliary_37 Copy of Auxiliary_37
Auxiliary_167

Auxiliary_172
Auxiliary_38 Copy of Auxiliary_38
Auxiliary_115 Auxiliary_115
Auxiliary_171
Auxiliary_165 Auxiliary_166

Auxiliary_169
standard cycle time
standard plus
additional

standard plus The higher the complexity, more time is


standard cycle time additional Auxiliary_176 needed to complete the process.
Complexity impacting cycle time
Auxiliary_175

Auxiliary_116 Copy of
Auxiliary_116 Probability

Copy of
Auxiliary_117 Copy of Auxiliary_117
Auxiliary_117
Auxiliary_102 Auxiliary_102 Auxiliary_117

Figure 15: The next or future stage of procurement model developed using system dynamics methodology.
14 Advances in Operations Research

model produces total number of days involved in completing


procurement process.
Level_1
Rate_1 Rate_2

Figure 16: Water tank model developed using system dynamics Conflicts of Interest
methodology.
There are no potential conflicts of interest in the study.

100 Acknowledgments
Level_1 (Liter)

50 The author would like to thank Roswidah Mat Lui of Telekom


Research & Development Sdn Bhd for providing invaluable
0 insight into procurement process.
0:00 6:00 12:00 18:00 0:00
01
References
Figure 17: The behavior of Scenario A.1’s Level 1.
[1] B. Asgari and M. A. Hoque, “A system dynamics approach to
supply chain performance analysis of the ready-made garment
10 industry in Bangladesh,” Ritsumeikan Journal of Asia Pacific
Level_1 (Liter)

8 Studies, vol. 32, 2013.


6
4 [2] A. Kussainov, “Use of system dynamics and simulation in
2 modeling and analysis of vaccine supply chain management,”
0 Information technologies, Management and Society, vol. 8, no. 1,
0:00 6:00 12:00 18:00 0:00 pp. 32–37, 2015.
01
[3] Z. A. Malik and J. K. Cheng, “A system dynamics model to
Figure 18: The behavior of Scenario A.2’s Level 1. understand the interrelationship between different knowledge
areas in construction project,” International Journal of Business
Management, vol. 2, no. 1, 2017.
[4] V. Latorre, M. Roberts, and M. J. Riley, “Development of a sys-
tank reached the level of 100 Liters or more, it (i.e., the tank) tems dynamics framework for KPIs to assist project managers’
decision making processes,” Revista de la Construccion, vol. 9,
will be flushed automatically and the whole process of filling
no. 1, pp. 39–49, 2010.
up the tank is repeated as shown in Figure 17. The behavior of
Level 1 as shown in Figure 17 especially before flushing could [5] W. Cahyo, K. O. El-Akruti, R. Dwight, and T. Zhang, “A
be explained by the following (mathematical) formula: resources provision policy for multi-unit maintenance pro-
gram,” in 8th World Congress on Engineering Asset Management
& 3rd International Conference on Utility Management & Safety,
{ 10 (𝑡 − 0) ; 𝑡 = 1, 2, . . . , 10 pp. 1–12, 2013.
{
{
{
Level 1 = {10 (𝑡 − 10) ; 𝑡 = 11, 12, . . . , 20 (A.1) [6] A. Sadreddin, R. Sawan, and A. Schiffauerova, “Using system
{
{ dynamics approach to model cost of quality in the procurement
{. ..
. process of the construction industry,” in Proceedings of the First
{. .
Asia-Pacific System Dynamics Conference of the System, Tokyo,
Japan, 2014.
Scenario A.2. The following are the equations used in water
[7] K. Ross-Smith and M. Yearworth, “Dynamics of operational
tank model: Rate 1 = 10 Liter/Hour; Level 1 = 0 Liter (at the
procurement: systems modelling for performance tracking
beginning); Rate 2 = Level 1 Liter/Hour. Over a period of 24 and auditing,” in Proceedings of the The 29th International
hours where the water tank is empty at the beginning, water Conference of the System Dynamics Society, Washington, USA,
flows into the tank at the rate of 10 Liters per hour. Water 2011.
in the tank increases exponentially until it reaches stationary
[8] S. Croom and R. Johnston, “E-service: Enhancing internal cus-
level at (approximately) 10 Liters. The behavior of Level 1 tomer service through e-procurement,” International Journal of
as shown in Figure 18 could be explained by the following Service Industry Management, vol. 14, no. 5, pp. 539–555, 2003.
(mathematical) formula:
[9] A. C. Marquez and C. Blanchar, “The procurement of strategic
−𝑡 parts. Analysis of a portfolio of contracts with suppliers using
Level 1 = 10 (1 − 𝑒 ) , 𝑡 = 1, 2, . . . . (A.2) a system dynamics simulation model,” International Journal of
Production Economics, vol. 88, no. 1, pp. 29–49, 2004.
Additional Points [10] J. Mula, F. Campuzano-Bolarin, M. Dı́az-Madroñero, and K. M.
Carpio, “A system dynamics model for the supply chain pro-
Highlights. (i) Using system dynamics methodology, a pro- curement transport problem: Comparing spreadsheets, fuzzy
curement model is developed; (ii) two scenarios are incor- programming and simulation approaches,” International Jour-
porated into the said (procurement) model; (iii) the said nal of Production Research, vol. 51, no. 13, pp. 4087–4104, 2013.
Advances in Operations Research 15

[11] M. Marinkovic, Designing outcome based performance manage-


ment systems through system dynamics modeling to frame cor-
ruption behavior in public procurement [Ph.D. thesis], Universita
Degli Studi Di Palermo, 2015.
[12] J. W. Forrester, Some basic concepts in System Dynamics, Sloan
School of Management, Massachusetts Institute of Technology,
Cambridge, UK, 2009.
[13] B. W. Silverman, Density Estimation for Statistics and Data
Analysis, Chapman & Hall, London, UK, 1986.
[14] L. Sachs, Applied Statistics: A Handbook of Techniques, Springer-
Verlag, 2nd edition, 1984.
Advances in Advances in Journal of The Scientific Journal of
Operations Research
Hindawi
Decision Sciences
Hindawi
Applied Mathematics
Hindawi
World Journal
Hindawi Publishing Corporation
Probability and Statistics
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 http://www.hindawi.com
www.hindawi.com Volume 2018
2013 www.hindawi.com Volume 2018

International
Journal of
Mathematics and
Mathematical
Sciences

Journal of

Hindawi
Optimization
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018

Submit your manuscripts at


www.hindawi.com

International Journal of
Engineering International Journal of
Mathematics
Hindawi
Analysis
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018

Journal of Advances in Mathematical Problems International Journal of Discrete Dynamics in


Complex Analysis
Hindawi
Numerical Analysis
Hindawi
in Engineering
Hindawi
Differential Equations
Hindawi
Nature and Society
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018

International Journal of Journal of Journal of Abstract and Advances in


Stochastic Analysis
Hindawi
Mathematics
Hindawi
Function Spaces
Hindawi
Applied Analysis
Hindawi
Mathematical Physics
Hindawi
www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018 www.hindawi.com Volume 2018

You might also like