Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/278036445

Causes and Effects of Delays in Construction of Medium Scale Drinking Water


Supply Projects in Sri Lanka

Article · January 2012

CITATIONS READS

0 1,735

2 authors, including:

Rangika Umesh Halwatura


University of Moratuwa
108 PUBLICATIONS   486 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Energy rating system for urban dwellings View project

Earthen thin shell slab systems for low-cost housing in Sri Lanka View project

All content following this page was uploaded by Rangika Umesh Halwatura on 12 June 2015.

The user has requested enhancement of the downloaded file.


Annual Transactions of IESL, pp. [151-159], 2012
© The Institution of Engineers, Sri Lanka

Causes and Effects of Delays in Construction of


Medium Scale Drinking Water Supply Projects in
Sri Lanka
W.D.A. Perera and R.U. Halwatura

Abstract: Most of the infrastructure developments are carried out on project basis. Construction
projects frequently suffer from delay, though there are many sophisticated tools and techniques
available for construction project management. This paper presents the results of a questionnaire
survey conducted to identify and rank the causes and effects of delays in construction of medium
scale drinking water supply projects in Sri Lanka. Both Severity Index (SI) and Frequency Index (FI)
were used to rank the importance of the factors and the findings of the study indicate that inclement
weather conditions, contractors’ financial difficulties, shortage of labour, rules and regulations of road
authorities, delays in sub contractors’ work, material import delays and ineffective planning and
scheduling of projects by contractors are among the most important factors causing delay in
construction of medium scale drinking water supply projects. Moreover, time overruns, cost overruns,
funding difficulties, development of unfair relationships among the parties and disputes are the most
important effects due to delay. Delays are costly for both clients and contractors and often result in
disputes and claims. Therefore in order to improve the situation and avoid /mitigate delays in
construction of medium scale water supply projects, several prescriptions are recommended for
clients and contractors.

Keywords: Water supply projects, Causes and effects of delays, Ranking of delay factors

tasks to be performed and a defined time


1. Introduction frame and also every construction contract
considers time as the essence of the project.
In Sri Lanka, a considerable amount of the Delay is a situation when the contractor and
national budget on infrastructure development the project owner jointly or individually
is channelled to water supply sector and at contribute to the non-completion of the project
present only around 37 percent of the within the original or the stipulated or agreed
population have access to pipe borne water [1]. contract period [2]. Delays in construction
The demand for pipe borne water is growing projects are frequently expensive, as they are
continuously with the increased level of usually involved with construction loans
urbanization, change in lifestyles and which charges interest, management staff
expansion of commercial and industrial dedicated to the project whose costs are time
activities. National Water Supply & Drainage dependent and ongoing inflation in wage and
Board is responsible for supplying pipe borne material prices [3].
drinking water to the nation. The operation
and maintenance of existing water supply Some projects are susceptible to delay due to
schemes and the implementation of projects to their nature and water and sewerage projects
construct new schemes to meet the growing are in this category with several influential
demand due to urbanization are among the factors causing delays. These factors include;
major tasks of it. In recent past, number of the projects are taken place in public roads and
water supply projects that had been planned to streets where special precautions are required,
supply water to developing areas in and high uncertainty associated as they require
around major cities of the country has failed to Eng. W D Anuruddha Perera, B.Sc.Eng.(Hons),
meet the time targets due to various reasons M.Sc.(CPM), C.Eng., MIE(Sri Lanka), Chief Engineer,
National Water Supply & Drainage Board, Avissawella.
and affected the socio-economic development Eng. (Dr.) R U Halwatura, BSc Eng. (Hons), PhD,
of the country. CEng., MIE(Sri Lanka), AMSSE, Senior Lecturer, Civil
Engineering Department, University of Moratuwa.
Most of the infrastructure developments are
carried out on project basis. Every construction
project has a defined goal or objective, defined
1

151
excavation and trenching works in varied soil site, changes in specifications and labour
and site conditions, works are heavily disputes and strikes were found to be the
dependent on equipment and machineries, major causes of schedule delay in road
which are susceptible to repairs and need to construction projects in Zambia [10].
get approvals from various authorities [4].
Further, the procedures in issuing of approval Both the project owners and contractors suffer
certificates for excavation for trenching from from the delays. The owner loses his money
government authorities are complex and time due to increased overheads for supervision,
consuming due to lack of coordination and contract administration and also delaying the
various other reasons [5]. There are different use of the final product or result of the project
perceptions among the major parties involved [4]. On the other hand, the contractor losses
in projects regarding the causes of project may be the lost opportunities for new projects,
delays. Both contractors and consultants agree increased overheads, etc. But, most of the
that owner interference, inadequate contractor construction projects suffer from delay, though
experience, financing and payments, labour there are many tools and techniques available
productivity, slow decision making, improper for project management.
planning and sub-contracting are among top
ten causes of construction delays in traditional However, there are only few previous studies
contracts [6]. In most of the developing available on this topic and related to our
countries, infrastructure development projects construction projects. Therefore, there is a
are implemented through the major need for more efforts to identify the causes and
government authorities that still act as effects of delays in different types of
traditional organizers and strictly bound to construction projects in Sri Lanka and made
follow government rules and regulations on awareness of the relevant parties involved to
procurement. There are a lot of criticisms on avoid or minimize them and complete the
the inefficiencies of these government projects successfully.
institutions regarding project implementation.
2. Objectives of the Study
The Contractor’s improper planning is the
major cause of delay in Malaysian construction
industry [7]. According to this study, · To identify and rank causes and effects of
contractors often fail to come out with a delays in construction of medium scale
practicable and workable “work program” at drinking water supply projects in Sri
the initial planning stage and this failure is Lanka.
interrelated with lack of systematic site
management and inadequate contractor’s · To study the difference in perceptions of
experience towards the projects. On the other the two major parties involved in
hand, the significant factors causing delays in construction of drinking water supply
Hong Kong construction projects are: ‘poor projects namely clients and contractors on
site management and supervision’, causes and effects of delays in construction
‘unforeseen ground conditions’, low speed of of medium scale drinking water supply
decision making involving all project teams’, ‘ projects.
client – initiated variations’ and ‘necessary
variations of work’ [8]. Further, the most · Propose measures to mitigate delays in
significant problems causing construction construction of medium scale drinking
project delays in Thailand includes lack of water supply projects.
resources, poor contractor management,
shortage of labour, design delays, planning
and scheduling deficiencies, change orders 3. Research Methodology
and contractors' financial difficulties[9].
Moreover, delayed payments, financial A detailed literature review was carried out to
processes and difficulties on the part of identify the previous studies in the research
contractors and clients, contract modification, area and found the major causes and effects of
economic problems, materials procurement, delays in projects in Sri Lanka and other
changes in drawings, staffing problems, counties. Then, a careful identification of the
equipment unavailability, poor supervision, factors related to the study were done and a
construction mistakes, poor coordination on survey questionnaire was developed to assess

152
the perceptions of contractors and clients who low productivity level of workers,
were involved in construction of medium scale shortage of labour, labour union actions.
water supply projects on the relative vii. External factors: Inclement weather
importance of causes and effects of conditions, delay in obtaining permits,
construction delays. The questionnaire services, etc. from local authorities and
consisted of four parts; part I- respondents’ other organizations such as electricity
details, part II–causes of delays, part III–effects board, traffic/security problems, changes
due to delays, part IV– mitigation actions. The in government regulations and laws, rules
first part of the questionnaire requested the and regulations of Road Development
respondents’ general details while the second Authority(RDA), Provincial Road
part of the questionnaire consisted of thirty Development Authority (PRDA) and local
nine causes of delay that were categorized government authorities (PS) on road
under seven major groups: excavation work approvals.
i. Project related: Inadequate project
The third part of the questionnaire consisted of
duration, Improper contract formulation
the effects due to delay checklist: Time overrun
(large Nos. of contracts for a single project,
cost overrun, dispute, arbitration, litigation,
intake civil construction work included in
total abandonment, funding difficulties, delay
a pump contract, etc.),type of project
in commissioning other related projects and
bidding and award (tendency in awarding
develop unfair relationships with other
the contracts to lowest bidder)
organizations such as RDA, PRDA, PS, etc. The
ii. Owner/consultant related: Delay in
last part of the questionnaire is for getting the
progress payments by owner, delay in
respondents prescriptions to reduce delays in
handing over the site to the contractor,
construction of medium scale water supply
delay in approval of shop drawings and
projects. For each cause/effect two questions
samples, delay in inspection and testing of
were asked: what is the frequency of
works, Inadequate Liquidated damages,
occurrence for this cause? and what is the
too many change orders, slow decision
degree of severity of this cause on project
making, poor contract management of
delay? Both frequency of occurrence and
owner/consultant.
degree of severity were categorized on a four
iii. Contractor related: Contractors financial
point scale. Frequency of occurrence was
difficulties, mistakes during construction
categorized as: Rarely, Sometimes, Often and
and rework, shortage of project staff with
Always. Similarly, degree of severity was
required experience, Poor
categorized as: Little, Moderate, Great and
coordination/communication by the
Extreme.
contractor with other parties, Ineffective
planning and scheduling of project by
In Sri Lanka, almost all the medium scale
contractor, improper construction methods
drinking water supply projects are carried out
implemented by contractor, delays in sub
by the National Water Supply and Drainage
contractors’ work, insufficient delegation
Board and the contractors are involved in
of power to the site management team.
these developments. The questionnaire was
iv. Design related: Delays in producing
distributed among the professionals of the
construction drawings, unclear and
above two groups and the sampling method
inadequate details in drawings, mistakes
used in this study was convenience and
and discrepancies in drawings and bills of
snowball sampling that comes under the class
quantities, inadequate specifications for
of non-probability sampling techniques [7].
materials.
v. Materials related: Shortage of construction
materials in market, changes in material 3.1 Ranking of delay factors
types and specifications during The ranking of causes and effects of delays
construction, restrictions on issuing from the viewpoints of three parties involved
permits to transport materials, rejection of in construction projects; owners, contractors
imported materials due to non-compliance and consultants can be done using three
with the contract specifications. indices; frequency index, severity index and
vi. Equipment and Labour related: Frequent importance index [11]. The similar method was
equipment breakdown, shortage of applied in the study and the following
equipment and hiring delays, low equations were used for the calculation of
productivity and efficiency of equipment, three indices. Frequency index (FI) is a formula

153
used in the study to rank causes of delay based 4.2 Data Analysis
on frequency of occurrence as identified by the The responses to the questionnaires were
participants. : analyzed from client’s, contractor’s and overall
perspectives based on severity and frequency
(FI) (%) = ∑a (n/N)*100/4 (1) of occurrence of the causes and effects to
identify the most important causes and effects
where, a is the constant expressing weighting of delays. The ranking indices were calculated
given to each response (ranging from 1 for using the three formulas stated under
rarely up to 4 for always), n is the frequency of methodology and are presented in Tables 3
the responses, and N is total number of and 4.
responses. Severity Index (SI) is a formula Table 2 - Respondent’s Qualifications
used in the study to rank causes of delay based Basic No. of
on severity as identified by the participants. Category Qualification Respondents %
Dip. 11 25.6

(SI) (%) = ∑a (n/N)*100/4 (2) B.Sc. 20 46.5


Client
M.Sc. 12 27.9
Ph.D. 0 0.0
where a is the constant expressing weighting Dip. 10 25.0
given to each response (ranges from 1 for little B.Sc. 25 62.5
Contractor
up to 4 for severe), n is the frequency of the M.Sc. 5 12.5
responses, and N is total number of responses. Ph.D. 0 0.0
Importance Index (IMPI) of each cause is Dip. 21 25.3
B.Sc. 45 54.2
calculated as a function of both frequency and Total
M.Sc. 17 20.5
severity indices.
Ph.D. 0 0.0

(IMPI) (%) = (FI) (%) *(SI) (%) (3)


5. Discussion of Results
4. Data analysis This section discusses the results obtained in
the analysis. First, the results obtained by
4.1 Sample Characteristics analyzing the causes of delay in construction
The questionnaires were distributed to a of medium scale water supply projects were
sample of professionals of the two major discussed and compared the client, contractor
parties (clients and contractors) involved in and overall perspectives. Then, the results
the construction of medium scale water supply obtained by analyzing the effects due to delay
projects by hand delivery, regular mail and were discussed.
also via internet. The survey was carried out
over the period from August 2010 to October 5.1 Causes of Delay
2010, and the response rate and the basic The importance of the identified thirty nine
qualifications of the sample were as shown in causes of delay in construction of medium
the Tables 1 and 2. scale water supply projects were depended on
both the severity and frequency of occurrence.
Table 1- Questionnaire Response Rate Severe delay factors
The results of the analysis show that the
Hand Regualr Via clients’ ranked ineffective planning and
Category Questionnaire sent Total
delivery mail Internet scheduling of the project by contractor
Nos. of participants 36 15 21 72 (SI=87.79), contractor’s financial difficulties
Client Nos. of respondents 28 12 3 43 (SI=84.30) and rejection of imported materials
Response rate% 77.78 80.00 14.29 59.70 (SI=83.72) as the most severe causes of delay
Nos. of participants 35 15 20 70 while the contractor considers weather
Contractor Nos. of respondents 30 4 6 40
conditions (SI=90.00), delays in sub
contractors’ work (SI=89.38) and delay in
Response rate% 85.71 26.67 30.00 57.14
progress payments by owner (SI=88.13). This
Nos. of participants 71 30 41 142
shows that there is a disagreement between
Total Nos. of Respondents 58 16 9 83 the two parties regarding the most severe
Response rate % 81.69 53.33 21.95 58.5 causes of delays. In Sri Lanka, almost all the
medium scale water supply projects are
implemented through National Water Supply
& Drainage Board and funded by either the
capital budget or foreign donor funds.
4

154
Table 3 - Ranking of Causes of Delay Table 4 - Ranking of Effects due to Delay
Client Contractor Overall
Factor Description Contractor's view Client's View Overall view

Rank

Rank
Imp.

Imp.

Imp.

Rank
Inde

Inde

Inde
No Effects due to delay

Index

Index

Index
SI

FI

SI

FI

SI

FI

Rank

Rank

Rank
Imp.

Imp.

Imp.
Causes of delay

SI
FI

SI

FI

SI

FI
Project related
1 Time overrun 78.8 90.0 70.9 1 80.2 86.6 69.50 1 82.8 88.3 73.10 1
1 Inadequate Contract duration 64.5 47.1 30.4 22 86.9 84.4 73.3 5 75.3 65.1 49.0 16
2 Cost overrun 84.4 81.9 69.1 2 79.7 76.2 60.66 2 81.9 78.9 64.65 2
2 Improper contract formulation 63.4 34.9 22.1 34 60.0 42.5 25.5 36 61.7 38.6 23.8 35
3 Dispute 36.3 85.0 30.8 7 34.9 89.5 31.23 5 44.0 88.6 38.94 5
3 Tendency in awarding the 51.7 77.9 40.3 18 68.1 76.9 52.4 21 59.6 77.4 46.2 17
4 Arbitration 68.1 51.9 35.3 5 63.4 47.1 29.84 6 70.5 51.8 36.51 6
contracts to lowest bidder
Owner/consultant related 5 Litigation 82.5 39.4 32.5 6 79.7 34.3 27.32 8 81.0 36.7 29.77 7
4 Delay in progress payments by 76.2 56.4 43.0 16 88.1 84.4 74.4 4 81.9 69.9 57.3 11 6 Total abandonment 96.9 28.8 27.9 8 94.8 29.1 27.55 7 88.6 28.9 25.61 8
owner
5 Delay in handing over the site to 77.3 72.1 55.7 8 81.3 78.1 63.5 19 79.2 75.0 59.4 9
7 Funding difficulties 83.8 81.3 68.0 3 66.3 75.0 49.71 3 72.9 78.0 56.86 3

the contractor Delay in commissioning other


6 Delay in approval of shop 51.7 50.0 25.9 31 76.9 88.1 67.7 15 63.9 68.4 43.7 20 8 41.9 42.5 17.8 9 48.8 37.8 18.46 9 45.5 34.9 15.89 9
related projects
drawings and samples
7 Delay in inspection and testing of 52.9 44.8 23.7 32 80.0 85.0 68.0 14 66.0 64.2 42.3 22 Develop unfair relationships with
works 9 other organizations such as RDA, 69.4 65.6 45.5 4 60.5 72.1 43.59 4 59.0 69.0 40.72 4
8 Inadequate application of 59.9 66.3 39.7 19 56.9 38.8 22.0 38 58.4 53.0 31.0 31 PRDA, PS,etc.
Liquidated damages Source: calculated from survey data
9 Too many change orders 72.7 75.6 54.9 9 80.6 83.8 67.5 16 76.5 79.5 60.8 8
10 Slow decision making 62.8 41.3 25.9 30 78.1 89.4 69.8 10 70.2 64.5 45.2 19
11 Poor contract management of 62.2 37.2 23.1 33 83.1 82.5 68.6 13 72.3 59.0 42.7 21 There is a high competition in the industry and
owner/consultant most of the contracts are awarded to lowest
Contractor related
12 financial difficulties 84.3 83.1 70.1 2 79.4 86.9 69.0 11 81.9 84.9 69.6 2
bidders who are normally having a little profit
13 Mistakes during construction and 52.3 54.1 28.3 27 56.9 51.9 29.5 31 54.5 53.0 28.9 32 margin. There are delays in monthly progress
rework payments to the contractors due to the
14 Shortage of project staff 63.4 74.4 47.2 12 64.4 56.9 36.6 27 63.9 66.0 42.1 23
15 Poor coordination/ 64.0 79.7 50.9 11 64.4 46.3 29.8 30 64.2 63.6 40.8 24
financial difficulties faced by the client. Hence,
communication the work progress can be delayed.
16 Ineffective planning and 87.8 92.4 81.2 1 73.8 56.9 41.9 25 81.0 75.3 61.0 7
scheduling of project
17 Improper construction methods 54.7 55.2 30.2 23 58.1 45.6 26.5 34 56.3 50.6 28.5 33 Frequent delay factors
18 Delays in sub contractors’ work 75.6 77.3 58.4 7 89.4 88.8 79.3 2 82.2 82.8 68.1 5 Frequency of occurrence of delay factors is also
19 Insufficient delegation of power to 56.4 52.9 29.8 24 59.4 60.6 36.0 29 57.8 56.6 32.7 29 a significant aspect, which uses to determine
the site
Design related
the importance of causes of delay. The client
20 Delays in producing construction 70.3 43.6 30.7 21 73.1 67.5 49.4 22 71.7 55.1 39.5 26 ranked Ineffective planning and scheduling of
drawings project by contractor (FI 92.44) as the most
21 Unclear and inadequate details in 55.8 50.6 28.2 28 87.5 80.0 70.0 9 71.1 64.8 46.0 18
drawings frequent factor causing delays in construction
22 Mistakes and discrepancies in 52.3 85.5 44.7 14 78.1 90.0 70.3 7 64.8 87.7 56.8 12 of medium scale water supply projects while it
drawings and BOQ
23 Inadequate specifications for 56.4 34.3 19.3 37 57.5 51.3 29.5 32 56.9 42.5 24.2 34
is ‘inclement weather conditions’ for both
materials contractor’s (FI 91.25) and overall (FI 88.6)
Materials related rankings. The inclement weather conditions
24 Shortage of construction materials 66.9 43.6 29.2 26 55.6 65.0 36.2 28 61.4 53.9 33.1 28
badly affect the construction of water supply
25 Material import delays (Pipes, 76.7 78.5 60.2 6 81.9 86.3 70.6 6 79.2 82.2 65.1 6 projects and in sometimes it will cease the
fittings, etc.)
26 Changes in material types and 59.9 35.5 21.2 36 57.5 44.4 25.5 35 58.7 39.8 23.4 37
construction activities until the weather
specifications becomes normal [12]. This supports the
27 Restrictions on issuing permits to 56.4 80.2 45.2 13 77.5 85.6 66.4 17 66.6 82.8 55.1 13
findings of the research and reconfirms that
transport materials.
28 Rejection of imported materials 83.7 44.2 37.0 20 81.9 53.8 44.0 24 82.8 48.8 40.4 25 inclement weather is a frequent cause of delay
Equipment and Labour related in construction of water supply projects and
29 Equipment breakdown 55.8 79.1 44.1 15 72.5 81.3 58.9 20 63.9 80.1 51.2 15 the project teams should draw special
30 Shortage of equipment and hiring 52.3 56.4 29.5 25 65.6 74.4 48.8 23 58.7 65.1 38.2 27
delays
attention to the inclement weather conditions
31 Low productivity and efficiency of 47.7 55.8 26.6 29 61.9 61.3 37.9 26 54.5 58.4 31.9 30 at the planning, design and construction stages
equipment of the medium scale water supply projects.
32 Low productivity level of workers 57.6 73.8 42.5 17 78.8 87.5 68.9 12 67.8 80.4 54.5 14
33 Shortage of labour 80.2 84.3 67.6 3 82.5 85.0 70.1 8 81.3 84.6 68.8 3
34 Labour union actions 51.2 28.5 14.6 39 56.3 31.3 17.6 39 53.6 29.8 16.0 39 Further, the delay factors such as RDA, PRDA,
External factors and PS rules and regulations on road
35 Inclement weather conditions 72.7 86.0 62.5 4 90.0 91.3 82.1 1 81.0 88.6 71.8 1
excavation work approvals, material import
36 Delay in obtaining permits, 64.0 84.9 54.3 10 75.6 85.0 64.3 18 69.6 84.9 59.1 10
services, etc.
delays (pipes, fittings, etc.) that occur due to
37 Traffic/security problems 44.2 48.3 21.3 35 51.3 51.9 26.6 33 47.6 50.0 23.8 36 the nature of water supply projects are
38 Changes in government 51.7 31.4 16.2 38 62.5 38.1 23.8 37 56.9 34.6 19.7 38 identified by clients as well as contractors as
regulations and laws
39 RDA, PRDA, PS. rules and 75.0 82.6 61.9 5 83.8 90.6 75.9 3 79.2 86.4 68.5 4 frequent causes of delay and ranked within
regulations first ten positions. Moreover, both the clients
and the contractors ranked the delay factors

155
‘labour union actions’ and ‘changes in
government regulations and laws’ as very rare Table 5 - Important Delay Factors
causes of delay in construction of medium Contractor’s Overall
Client’s view
scale water supply projects although in some view view
other sectors in Sri Lanka ‘union actions’ are 1 Ineffective Inclement Inclement
very frequent. One of the reasons for this is planning and weather weather
less opportunities in the construction industry scheduling of conditions conditions
to organize for bargaining for their benefits. project by
contractor
But in the recent past the union actions of
2 Contractors Delays in sub Contractors
clients professional staff had been affected financial contractors’ financial
project activities and there had been delays in difficulties work difficulties
extra work approvals, tender evaluations, 3 Shortage of RDA, PRDA, Shortage of
tender awarding, and etc., which caused labour and PS rules labour
delays in construction of water supply and
projects. regulations on
road
The construction of water supply projects excavation
work
requires getting various types of approvals
approvals
from government institutions. Due to 4 Inclement Delay in RDA,
improper coordination with these weather progress PRDA, PS.
organizations, it has been facing difficulties in conditions payments by rules and
getting these approvals on time. The delays in owner regulations
getting approvals for road excavation that on road
requires for pipe laying in public roads have excavation
been identified as a frequent causes of delay in work.
construction of water supply projects. Further, 5 RDA, PRDA, Inadequate Delays in
PS. rules and contract sub
the introduction of new rules and regulations
regulations on duration contractors’
of Road Development Authority (RDA) on road excavation work
road reinstatement after trenching has severely work approvals
affected the implementation of water supply 6 Material import Material Material
projects, as it requires some time to adjust to delays (Pipes, import delays import
new requirements and take necessary policy fittings, etc.) (pipes, fittings, delays
decisions to develop relevant systems to carry etc.) (Pipes,
out the works. Therefore early attention fittings, etc.)
should be drawn in this regard and develop 7 Delays in sub Mistakes and Ineffective
contractors’ discrepancies planning
some effective and efficient systems to handle
work in drawings and
RDA requirements and provide necessary and bills of scheduling
provisions in contracts to do the temporary as quantities of project by
well as permanent road reinstatement. contractor
8 Delay in Shortage of Too many
Important delay factors handing over labour change
The results of the analysis show that there are the site to the orders
several important factors underlying causes of contractor
delay in construction of medium scale water 9 Too many Unclear and Delay in
change orders inadequate handing
supply projects in Sri Lanka. Ten most
details in over the site
important delay factors as identified by clients,
drawings to the
contractors and overall view are presented in contractor
Table 5. 10 Delay in Slow decision Delay in
obtaining making obtaining
Contractors ranked inclement weather permits, permits,
conditions first, whereas the clients ranked it services, etc. services, etc.
fourth. The construction of medium scale from local
water supply projects normally includes authorities and
other
construction of head works, laying of
organizations
transmission and distribution systems and
such as
construction of office, stores and other Electricity
facilities. Board.

156
medium scale water supply projects due to
The inclement weather affects most of these many reasons, the relevant organizations have
works, and especially for pipe laying works taken measures to complete the projects
and intake construction works. Contractor’s without abandonment. Further, the clients and
ineffective planning and scheduling of the contractors agreed that time overruns and cost
project will make worse the situation if he does overruns are among the most severe effects
not consider or fails to predict the weather due to delay. These effects may lead to other
pattern at the initial planning. effects such as disputes, funding difficulties,
delay in commissioning related projects, etc.
Skills and experience of workforce,
management, job planning, workers On the other hand, both clients and contractors
motivation, and material availability were the agreed that time overruns, cost overruns and
major drivers of productivity of water and disputes are the most frequent effects due to
waste water treatment plant construction delay in construction of medium scale
works [13]. It is essential to draw special drinking water supply projects in Sri Lanka.
attention to these factors and apply in Most of the delay factors, which were
construction of medium scale water supply categorized under seven sections in this study,
projects as this will help to speed up of the affect the completion of the projects and cause
works and also help to expedite the delayed time overrun, cost overrun and disputes.
works due to various causes identified in this Similar effects have been identified as the most
study. frequent effects due to delays in Nigerian
construction industry through a study carried
Agreement among groups out concentrating the building construction
The degree of agreement between the clients industry [15]. This study mainly
and contractors on causes of delays in recommended providing sufficient
construction of medium scale water supply contingency provisions in total cost estimates
projects was calculated using spearman’s rank to handle the project uncertainties. As the
correlation coefficient. The equation, rs = 1- construction of water supply projects also
(6∑d2/N(N2-1)) was used to calculate this faces a lot of uncertainties due to their nature
coefficient when there are no tied links [14]. [4], it is better to consider this recommendation
Where rs = Spearman’s rank correlation and decide contingency percentages wherever
coefficient, d = the difference in ranking necessary after carefully considering the
between the clients and the contractors and N requirements rather than providing fixed
= the number of variables. The spearman’s percentages from the contract value.
correlation coefficient calculated was 0.55 for
the causes of delays ranked by the clients and The importance of the effects due to delay the
contractors. Spearman’s rank correlation same as the importance of causes of delay is
coefficient equals to +1 means that two determined by considering both severity and
variables are having perfectly positive frequency of occurrence. Hence some effects
correlation while -1 gives perfectly negative due to delay, which were having higher
relationship. The somewhat low value of rank frequency indices with low severity indices,
correlation coefficient (0.55) indicates low were ranked as the lesser important factors. As
agreement between clients and contractors on an example, “Disputes” has the highest
the ranking of the factors. This low agreement frequency index of 88.6% and the least severity
has created disputes between the parties and index of 44.0% as per the overall view, were
the most delays occur at the project ranked at 5th as per the importance with
construction phase. 38.94% importance index. Therefore the
identification of these effects due to delay
5.2 Effects due to Delay based on the above three indices will help the
Clients as well as contractors ranked, total project management to select the causes of
abandonment as the most severe effect due to delay, which requires more attention based on
delay in construction of medium scale water their consequences.
supply projects and the severity indices
calculated for them are 94.8 and 96.9,
respectively. But they ranked it as a very rare
effect due to delay and the frequency indices
are 29.1 and 28.8, respectively. This depicts
that though there are delays in construction of
7

157
6. Conclusions and construction of medium scale drinking water
Recommendations supply projects.

There are delays in construction of medium Prescriptions for Contractors


scale drinking water supply projects in Sri · Contractors must consider their financial
Lanka. As per the overall view inclement capabilities before bidding projects and
weather conditions, contractors’ financial should employ a qualified staff for the
difficulties, shortage of labour, rules and financial management of projects.
regulations of road authorities and delays in · Contractors should not take up the job in
sub contractors’ work are the first five which they do not have sufficient
important factors causing delays in expertise.
construction of medium scale water supply · Contractors should employ qualified and
projects. Further, both clients and contractors well experienced site staff during the
agree that rules and regulations of road project period.
authorities and inclement weather conditions · The planning and scheduling of the project
are among the most important delay factors. should be done properly and the revision
On the other hand, as per the overall view of the schedules has to be done as
inclement weather conditions, mistakes and required.
discrepancies in drawings and bills of · When employing sub-contractors it has to
quantities, rules and regulations of road be done after considering his capabilities
authorities, delay in obtaining permits services, and by entering into a formal agreement.
etc. and contractor’s financial difficulties are · Contractors should keep site records
the most frequent causes of delay while properly.
rejection of imported materials due to non- · Contractors should submit their claims as
compliance with contract, delay in sub- per the requirements given in the contract.
contractors ‘ work, delay in progress payments
by owner, contractors financial difficulties and Prescriptions for Clients
shortage of labour are ranked as the most
severe causes of delay. · Contractors should not be selected based
only on the lowest bid. The client should
On the other hand, time overruns, cost consider contractor’s experience in similar
overruns, funding difficulties, disputes, works and his technical and financial
arbitration, litigation, delay in commissioning capabilities, before awarding the contracts.
related projects, total abandonment and · It is necessary to decide realistic project
develop unfair relationships with road durations by the client considering various
authorities are the effects due to delay in aspects.
construction of medium scale water supply · The client should take necessary measures
projects. Both clients and the contractors felt to use qualified and experienced
that time overruns, cost overruns, funding professionals for planning and designs of
difficulties and develop unfair relationships projects.
with other organizations appear to be the most · The clients must take necessary actions to
important effects due to delay in construction handover the possession of site to the
of medium scale water supply projects. As per contractors without delay.
the overall view, disputes and time overruns · The client should employ a capable and
are the most frequent effects while total well experienced project staff for the
abandonment and time overruns are the most construction stage. They have to closely
severe effects due to delay. monitor the progress of work and propose
necessary steps to expedite the works to
A proper understanding of these causes of the contractor if the progress is behind the
delays and their consequences will help the schedule.
relevant project professionals to better manage · Appropriate total cost estimates should be
delay situations in construction of medium prepared at the initial stage of projects and
scale water supply projects. the client should settle the contractors’
claims without delay.
Further, based on the study, the following · Enforcing liquidated damage clauses and
prescriptions are recommended for clients and offering incentives for early completion.
contractors to avoid/mitigate delays in

158
· Minimize change orders during 10. Chabota Kaliba, A, Cost escalation and
construction to avoid delays. schedule delays in road construction projects
· The client should coordinate with other in Zambia. International Journal of Project
Management, pp.522-531, 2009.
organizations such as local authorities, road
authorities and various other government 11. Assaf, S., & Al-Hejji, S., Causes of delay in
organizations at various stages of projects. large construction projects. International
Journal of Project Management, pp.349-357,
2006.
6.1 Recommendations for Future Studies
Similar study can be conducted for other types 12. Frimpong, Y., Oluwoye, & Crawford, L.,
of infrastructure development projects such as Causes of delay and cost overruns in
road development projects, telecommunication construction of ground water projects in
projects, power generation projects, etc. and developing countries; Ghana as a case study.
compare the similarities and differences of International Journal of Project Management,
pp.321-326, 2003.
causes and effects of delays in these projects.

13. Mojahed, S., & Aghazadeh, F., Major factors


References influencing productivity of water and waste
water treatment plant construction: Evidence
from the deep South USA. International
1. Report, C. B. (2010), Central Bank Report, Journal of Project Management, pp.195-202,
pp.23-45. 2008.

2. Levy, S. M. (1994), Project Management in 14. Dowdy, S., & Wearden, S., Statistics for
Construction. Mgraw-Hill Inc.USA, pp. 54-65. research. New York: John Wiley & Sons,
pp.233-247, 1985.
3. Trauner, T.J., Construction Delays, Publisher,
Butterworth Heinemann, pp.126-143, 2009.
15. Aibinu, A., & Jagboro, G., The Effects of
4. Al-Khalil, M., & Al-Ghafly, M., Delay in public Construction Delays on project delivery in
utility projects in Saudi Arabia. International Nigerian Construction Industry. International
Journal of Project Management, pp.101-106, Journal of Project Management, pp.593-599,
1999. 2002.

5. Luu, V., Kim, S., Tuan, N., & Ogulana, S.,


Quantifying schedule risk in construction
projects using Baysian belief networks.
International journal of project management,
pp.425-437, 2008.

6. Odeh, A., & battaineh, H., Causes of


construction delay: traditional contracts.
International Journal of Project Management,
pp.67-73, 2002.

7. Sambasivan, M., & Soon, Y., Causes on effects


of delays in Malaysian Construction Industry.
International Journal of Project Management,
pp.517-527, 2007.

8. Chan, D., & Kumaraswamy, M., A


comparative study of causes of time overruns
in Hong Kong construction projects.
International Journal of Project Management,
pp.55-63, 1997.

9. Toor, S., & Ogunlana, S., Problems causing


delays in major construction projects in
Thailand. Construction Management &
Economics, pp.395-408, 2008.

159
View publication stats

You might also like