3) Project Schedule
3) Project Schedule
3) Project Schedule
01
Page 1 of 7
Actual Level of Effort Critical Remaining Work Date Revision Checked Approved
19-May-19 Schedule Rev.1 RS
Actual Work Milestone
Remaining Work summary
Construction of New Pumping Station at Jabel Hafeet Base N-16297 - Rev. 01
Page 2 of 7
N16297-EXI-DCO-1000 Disconnecting of power supplies, utilities, external instruments 30 Disconnecting of power supplies, utilities, external instruments
N16297-EXI-DCO-1010 Demolition of existing Pump Hall, Green Mubazzarah water pump station, gate house, roads
20 and paved area... Demolition of existing Pump Hall, Green Mubazzarah water pump station, gate house, roads and paved area...
N16297-EXI-DCO-1020 Reinstating the area 12 Reinstating the area
N16297-EXI-DCO-1030 Project Hand over 0 Project Hand over
Warranty Period after Project Handover 730 Warranty Period after Project Hand
N16297-EXI-WAR-1000 Warranty Period after Project Hand over 730 Warranty Period after Project Hand