Jurong Station King Post and Bored Pile

BORED PILE

No of Piles
Adopted Total Pile Length
Area Pile Diameter (mm) for each
Pile Length (m) in Soil (m)
section

STATION 1000 13 9.2 8.2


ENTRANCE A 1000 8 15.2 14.2

KING POST

No of Piles
Area UC Member Size for each UC Member Length
(kg/m) Weight (kg)
section
STATION 356 X 406 X 340 13 340 18
ENTRANCE A 356 X 406 X 340 8 340 12
Per Pile

% of Total
Pile Length in Rock Diameter % of Main Shear Concrete
No Shear Reinforcem
(m) (mm) Bar Steel Link Volume (m3)
Link ent (%)

1 20 25 1.00 T12-150 0.3 1.30 7.2


1 20 25 1.00 T12-150 0.3 1.30 11.9

Per Sections

UC Member
Weight (tonnage)

79.56
32.64
Per Pile Per Sections

Rebar
Rebar Rebar Weight Rebar
Weight Concrete Rebar Volume Rebar Weight
Volume (tonnage) Weight
(kg) Volume (m3) (m3) (kg)
(m3) [+15%] (tonnage)
[+15%]

0.09 848.0 0.8 93.9 1.22 11023.8 11.0


0.16 1401.0 1.4 95.5 1.24 11208.2 11.2
189.4 2.5 22232.0 22.2
TABLE 1: KING POST DETAILS AND QUANTITY TAKE OFF TABLE 2: BORED PILE DETAILS AND QUANTITY TAKE OFF

NUMBER OF SECTION MAIN CONCRETE


UC SECTION SIZE LENGTH OF TOTAL PILE PILE LENGTH ROCK SOCKET LINK REINFORCEMENT
LOCATION KING POST WEIGHT LOCATION REINFORCEMENT VOLUME
(mm x mm x kg) KING POST (m) LENGTH (m) IN SOIL (m) (m) ARRANGMENT WEIGHT (TONNAGE)
(nos) (TONNAGE) ARRANGMENT (m3)

UNDERGROUND UNDERGROUND
18 13 79.6 9.2 8.2 1.0 25 T 20 T12 - 150 94.0 11.1
STATION STATION
356 x 406 x 340
ENTRANCE A 12 8 32.7 ENTRANCE A 15.2 14.2 1.0 25 T 20 T12 - 150 96.0 11.3