SCHEDULE OF REMAINING WORK AT FACTORY AREA

CHOCOLATE MANUFACTURING PROJECT


Project : CHOCOLATE MANUFACTURING PROJECT - PURWAKARTA Date : 10 April, 2019

April May
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri 10
June
~ 20
I FACTORY AREA June
1. Epoxy Work
a. Area P4, P5 and P6

R-Skirting

b. Area Oil Stock Tank Room, Melting Room, Powder Handling Room & Raw
Material Pass Room, Raw Material Preparation Room & Store Area,

Floor Epoxy

R-Skirting

c. Area P7 and P8 Production Room


Floor Epoxy

R-Skirting

d. Packing Room
Floor Epoxy

R-Skirting

e. Liquid and Powder Services Tank Room


Floor Epoxy

R-Skirting

f. Raw Material Warehouse


Floor Epoxy

R-Skirting

g Product Warehaouse
Floor Epoxy

R-Skirting

2. Leveling Ceiling T-Bar Area Warehouse

3. Glasswool Installation

Page 1 of 1