SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.

00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Power Transformer - Storage, Handling, and Preservation
SATR-P-3910 3-Jul-18 ELECT
(SHP) Vibration Monitoring
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. Document Review

Schedule Q
A1 Review documents of Material Receiving for the Power Transformer. Att. IV
Sec. 3.3

Schedule Q
Identification procedure reviewed and implemented for the Power
A2 Att. IV
Transformer.
Sec. 4.2

Material identification shall be implemented for all materials, parts and


components, including partially fabricated assemblies. Power Transformer Schedule Q
A3 shall be identified by using tags, stamps, color coding, stencils or labels. Att. lV
The location and method of identification shall not affect the function or Sec.4.2
quality of the material.

B. General Requirements

Documentation for traceability reviewed and implemented. Power


Schedule Q
Transformer shall be traceable from the manufacturer and supplier
B1 Att. lV
through delivery, storage, fabrication, erection, installation, repair,
Sec. 4.3
modification and use.

Schedule Q
Documented Control System shall be implemented for all Saudi Aramco
B2 Att. lV
supplied material and equipment.
Sec. 5

C. Material Inspection

QC Before Installation- Power Transformer shall conform to all applicable Schedule Q


C1 requirements, standards, and specifications prior to release to be used as Att. IV
part of work. Sec. 3.3

Schedule Q
Incoming Power Transformer shall be visually inspected for damage /
C2 Att. IV
defects occurred during transportation.
Sec. 3.3

Schedule G Sec.
C3 Power Transformer shall be new and unused.
2.1

Power Transformer shall be in accordance with the Saudi Aramco-


C4 approved project-specific design drawings, diagrams, schedules, lists, Schedule G
databases, and associated design documents.

Page 1 of 5
Check that the Contractor or it's Saudi Aramco approved third party
Schedule Q
inspector performed the quality activities at the supplier and sub-supplier
C5 Att. llI
locations as required by the inspection level assigned for the materials
Sec. 3.2
and equipment identified in SAER-1972 Inspection Requirements.

Page 2 of 5
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Power Transformer - Storage, Handling, and Preservation
SATR-P-3910 3-Jul-18 ELECT
(SHP) Vibration Monitoring
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

D. TEST PROCEDURE AND CHECKLIST

Inspect impact recorder prior to unloading, if applicable. SAES-P-121


D1
NETA, ATS- Sec. 7.2.2.1.3 Sec. 3.2

GENERAL DESCRIPTION OF VIBRATION EVENT:

Vibration Event / Recorder / Transportation Data


SAES-P-121
D2 Log System (such as Cargo log FAT90) is a computerized system for
Sec. 3.2
measuring and registration of impacts during transportation and handling
of transformers.
Refer to Manufacturer's Recommendation.

The registration unit is normally placed in a tight box on the transformer in


SAES-P-121
D3 order to protect the measuring device from outside damage.
Sec. 3.2
Refer to Manufacturer's Recommendation.

This registration unit records Humidity, Acceleration X-Y-Z, Temperature,


SAES-P-121
D4 Tilt and Vibration.
Sec. 3.2
Refer to Manufacturer's Recommendation.

The registration unit is a battery-operated data logging unit fitted with built-
SAES-P-121
D5 in sensors for the above mentioned fields of operation.
Sec. 3.2
Refer to Manufacturer's Recommendation.

The unit is equipped with a 3.6 volt lithium battery and the collected values
SAES-P-121
D6 are being stored in a built in computer memory.
Sec. 3.2
Refer to Manufacturer's Recommendation.

The measurements are initiated and analyzed by a PC / Windows


SAES-P-121
D7 program and the measuring unit is started by setting pre-adjusted limit
Sec. 3.2
values. Refer to Manufacturer's Recommendation.

The registration unit is fitted with an indication system for immediate


analysis of the measuring period. By using the indication system, the user
can establish whether the pre-adjusted limit values have been exceeded
or not. This can be done as following description without using the PC-
program:
a) Open the protection box by loosening the four corner screws.
b) Four incident lamps are placed on the measuring unit. SAES-P-121
D8
Sec. 3.2
c) One test button is located to the right of the incident lamps.
d) Push the
test button and release, if any of the pre-adjustable limits have been
exceeded the incident lamp for that function will lit up. If any of the incident
lamps shines, the manufacturer of transformer shall be notified.
Refer to Manufacturer's Recommendation

STORAGE:
The Vibration
SAES-P-121
D9 Event Recorder shall be switched-off when the transformer is stored in
Sec. 3.2
yard or at concrete foundation pad.
Refer to Manufacturer's Recommendation.

HANDLING:
The Vibration Event / Recorder / Transportation Data Log System (such
SAES-P-121
D10 as Cargo log FAT90) shall be in operation during any kind of transformer
Sec. 3.2
handling from one location to another.
Refer to Manufacturer's Recommendation.

Page 3 of 5
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Power Transformer - Storage, Handling, and Preservation
SATR-P-3910 3-Jul-18 ELECT
(SHP) Vibration Monitoring
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

INSTALLATION:
Prior to start
assembly and installation of transformer, all the impact recorders shall be SAES-P-121
D11
removed and kept in store up to the commissioning & in operation of Sec. 3.2
transformer.
Refer to Manufacturer's Recommendation.

E. CONCLUSIONS

Test results are acceptable and in accordance with Saudi Aramco


E1 N/A
Engineering Standards and contractual requirements.

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule Q -- Quality Requirements (Pro Forma Contract), February 2008
2. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract)
4. NETA -- Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems, 2009
5. SAES-P-121 Transformers and Reactors 28 January 2016
6. Manufacturer's Catalogue as a reference- ABB Transformers Product Information No. 1ZSE469004-3E, 2001-01-25
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose
listing states that the equipment, material, or services either meets appropriate designated standards or has been tested and found
suitable for a specified purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified
organization concerned with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by
manufacturer
whose labeling the manufacturer indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Name, Title, Department,
Name, Initials and Date:
Company, Initials and Date:

QC Inspector PID Representative


Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others

Page 4 of 5
SAUDI ARAMCO ID/PIEU -3- July-2018 - REV. 2018.04.00 (Standards Cutoff -April 30, 2018) Rev. 2018.04.00 30-Apr-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Power Transformer - Storage, Handling, and Preservation
SATR-P-3910 3-Jul-18 ELECT
(SHP) Vibration Monitoring
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED