Professional Documents
Culture Documents
Summary of Quantities: Item No. Description Unit Quantity Remarks
Summary of Quantities: Item No. Description Unit Quantity Remarks
Summary of Quantities: Item No. Description Unit Quantity Remarks
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 5.89 611.92 3,605.55
b. Laborer 4 5.89 342.24 8,066.17
E. Materials
Sub-total for E -
F. Direct Unit Cost ( C + E ) 12,838.89
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 1,925.83
H. Contractors Profit ( CP ) 10% 1,283.89
I. Value Added Tax ( VAT ) 5% 802.43
J. Total Unit Cost 178.74
DETAILED UNIT PRICE ANALYSIS
PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R) - Fencing Type-C
Fleet-Marine Detachment, Rio Hondo, Zamboanga City
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 12.61 611.92 7,716.31
b. Laborer 4 12.61 342.24 17,262.59
E. Materials
Sub-total for E -
F. Direct Unit Cost ( C + E ) 27,476.79
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 4,121.52
H. Contractors Profit ( CP ) 10% 2,747.68
I. Value Added Tax ( VAT ) 5% 1,717.30
J. Total Unit Cost 714.97
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 1.82 611.92 1,114.18
b. Laborer 2 1.82 342.24 1,246.30
B. Equipment Cost
Sub-total for B -
C. Total (A + B) 2,360.48
D. Output / day 16.64 cu.m./day
E. Materials
Sub-total for E -
F. Direct Unit Cost ( C + E ) 2,360.48
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 354.07
H. Contractors Profit ( CP ) 10% 236.05
I. Value Added Tax ( VAT ) 5% 147.53
J. Total Unit Cost 102.26
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 3.03 611.92 1,856.40
b. Skilled Laborer 2 3.03 443.20 2,689.10
E. Materials
a. Reinforcing Steel Bars, Grade 40 358.04 kgs. 43.00 15,395.79
b. #16 G.I. Tie Wire 7.16 kgs. 78.00 558.54
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.22 611.92 1,360.41
b. Skilled Laborer 2 2.22 443.20 1,970.62
E. Materials
a. Reinforcing Steel Bars, Grade 40 262.38 kgs. 43.00 11,282.31
b. #16 G.I. Tie Wire 5.25 kgs. 78.00 409.31
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 5.65 611.92 3,459.38
b. Skilled Laborer 3 5.65 443.20 7,516.65
E. Materials
a. Reinforcing Steel Bars, Grade 40 1,000.81 kgs. 43.00 43,034.70
b. #16 G.I. Tie Wire 20.02 kgs. 78.00 1,561.26
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 3.24 611.92 1,980.19
b. Skilled Laborer 3 3.24 443.20 4,302.61
E. Materials
a. Reinforcing Steel Bars, Grade 40 572.87 kgs. 43.00 24,633.54
b. #16 G.I. Tie Wire 11.46 kgs. 78.00 893.68
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.42 611.92 1,481.99
b. Skilled Laborer 4 2.42 443.20 4,293.50
c. Laborer 4 2.42 342.24 3,315.45
E. Materials
a. Portland Cement 73.63 bags 265.00 19,510.63
b. Sand 3.88 cu.m. 901.00 3,491.38
c. Gravel 7.75 cu.m. 901.00 6,982.75
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.96 611.92 1,813.37
b. Skilled Laborer 2 2.96 443.20 2,626.77
c. Laborer 2 2.96 342.24 2,028.40
E. Materials
a. Portland Cement 46.17 bags 265.00 12,235.05
b. Sand 2.43 cu.m. 901.00 2,189.43
c. Gravel 4.86 cu.m. 901.00 4,378.86
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 4.54 611.92 2,778.74
b. Skilled Laborer 6 4.54 443.20 12,075.47
c. Laborer 4 4.54 342.24 6,216.47
E. Materials
a. Portland Cement 69.02 bags 265.00 18,291.21
b. Sand 3.63 cu.m. 901.00 3,273.16
c. Gravel 7.27 cu.m. 901.00 6,546.33
d. Assorted Coco Lumber (4 uses) 544.92 bd.ft. 15.00 8,173.83
e. ¼" x 4' x 8' Ordinary Plywood (4 uses) 10.00 pcs. 350.00 3,500.00
f. Assorted C.W. Nails 10.90 kgs. 57.50 626.66
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.76 611.92 1,688.20
b. Skilled Laborer 5 2.76 443.20 6,113.62
c. Laborer 3 2.76 342.24 2,832.57
E. Materials
a. Portland Cement 38.48 bags 265.00 10,195.88
b. Sand 2.03 cu.m. 901.00 1,824.53
c. Gravel 4.05 cu.m. 901.00 3,649.05
d. Assorted Coco Lumber (4 uses) 303.75 bd.ft. 15.00 4,556.25
e. ¼" x 4' x 8' Ordinary Plywood (4 uses) 10.00 pcs. 350.00 3,500.00
f. Assorted C.W. Nails 6.08 kgs. 57.50 349.31
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 8.48 611.92 5,190.11
b. Mason 4 8.48 443.20 15,036.31
c. Laborer 4 8.48 342.24 11,611.07
E. Materials
a. CHB 4"x8"x16" 3,240.00 pcs. 13.00 42,120.00
b. Portland Cement 103.00 bags 265.00 27,295.00
c. Washed Sand 12.00 cu.m. 901.00 10,812.00
d. 10mmΦ Reinforcement Bars 624.46 kgs. 43.13 26,932.93
e. #16 G.I. Tie Wire 7.00 kgs. 78.00 546.00
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 7.59 611.92 4,642.54
b. Mason 4 7.59 443.20 13,449.95
c. Laborer 4 7.59 342.24 10,386.08
E. Materials
a. Portland Cement 139.00 bags 265.00 36,835.00
b. Washed Sand 11.53 cu.m. 901.00 10,390.33
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 6.00 611.92 3,671.52
b. Carpenter 4 6.00 443.24 10,637.76
c. Laborer 4 6.00 342.24 8,213.76
E. Materials
a. Assorted Coco Lumber 700.00 bd.ft. 15.00 10,500.00
b. Assorted C.W. Nails 7.00 kgs. 57.50 402.50
Miscellaneous (5% of Materials) 545.13
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 1.0 611.92 611.92
b. Carpenter 1 1.0 443.20 443.20
c. Laborer 2 1.0 342.24 684.48
No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
Sub-total for B -
C. Total (A + B) 1,739.60
D. Output / day
Name and Specification Quantity Unit Unit Cost Total
E. Materials
a. 1/4" thk. 4' x 8' Marine Plywood 1.00 pc. 375.00 375.00
b. Tarpaulin (4' x 8') 1.00 pc. 600.00 600.00
c. Assorted Sizes Lumber 50.00 bd.ft. 37.00 1,850.00
d. C.W. Nails, Assorted Sizes 2.00 kg. 57.50 115.00
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Safety Practitioner 1 10.50 611.92 6,425.16
b. First Aider 1 42.00 443.20 18,614.40
Sub-total for B -
C. Total (A + B) 25,039.56
D. Output / day
Name and Specification Quantity Unit Unit Cost Total
E. Materials
a. Pairs, Rubber Boots Men, Long with Steel Toe, Black 5.00 pair 400.00 2,000.00
b. Pairs, Working Gloves (Leather Materials) 5.00 pair 150.00 750.00
c. Pcs., Rain Coats (Rainforced, Hip Length Small, Medium & Large) 3.00 pc. 150.00 450.00
No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
-
Sub-total for A -
No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Low Bed Trailer
b. Transit Mixer (5 cu.m.)
c. Backhoe w/ Breaker (0.80 cu.m.)
d. Payloader (1.50 cu.m.), LX80-2C
e. Dump Truck (10 cu.m.)
f. Bulldozer (155 HP), D65A-8
g. Concrete Paver, GP-2000 Slipform
h. Motorized Road Grader, G710A
i. Vibratory Roller (10 m.t.), SP56
j. Water Truck
k. Cargo Truck (5T)
l. Conc. Mixer (1 bagger) 1 2.00 1,376.00 2,752.00
m. Welding Machine
n. Concrete Vibrator
o. Concrete Saw, Blade Ø 14" (7.5 Hp)
p. Bar Cutter, Single Phase, 25mm. 1 2.00 1,758.00 3,516.00
E. Materials
-
Sub-total for E -
F. Direct Unit Cost ( C + E ) 6,268.00
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% -
H. Contractors Profit ( CP ) 10% -
I. Value Added Tax ( VAT ) 5% 313.40
J. Total Unit Cost 6,581.40
Republic of the Philippines
Department of Public Works and Highways
Bureau : DPWH
Region : IX
District/City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
Date : Nov. 05, 2019
I. ESTIMATED COST
A. DIRECT COST
B. INDIRECT COST
MARK-UPS IN
ESTIMATED TOTAL MARK-UPS TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT
DIRECT COST COST
OCM PROFIT % VALUE
(9) (10) (11)
(1) (2) (3) (4) (5) (6) (7) (8)
(5) x (8) 5%[(5) + (9] (9) + (10)
801 Removal of Structures & Obstructions (Existing Fence) 94.28 ln.m. 12,838.89 15.00 10.00 25.00 3,209.72 802.43 4,012.15
803 Excavation of Footing & Wall Footing 50.44 cu.m. 27,476.79 15.00 10.00 25.00 6,869.20 1,717.30 8,586.50
804(a) Backfilling of Excavated Materials 30.30 cu.m. 2,360.48 15.00 10.00 25.00 590.12 147.53 737.65
404(a) Reinforcing Steel for Column Footing 340.99 kgs. 23,166.50 15.00 10.00 25.00 5,791.62 1,447.91 7,239.53
404(b) Reinforcing Steel for Wall Footing 249.89 kgs. 16,976.82 15.00 10.00 25.00 4,244.21 1,061.05 5,305.26
404(c) Reinforcing Steel for Columns 953.15 kgs. 60,541.25 15.00 10.00 25.00 15,135.31 3,783.83 18,919.14
404(d) Reinforcing Steel for Beams 545.59 kgs. 34,654.49 15.00 10.00 25.00 8,663.62 2,165.91 10,829.53
900(a) R.C. Column Footing 7.75 cu.m. 44,176.16 15.00 10.00 25.00 11,044.04 2,761.01 13,805.05
900(b) R.C. Wall Footing 4.86 cu.m. 31,512.83 15.00 10.00 25.00 7,878.21 1,969.55 9,847.76
900(c) R.C. Columns 7.27 cu.m. 71,045.25 15.00 10.00 25.00 17,761.31 4,440.33 22,201.64
900(d) R.C. Beams 4.05 cu.m. 40,519.56 15.00 10.00 25.00 10,129.89 2,532.47 12,662.36
506(a.1) Masonry Works (Concrete Hollow Blocks) 259.20 sq.m. 151,214.21 15.00 10.00 25.00 37,803.55 9,450.89 47,254.44
1027 Cement Plaster Finish 576.60 sq.m. 86,143.40 15.00 10.00 25.00 21,535.85 5,383.96 26,919.81
414 Forms and Falseworks 1.00 l.s. 36,222.97 15.00 10.00 25.00 9,055.74 2,263.94 11,319.68
B.5 Project Billboard / Signboard 1.00 each 4,679.60 15.00 10.00 25.00 1,169.90 292.48 1,462.38
B.7 (2) Occupational Safety and Health Program 1.00 l.s. 31,989.56 0.00 10.00 10.00 3,198.96 1,759.43 4,958.38
B.9 Mobilization/Demobilization 1.00 l.s. 6,268.00 0.00 0.00 0.00 - 313.40 313.40
T O T A L 681,786.75 42,293.40
APPROVED BUDGET FOR THE CONTRACT
Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Zamboanga City
60.00
(12) (13)
(5) + (11) (12) / (3)
16,851.04 178.74
36,063.28 714.97
3,098.13 102.26
30,406.03 89.17
22,282.08 89.17
79,460.39 83.37
45,484.01 83.37
57,981.21 7,481.45
41,360.59 8,510.41
93,246.89 12,833.98
53,181.92 13,131.34
198,468.65 765.70
113,063.22 196.09
47,542.65 47,542.65
6,141.98 6,141.98
36,947.94 36,947.94
6,581.40 6,581.40
888,161.40
Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Zamboanga City
S U M M A R Y OF D E T A I L E D E S T I M A T E S
801 Removal of Structures & Obstructions (Existing Fence) 1,167.17 11,671.72 - 12,838.89
404(a) Reinforcing Steel for Column Footing 2,666.65 4,545.51 15,954.33 23,166.50
404(b) Reinforcing Steel for Wall Footing 1,954.17 3,331.03 11,691.62 16,976.82
506(a.1) Masonry Works (Concrete Hollow Blocks) 11,670.79 31,837.50 107,705.93 151,214.21
B.7 (2) Occupational Safety and Health Program - 25,039.56 6,950.00 31,989.56
6 WORKING DAYS
DURATION NO.
ITEM NO. DESCRIPTION QUANTITY
OF DAYS
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15
TOTAL
804(a) Backfilling of Excavated Materials 30.30 1.82 WORKING : 42
DAYS
SUNDAYS &
404(a) Reinforcing Steel for Column Footing 340.99 3.03 HOLIDAYS
: 9
INCLEMENT
404(b) Reinforcing Steel for Wall Footing 249.89 2.22 WEATHER & : 9
CURING
TOTAL NO. OF
404(c) Reinforcing Steel for Columns 953.15 5.65 CAL. DAYS
: 60
DISTANCE
FROM TO
(Km.)
TOTAL 5.00
QUANTITY
DESCRIPTION
(Bags)
T O T A L -
Quantity = - Bags
S I T E HAULING DISTANCE
*Average hauling distance from Source to assumed Stockpiling area less 5.00 km. free haul:
say - km.
=P - / bag
Terrain : Rolling
8.0 x 60.00
No. of trips for Dumptruck per day = = 10.53 say 10.53 trip
45.60
2. No. of days for Labor, for unloading = complimentary to D. Truck days = 0.00 days
DELIVERY COST :
Sub - Total P -
LABOR :
Sub - Total P -
MATERIALS :
Grand Total P -
Delivery Cost P -
Labor P -
Materials P -
COMPUTATION OF HAULING COST (DPWH REGION IX)
(STEEL REINFORCEMENT)
ZAMBOANGA DEL NORTE 3RD ENGINEERING OFFICE (STA. 1988 + 690.00)
PROJECT SITE (STA. 2084 + 805.00)
NET DISTANCE : - km.
I. CYCLE TIME :
A.) Without Load :
where :
Distance = - km.
Velocity = 55.00 km./hr.
Hour = 60.00 min./hr.
0.00 km.
Time =
55.00 km./hr.
0.00 km.
Time =
0.92 km./min.
Time = - mins.