Summary of Quantities: Item No. Description Unit Quantity Remarks

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 31

SUMMARY OF QUANTITIES

ITEM NO. DESCRIPTION UNIT QUANTITY REMARKS

801 REMOVAL OF EXISTING FENCE LN.M. 94.28 Existing Gate to be re-installed

803 EXCAVATION OF FOOTING & WALL FOOTING CU.M. 50.44

804(a) BACKFILLING OF EXCAVATED MATERIALS CU.M. 30.30

404(a) REINFORCING STEEL FOR COLUMN FOOTINGS (Gr.40) KGS. 340.99

404(b) REINFORCING STEEL FOR WALL FOOTINGS (Gr.40) KGS. 249.89

404(c) REINFORCING STEEL FOR COLUMNS (Gr.40) KGS. 953.15

404(d) REINFORCING STEEL FOR BEAMS (Gr.40) KGS. 545.59

900(a) REINF. CONCRETE COLUMN FOOTINGS CU.M. 7.75

900(b) REINF. CONCRETE WALL FOOTINGS CU.M. 4.86

900(c) REINF. CONCRETE COLUMNS CU.M. 7.27

900(d) REINF. CONCRETE BEAMS CU.M. 4.05

506(1) MASONRY WORKS (4" CHB) SQ.M. 259.20

1027 CEMENT PLASTER FINISH SQ.M. 576.60 Plastering bothsides

414 FORMS & FALSEWORKS L.S. 1.00


DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 801 Removal of Structures & Obstructions (Existing Fence)


Unit of Measurement : ln.m.
Output per hour : 2.00 ln.m./hr.
Quantity : 94.28

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 5.89 611.92 3,605.55
b. Laborer 4 5.89 342.24 8,066.17

Sub-total for A 11,671.72


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
Minor Tools (10% of Labor) 1,167.17

Sub-total for B 1,167.17


C. Total (A + B) 12,838.89
D. Output / day 16.00 ln.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials

Sub-total for E -
F. Direct Unit Cost ( C + E ) 12,838.89
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 1,925.83
H. Contractors Profit ( CP ) 10% 1,283.89
I. Value Added Tax ( VAT ) 5% 802.43
J. Total Unit Cost 178.74
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R) - Fencing Type-C
Fleet-Marine Detachment, Rio Hondo, Zamboanga City

Item No./Description : 803 Excavation of Footing & Wall Footing


Unit of Measurement : cu.m.
Output per hour : 0.50 cu.m./hr.
Quantity : 50.44

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 12.61 611.92 7,716.31
b. Laborer 4 12.61 342.24 17,262.59

Sub-total for A 24,978.90


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
Minor Tools (10% of Labor) 2,497.89

Sub-total for B 2,497.89


C. Total (A + B) 27,476.79
D. Output / day 4.00 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials

Sub-total for E -
F. Direct Unit Cost ( C + E ) 27,476.79
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 4,121.52
H. Contractors Profit ( CP ) 10% 2,747.68
I. Value Added Tax ( VAT ) 5% 1,717.30
J. Total Unit Cost 714.97
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 804(a) Backfilling of Excavated Materials


Unit of Measurement : cu.m.
Output per hour : 2.080 cu.m./hr.
Quantity : 30.298

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 1.82 611.92 1,114.18
b. Laborer 2 1.82 342.24 1,246.30

Sub-total for A 2,360.48


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days

B. Equipment Cost

Sub-total for B -
C. Total (A + B) 2,360.48
D. Output / day 16.64 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials

Sub-total for E -
F. Direct Unit Cost ( C + E ) 2,360.48
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 354.07
H. Contractors Profit ( CP ) 10% 236.05
I. Value Added Tax ( VAT ) 5% 147.53
J. Total Unit Cost 102.26
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 404(a) Reinforcing Steel for Column Footing


Unit of Measurement : kgs.
Output per hour : 14.05 kgs./hr.
Quantity : 340.99

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 3.03 611.92 1,856.40
b. Skilled Laborer 2 3.03 443.20 2,689.10

Sub-total for A 4,545.51


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Bar Cutter (Grade 40, Single Phase) 1 1.52 1,758.00 2,666.65

Sub-total for B 2,666.65


C. Total (A + B) 7,212.16
D. Output / day 112.40 kgs./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Reinforcing Steel Bars, Grade 40 358.04 kgs. 43.00 15,395.79
b. #16 G.I. Tie Wire 7.16 kgs. 78.00 558.54

Sub-total for E 15,954.33


F. Direct Unit Cost ( C + E ) 23,166.50
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 3,474.97
H. Contractors Profit ( CP ) 10% 2,316.65
I. Value Added Tax ( VAT ) 5% 1,447.91
J. Total Unit Cost 89.17
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 404(b) Reinforcing Steel for Wall Footing


Unit of Measurement : kgs.
Output per hour : 14.05 kgs./hr.
Quantity : 249.89

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.22 611.92 1,360.41
b. Skilled Laborer 2 2.22 443.20 1,970.62

Sub-total for A 3,331.03


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Bar Cutter (Grade 40, Single Phase) 1 1.11 1,758.00 1,954.17

Sub-total for B 1,954.17


C. Total (A + B) 5,285.20
D. Output / day 112.40 kgs./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Reinforcing Steel Bars, Grade 40 262.38 kgs. 43.00 11,282.31
b. #16 G.I. Tie Wire 5.25 kgs. 78.00 409.31

Sub-total for E 11,691.62


F. Direct Unit Cost ( C + E ) 16,976.82
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 2,546.52
H. Contractors Profit ( CP ) 10% 1,697.68
I. Value Added Tax ( VAT ) 5% 1,061.05
J. Total Unit Cost 89.17
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 404(c) Reinforcing Steel for Columns


Unit of Measurement : kgs.
Output per hour : 21.08 kgs./hr.
Quantity : 953.15

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 5.65 611.92 3,459.38
b. Skilled Laborer 3 5.65 443.20 7,516.65

Sub-total for A 10,976.03


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Bar Cutter (Grade 40, Single Phase) 1 2.83 1,758.00 4,969.27

Sub-total for B 4,969.27


C. Total (A + B) 15,945.30
D. Output / day 168.60 kgs./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Reinforcing Steel Bars, Grade 40 1,000.81 kgs. 43.00 43,034.70
b. #16 G.I. Tie Wire 20.02 kgs. 78.00 1,561.26

Sub-total for E 44,595.96


F. Direct Unit Cost ( C + E ) 60,541.25
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 9,081.19
H. Contractors Profit ( CP ) 10% 6,054.13
I. Value Added Tax ( VAT ) 5% 3,783.83
J. Total Unit Cost 83.37
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 404(d) Reinforcing Steel for Beams


Unit of Measurement : kgs.
Output per hour : 21.08 kgs./hr.
Quantity : 545.59

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 3.24 611.92 1,980.19
b. Skilled Laborer 3 3.24 443.20 4,302.61

Sub-total for A 6,282.80


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Bar Cutter (Grade 40, Single Phase) 1 1.62 1,758.00 2,844.46

Sub-total for B 2,844.46


C. Total (A + B) 9,127.26
D. Output / day 168.60 kgs./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Reinforcing Steel Bars, Grade 40 572.87 kgs. 43.00 24,633.54
b. #16 G.I. Tie Wire 11.46 kgs. 78.00 893.68

Sub-total for E 25,527.22


F. Direct Unit Cost ( C + E ) 34,654.49
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 5,198.17
H. Contractors Profit ( CP ) 10% 3,465.45
I. Value Added Tax ( VAT ) 5% 2,165.91
J. Total Unit Cost 83.37
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 900(a) R.C. Column Footing


Unit of Measurement : cu.m.
Output per hour : 0.400 cu.m./hr.
Quantity : 7.75

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.42 611.92 1,481.99
b. Skilled Laborer 4 2.42 443.20 4,293.50
c. Laborer 4 2.42 342.24 3,315.45

Sub-total for A 9,090.94


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. One Bagger Mixer 1 2.42 1,376.00 3,332.50
b. Concrete Vibrator 1 2.42 730.00 1,767.97

Sub-total for B 5,100.47


C. Total (A + B) 14,191.41
D. Output / day 3.20 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Portland Cement 73.63 bags 265.00 19,510.63
b. Sand 3.88 cu.m. 901.00 3,491.38
c. Gravel 7.75 cu.m. 901.00 6,982.75

Sub-total for E 29,984.75


F. Direct Unit Cost ( C + E ) 44,176.16
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 6,626.42
H. Contractors Profit ( CP ) 10% 4,417.62
I. Value Added Tax ( VAT ) 5% 2,761.01
J. Total Unit Cost 7,481.45
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 900(b) R.C. Wall Footing


Unit of Measurement : cu.m.
Output per hour : 0.21 cu.m./hr.
Quantity : 4.86

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.96 611.92 1,813.37
b. Skilled Laborer 2 2.96 443.20 2,626.77
c. Laborer 2 2.96 342.24 2,028.40

Sub-total for A 6,468.54


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. One Bagger Mixer 1 2.96 1,376.00 4,077.66
b. Concrete Vibrator 1 2.96 730.00 2,163.29

Sub-total for B 6,240.95


C. Total (A + B) 12,709.49
D. Output / day 1.64 kgs./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Portland Cement 46.17 bags 265.00 12,235.05
b. Sand 2.43 cu.m. 901.00 2,189.43
c. Gravel 4.86 cu.m. 901.00 4,378.86

Sub-total for E 18,803.34


F. Direct Unit Cost ( C + E ) 31,512.83
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 4,726.92
H. Contractors Profit ( CP ) 10% 3,151.28
I. Value Added Tax ( VAT ) 5% 1,969.55
J. Total Unit Cost 8,510.41
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 900(c) R.C. Columns


Unit of Measurement : cu.m.
Output per hour : 0.20 cu.m./hr.
Quantity : 7.27

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 4.54 611.92 2,778.74
b. Skilled Laborer 6 4.54 443.20 12,075.47
c. Laborer 4 4.54 342.24 6,216.47

Sub-total for A 21,070.68


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. One Bagger Mixer 1 4.54 1,376.00 6,248.44
b. Concrete Vibrator 1 4.54 730.00 3,314.94

Sub-total for B 9,563.38


C. Total (A + B) 30,634.05
D. Output / day 1.60 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Portland Cement 69.02 bags 265.00 18,291.21
b. Sand 3.63 cu.m. 901.00 3,273.16
c. Gravel 7.27 cu.m. 901.00 6,546.33
d. Assorted Coco Lumber (4 uses) 544.92 bd.ft. 15.00 8,173.83
e. ¼" x 4' x 8' Ordinary Plywood (4 uses) 10.00 pcs. 350.00 3,500.00
f. Assorted C.W. Nails 10.90 kgs. 57.50 626.66

Sub-total for E 40,411.19


F. Direct Unit Cost ( C + E ) 71,045.25
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 10,656.79
H. Contractors Profit ( CP ) 10% 7,104.52
I. Value Added Tax ( VAT ) 5% 4,440.33
J. Total Unit Cost 12,833.98
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 900(d) R.C. Beams


Unit of Measurement : cu.m.
Output per hour : 0.18 cu.m./hr.
Quantity : 4.05

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 2.76 611.92 1,688.20
b. Skilled Laborer 5 2.76 443.20 6,113.62
c. Laborer 3 2.76 342.24 2,832.57

Sub-total for A 10,634.40


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. One Bagger Mixer 1 2.76 1,376.00 3,796.19
b. Concrete Vibrator 1 2.76 730.00 2,013.96

Sub-total for B 5,810.15


C. Total (A + B) 16,444.54
D. Output / day 1.47 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Portland Cement 38.48 bags 265.00 10,195.88
b. Sand 2.03 cu.m. 901.00 1,824.53
c. Gravel 4.05 cu.m. 901.00 3,649.05
d. Assorted Coco Lumber (4 uses) 303.75 bd.ft. 15.00 4,556.25
e. ¼" x 4' x 8' Ordinary Plywood (4 uses) 10.00 pcs. 350.00 3,500.00
f. Assorted C.W. Nails 6.08 kgs. 57.50 349.31

Sub-total for E 24,075.01


F. Direct Unit Cost ( C + E ) 40,519.56
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 6,077.93
H. Contractors Profit ( CP ) 10% 4,051.96
I. Value Added Tax ( VAT ) 5% 2,532.47
J. Total Unit Cost 13,131.34
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 506(a.1) Masonry Works (Concrete Hollow Blocks)


Unit of Measurement : sq.m.
Output per hour : 3.82 sq.m./hr.
Quantity : 259.20

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 8.48 611.92 5,190.11
b. Mason 4 8.48 443.20 15,036.31
c. Laborer 4 8.48 342.24 11,611.07

Sub-total for A 31,837.50


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Bagger Mixer 1 8.48 1,376.00 11,670.79

Sub-total for B 11,670.79


C. Total (A + B) 43,508.28
D. Output / day 30.56 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. CHB 4"x8"x16" 3,240.00 pcs. 13.00 42,120.00
b. Portland Cement 103.00 bags 265.00 27,295.00
c. Washed Sand 12.00 cu.m. 901.00 10,812.00
d. 10mmΦ Reinforcement Bars 624.46 kgs. 43.13 26,932.93
e. #16 G.I. Tie Wire 7.00 kgs. 78.00 546.00

Sub-total for E 107,705.93


F. Direct Unit Cost ( C + E ) 151,214.21
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 22,682.13
H. Contractors Profit ( CP ) 10% 15,121.42
I. Value Added Tax ( VAT ) 5% 9,450.89
J. Total Unit Cost 765.70
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 1027 Cement Plaster Finish


Unit of Measurement : sq.m.
Output per hour : 9.50 sq.m./hr.
Quantity : 576.60

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 7.59 611.92 4,642.54
b. Mason 4 7.59 443.20 13,449.95
c. Laborer 4 7.59 342.24 10,386.08

Sub-total for A 28,478.58


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Bagger Mixer 1 7.59 1,376.00 10,439.49

Sub-total for B 10,439.49


C. Total (A + B) 38,918.07
D. Output / day 76.00 cu.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Portland Cement 139.00 bags 265.00 36,835.00
b. Washed Sand 11.53 cu.m. 901.00 10,390.33

Sub-total for E 47,225.33


F. Direct Unit Cost ( C + E ) 86,143.40
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 12,921.51
H. Contractors Profit ( CP ) 10% 8,614.34
I. Value Added Tax ( VAT ) 5% 5,383.96
J. Total Unit Cost 196.09
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : 414 Forms and Falseworks


Unit of Measurement : l.s.
Output per hour : -
Quantity : 1.00

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Construction Foreman 1 6.00 611.92 3,671.52
b. Carpenter 4 6.00 443.24 10,637.76
c. Laborer 4 6.00 342.24 8,213.76

Sub-total for A 22,523.04


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
Minor Tools (10% of Labor) 2,252.30

Sub-total for B 2,252.30


C. Total (A + B) 24,775.34
D. Output / day - sq.m./day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
a. Assorted Coco Lumber 700.00 bd.ft. 15.00 10,500.00
b. Assorted C.W. Nails 7.00 kgs. 57.50 402.50
Miscellaneous (5% of Materials) 545.13

Sub-total for E 11,447.63


F. Direct Unit Cost ( C + E ) 36,222.97
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 5,433.45
H. Contractors Profit ( CP ) 10% 3,622.30
I. Value Added Tax ( VAT ) 5% 2,263.94
J. Total Unit Cost 47,542.65
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City

Item No./Description : B.5 Project Billboard / Signboard


Unit of Measurement : each
Output per hour :
Quantity : 1.00

No. of
Designation No. of Person Daily Rate Amount
Days

A. Labor
a. Construction Foreman 1 1.0 611.92 611.92
b. Carpenter 1 1.0 443.20 443.20
c. Laborer 2 1.0 342.24 684.48

Sub-total for A 1,739.60

No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days

B. Equipment Cost (2009 ACEL Rates)

Sub-total for B -
C. Total (A + B) 1,739.60
D. Output / day
Name and Specification Quantity Unit Unit Cost Total

E. Materials

a. 1/4" thk. 4' x 8' Marine Plywood 1.00 pc. 375.00 375.00
b. Tarpaulin (4' x 8') 1.00 pc. 600.00 600.00
c. Assorted Sizes Lumber 50.00 bd.ft. 37.00 1,850.00
d. C.W. Nails, Assorted Sizes 2.00 kg. 57.50 115.00

Sub-total for E 2,940.00


F. Direct Unit Cost ( C + E ) 4,679.60
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% 701.94
H. Contractors Profit ( CP ) 10% 467.96
I. Value Added Tax ( VAT ) 5% 292.48
J. Total Unit Cost 6,141.98
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City
Item No./Description : B.7 (2) Occupational Safety and Health Program
Unit of Measurement : l.s.
Output per hour :
Quantity : 1.00

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
a. Safety Practitioner 1 10.50 611.92 6,425.16
b. First Aider 1 42.00 443.20 18,614.40

Sub-total for A 25,039.56


No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost

Sub-total for B -
C. Total (A + B) 25,039.56
D. Output / day
Name and Specification Quantity Unit Unit Cost Total
E. Materials
a. Pairs, Rubber Boots Men, Long with Steel Toe, Black 5.00 pair 400.00 2,000.00
b. Pairs, Working Gloves (Leather Materials) 5.00 pair 150.00 750.00

c. Pcs., Rain Coats (Rainforced, Hip Length Small, Medium & Large) 3.00 pc. 150.00 450.00

d. Hard Hat 5.00 pc. 250.00 1,250.00


e. Medical Supplies 1.00 set 2,500.00 2,500.00

Sub-total for E 6,950.00


F. Direct Unit Cost ( C + E ) 31,989.56
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% -
H. Contractors Profit ( CP ) 10% 3,198.96
I. Value Added Tax ( VAT ) 5% 1,759.43
J. Total Unit Cost 36,947.94
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)


Zamboanga City
Item No./Description : B.9 Mobilization/Demobilization
Unit of Measurement : l.s.
Output per hour :
Quantity : 1.00

No. of
Designation No. of Person Daily Rate Amount
Days
A. Labor
-

Sub-total for A -
No. of No. of
Name and Capacity Daily Rate Amount
Equipment Days
B. Equipment Cost
a. Low Bed Trailer
b. Transit Mixer (5 cu.m.)
c. Backhoe w/ Breaker (0.80 cu.m.)
d. Payloader (1.50 cu.m.), LX80-2C
e. Dump Truck (10 cu.m.)
f. Bulldozer (155 HP), D65A-8
g. Concrete Paver, GP-2000 Slipform
h. Motorized Road Grader, G710A
i. Vibratory Roller (10 m.t.), SP56
j. Water Truck
k. Cargo Truck (5T)
l. Conc. Mixer (1 bagger) 1 2.00 1,376.00 2,752.00
m. Welding Machine
n. Concrete Vibrator
o. Concrete Saw, Blade Ø 14" (7.5 Hp)
p. Bar Cutter, Single Phase, 25mm. 1 2.00 1,758.00 3,516.00

Sub-total for B 6,268.00


C. Total (A + B) 6,268.00
D. Output / day

Name and Specification Quantity Unit Unit Cost Total

E. Materials
-

Sub-total for E -
F. Direct Unit Cost ( C + E ) 6,268.00
G. Overhead Contingencies & Miscellaneous ( OCM ) 15% -
H. Contractors Profit ( CP ) 10% -
I. Value Added Tax ( VAT ) 5% 313.40
J. Total Unit Cost 6,581.40
Republic of the Philippines
Department of Public Works and Highways
Bureau : DPWH
Region : IX
District/City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
Date : Nov. 05, 2019

NAME/LOCATION OF PROJECT : Appropriation : P 920,000.00


Source of Funds :
Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Issued Obligated Authority :
Zamboanga City
Released :
PROJECT CATEGORY : Cal. Days to Complete : 60 Calendar Days
Desirable Starting Date : Upon Approval
BUILDING (FENCING) Mode of Implementation : By Contract

PROJECT DESCRIPTION : NET LENGTH:


Scope of Work : New Construction 94.28 LN.M.

MINIMUM EQUIPMENT REQUIREMENT : TECHNICAL PERSONNEL REQUIRED :


Description No. Description No. Description No.
Dumptruck (10 cu.m.) 1 Bar Cutter, Single Phase 1 Project Engineer 1
Water Truck 1 Bar Bender 1 Materials Engineer 1
Payloader 1 Bagger Mixer 2 Safety Practitioner 1
Concrete Vibrator 2 Foreman 1
Carpenter 4
Mason 4
Laborer 8

ESTIMATED COST OF PROPOSED WORK


% OF DIRECT COST
ITEM NO. DESCRIPTION UNIT QUANTITY
TOTAL TOTAL UNIT COST
801 Removal of Structures & Obstructions (Existing Fence) 1.883 ln.m. 94.28 12,838.89 136.19
803 Excavation of Footing & Wall Footing 4.030 cu.m. 50.44 27,476.79 544.74
804(a) Backfilling of Excavated Materials 0.346 cu.m. 30.30 2,360.48 77.91
404(a) Reinforcing Steel for Column Footing 3.398 kgs. 340.99 23,166.50 67.94
404(b) Reinforcing Steel for Wall Footing 2.490 kgs. 249.89 16,976.82 67.94
404(c) Reinforcing Steel for Columns 8.880 kgs. 953.15 60,541.25 63.52
404(d) Reinforcing Steel for Beams 5.083 kgs. 545.59 34,654.49 63.52
900(a) R.C. Column Footing 6.479 cu.m. 7.75 44,176.16 5,700.15
900(b) R.C. Wall Footing 4.622 cu.m. 4.86 31,512.83 6,484.12
900(c) R.C. Columns 10.420 cu.m. 7.27 71,045.25 9,778.27
900(d) R.C. Beams 5.943 cu.m. 4.05 40,519.56 10,004.83
506(a.1) Masonry Works (Concrete Hollow Blocks) 22.179 sq.m. 259.20 151,214.21 583.39
1027 Cement Plaster Finish 12.635 sq.m. 576.60 86,143.40 149.40
414 Forms and Falseworks 5.313 l.s. 1.00 36,222.97 36,222.97
B.5 Project Billboard / Signboard 0.686 each 1.00 4,679.60 4,679.60
B.7 (2) Occupational Safety and Health Program 4.692 l.s. 1.00 31,989.56 31,989.56
B.9 Mobilization/Demobilization 0.919 l.s. 1.00 6,268.00 6,268.00
TOTAL 100.000 P 681,786.75
NAME OF PROJECT : Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Zamboanga City

BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL AMOUNT

I. ESTIMATED COST

A. DIRECT COST

A.1. Materials 42.10 387,312.31

A.2. Labor 24.71 227,297.29

A.3. Equipment Expenses 7.30 67,177.15

SUB-TOTAL (DIRECT COST) 74.11 P 681,786.75

B. INDIRECT COST

B.1. Overhead, Contingency & Misc. 10.49 96,529.38

(9% Max. of D.C.)

B.2. Profit (8 % Max. of D.C.) 7.34 67,551.87

C. VAT (5% of D.C. and I.C.) 4.60 42,293.40

SUBTOTAL (CONTRACT COST) 96.54 P 888,161.40

II. ESTIMATED GOVERNMENT EXPENDITURES

1. Engineering and Administrative Overhead (3.50%) 2.50 23,000.00

2. Detailed Engineering (1%)

3. Reserved for the Payment of RROW 0.00 -

4. Physical Reserved 0.96 8,838.60

TOTAL ESTIMATED PROJECT COST 100.00 P 920,000.00


APPROVED BUDGET FOR THE CONTRACT
Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Zamboanga City
Contract Duration : (C.D.)

MARK-UPS IN
ESTIMATED TOTAL MARK-UPS TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT PERCENT VAT
DIRECT COST COST
OCM PROFIT % VALUE
(9) (10) (11)
(1) (2) (3) (4) (5) (6) (7) (8)
(5) x (8) 5%[(5) + (9] (9) + (10)
801 Removal of Structures & Obstructions (Existing Fence) 94.28 ln.m. 12,838.89 15.00 10.00 25.00 3,209.72 802.43 4,012.15
803 Excavation of Footing & Wall Footing 50.44 cu.m. 27,476.79 15.00 10.00 25.00 6,869.20 1,717.30 8,586.50
804(a) Backfilling of Excavated Materials 30.30 cu.m. 2,360.48 15.00 10.00 25.00 590.12 147.53 737.65
404(a) Reinforcing Steel for Column Footing 340.99 kgs. 23,166.50 15.00 10.00 25.00 5,791.62 1,447.91 7,239.53
404(b) Reinforcing Steel for Wall Footing 249.89 kgs. 16,976.82 15.00 10.00 25.00 4,244.21 1,061.05 5,305.26
404(c) Reinforcing Steel for Columns 953.15 kgs. 60,541.25 15.00 10.00 25.00 15,135.31 3,783.83 18,919.14
404(d) Reinforcing Steel for Beams 545.59 kgs. 34,654.49 15.00 10.00 25.00 8,663.62 2,165.91 10,829.53
900(a) R.C. Column Footing 7.75 cu.m. 44,176.16 15.00 10.00 25.00 11,044.04 2,761.01 13,805.05
900(b) R.C. Wall Footing 4.86 cu.m. 31,512.83 15.00 10.00 25.00 7,878.21 1,969.55 9,847.76
900(c) R.C. Columns 7.27 cu.m. 71,045.25 15.00 10.00 25.00 17,761.31 4,440.33 22,201.64
900(d) R.C. Beams 4.05 cu.m. 40,519.56 15.00 10.00 25.00 10,129.89 2,532.47 12,662.36
506(a.1) Masonry Works (Concrete Hollow Blocks) 259.20 sq.m. 151,214.21 15.00 10.00 25.00 37,803.55 9,450.89 47,254.44
1027 Cement Plaster Finish 576.60 sq.m. 86,143.40 15.00 10.00 25.00 21,535.85 5,383.96 26,919.81
414 Forms and Falseworks 1.00 l.s. 36,222.97 15.00 10.00 25.00 9,055.74 2,263.94 11,319.68
B.5 Project Billboard / Signboard 1.00 each 4,679.60 15.00 10.00 25.00 1,169.90 292.48 1,462.38
B.7 (2) Occupational Safety and Health Program 1.00 l.s. 31,989.56 0.00 10.00 10.00 3,198.96 1,759.43 4,958.38
B.9 Mobilization/Demobilization 1.00 l.s. 6,268.00 0.00 0.00 0.00 - 313.40 313.40

T O T A L 681,786.75 42,293.40
APPROVED BUDGET FOR THE CONTRACT
Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Zamboanga City
60.00

TOTAL COST UNIT COST

(12) (13)
(5) + (11) (12) / (3)
16,851.04 178.74
36,063.28 714.97
3,098.13 102.26
30,406.03 89.17
22,282.08 89.17
79,460.39 83.37
45,484.01 83.37
57,981.21 7,481.45
41,360.59 8,510.41
93,246.89 12,833.98
53,181.92 13,131.34
198,468.65 765.70
113,063.22 196.09
47,542.65 47,542.65
6,141.98 6,141.98
36,947.94 36,947.94
6,581.40 6,581.40

888,161.40
Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
Zamboanga City

S U M M A R Y OF D E T A I L E D E S T I M A T E S

ITEM NO. DESCRIPTION EQUIPMENT LABOR MATERIALS TOTAL

801 Removal of Structures & Obstructions (Existing Fence) 1,167.17 11,671.72 - 12,838.89

803 Excavation of Footing & Wall Footing 2,497.89 24,978.90 - 27,476.79

804(a) Backfilling of Excavated Materials - 2,360.48 - 2,360.48

404(a) Reinforcing Steel for Column Footing 2,666.65 4,545.51 15,954.33 23,166.50

404(b) Reinforcing Steel for Wall Footing 1,954.17 3,331.03 11,691.62 16,976.82

404(c) Reinforcing Steel for Columns 4,969.27 10,976.03 44,595.96 60,541.25

404(d) Reinforcing Steel for Beams 2,844.46 6,282.80 25,527.22 34,654.49

900(a) R.C. Column Footing 5,100.47 9,090.94 29,984.75 44,176.16

900(b) R.C. Wall Footing 6,240.95 6,468.54 18,803.34 31,512.83

900(c) R.C. Columns 9,563.38 21,070.68 40,411.19 71,045.25

900(d) R.C. Beams 5,810.15 10,634.40 24,075.01 40,519.56

506(a.1) Masonry Works (Concrete Hollow Blocks) 11,670.79 31,837.50 107,705.93 151,214.21

1027 Cement Plaster Finish 10,439.49 28,478.58 47,225.33 86,143.40

414 Forms and Falseworks 2,252.30 22,523.04 11,447.63 36,222.97

B.5 Project Billboard / Signboard - 1,739.60 2,940.00 4,679.60

B.7 (2) Occupational Safety and Health Program - 25,039.56 6,950.00 31,989.56

B.9 Mobilization/Demobilization - 6,268.00 - 6,268.00

TOTAL 67,177.15 227,297.29 387,312.31 681,786.75


Zamboanga Roadmap to Recovery & Reconstruction (Z3R)
PROJECT :
Zamboanga City

6 WORKING DAYS
DURATION NO.
ITEM NO. DESCRIPTION QUANTITY
OF DAYS
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15

801 Removal of Structures & Obstructions (Existing Fence) 94.28 5.89

803 Excavation of Footing & Wall Footing 50.44 12.61

TOTAL
804(a) Backfilling of Excavated Materials 30.30 1.82 WORKING : 42
DAYS

SUNDAYS &
404(a) Reinforcing Steel for Column Footing 340.99 3.03 HOLIDAYS
: 9

INCLEMENT
404(b) Reinforcing Steel for Wall Footing 249.89 2.22 WEATHER & : 9
CURING

TOTAL NO. OF
404(c) Reinforcing Steel for Columns 953.15 5.65 CAL. DAYS
: 60

404(d) Reinforcing Steel for Beams 545.59 3.24

900(a) R.C. Column Footing 7.75 2.42

900(b) R.C. Wall Footing 4.86 2.96

900(c) R.C. Columns 7.27 4.54

900(d) R.C. Beams 4.05 2.76

506(a.1) Masonry Works (Concrete Hollow Blocks) 259.20 8.48

1027 Cement Plaster Finish 576.60 7.59

414 Forms and Falseworks 1.00 6.00

B.5 Project Billboard / Signboard 1.00 1.00

B.7 (2) Occupational Safety and Health Program 1.00 42.00

B.9 Mobilization/Demobilization 1.00 2.00


UNIT COST ANALYSIS FOR HAULING COST FOR ALL AGGREGATES
TOTAL DISTANCE FROM ZAMBOANGA DEL NORTE 3rd DISTRICT ENGINEERING OFFICE TO PROJECT SITE:

DISTANCE
FROM TO
(Km.)

Pisawak Quarry to Jct. Labason-Siocon-Sirawai National Jct. Labason-Siocon-Sirawai Nat'l. Highway


0.00
Highway (Sta. 2074+560)

Jct. Labason-Siocon-Sirawai Nat'l. Highway Project Site (Sta.


5.00
(Sta. 2074+560) 2123+050)

TOTAL 5.00

LESS: (FREE HAUL DISTANCE) 5.00

AVERAGE HAULING DISTANCE 0.00

Item No : ALL AGGREGATES


Quantity : 1,000.00 Terrain Condition : Rolling
Road Condition : Paved
Hauling Distance : 5.00 km.
Effective Working Hours : 8.00 hrs.

Hauling : Using 10.00 cu.m. capacity Dumptruck


Weight of Dumptruck (cap. 10.00 cu.m.) : 16,000.00 kgs.
Unit Weight of Fine Aggregates : 1,640.00 kg./m³
Unit Weight of Coarse Aggregates : 1,534.00 kg/m³
Maximum Volume to be carried per DT : 11.57 cu.m.

Computation of Cycle Time:


Dumptruck (10 wheeler) days computation : TIME-MOTION ANALYSIS
Average Haul Distance = 5.00 km.
Speed when loaded = 30.00 kph
Speed when unloaded = 40.00 kph

LOADING TIME = 3.00 mins.


LOADED TRAVEL TIME
First 200m @ 20 kph = 0.60 min
Succeeding 4600 @ 30 kph = 9.20 min
Next 200m @ 20 kph = 0.60 min

UNLOADING AND MANUEVERING = 2.00 min


RETURN EMPTY :
First 200m @ 30 kph = 0.40 min
Succeeding 4600 @ 40 kph = 6.90 min
Next 200m @ 30 kph = 0.40 min
CYCLE TIME = 23.10 min

ALLOWANCE FOR DELAY/TRAFFIC


(10% of cylce time)
= 2.31 min

TOTAL CYCLE TIME = 25.41 min

No. of trips for Dumptruck per day 8.00 x 60.00


= = 18.89 trips
25.41
Dumptruck Daily Output = 10.00 x 18.89 = 188.90 Cu.m.
Using 4.00 Dumptruck = 4.00 x 188.90 = 755.61 Cu.m.
1,000.00
No. of days for Dumptruck = = 1.32 days
755.61

EQUIPMENT USED: (2009 ACEL RATES)

4.00 Unit Dumptruck @P 11,360.00 /day x 1.32 days = P 60,137.00


Sub-total P 60,137.00

Estimated Quantity 1,000.00 cu.m.


Unit Cost P 12.03 /cu.m./km. (Unit Cost, Hauling per cu.m. per km.)
Grand Total P 60,137.00
Equipment P 60,137.00
Labor P -
Materials P -
ZAMBOANGA CITY DISTRICT ENGINEERING OFFICE:

Hauling Unit Cost per Hauling Cost


Unit Price Unit Cost per cu.m.
Distance cu.m./km. per cu.m.

Cost of Fine Aggregates: - x 12.03 = 0.00 + 901.00 = 901.00

Cost of Coarse Aggregates: - x 12.03 = 0.00 + 901.00 = 901.00

Cost of Item 200 Materials: - x 12.03 = 0.00 + 618.00 = 618.00

Cost of Item 300 Materials: - x 12.03 = 0.00 + 755.00 = 755.00

Cost of Boulders: - x 12.03 = 0.00 + 1,100.00 = 1,100.00

Cost of Item Embankment


- x 12.03 = 0.00 + 270.00 = 270.00
Common Borrow:

Cost of Item Embankment Selected


- x 12.03 = 0.00 + 350.00 = 350.00
Borrow:
UNIT COST DERIVATION FOR PORTLAND CEMENT

TOTAL QUANTITY REQUIREMENTS FOR PORTLAND CEMENT

QUANTITY
DESCRIPTION
(Bags)

T O T A L -

Quantity = - Bags

*Source of Portland Cements, LABASON DISTRICT ENG"G OFFICE

Delivery Charge = P 0.120 / bag / km.

S I T E HAULING DISTANCE

ZAMBOANGA NORTE 2ND DEO


(STA. 1988+300)
134.75
PROJECT SITE
Km. 2123+050

*Average hauling distance from Source to assumed Stockpiling area less 5.00 km. free haul:

say - km.

Delivery Charge = P 0.120 x 0.00

=P - / bag

*Delivery Truck : 0.00 bags., (hauling works)

20,000.00 kgs., (capacity per haul)

or 500.00 bags, (capacity per haul)

Terrain : Rolling

Road condition : Paved

*Capacity of Laborers unloading bags of Cement from Delivery Truck :

Assume ( 10 ) laborers can unload 500.00 bags of Cement.

*Dumptruck (10 Wheeler) days computation : TIME-MOTION ANALYSIS

Speed when loaded : 30.00 kph

Speed when unloaded : 40.00 kph

Loading and Unloading = 45.00 mins.

LOADED TRAVEL TIME :


First 200 m. @ 20 kph = 0.60 mins.
Succeeding 42,530 m.@ 30 Kph = -0.80 mins.
Next 200 m. @ 20 Kph = 0.60 mins.
RETURN EMPTY :
First 200 m. @ 30 kph = 0.40 mins.
Succeeding 42,530 m.@ 40 Kph = -0.60 mins.
Next 200 m. @ 30 Kph = 0.40 mins.

TOTAL CYCLE TIME = 45.60 mins.

Capacity of Dumptruck : 500.00 bags

8.0 x 60.00
No. of trips for Dumptruck per day = = 10.53 say 10.53 trip
45.60

Dumptruck daily output = 500 x 10.53 = 5,263.16 bags

Using ( 4 ) Dumptrucks = 4 x 5263.16 = 21,052.63 bags


0.00
1. No. of days for Delivery Truck = = 0.00 say 0.00 days
21,052.63

2. No. of days for Labor, for unloading = complimentary to D. Truck days = 0.00 days

DELIVERY COST :

- - Bags, Portland Cement @P - / bag =P -

Sub - Total P -

LABOR :

1 - Foreman @P 611.92 /day x - days = P -

10 - Laborers, unloading @P - /day x - days = P -

Sub - Total P -

MATERIALS :

0.00 - Bags, Portland Cement @P 265.00 / bag =P -

(Pick-Up Price) Sub - Total P -

Estimated Quantity - Bags

Unit Cost P #DIV/0! / Bag, say P #DIV/0! / Bag

Grand Total P -

Delivery Cost P -

Labor P -

Materials P -
COMPUTATION OF HAULING COST (DPWH REGION IX)
(STEEL REINFORCEMENT)
ZAMBOANGA DEL NORTE 3RD ENGINEERING OFFICE (STA. 1988 + 690.00)
PROJECT SITE (STA. 2084 + 805.00)
NET DISTANCE : - km.

I. CYCLE TIME :
A.) Without Load :
where :
Distance = - km.
Velocity = 55.00 km./hr.
Hour = 60.00 min./hr.
0.00 km.
Time =
55.00 km./hr.

0.00 km.
Time =
0.92 km./min.
Time = - mins.

B.) With Load :


where :
Distance = - km.
Velocity = 35.00 km./hr.
Hour = 60.00 min./hr.
0.00 km.
Time =
35.00 km./hr.
0.00 km.
Time =
0.58 km./min.
Time = - mins.
C.) Allowance of delay (10% of Cycle Time)
Time = (A + B) x 10%
Time = - + - x 10%
Time = - mins.
D.) Total Time :
Total = (A + B + C) x 6.25%
Total = - + - + - / 60
Total = - hr.

II.) Hauling Cost :


A.) Cost of Hauling :
where :
1 - Cargo Truck = Php 1,212.00 /hr.
2 - Helper = Php 42.78 /man-hr.
Total Time = - hr.
Cost = 1,212.00 + 42.78 x 2.00
Cost = 1,297.56 /hr.
Haul Cost = 1,297.56 x -
Haul Cost = -
B.) Unloading :
where :
1 - 25 Ton Crane = Php 1,861.00 /hr.
2 - Helper = Php 42.78 /man-hr.
Total Time = 1.00 hr.
Cost = 1,861.00 + 42.78 x 2.00
Cost = 1,946.56 /hr.
Haul Cost = 1,946.56 x 1.00
Haul Cost = 1,946.56
C.) Total Cost = Haul Cost + Unloading
Total Cost = - + 1,946.56
Total Cost = 1,946.56
D.) Total Capacity of Truck = 15,000.00 kg.
E.) 1,946.56
Cost of Hauling/kg. =
15,000.00
Cost of Hauling/kg. = 0.13 kg.
Base Price, DEO = 43.00 kg.
Total amount = Hauling Cost + Base Price
Total amount = 0.13 + 43.00
Total amount = 43.13
Contingency 3%

You might also like