Process Description Quality Control Activities Reference / Acceptance Criteria Verifying Document
Process Description Quality Control Activities Reference / Acceptance Criteria Verifying Document
2.1 Blasting Abrasives Check size, cleanliness and 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
dryness of blasting abrasives. 21008-BAE-63199-ME-SP-0002
Paint Maker’s
Specification/Recommendation
2.2 Surface Preparation Check material free from oil, 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
grease and other contaminants. 21008-BAE-63199-ME-SP-0002
Check profile and degree of Paint Maker’s
cleanliness of blasted surface is Specification/Recommendation
in accordance to requirement.
2.3 Paint Mixing Check paint mixing and thinning 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
is in accordance to 21008-BAE-63199-ME-SP-0002
manufacturer’s recommendation. Paint Maker’s
Specification/Recommendation
2.4 Painting Application Check relative humidity, dew 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
point and surface temperature 21008-BAE-63199-ME-SP-0002
prior to paint. Check paint is Paint Maker’s
uniformly applied and meet Specification/Recommendation
specified thickness.
2.5 Painting Inspection Check surface appearance free 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
from sagging, drip mark, 21008-BAE-63199-ME-SP-0002
blistering, pinholes, dirt, etc. Paint Maker’s
Specification/Recommendation
2.6 Thickness Measurement Carry out dry film thickness 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
measurement and ensure paint 21008-BAE-63199-ME-SP-0002
thickness is within the minimum Paint Maker’s
thickness required. Specification/Recommendation
3.0 SURFACE
PREPARATION &
COATING
APPLICATION
3.1 Blasting Abrasives / Power Check size, cleanliness and 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
Tools dryness of blasting abrasives. 21008-BAE-63199-ME-SP-0002
Check power tools to be used. Paint Maker’s
Specification/Recommendation
2
PROCESS QUALITY CONTROL REFERENCE / VERIFYING
NO. KSL PM BAB
DESCRIPTION ACTIVITIES ACCEPTANCE CRITERIA DOCUMENT
sweep or spot blast, power Paint Maker’s
tooling). Check surface area is Specification/Recommendation
free from oil, grease, grindings,
burrs, and sharp edges. Check
blasted surface cleanliness and
profile.
3.3 Paint Mixing Check paint mixing and thinner 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
is in accordance to 21008-BAE-63199-ME-SP-0002
manufacturer’s recommendation. Paint Maker’s
Specification/Recommendation
3.4 Painting Application Check relative humidity, dew 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
point and surface temperature 21008-BAE-63199-ME-SP-0002
prior to paint. Check paint is Paint Maker’s
uniformly applied and meet Specification/Recommendation
specified thickness.
3.5 Painting Inspection Check surface appearance free 21008-BAE-63199-ME-SP-0001 Inspection Reports W W M
from sagging, drip mark, 21008-BAE-63199-ME-SP-0002
blistering, pinholes, dirt, etc. Paint Maker’s
Specification/Recommendation
3.6 Thickness Measurement Carry out dry film thickness 21008-BAE-63199-ME-SP-0001 Inspection Reports W W M
measurement and ensure paint 21008-BAE-63199-ME-SP-0002
thickness is within the minimum Paint Maker’s
thickness required. Specification/Recommendation
4.0 INTERMEDIATE
COATING
APPLICATION
4.1 Surface Preparation Check surface preparation e.g. 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
sanding or solvent cleaning. 21008-BAE-63199-ME-SP-0002
Check cleanliness of the surface. Paint Maker’s
Specification/Recommendation
4.2 Paint Mixing Check paint mixing and thinner 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
is in accordance to 21008-BAE-63199-ME-SP-0002
manufacturer’s recommendation. Paint Maker’s
Specification/Recommendation
4.3 Painting Application Check relative humidity and 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
surface temperature prior to 21008-BAE-63199-ME-SP-0002
paint. Check paint is uniformly Paint Maker’s
applied and meet specified Specification/Recommendation
thickness.
4.4 Painting Inspection Check surface appearance free 21008-BAE-63199-ME-SP-0001 Inspection Reports W W M
from sagging, drip mark, 21008-BAE-63199-ME-SP-0002
blistering, pinholes, dirt, etc. Paint Maker’s
Specification/Recommendation
4.5 Thickness Measurement Carry out dry film thickness 21008-BAE-63199-ME-SP-0001 Inspection Reports W W M
measurement and ensure paint 21008-BAE-63199-ME-SP-0002
thickness is within the minimum Paint Maker’s
thickness required. Specification/Recommendation
5.1 Surface Preparation Check surface preparation e.g. 21008-BAE-63199-ME-SP-0001 Inspection Reports W M M
sanding or solvent cleaning. 21008-BAE-63199-ME-SP-0002
Check cleanliness of the surface. Paint Maker’s
Specification/Recommendation
3
PROCESS QUALITY CONTROL REFERENCE / VERIFYING
NO. KSL PM BAB
DESCRIPTION ACTIVITIES ACCEPTANCE CRITERIA DOCUMENT
5.2 Paint Mixing Check paint mixing and thinner 21008-BAE-63199-ME-SP-0001 Inspection Report W M M
is in accordance to 21008-BAE-63199-ME-SP-0002
manufacturer’s recommendation. Paint Maker’s
Specification/Recommendation
5.3 Painting Application Check relative humidity and 21008-BAE-63199-ME-SP-0001 Inspection Report W M M
surface temperature prior to 21008-BAE-63199-ME-SP-0002
paint. Check paint is uniformly Paint Maker’s
applied and meet specified Specification/Recommendation
thickness.
5.4 Painting Inspection Check surface appearance free 21008-BAE-63199-ME-SP-0001 Inspection Report W W M
from sagging, drip mark, 21008-BAE-63199-ME-SP-0002
blistering, pinholes, dirt, etc. Paint Maker’s
Specification/Recommendation
5.5 Thickness Measurement Carry out dry film thickness 21008-BAE-63199-ME-SP-0001 Inspection Report W M M
measurement and ensure paint 21008-BAE-63199-ME-SP-0002
thickness is within the minimum Paint Maker’s
thickness required. Specification/Recommendation
5.6 Adhesion Test (only if Carry out adhesion test if 21008-BAE-63199-ME-SP-0001 Inspection Report W W W
required) required. 21008-BAE-63199-ME-SP-0002
Paint Maker’s
Specification/Recommendation
6.1 Surface Preparation Check surface preparation e.g. 21008-BAE-63199-ME-SP-0001 Inspection Report W M M
spot blast, power tooling, 21008-BAE-63199-ME-SP-0002
sanding, featheredge, etc. Paint Maker’s
Specification/Recommendation
6.2 Paint Mixing Check paint mixing and thinner 21008-BAE-63199-ME-SP-0001 Inspection Report W M M
is in accordance to 21008-BAE-63199-ME-SP-0002
manufacturer’s recommendation. Paint Maker’s
Specification/Recommendation
6.4 Painting Inspection Check surface appearance free 21008-BAE-63199-ME-SP-0001 Inspection Report W W M
from sagging, drip mark, 21008-BAE-63199-ME-SP-0002
blistering, pinholes, dirt, etc. Paint Maker’s
Specification/Recommendation
6.5 Thickness Measurement Carry out dry film thickness 21008-BAE-63199-ME-SP-0001 Inspection Report W M M
measurement and ensure paint 21008-BAE-63199-ME-SP-0002
thickness is within the minimum Paint Maker’s
thickness required. Specification/Recommendation
7.1 Final Visual Inspection Carry out final visual inspection 21008-BAE-63199-ME-SP-0001 Inspection Report W W R
e.i. Tank Close-out of tanks, compartment, areas, 21008-BAE-63199-ME-SP-0002
structures, etc. with Owner Rep Paint Maker’s
and Paint Rep for final Specification/Recommendation
acceptance.
4
PROCESS QUALITY CONTROL REFERENCE / VERIFYING
NO. KSL PM BAB
DESCRIPTION ACTIVITIES ACCEPTANCE CRITERIA DOCUMENT
8.0 DOCUMENTATION
8.1 Review of Documentation Review of completion records Final Documentation Procedure; Manufacturer Data R R+A R+A
required for submission 21008-BAE-63199-ME-SP-0001 Record (MDR)
21008-BAE-63199-ME-SP-0002
Note:
W = Witness: Total or detailed inspection is required. A request for inspection is mandatory and it has to be given to Client and/or
Paint Maker at least one (1) day prior to the appointed time of inspection or test.
M = Monitor: Also known as patrol inspection or surveillance. A request for inspection maybe required by Client and/or Paint
Maker subject to the criticality of the item(s) to be inspected.
H = Hold Point: No work or activities can commence without the final approval or disposition from Client and/or Paint Maker.
R = Review: Review of documents such as work procedures, drawings, material certificates, welders certificates, results of
inspection & test, NDT report, dimensional report, etc.
A = Approval Document or report need to be approved or accepted by Client and/or Paint Maker.