Infratech Construction Company Limited - Idea Engineers Limited

Name of Project : Re-Construction of 12.30km Road From Kuril Flyover to Kanchon Bridge Intersection
(Purbachal Link Road Package-03)
Consultant : Data Experts (Pvt.) Limited Client : 24 Engineer Construction Brigade

Date : 03/11/2020 (Tuesday)


Daily Work Program
Chainage (Km) Tools
RFI
SL No. Work Description Length Side Planned Providing Providing Responseible Person Contact No. Remarks
Reference From To Planned Equipment
Manpower Manpower Equipment
1. Permanent Work

Roadway Excavation, Main Excavator (0.5): 01 Excavator (0.5): 01


a) N/A 5+500 5+600 100 m L/S Engr. Saiful 01729854742
Carrigeway with Green Zone Drum Truck: 01 Drum Truck: 01

2. Temporary Work

a) No temporary work will be executed on tomorrow.

3. Survey Work

Survey - Level Check (Sub- Surveyor Jahangir 01912754374


a) N/A 5+350 5+600 250 m L/S Total Station Total Station
Grade Level) Asst. Surveyor Enamul 01999823545

Alignment Check of Right of


Surveyor Jahangir 01912754374
b) Way of Road and Boundary N/A 3+604 6+822 3218 m R/S Total Station Total Station
Asst. Surveyor Enamul 01999823545
Wall
4. Laboratoty Work

CBR Testing of local sand Lab Technocian Mostofa 01718305392


a) N/A Location: Site Laboratory
for ISG Lab Technician Redwan 01779373106

Sample Collection of new


Location: Sub Camp beside Lab Technocian Mostofa 01718305392
b) Brick Chips for Sub Base N/A
Purbachal Army Camp Lab Technician Redwan 01779373106
Mix Design (4:00 PM)
5. Safety Maitaining Work

Traffic Flag: 02 Traffic Flag: Safety Officer Salahuddin 01717913504


a) Traffic Flow Control N/A 5+200 5+700 500 m L/S
No.s 02 No.s Safety Supervisor Jakir 01406480891

6. Camp/Stackyard Work

Unloading Excavated Soil Dozer: 01 Dozer: 01


a) N/A 5+100 Stackyard Supervisor Sumon 01768953509
from existing Service Lane Drum Truck: 01 Drum Truck: 01

7. Meetings

a) No meeting has been scheduled yet for tomorrow

Project Manager
ICCL-IEL JV.
Purbachal Link Road Project (Package-03)