Professional Documents
Culture Documents
ORN 01 - Maintenance Management For District Engineers - Old
ORN 01 - Maintenance Management For District Engineers - Old
Department of Transport
Overseas Development Administration
Maintenance management
for district engineers
(2nd edition)
Overseas Unit
Transport and Road Research Laboratory
Crowthorne Berkshire United Kingdom
1987
ACKNOWLEDGEMENTS
Overseas Centre
Transport Research Laboratory
Crowthorne, Berkshire, RG45 6AU
United Kingdom
ISSN 0951-8987
CONTENTS
page
1. Introduction 1
Purpose and scope 1
Structure of the Note I
2. The role of the maintenance engineer 1
Management responsibilities 1
Involvement on site 1
Delegation 2
Training 2
Using microcomputers 2
Implementation 2
3. Maintenance activities 3
4. Management tasks 3
5. Inventory 4
Content and preparation 4
Presentation 4
6. Inspection 6
Frequency of inspection 6
Condition survey 6
Recording results 7
7. Determination of maintenance requirements 11
Recurrent and periodic maintenance of unpaved roads 11
Intervention levels on paved roads 12
Diagnozing the cause of deterioration 12
Specifying the work required 12
8. Resource estimation 16
Choice of work method 16
Use of contractors 16
Labour 16
Equipment 17
Materials 19
Resource allocation 20
9. Identification of priorities 22
Maintenance activities by order of importance 22
Roads by order of importance 22
Priority matrix 23
Adapting priorities to local conditions 23
Determining the work programme 23
10. Work scheduling and execution 24
Schedules 24
Worksheets 24
11. Monitoring 26
Site inspections 26
Desk review 26
page
References 26
Appendix A - Field procedures for inventory and condition measurement surveys 27
A.l General procedure 27
Recording 27
Organization of teams 27
Safety 27
Transport 27
Notes for inspectors 28
Duties of team members 28
Order of work 28
Accuracy 28
A.2 Condition measurement 28
General considerations 28
Side drains and turnouts (all roads) 28
Loss of material (gravel roads) 29
Deformation (all roads) 29
Cracking (paved roads) 29
Pot-holes (all roads) 29
Edge drainage (paved roads) 29
Edge step (paved roads) 29
Appendix B - Management of grading for unpaved roads 32
B.1 Determining optimum grading frequencies 32
B.2 Monitoring of optimum frequencies 32
B.3 Measurement methods 33
Reference 33
Appendix C - Traffic counting 34
C.1 Frequency and duration of counts 34
C.2 Estimation of ADT from counts 34
C.3 Manual counts 34
C.4 Automatic counters 34
C.5 Moving observer counts 34
C.6 Development of traffic counts 35
Appendix D - Recommended standard forms 36
Appendix E - Illustrations of typical defects 42
1. INTRODUCTION 2. THE ROLE OF THE
MAINTENANCE ENGINEER
Purpose and scope
2.1 Roads are expensive to build. They repay their
1.1 This Note is a practical guide to the management of initial investment only by means of long4erm care and
maintenance operations. It outlines a rational approach maintenance. A road system that is well maintained
that will help maintenance engineers organize and brings important social and economic benefits:
control the activities for which they are responsible, so as • the transport links on which development
to improve efficiency and make more productive use of depends are kept in good working order
maintenance resources. • roads have a longer lifetime of service because
their surfaces do not deteriorate so rapidly
1.2 The maintenance operations discussed here are those • vehicle operating costs are reduced because
required to keep roads in good condition and repair. The traffic is able to run smoothly
Note does not deal with any form of road improvement • transport operations are safer and more reliable
works, pavement strengthening or reconstruction, even
where these activities are undertaken by an organization 2.2 The maintenance engineer responsible for
responsible also for normal maintenance. operations at regional or district level has a key role
to play in achieving these benefits. His success
1.3 The Note offers advice on techniques basic to good depends largely on the way he approaches the task
maintenance practice, but it does not set out to define of management.
'model' systems that should be copied generally or to
describe all the management procedures an ideal Management responsibilities
maintenance organization would follow. This is because
in any location the best management system will be one
which is matched closely to the technical skills, human 2.3 This task normally involves five main
resources and equipment available to the individual responsibilities:
maintenance organization; and the most effective • planning the annual programme of
procedures will be those that are appropriate to the maintenance work for his area, assessing the
experience and capabilities of its staff. Using this Note, resources needed and preparing an appropriate
engineers will be able to assess the range of management budget estimate
techniques applicable to road maintenance and so • arranging that funds are allocated fairly to the
identity methods they can usefully put into practice various parts of the road network, and deciding
within the context of their own organizations. on priorities if the funds available do not allow
him to undertake the full programme
Structure of the Note • authorising and scheduling work
• making sure that his staff know how to carry
1.4 Following this introduction, Section 2 summarizes out the work methodically and efficiently
the responsibilities of the maintenance engineer and • monitoring the quality and effectiveness of
comments on the approach he should adopt to key maintenance activities.
management tasks. Section 3 sets out a classification of
maintenance activities, and Section 4 defines the 2.4 Each of these responsibilities forms a major step in
sequence of management tasks which the engineer has to the sequence of maintenance management explained in
fulfil. These tasks are the subject of Sections 5 to 11, Sections 5 to 11 of this Note.
which explain each stage of the management process in
turn. Appendices A to D provide details of technical Involvement on site
procedures and illustrate standard forms and worksheets.
Appendix E illustrates typical defects found on roads. 2.5 In performing his management role, the maintenance
engineer will, of course, have many hours of office work
on matters such as planning and administration. But it is
essential that he also gets out into the field as much as
possible. The simple procedure of seeing things for
themselves would help maintenance engineers overcome
many of the problems that at present affect their
operations.
1
• they enable the maintenance engineer to become Using microcomputers
thoroughly familiar with road conditions in the area,
and so recognize trouble spots and other places 2.10 Now that 'micros' are becoming widely
where difficulties are likely to occur available, their application to maintenance management
is a subject where staff training may be particularly
• he can gain first-hand knowledge of the extent and useful. A growing range of specialised software is
quality of the maintenance that has actually been available to help process data and analyze problems, and
carried out, instead of having to rely on what he using a micro can save considerable time beside freeing
reads in reports the maintenance engineer for inspection and monitoring
on site. But expenditure on computers can prove an
• he can use this knowledge to assess maintenance expensive mistake if the system is not chosen with care
priorities much more confidently and if suitable personnel are not available to make the
best use of it. Maintenance can be managed efficiently
• his presence on the spot means that he can advise on without a micro; and even if there is one in the office, it
problems as they arise does not lessen the need for regular and accurate data
collection in the field.
• seeing him regularly on site should boost the morale
of road gangs and improve their standard of work Implementation
and their output. His attitude will have more
influence on their performance than any other
2.11 For most organizations, the management
factor, and site visits are the most effective way of
approach recommended in this Note will take some time
demonstrating his commitment to getting the job
to implement - perhaps a period of several years. The
done successfully.
maintenance engineer should not try to put everything
into practice at once. It is better to introduce new
Delegation methods and procedures gradually, starting with
straightforward measures that will produce early and
2.7 The maintenance engineer should use his positive results. Proceed step by step, and wait until one
knowledge of road conditions to decide which operations stage is working reasonably well before moving to the
need his personal supervision and which he can safely next. Concentrate first on the sections of road that carry
delegate to staff. On lengths of road where maintenance the largest volumes of traffic and ensure these are
is straightforward and easy to specify in advance, it adequately maintained before dealing with less busy
should be possible to leave day-to-day work in the hands roads.
of suitably trained foremen or contractor's staff. On other
roads where there are problems requiring complicated
treatment and on-the-spot judgment, the maintenance
engineer will have to become personally involved in
determining what needs to be done and supervising the
work. Thy key point is that he should not let his time be
taken up by simple operations which less qualified staff
are able to manage.
Training
2
3. MAINTENANCE ACTIVITIES 4. MANAGEMENT TASKS
3.1 For the purposes of management, the most useful way 4.1 As noted in para 2.3, the maintenance engineer has the
to classify maintenance activities is in terms of their responsibility of structuring these activities into a
frequency. There are four categories: programme of maintenance work throughout his area, with
an appropriate allocation of resources. This responsibility
• routine maintenance, required continually on every involves a sequence of tasks, which are discussed in turn in
Sections 5 to 11, and can be summarised as follows:
road whatever its engineering characteristics or traffic
volume
(i) inventory: recording the basic characteristics of
each section of the road network
• recurrent maintenance, required at intervals during
the year with a frequency that depends on the volume of
(ii) inspection: examining the road and measuring its
traffic using the road
condition
recurrent on paved roads: 4.2 Because unpaved roads deteriorate more rapidly than
repairing pot-holes; patching; repairing edges; sealing cracks paved roads, they require more frequent attention. The
recurrent maintenance listed for unpaved roads in para 3.2
periodic on unpaved roads: should be applied at regular and predetermined intervals
throughout the year. These activities must not be deferred
regravelling until defects show up in the course of an annual or seasonal
inspection. Methods of calculating how frequently they need
periodic on paved roads: to be undertaken during the year are discussed in Section 7.
resealing (surface dressing, slurry sealing, fog spray, etc.);
regravelling shoulders; road surface marking
urgent:
removal of debris and other obstacles; placement of warning
signs and diversion works.
3
5. INVENTORY Presentation
Content and preparation 5.6 There are three useful ways of presenting the
information recorded in the inventory:
5.1 The inventory is a set of information about the basic
engineering and traffic characteristics of the road network. It • diagrammatic maps
defines the key features of each section of road and indicates
the level of traffic use. This information is an essential
• strip maps
reference source for the subsequent stages of inspection and
analysis.
• card index systems.
5.2 The content of the inventory should be directly
relevant to maintenance management. When it is first drawn 5.7 Fig. 5.1 shows a typical diagrammatic map. It is
up, it should be as simple as possible and need contain basically a road plan of the area marked to indicate traffic
information only on the following items: levels, categories of road surface and road widths. This kind
of map is particularly helpful in giving an overview of the
• type of surface and construction whole network, enabling the maintenance engineer to see at
a glance how roads with differing features relate to each
carriageway and shoulders
other.
• cross-section width 5.8 Fig. 5.2 is an example of a strip map. This is a simple
carriageway and shoulders annotated drawing which records significant information
about a section of road and its surroundings. Its principal use
is in the field, where it provides a quick means of reference
• traffic volume during inspections and surveys - especially for the location
annual average daily traffic (numbers of vehicles per of chainage. It is often convenient to staple strip maps
day). together so as to form a pocket-sized notebook for each road.
4
Fig.5.1 Diagrammatic map of maintenance district
5
6. INSPECTION
6.1 Recommended procedures for field inspections are
described in Appendix A: they are similar to inventory
procedures, but their emphasis is on the condition of the
road rather than its basic characteristics. They identify
locations where deterioration is occurring, measure the
extent of the problem and define the action needed to put
matters right. It is likely that, while the management
system is being developed, the early inspections will have
to rely largely on a visual assessment of defects: but
measurement techniques should be introduced as soon as
it is practicable to do so, following the guidance in
Appendix A.
Frequency of inspection
Condition surveys
6
determine the requirements for periodic work
by making such additional investigations,
measurements and analyses as are required.
Recording results
7
8
Fig.6.1 Example of inspection form for paved road
9
Fig.6.2 Example of inspection form for unpaved roads
10
Fig.6.3 Example of inspection form for structures and road furniture
recommended frequency. which
7. DETERMINATION is the one that should normally be adopted. Grading the
OF MAINTENANCE road more frequently than the mean will give road users a
higher level of traffic service: correspondingly, a grading
REQUIREMENTS frequency less than the mean will result in a lower level of
service.
Recurrent and periodic maintenance of unpaved
7.4 Dragging. This needs to be done regularly where
roads loose material lies on the road or where corrugations are
liable to form. In the latter case the operation may have to
7.1 As noted in para 4.2, unpaved roads need a be repeated every few days. The maintenance engineer
programme of regular and systematic attention. The should determine the necessary frequency from a series of
requirements for recurrent maintenance on these roads have practical tests, by seeing how long it takes the corrugations
to be determined independently of the results of network to return after dragging is carried out. The frequency will
inspections. vary for different materials, design of drag, traffic volumes
and physical conditions.
7.2 Grading. The maintenance engineer must decide
how many times during the year each unpaved road will 7.5 Monitoring recurrent maintenance. Appendix B
need grading so as to provide the best level of traffic describes procedures for monitoring the effectiveness of
service possible in the local conditions. In assessing this, he recurrent maintenance activities on unpaved roads. The
will have to take account of a range of factors including the maintenance engineer should identify several roads that are
type and size of the road material, the amount of traffic representative of the network and arrange for a series of
using the road, the local topography, climatic regime and inspection surveys to be performed immediately before the
other physical features. dates on which recurrent maintenance is scheduled. The
inspection results will enable him to check whether he has
7.3 If he has access to a computing facility such as a gauged accurately the appropriate frequency of grading and
micro or a programmable calculator, and has roughness dragging operations. If, for example, a high degree of
measuring equipment available, he should use the method deterioration is still evident, he should adjust the existing
outlined in Appendix B to determine the optimum grading schedule so as to perform these operations more frequently.
frequency for the road. If not, he should use Fig. 7.1 to As noted in para 6.7, the inspection form should include
gauge the frequency appropriate to the annual average daily space to record the results of these monitoring surveys.
traffic on the road. Fig. 7.1 is derived from studies
undertaken by TRRL. The solid line indicates the mean
11
7.6 Regravelling. This is a periodic activity that will measurements to be made, as explained in Appendix A.
need to be performed whenever the existing layer of gravel Others involve simply a visual assessment. While the
becomes unacceptably thin. If this layer is found to be less management system is being introduced, it is likely that the
than 50mm thick for more than 20 per cent of the length of maintenance engineer will have to rely entirely on the
the sub-section of road being inspected (Table 7.1), visual assessment of defects, but he should try to introduce
regravelling should take place. Appendix A includes advice the use of measurement techniques as skills and resources
on the inspection procedure. permit.
7.7 In dealing with paved roads, the maintenance 7.10 It is important to identify the cause of deterioration
engineer must interpret the inspection results (Section 6) so and to put this right if possible, rather than just treating the
as to decide when and where repairs are needed and what symptom. For example, there is little point in continually
form of maintenance activity is required. Like a doctor filling in pot-holes in a road if they keep occurring only
treating an illness, he has to recognize the symptoms that because of poor drainage. Finding the real problem and
indicate it is time to take remedial action. These indications focusing attention on its solution will produce a more cost-
are termed 'intervention levels': i.e. they identify the stage effective use of maintenance resources.
or circumstance in which the maintenance engineer should
intervene and the action he should take to stop farther 7.11 Some problems, of course, may be outside the scope
deterioration. Intervention levels can be defined for of maintenance. For example, a road across flat country
unpaved roads too, as shown in Table 7.1, though the with inadequate drainage outfalls may experience base
frequency of recurrent operations is determined in advance failure as a result of the capillary rise of water in the wet
(paras 7.1-7.5). season. The only solution to the problem is to raise the level
of the road. This would be a road improvement, not a
7.8 It is advisable always to adopt intervention levels maintenance operation: as such, it may warrant a special
suited to the particular local conditions. As a guide, Tables allocation of resources in accordance with the
7.1-7.3 set out recommended intervention levels for organization's procedures for road improvement work.
unpaved roads, paved roads, and road structures and
furniture, respectively. The recommended levels are based Specifying the work required
on the assumption that the road network is already being
maintained to an adequate standard and that sufficient 7.12 The maintenance engineer should examine the
resources are available to keep up this standard. In other completed inspection forms (para 6.7) and compare the
words, they represent a target that the maintenance engineer inspection results with intervention levels of the type
should aim eventually to achieve. If, as will often be the recommended in Tables 7.1-7.3. He can then determine the
case, he has too few resources at his disposal to apply the maintenance needs of each sub-section of the road network
recommended levels, he can adopt alternative levels that are and specify the work required. The necessary action should
more appropriate to the workload and capabilities of his be marked on the inspection forms, preferably in a different
organization. colour from that used for the survey results. The forms will
provide a permanent record of maintenance requirements.
7.9 Some of the intervention levels in Tables 7.1-7.3 are
expressed in quantitative terms and require
TABLE 7.1
Extent (% of
Defect Level Sub-section length) Action Programme Notes
Gravel <50mm >20 Regravel Periodic
thickness
Camber
Roughness (See paras − Grade/drag Recurrent Planned on a
Rutting 7.1-7.5) programmed basis
Corrugations
Pot-holes
12
TABLE 7.2
13
TABLE 7.2 (Continued)
14
TABLE 7.3
15
8. RESOURCE ESTIMATION 8.5 Contracting work out can have the advantage of
relieving pressure on the organization's labour resources
and it can offer a high level of efficiency at a competitive
Choice of work method cost. On the other hand, the organization will have to
prepare detailed contract documents, set up a tendering
8.1 Maintenance operations involve three types of procedure and provide contract supervision - all of which
resources materials, labour and equipment. It is easy to may require a substantial amount of time and effort on
estimate directly the quantities of materials needed for an the part of its staff. There is also a risk that contractors
operation (para 8.15), but the amounts of labour and bidding for maintenance work on a regular basis may
equipment required will depend on the method used in introduce 'price fixing' to increase their profitability, and
carrying out the work. There are some activities that can so involve the organization in higher costs. The
only be done by manual labour; there are others where maintenance engineer will have to weigh up these factors
plant and machinery are essential; but many activities in relation to the capacities of his organization and the
offer the option of either method. Trying to combine performance of local contractors.
manual labour and machinery on the same task will
normally lead to inefficiency. The maintenance engineer 8.6 The following activities should present no
will therefore have to choose between a method that significant problems of administration or quality control
largely makes use of manual labour and a method based if contracted out on the basis of competitive tenders:
on the use of machinery.
• Supply of materials
8.2 In making this choice he has to take account of Steel reinforcement
several factors: Bitumen products
Cement and lime
• the probable costs of each method in relation to the Natural gravel
available budget Screened gravel
Rock aggregate (for subsequent crushing by the
• the standard of work resulting from each method. highways department)
Machinery normally produces a truer surface and a Crushed aggregate (for surface dressing and
more consistent finish than manual labour. but this concrete)
may not always be required. For example, it would Washed sand (for concrete or slurry sealing)
be difficult to find any economic justification for Precast concrete blocks
giving low-volume roads the close tolerances of Precast concrete box culverts or pipes
level and smoothness that machinery can achieve Gabion baskets.
• the implications for the way the work is organized. • Maintenance operations
If large-scale works are involved, labour-based Recutting of side drains and turnouts
methods will require precise organization and Reconstruction of culverts
management. Labour has to be available in Regravelling
sufficient numbers in the right place and at the right Resealing: surface dressing, slurry sealing, fog
time. Transporting the labour force to and from spray, etc.
worksites can cause problems; standardised, good- Grass cutting and bush clearing.
quality tools and equipment will be needed to
achieve high levels of output; the health and 8.7 Specialist contractors can also be brought in to
nutrition of the men must be thought about, since undertake the supply and maintenance of machinery and
improved standards help to increase productivity. vehicles.
8.3 Table 8.1 gives an assessment of the potential 8.8 The maintenance engineer should satisfy himself
offered by various maintenance activities for the use of that any contractor invited to tender for a job is capable
labour-based and machinery-based methods. of completing it satisfactorily, has the necessary
personnel and equipment available, and is sufficiently
Use of contractors knowledgeable about estimating procedures and current
8.4 Though maintenance organizations normally market rates to submit realistic prices.
employ their own labour force, there is a range of
activities that can be undertaken for them by local 8.9 It is vital that the maintenance engineer ensures that
contractors. If the policies of his organization allow the all contracts are properly supervised and that all
use of contractors, the maintenance engineer should specifications are met before he authorises payment.
examine this possibility.
Labour
8.9 Table 8.2 indicates the outputs of work that can be
16
expected from teams engaged on normal maintenance guide in assessing the levels of productivity associated
activities, using manual labour or machinery as with various operations, and estimating the amount of
appropriate. Each output is expressed as a range: the labour required for each activity.
amount of work that a team in fact achieves should lie
within this range, depending on local conditions. For 8.11 The values given in the table refer only to
example, a labour-based approach to clearing side drains working time. They make no allowance for time that is
is likely to involve between 4 and 10 men using simple non-productive, i.e. not spent actually working. Non--
hand equipment, and the team can be expected to clear productive time can build up significantly during
between 30 and 60 metres of drain per man-day. A maintenance operations, and it should be an aim of
machinery-based approach to the same task will reduce management to reduce it to a minimum.
the labour requirement to 2 or 3 men using a grader and
shovels, and they will be able to clear as a team between Equipment
4 and 7 km per day.
8.12 Many activities need only simple equipment such
8.10 The maintenance engineer should use Table 8.2 as a as picks and shovels. It is important to have enough of
these available to meet day-to-day requirements.
TABLE 8.1
NOTES:
(*) The potential in these activities is dependent upon suitable design of the ditch cross-section. 'V'-shaped
ditches are suitable for maintenance by grader, whereas flat bottomed ditches are suitable for maintenance by
hand or mechanical shovel.
(**) The potential in this activity is dependent on the width of the shoulder and presence of obstructions such as
road furniture and culvert headwalls.
◆ Some methods of manufacture may require the use of specialised plant (eg. vacuum application of reflective
sheeting to sign plates).
$ The expression 'skilled' implies that specific training of operatives is essential.
17
TABLE 8.2
OUTPUTS OF WORK
* The unit of ‘pass-km’ is the actual distance the grader travels while working. To determine the length of road graded, this
figure must be divided by the number of ‘passes’ necessary to cover the whole width of the road.
18
TABLE 8.2 (Continued)
8.13 The maintenance engineer will probably not be • checking for himself that the daily maintenance
responsible for the supply of plant and vehicles, since routine is being carried out, and demonstrating his
this is usually handled separately within the organization. personal concern for maintenance standards
But he should keep aware of the supply situation and
must do his best to make sure that equipment is • using his site visits to observe how operators treat
systematically maintained in good working order. their equipment and discouraging its mishandling or
Shortage of working equipment or vehicles is almost misuse.
always a major symptom of inefficiency in maintenance
organizations. Materials
8.14 The essential point is to establish a daily routine 8.15 The procedures for estimating quantities of
of equipment maintenance. This can be done through the materials needed in maintenance operations are relatively
following measures carried out by the maintenance straightforward. Where the extent of the work can be
engineer: defined precisely - for example, in the case of surface
dressing or regravelling - quantities are taken off in
• ensuring that operators appreciate the purpose and accordance with standard engineering practice. For other
benefits of preventative maintenance, understand the activities where requirements are less easy to define
maintenance needs of the equipment they use, and such as edge repairs to bituminous surfaces, patching
are trained to look after this equipment on a daily pot-holes and repairing defects in culverts -quantities are
basis gauged on the basis of inspection results, again following
standard practice; but these estimates will of necessity be
• arranging for a regular supply of oil and grease, etc, less precise. The quantities ordered should include an
to be made available; this supply will need secure allowance for any emergency work that may be needed,
storage facilities under the supervision of a storeman for example in repairing storm damage to culverts or
vehicle damage to bridge parapets.
19
8.16 In planning his programme of work, the
maintenance engineer should take account of the delivery
periods for materials. If deliveries are likely to be
uncertain, it will be advisable to stockpile basic materials
such as aggregates cement and bitumen. These will need
to be stored securely and kept in good condition.
Resource allocation
20
Fig.8.1 Example of resource requirements form
21
9. IDENTIFICATION OF Periodic work
PRIORITIES • Regravelling of unpaved roads
9.1 If he is fortunate, the maintenance engineer may • Surface dressing of paved roads
find that he has all the resources he needs to carry out the
full programme of work. But it is more likely that resources Periodic work can be treated as a series of distinct
will be limited and he will have to decide the most effective projects that have to compete for the resources
way of applying them. This means working out an order or available and can be undertaken separately,
priority, with the operations that have the strongest claim deferred or brought forward as required.
on resources placed at the head of the list and those that
have least claim placed at the end. This section of the Note Other routine work
explains a method that will enable the maintenance
engineer to identify priorities objectively and consistently. • Filling on shoulders and slopes
• Repair of drainage structures 9.5 The remainder of the network should be classified
by the level of traffic on each road. This level is usually
This work always deserves high priority because expressed in terms of the estimated annual average daily
neglected drainage can rapidly lead to deterioration traffic (ADT); i.e. the total traffic in both directions
of the whole road. It should not be assumed that all during the year. divided by 365. The estimate can only
drainage work must take precedence over all be reliable if it is derived from actual traffic counts. This
recurrent work. The key point is that repairing means that traffic information is needed about every part
surface defects caused by poor drainage will be a of the network, including minor and unpaved roads. For
waste of time and effort unless the drainage is put the purposes of maintenance planning, a simple traffic
right first. count procedure as outlined in Appendix C will be
adequate; but the maintenance engineer should note that
Recurrent work counts lasting for less than 7 consecutive days are liable
to very large errors, particularly where traffic levels are
low.
• Dragging, brushing, grading or filling of unpaved
roads
22
TABLE 9.1
Priority matrix
ROADS CLASSIFIED BY
CATEGORY OF IMPORTANCE 9.8 Fig 9.1 is a matrix which shows how the
classification of maintenance activities should be related
Category ADT Surface Type to the classification of roads. Maintenance activities are
numbered from 1 (highest priority - urgent maintenance
1 (Strategic roads) Paved on strategic roads) to 48 (lowest priority -special works
2 Greater than 1000 Paved on unpaved roads with very low levels of traffic). The
3 500 – 1000 Paved matrix is designed to ensure that every road in the
network receives at least the minimum maintenance
4 200 – 500 Paved needed to keep it operational, while at the same time
5 Greater than 200 Unpaved focusing recurrent and periodic maintenance on the
6 Less than 200 Paved economically important roads with high traffic levels. As
noted in para 9.4, strategically important roads have
7 50 – 200 Unpaved absolute priority for resources, even where special works
8 Less than 50 Unpaved are concerned.
23
1O. WORK SCHEDULING AND
periodic maintenance are not interchangeable. Some EXECUTION
flexibility and adjustment of priorities may be necessary
to make sure that all the funds available for a particular
category of work are used. Schedules
9.13 It is often useful to have routine and recurrent 10.1 The maintenance engineer's next task is to
maintenance work organized at a sub-district level. In prepare detailed work schedules for the teams under his
this case each sub-district should be given a programme direction. The schedules are essentially sets of
of work based on the priorities defined in the master list. instructions which tell the foremen or technicians
Periodic maintenance work organized directly at district supervising an activity how much work is to be done
level should have its priorities assessed in the same way. each day, the time it should take and the labour,
In this situation, the maintenance engineer should give equipment and materials to be used. Schedules should
careful thought to the location and organization of his cover periods of not less than 2 weeks and not more than
maintenance crews so as to check whether existing 4 weeks: shorter periods would probably not warrant the
arrangements meet the requirements of the district as effort of preparing a schedule, while longer periods
efficiently as possible. He should recommend to would risk losing a sense of urgency.
headquarters any necessary changes.
10.2 In drawing up schedules, the maintenance
engineer should first discuss the work with the foremen
and supervisors who will have to put the schedules into
practice. It is essential for these personnel to feel
confident that the 'production target' the output of work
required each day is pitched at a realistic level. One
useful idea is to ask the foremen to draft their own
schedules: the maintenance engineer can use these as a
basis for discussion and the results can be helpful in
developing the work schedules that are issued to teams.
Worksheets
24
25
Fig.10.1 Example of worksheet
11. MONITORING REFERENCES
11.1 Monitoring serves two main purposes: it enables TRANSPORT AND ROAD RESEARCH
the maintenance engineer to check the quality and LABORATORY, 1978. A guide to the measurement of
effectiveness of the work being done, as noted in para axle loads in developing countries using a portable
4.1; and it provides data that can be used to improve the weighbridge. Road Note 40. London: HMSO, available
management and performance of future maintenance from TRRL Overseas Unit.
operations. There are two aspects to the task:
TRRL OVERSEAS UNIT, 1985. Maintenance
• site inspections techniques for District Engineers. Overseas Road Note
2. Crowthorne: Transport and Road Research
• desk review. Laboratory, 2nd edition, available from TRRL
Overseas Unit.
Site inspections
Desk review
26
APPENDIX A TABLE A1
27
Notes for inspectors A.1.13 Once on site. the inspector must establish the
start of the length to be inspected. From this point, he
and his team should methodically record defects or
A.1.9 The maintenance engineer should prepare notes
features. The start point should be a kilometre post or a
for inspectors which include further guidance on the
structure, if possible.
recommendations given in this Note and rules and
interpretations suited to local conditions. The notes
should include any additional detail necessary for Accuracy
assessing and recording individual items, together with a
list of standard criteria. A.1.14 Correct, accurate and legible recording in the
field is essential to avoid unnecessary effort in checking
A.1.10 Clerical work should be done by the inspectors. errors later. It is important to record the correct chainages
This will give them closer involvement in the for the start and end of defective areas, in the case of
management process, and is likely to result in higher condition measurement surveys, or changes in
standards of inspection and recording. characteristics in the case of an inventory. Chainages
should be recorded to the nearest metre, and widths to the
Duties of team members nearest 0.1 metre. For condition measurement surveys, it
is also useful at this time to paint the outline of areas of
paved roads that need patching, since this will make
A.1.Il them easier to find when the work is carried out later.
• Team leader
He has the overall responsibility for the work of the
team. He should carry out a visual inspection of the A.2 CONDITION MEASUREMENT
carriageway, shoulders and drainage, assess
structural condition and record all information on
the relevant forms. With a team of two, the leader General considerations
usually pushes a measuring wheel
A.2.1 In order to establish maintenance needs, it is
• Assistant necessary to compare the measured condition of the road
When inspecting procedures are first introduced, the with maintenance intervention levels such as those set
team leader will make his assessment on the basis of out in Tables 7.1-7.3. These levels may need to be
a visual inspection. As the maintenance system is modified by the maintenance engineer to suit local
developed, assessments will be based on the conditions as noted in para 7.8.
detailed measurement of defects. An assistant will
be needed to carry out these measurements. A.2.2 When the maintenance system is introduced, it
On roads where traffic is heavy, additional will probably only be possible for the inspector to assess
assistants may be needed, in particular to make the severity of defects by observation. As the system is
rutting measurements on the far side of the developed, physical measurement of defects should be
carriageway, to control traffic and generally to assist gradually introduced into the inspection procedure; but
in measurement procedures the quality of visual assessment can be improved by
having first-hand knowledge of the physical
measurement techniques.
• Driver
When a vehicle is provided, a driver is necessary to A.2.3 Most defects require either the area or the
enable the inspector to concentrate on the job in length of deterioration to be measured. The area or length
hand. The driver should be responsible for erecting of deterioration must first be identified and classified
and moving advance warning signs where no other using the method outlined in the following paragraphs.
person is provided for this task. He can also assist in As each sub-section is approximately 100-200 metres
traffic control or in making measurements. Where long, it is probable that several occurrences of the same
possible he should, as a safety measure, park his type of deterioration will be found within the sub-
vehicle on the road between the on-coming traffic section. These should be added together to give the total
and the inspection team and switch on his hazard extent for each sub-section.
warning lights.
Side drains and turnouts (all roads)
Order of work
A.2.4 The level of the water table beneath the road
A.1.12 Before leaving the depot, the inspector should has a major influence on the strength of the subgrade. To
personally check that all of the equipment needed has keep water out of the pavement structure, side drains
been collected together and loaded in the vehicle. He should
should ensure that the vehicle has sufficient fuel or that
arrangements have been made to refuel on the way.
28
be maintained at least one metre below the road surface. Cracking (paved roads)
The depth of side drains should be measured at
approximately 25 metre intervals using a straightedge A.2.10 A crack can have the appearance of a line in
and measuring tape as indicated in Fig. Al. the surfacing (particularly for asphalt) without two
clearly defined edges. This condition indicates an early
Loss of material (gravel roads) stage in the deterioration process, when the surfacing still
remains waterproof. For the purpose of condition
A.2.5 An estimate can be made of the thickness of measurement surveys, it is more practical to define a
gravel on the road by examining pot-holes or by digging crack as being visible from standing height. Such a crack
a small hole in the road surface until subgrade is reached would, on close inspection, have two clearly defined
and probing the depth with a measuring tape. Material edges at the surface. It should be remembered that this
should then be replaced and compacted with a hand condition is much further along the deterioration path
tamper or punner. than that described above. Water may be penetrating into
the pavement through cracks of this severity whether the
A.2.6 Ideally, thicknesses should be measured road is surfaced in asphalt or surface dressing.
immediately after grading. But in view of the difficulty
of timing such measurements and the need to carry out A.2.ll In bright sunlight, it is often very difficult to
surveys on a routine basis, the following approach may see even quite wide cracks. A method of shading the area
be more appropriate. The survey team should take under observation should be used. The width of cracks in
measurements on each sub-section or at 200 metre asphalt can change markedly between early morning and
intervals along the road. At each survey point, the team mid-day owing to thermal expansion. In some cases,
should identify any obvious ruts and should dig two cracks can close completely and not be seen at all.
holes: one in the rut and the other at the peak between Surveys are best carried out in the morning or during
ruts. The gravel thickness should be recorded as the cloudy weather conditions, particularly when the road is
average of the two measurements, as shown in Fig. A2. drying out after rain.
29
Fig.A1 Measuring depth of side drains with straight edge and measuring tape
30
Fig.A3 Deformation gauge (straight-edge and calibrated wedge)
31
APPENDIX B
MANAGEMENT OF GRADING FOR
UNPAVED ROADS
B.1 DETERMINING OPTIMUM GRADING
FREQUENCIES
Overseas Centre
Transport Research Laboratory
Crowthorne
Berkshire RG45 6AU
United Kingdom.
32
monitored for a period of at least one year, and an estimate of roughness to be obtained without complex
measurements should be taken of roughness and rut depth calculation (Cundill 1991). Drawings of the MERLIN are
immediately before and after each scheduled maintenance available from the Overseas Centre, TRL.
grading. Traffic levels on these roads should also be
monitored. REFERENCES
B.2.2 Modifications to the grading frequencies can then CUNDILL, M A, (1991). The MERLIN low-cost road
be made to ensure that the mean values of roughness and roughness measuring machine. TRRL Research Report RR
rut depth measured in the field agree with those required by 301. Crowthorne: Transport Research Laboratory, available
the analysis using the investment model. This ensures that from TRL Overseas Centre.
the sum of road maintenance and vehicle operating cost is
minimised. In this way, by the end of the year, grading SAYERS, M W et a l, 1986. Guidelines for conducting and
frequencies will have been obtained that are suitable for calibrating road roughness measurements. World Bank
local conditions and are close to the optimum. A sample of Technical Paper 46. Washington DC: International Bank
the road network should have its performance monitored on for Reconstruction and Development.
a continuing basis to make sure that the grading frequencies
effectively keep roads in a condition that is close to the
optimum. Adjustments can then be made to the grading
frequencies as necessary.
33
The ADT is taken as the weighted mean of the seasonal
APPENDIX C flows, calculated thus:
ADT = (8/12 x 28) + (4/12 x 54) = 37 vehicles
TRAFFIC COUNTING C.3 MANUAL COUNTS
C.1 FREQUENCY AND DURATION OF C.3.1 The equipment required for manual counting
COUNTS comprises a supply of pre-printed forms, pencils and
clip-boards. A shelter from sun or rain may be required.
C.1.1 The purpose of the traffic counts is to classify At low traffic volumes, the work is not demanding and
roads in broad categories for maintenance planning the main problem is likely to be ensuring that the
purposes. A high level of accuracy is not required. On enumerators stay on the job. Unscheduled visits by the
roads carrying more than about 1000 vehicles per day, a engineer or a senior supervisor may be necessary to
one-day manual count will usually be sufficient to secure discipline and attention to the work. If the
provide an estimate of ADT for the maintenance proportion of heavy vehicles in the traffic flows is
classification. On roads with fewer vehicles, account expected to be high, classified counts may be necessary.
should be taken of daily and seasonal variations:
C.4. AUTOMATIC COUNTERS
• the effects of local market days, which may
account for a high proportion of annual traffic on C.4.1 It is now possible to obtain cheap and reliable
low-volume roads, may be allowed for by making automatic traffic counters recording total numbers of axle
two counts, one on a market day and one on a pairs which can be used to supplement manual counts or
non-market day to count for periods of more than one day on low volume
roads. The equipment normally consist of a small rubber
• a count should be carried out during each main tube fixed across the road and attached to a pneumatic
climatic and/or agricultural season so that the counter. When vehicles drive over the tube. it is
effect of seasonal rainfall and of variations in compressed and a pulse of air triggers the counter. The
agricultural activity (especially during and just instrument records one count for the passage of two
after harvest-time, when traffic flows usually axles. These traffic counters need careful adjustment to
show a marked increase) are taken into account. ensure that bicycles, motorcycles and pedestrians are not
Counts extending over 16 hours (from 6 am to 10 counted and that heavy or fast vehicles are not 'double
pm) will usually be adequate, but, in some counted'. Provided that they are checked regularly and
countries where traffic is heavy at night counts the rubber tube replaced when it is damaged, their use is
should extend over 24 hours. recommended.
C.2 ESTIMATION OF ADT FROM C.4.2 Buried loop detectors can be used instead of
COUNTS pneumatic tubes and are generally more reliable.
However, their permanent installation will not normally
be justified solely for traffic counts for maintenance
C.2.1 The estimation of ADT must take account of the
purposes.
factors noted above. The following example indicates the
recommended procedure:
C.4.3 The maintenance engineer should select one of
his staff trained in the installation and use of counters to
Example be responsible for their checking and maintenance. He
should also arrange for the daily inspection of the counter
C.2.2 Counts were taken near a village which has a and recording of the counter reading. In some locations,
market every eight days. The wet season lasts for about automatic counters may be subject to theft or damage.
four months and the dry season eight months. The counters themselves can be protected by lockable
cabinets attached to solid objects, but the tubes cannot be
1. Two 16-hour counts were taken at the end of the dry effectively protected from deliberate interference. When
season (low level of agricultural activity) this is experienced and regular inspection is not sufficient
Count on market day = 73 vehicles to prevent it, automatic counters of this type should not
Count on non-market day = 21 vehicles be used.
2. Two 16-hour counts were taken at the end of the wet C.5 MOVING OBSERVER COUNTS
season (harvest time)
Count on market day = 94 vehicles
C.5.1 Moving observer counts can usually be carried
Count on non-market day = 48 vehicles
out by the maintenance engineer or supervisor in the
course of personal inspections, using a hand-tally to
C.2.3 For this example of an eight day traffic cycle, the
record the
average daily traffic is calculated for each season as
follows:
Average daily traffic (dry season)
Tdry = (1/8 x 73) + (7/8 x 21) = 28 vehicles
34
number of vehicles. The flow can be estimated from the
expression: -
(x + y)
q =
t
x
q = _______
35
APPENDIX D
36
37
38
39
40
41
APPENDIX E
ILLUSTRATIONS OF TYPICAL
DEFECTS
42
Debris on road.
43
Side drain silted and too shallow.
44
Scoured side drain
46
Structural damage of bridge superstructure.
48
Missing road sign.
50
High vegetation growth and standing water.
53
Stripping of aggregate from paved road.
54
Pot-hole on paved road.
55
Edge step on paved road.
56
Wheeltrack rutting and cracking on paved road.