REV.

_00 Page 1 of 4

PROJECT: WATER TANK & PUMP ROOM IN PROPOSED GREENFEILD PLANT AT


HABIRBARI, BHALUKA
Bill of Quantity of Civil Work : Date: 25/Nov/20
Item. No. Description Quantity Unit Rate in BDT Amount in BDT Remarks
1.0 Price of the land 750.00 SQM 3000.00 2250000.00
2.0 Drawings and designs 1.00 LS 500000.00 500000.00
3.0 Excavation Works 4092.00 CUM 353.00 1444476.00
4.0 Sand Filling Works 4092.00 CUM 706.00 2888952.00
5.0 Granular Sub base (GSB) 223.00 CUM 7555.00 1684765.00
6.0 Concrete for PCC Works 50.00 CUM 7850.00 392500.00
7.0 Concrete RCC Works 1441.00 CUM 13500.00 19453500.00
8.0 Rein. For RCC Works 36.03 MT 95000.00 3422375.00
9.0 Formwork 2077.00 SQM 860.00 1786220.00
10.0 Plastering Works 1205.00 SQM 430.00 518150.00
11.0 Water proofing inside tank 1088.00 SQM 1237.00 1345856.00
12.0 Plumbing Works 1.00 LS 2500000.00 2500000.00
13.0 Electrical Works 1.00 LS 750000.00 750000.00
14.0 Temporary Works 1.00 LS 450000.00 450000.00
Total = 39386794.00

COST OF DISMANTLING OLD TANK


Item. No. Description Quantity Unit Rate in BDT Amount in BDT Remarks
1.0 Concrete for PCC Works 50.00 CUM 7060.00 353,000.00
2.0 Concrete RCC Works 1441.00 CUM 7060.00 10,173,460.00
3.0 Excavation Works 4092.00 CUM 353.00 1,444,476.00
4.0 Sand Filling Works 4092.00 CUM 706.00 2,888,952.00
Total = 14,859,888.00
REV._00 Page 2 of 4
REV._00 Page 3 of 4

PROJECT: ROADS IN PROPOSED GREENFEILD PLANT AT HABIRBARI, BHALUKA

Bill of Quantity of Civil Work : Date: 25/Nov/20


Item. No. Description Quantity Unit Rate in BDT Amount in BDT Remarks
1.0 Demolition works 1,625.25 CUM 5295.00 8605698.75
Excavation 3,546.00 CUM 353.00 1251738.00
2.0 Compaction of subgrade 3,546.00 SQM 530.00 1879380.00
Compaction of granular
3.0 1182.00 CUM 7550.00 8924100.00
Sub base
4.0 PCC casting 591.00 CUM 9500.00 5614500.00
5.0 Rebar 31618.50 KG 95.00 3003757.50
6.0 Concreting 1034.25 CUM 12500.00 12928125.00
7.0 Saw cut joint 4000.00 RM 150.00 600000.00
8.0 Constrruction Joint 900.00 RM 450.00 405000.00
9.0 Formwork 735.36 SQM 460.00 338266.75
Total = 43550566.00
REV._00 Page 4 of 4

PROJECT: SEWAGE LINE PROPOSED GREENFEILD PLANT AT HABIRBARI, BHALUKA

Bill of Quantity of Civil Work : Date: 25/Nov/20


Item. No. Description Quantity Unit Rate in BDT Amount in BDT Remarks
1.0 Design and drawings 1.00 LS 350000 350000.00
2.0 Excavation Works and trench 720.00 CUM 353.00 254160.00
making
3.0 Compaction of the under 216.00 SQM 250.00 54000.00
lying soil
4.0 Bedding concrete 40.00 cum 10500.00 420000.00
5.0 Construction of the pit 10.00 Nos 153000.00 1530000.00
6.0 180.00 RM 1150.00 207000.00
Installaiton of the pipe line

7.0 Connection between old 1.00 LS 250000.00 250000.00


line and new line
Total = 3065160.00