PERT, CPM Toilets 90 Days
PERT, CPM Toilets 90 Days
CRITICAL PATH II
86 DAYS
VI
E 21 DAYS
V
D
21 DAYS
LEGEND:
I - MOBILIZATION
II - HEALTH AND SAFETY PROVISION
III - REMOVAL AND DISMANTLING WORKS
IV - PLUMBING WORKS
V - MECHANICAL WORKS
VI - ELECTRICAL WORKS
VII - ARCHITECTURAL WORKS LOURDES P. AUSTRIA
VIII - DEMOBILIZATION Authorized Representative