Professional Documents
Culture Documents
Remaining Works Schedule at Second Floor New Building
Remaining Works Schedule at Second Floor New Building
Remaining Works Schedule at Second Floor New Building
Duration/w
No. Description/Scope of Works Unit Qty. Unit Cost Total Cost Weighted %
eek
1 Completion of Ceiling at Living & Kitchen sq. m 100 700.00 70,000.00 11.2 2
625,000.00 100
Accomplishment as
Start End P/A
of 5th week
P
11.2 1 2
A
P
6 2 6
A
P
0 6 7
A
P
0 7 8
A
P
0 7 10
A
P
8 3 5
A
P
3 4 5
A
P
8 3 8
A
P
3 6 8
A
39.2
/
Remaining Works Schedule at Second Floor New Building
2 Painting Works at Master BR, Living & Kitchen and Portion at Front sq. m 500
1 2 3 4 5 6 7
X X
Y Y
X X X X X
Y Y Y Y Y
X X
Y Y
X
Y
X
Y
X X X
Y Y Y
X X
Y Y
X X X X X
Y Y Y Y Y
X X
Y Y
8 9 10
X
Y
X X X
Y Y Y
X
Y
X
Y
Remaining Works Schedule at Second Floor New Building
No. Description/Scope of Works Unit Qty.
3rd week 4th week 5th week 6th week 7th week 8th week 9th week
6.75 9.15 9.15 19.68 24.00 10.00 4.00
20.03 29.17 38.32 58.00 82.00 92.00 96.00
10th week
4.00
100.00
25,000.00
625,000.00
25,250.00
645,561.08
Weeks
6 7 8 9 10
2.08
2.08
14 14
14 14
2.4 2.4
2.4 2.4
4 4 4 4
4 4 4 4
2 2 2
2 2 2
1.6 1.6 1.6
1.6 1.6 1.6
Remaining Works Schedule at Second Floor New Building
No. Description/Scope of Works Unit Qty. Unit Cost Total Cost Weighted %
1 Completion of Ceiling at Living & Kitchen sq. m 100 700.00 70,000.00 11.2
625,000.00 100
0 0 0 0 0 0 0 0 0
week 3rd week 4th week 5th week 6th week 7th week 8th week 9th week 10th week