1. Author GEOVANNI HUERTA


2. SOW Section # TBD
3. SOW Section TBD
Owner
4. Approved 17-NOV-20
By/Date
5. Last Revision TBD
By/Date
6. Next Review TBD
Date
7. EAM – Computerized Maintenance Management System
Acronyms/Definitio MHE – Material Handling Equipment
ns CP- Control Panel
PLC – Programmable Logic Controller
PIT - Powered Industrial Truck
HVAC – Heating Ventilation and Air Conditioning
UPS - Uninterruptable Power Supply
TT – Trouble Ticket http://tt.amazon.com
COE – Chain of Events (incident summary)
E-Stop – Emergency Stop button
FC – Fulfillment Center
SC - Sortation Center
OE – JLL Operations Engineer
FM – JLL Facility Manager
IR – Infrared scanner
PM – Preventative Maintenance
PdM – Predictive Maintenance (ie: IR scan, ultrasonic, etc)
AHJ – Authority Having Jurisdiction (ie: fire marshall, OSHA, etc)
MPS – Maintenance Planner Scheduler

8. Objective Guarantee the functioning of the Equipment in the Delivery Center

9. Scope Detect possible failures in the delivery center equipment.

10. Responsibilities Validate and guarantee the functioning of the teams in the delivery
centers.

11. Records to be Bring the equipment to zero downtime due to maintenance failures.
Maintained
Process/Procedure 0.- Make known to Amazon leader of inspections area

1.- Daily visual inspection of all stationary conveyance and all flex
conveyance.

2.- Ensure all safety guards are in place.

3.- Inspect all electrical conduit and j-boxes, no visible damage or


exposed wires.

4.- Inspect communication cable(s) and plugs for any exposed


wires, loose connections, or damage.

5.- Inspect power cable(s) and plugs for any exposed wires, loose
connections, or damage.

6.- Ensure that all control box covers are in place and secure.
Replace or secure as needed.

7.- Where applicable inspect O-bands are present on each roller.

8.- Where applicable inspect transport belts are in good condition


no visible rips or holes, lacing and pin is intact, tracks in middle of
bed.

9.- Inspect debris catch pan(s), if more than 50% full, create a PM
Follow up WO to clean out debris.

10.-Where applicable inspect motor/gearbox(s) for signs of leaks.

11.- Ensure that conveyor and/or system start/stops properly.

12.- Ensure proper operation: Product travels with no dead spots


and no jams.