Date 18-Apr-18

Voyager Steady State


Page : 1 / 3
Estimation Agreement
CM Ref – CHG0033624

CHANGE REQUEST ESTIMATION AGREEMENT

Agreement Between Telenor Global Shared Services AS & Tieto Norway AS


Ordered By Taha Bin Zahid Proposed By Priyanka Pokharkar
CM Reference CHG0033624 JIRA Reference VATL-35435
Project Team (s) ATLAS AM Change Type Enhancement
CM Title Addition of 3 columns in existing report pa_sb_paglauu_11i
Call Off Reviewer Mahajan Saurabh, Kamal Malkani
Proposed Release Jun-18 Call off Version 1.0
Proposed Estimates 21 Hours
Proposal Date Click here to enter a Valid Till Click here to enter a date.May 17,
date.April 18, 2018 2018
.Description of Work

Requirement:
The existing report pa_sb_paglauu_11i is fetching right columns however there is a business need to add 3 new columns
in it.
• Update by TID
• Update by Name (description)
• Update Date.
Proposed Solution:
Modification in view attached to discoverer report pa_sb_paglauu_11i.
4 worksheets attached to report have to be modified to display above 3 new columns.
Estimation and Delivery

• Estimation Breakup for the Proposed Solution is as follows:

Element Description Estimated effort Hourly rate <number Cost <NOK>


of hours/rate>

Analysis Analysis
2 214 428

Design
0 0 0
Design

Code development, installation script


8 214 1712
Development

Testing on SIT
4 214 856
Testing
Date 18-Apr-18

Voyager Steady State


Page : 2 / 3
Estimation Agreement
CM Ref – CHG0033624

UAT support
1 214 214
Support

Standard change documentation


4 214 856
Documentation

Communication with GSS


1 291 291
Communication

Production Change verification 1 214 214


Verification

Total <n/a> 21 <n/a> 4571

The estimate cost is indicative and for internal reference and purposes only. Current contractual KPI and estimate
precision is linked only to estimated hours.

• Estimated Delivery Timelines for the Proposed Solution is as follows:

Ready for UAT Deployment Monday, June 11, 2018


Tentative Production Go Live Monday, June 25, 2018
Estimated Release Jun-18
IMPACTS

• Impact in future maintenance – NA.


• Impact on Voyager Agreement – NA

DELIVERABLES

Delivery Documentation NA

AGREED CONDITIONS

Services Required • ATLAS


From Resources

UAT/RT Testing • User Acceptance Test will be performed by USER (not included in
estimate).

Acceptance Criteria • Change is considered as ACCEPTED when appropriate change is


deployed in Production
Date 18-Apr-18

Voyager Steady State


Page : 3 / 3
Estimation Agreement
CM Ref – CHG0033624

Other Resources / • NA
Parties Involved
• NA
Cost and Payment
Conditions

Special Conditions
from Contractor

APPROVAL AUTHORIZATION

CUSTOMER Name:
BUDGET Title:
APPROVER Date:
Signature:

TIETO Name:
DELIVERY Title:
MANAGER Date:
Signature: