Pile Cap Check For PE7PTC-15,30 15-07-20 (Shear Enhancement)
Pile Cap Check For PE7PTC-15,30 15-07-20 (Shear Enhancement)
Materials :
Concrete, f ck = 35 N/mm2
2
Concrete, f cu = 40 N/mm
2
Reinforcement, f yk = 460 N/mm
Unit weight of concrete = 24 kN/m3
Pile Capacity = 1950 kN
Assumed : Main Bar = 32 mm
Secondary Bar = 16 mm
Pile Embedded, e = 75 mm
C nominal = 75 mm
Pier Column = 1.19 x 1.1 m
Pile Size = 350 mm H-section Steel Pile
Analysis :
Ultimate load per pile , F (y-direction) = P/n + Mx/I
= 2102.00 kN
Ultimate load per pile , F (x-direction) = P/n + Mx/I
= 2010.00 kN
Maximum moment at column face, (Moment taken to the face column from pile reaction)
Myy = 21.02 kNm
Mxx = 3236.10 kNm
Project: R8201- Structural Assessment of Pile Cap Date : 16/7/2020
member : Type: Pile Cap - 4 Pile
Longitudinal Bar :
Bending Moment, M = 3236.10 kNm
K = M/bd2 fcu
= 0.0022 < K' = 0.156
z = d[0.5 + 0.25 − K/0.9
= 1032 ≤ 0.95d = 983
Use 0.95d
As = M/0.95fy z
= 7534 mm2
As = 7534 mm2
Asmax = 0.04Ac
= 157500 mm2
Asmax = 0.04Ac
= 85500 mm2
Project: R8201- Structural Assessment of Pile Cap Date : 16/7/2020
member : Type: Pile Cap - 4 Pile
𝑏𝑣 (𝑆𝑣)
Clause 3.7.7.4 ii. Punching Shear : Critical at perimeter 1.5d from column face
BS8110 1997 Maximum shear resistance, 𝑉
Clause 3.11.4.5 v,max = 𝑢𝑜 𝑑
u( perimeter of column face) = 4580 mm
d,(average d) = 1018 mm
v,c = 0.5305 N/mm2
v,max = 1.664 N/mm2 > 0.531
Shear reinforcement is required.
and check against provided shear reinforcement
Where it is desired to check perimeter closer to the loaded area than 1.5d, vc may be increase by a factor 1.5d/av
where av is the distance from face of column to critical section
Clause 3.7.7.5 For cases where v ≤ 1.6vc shear For cases where 1.6vc ≤v≤2vc shear
BS8110 1997 reinforcement should be provided in reinforcement should be provided in
𝑣−𝑣𝑐 𝑢𝑑 5(0.7𝑣−𝑣𝑐 )𝑢𝑑
𝐴𝑠𝑣 sin 𝛼 ≥ 𝐴𝑠𝑣 sin 𝛼 ≥
0.95𝑓𝑦𝑣 0.95𝑓𝑦𝑣
where
𝐴𝑠𝑣 = is the total area of shear reinforcement (in mm2)
α= is the angle between the shear reinforcement and the plane of the slab= 90
OK, the provided shear link enough for cater punching shear
Cracking :
h = 1125 mm
Assume steel stress under quasi permanent loading ,
fyk As,req
= 0.55( )( )
1.15 As,prov
= 532 N/mm2
Table 7.3 N For design crack width = 0.3 mm
EN 1992-1-1 Maximum allowable bar spacing = 250 mm
Maximum bar spacing 1 provided = 150 mm < 250 OK
Maximum bar spacing 2 provided = 150 mm < 250 OK