The document lists 26 items including materials and work types for a construction project. It includes excavation materials, concrete, formwork, reinforcement materials, backfill materials, and labor categories. For each item it provides an identification number, name, type, material label or group, maximum units, standard and overtime rates, and how costs accrue. The document appears to be a cost breakdown or schedule of values for a construction project.
The document lists 26 items including materials and work types for a construction project. It includes excavation materials, concrete, formwork, reinforcement materials, backfill materials, and labor categories. For each item it provides an identification number, name, type, material label or group, maximum units, standard and overtime rates, and how costs accrue. The document appears to be a cost breakdown or schedule of values for a construction project.
The document lists 26 items including materials and work types for a construction project. It includes excavation materials, concrete, formwork, reinforcement materials, backfill materials, and labor categories. For each item it provides an identification number, name, type, material label or group, maximum units, standard and overtime rates, and how costs accrue. The document appears to be a cost breakdown or schedule of values for a construction project.
ID Resource Name Type Material Label Initials Group Max. Units Std. Rate Ovt.
Rate Cost/Use Accrue At
1 Excavation Top Soil Material E RM9.80 RM0.00 Prorated
2 Excavation Trench Material E RM20.50 RM0.00 Prorated
3 Concrete Material C RM275.00 RM0.00 Prorated 4 Formwork Beam Material F RM51.80 RM0.00 Prorated 5 Formwork Stump Material F RM42.20 RM0.00 Prorated 6 Formwork Footing Material F RM42.20 RM0.00 Prorated 7 Formwork Column Material F RM47.10 RM0.00 Prorated 8 Formwork Slab Material F RM47.00 RM0.00 Prorated 9 R6 beam Material R RM4.30 RM0.00 Prorated 10 R6 column Material R RM4.30 RM0.00 Prorated 11 R6 stump Material R RM4.30 RM0.00 Prorated 12 T10 beam Material T RM4.00 RM0.00 Prorated 13 T12 beam Material T RM4.00 RM0.00 Prorated 14 T10 column Material T RM4.00 RM0.00 Prorated 15 T10 stump Material T RM4.00 RM0.00 Prorated 16 T10 footing Material T RM4.00 RM0.00 Prorated 17 BRC A7 Material B RM102.33 RM0.00 Prorated 18 Sand Material S RM41.00 RM0.00 Prorated 19 Crusher Run Material C RM34.00 RM0.00 Prorated 20 General Labour Work G 8 RM60.00/day RM0.00/hr RM0.00 Prorated 21 Skilled Labour Work S 6 RM95.00/day RM0.00/hr RM0.00 Prorated 22 Semi-Skilled Labour Work S 6 RM75.00/day RM0.00/hr RM0.00 Prorated
23 Excavator Work E 2RM1,000.00/day RM0.00/hr RM0.00 Prorated
24 Concrete Mixer Work C 2 RM420.00/mon RM0.00/hr RM0.00 Prorated 25 Vibrator Material V RM270.00 RM0.00 Prorated 26 Backhoe Work B 1 RM550.00/day RM0.00/hr RM0.00 Prorated