Department: Engineering (Planning)

Project: Proposed Alturas Ricemill- Loading/Utility Area


Location: Lumangog, Ubay, Bohol
Client: Alturas Group of Companies
Date: 26-Nov-20

EXECUTIVE SUMMARY/REV 1.0

Contract Milestone
Remarks Remarks
Planned Start Date 24-Mar-20 Elapsed Days: 247
Planned Finish Date 24-Mar-21 Remaining Days: 118
Revised Completion Date Calendar Days: 365
Scope % wt Planned % Planned Value Actual % Actual Value

PRELIMINARIES 9.14% 46.06% 4.21% 50.32% 4.60%

EARTHWORKS (Excavation, backfilling) 5.24% 64.15% 3.36% 63.15% 3.31%

COLUMN FOOTINGS 5.30% 97.96% 5.19% 75.00% 3.97%

COLUMN PEDESTAL 12.48% 97.80% 12.21% 68.00% 8.49%

WALL FOOTING AND CHB WALLS 28.68% 13.64% 3.91% 26.45% 7.59%

STRUCTURAL WORKS & ARCHITECTURAL WORKS 17.02% 66.24% 11.27% 54.31% 9.24%

SLAB ON GRADE 22.13% 3.33% 0.74% 58.19% 12.88%

Total 100.00% 40.89% 50.08%

Issues and Reminders Variance: 9.19%

1. Slippage at 2nd week of December

Prepared by: Checked by:

Rogemie Cherrehan Tano Neil E. Sabal


MCBI - Planner MCBI - Project in Charge

Approved by: Noted by:

Urbano Curit Mario Tancinco


MCBI - Project Manager MCBI - Operations Manager