Ricemill Executive Summary (Utility Area) (REV 1.0 - Nov 26, 2020) PDF
Ricemill Executive Summary (Utility Area) (REV 1.0 - Nov 26, 2020) PDF
Ricemill Executive Summary (Utility Area) (REV 1.0 - Nov 26, 2020) PDF
Contract Milestone
Remarks Remarks
Planned Start Date 24-Mar-20 Elapsed Days: 247
Planned Finish Date 24-Mar-21 Remaining Days: 118
Revised Completion Date Calendar Days: 365
Scope % wt Planned % Planned Value Actual % Actual Value
WALL FOOTING AND CHB WALLS 28.68% 13.64% 3.91% 26.45% 7.59%
STRUCTURAL WORKS & ARCHITECTURAL WORKS 17.02% 66.24% 11.27% 54.31% 9.24%