Ricemill Mezzanine Area S-Curve (Rev 1.2-Nov 26, 2020)
Ricemill Mezzanine Area S-Curve (Rev 1.2-Nov 26, 2020)
1.3 Surveying and Layout for project duration 360,000.00 0.42% IN PROGRESS
2.0 SUBMITTALS 0.00% IN PROGRESS
93.14%
2.1 Construction Schedule 72,000.00 0.08% IN PROGRESS
2.2 Progress Report 72,000.00 0.08% IN PROGRESS 90.00%
2.3 Shop Drawings, Product Data & Samples 300,000.00 0.35% IN PROGRESS
88.55%
3.0 QUALITY CONTROL 0.00% IN PROGRESS
3.1 Testing Laboratory Services / FDT / Dye Penetrant 250,000.00 0.29% IN PROGRESS
PLANNED
6.0 SITE MANAGEMENT 500,000.00 0.59% IN PROGRESS
7.0 COMMUNICATION AND TRANSPORTATION 300,000.00 0.35% IN PROGRESS
74.56%
II. CONSTRUCTION PHASE
3.2 Fabrication & Installation of Rebars, Including Consumables 4,011,934.90 4.70% 50.00% 51.00%
6.2 Supply & Installation of Moisture Barrier Polyethelene Sheet 414,017.94 0.48%
8.1 Fabrication & Installation of Rebars, Including Consumables 601,128.00 0.70% 10.00%
8.2 Concrete Pouring and Curing 1,062,720.00 1.24%
Weekly Cummulative Accomplishment Percentage 0.00% 0.33% 0.54% 0.80% 1.02% 1.30% 1.72% 2.84% 4.89% 8.13% 13.54% 22.52% 36.01% 51.00% 63.88% 74.56% 82.34% 88.55% 93.14% 96.66% 98.98% 100.00%
Semi-monthly Accomplishment Percentage 0.33% 0.47% 0.50% 1.54% 5.29% 14.39% 28.48% 23.56% 13.99% 8.11% 3.34%
PLANNED Semi-monthly Accomplishment Cost ₱ 281,761.50 ₱ 401,296.67 ₱ 426,911.36 ₱ 1,314,886.98 ₱ 4,516,722.15 ₱ 12,286,508.83 ₱ 24,316,870.85 ₱ 20,116,063.11 ₱ 11,944,979.75 ₱ 6,924,502.20 ₱ 2,851,767.86
Monthly Cummulavtive Accomplishment Percentage ₱ 281,761.50 ₱ 1,109,969.53 ₱ 6,941,578.65 ₱ 43,544,958.33 ₱ 75,606,001.19 ₱ 85,382,271.24
Weekly Cummulative Accomplishment Percentage 0.00% 0.36% 0.36% 0.36% 0.42% 0.75%