Professional Documents
Culture Documents
Adil Bhai B-17 Plaza STR Drawings (Revised 18-Oct-2020)
Adil Bhai B-17 Plaza STR Drawings (Revised 18-Oct-2020)
STRUCTURAL DRAWINGS
COLUMNS & SIDE OF BEAMS & WALLS 24 HOURS 1. FOOTING 2" above PCC and 3" on other sides
3. SLAB
a. FOUNDATIONS TO BE PLACED ON WELL COMPACTED SOIL AS PER 3/4"
a. EXPANSION JOINTS BE FINALIZED AND GOT APPROVED 5. CONFINING ELEMENT/LINTEL BEAM 1"
a. STEEL BARS BE PLACED IN THE FORM AS PER DRAWINGS. 1/2" 2.5 3.0 6.0
4. W:C:S: AGGREGATES AND SIZES b. ALL JUNCTION OF THE BARS / CROSS BE TIED WITH BINDING 5/8" 2.5 4.0 7.5
FRESH WATER: IN ACCORDANCE OF UBC 97 SECTION 1903.4 WIRE. 3/4" 3.0 4.5 9
B/2
COLUMNS & BEAMS 3/4 DOWN GRADED
12. BRICK , CONC BLOCK MASONRY
A
SLABS 3/4" DOWN GRADED
a. FIRST CLASS BRICKS BE USED FOR MASONRY WORK.
3/4" DOWN GRADED MEANS 1/2" AND 3/8" MIX b. BRICKS BE SOACKED IN WATER A DAY BEFORE USE. B
3/8" 18 7.5
1/2" 24 9.5
3/4" 30 14.5
h/2
given in the center portion of column
1" 48 19
h
STRAIGHT BARS WITH STANDARD HOOK
1/2" 22 11"
5/8" 30 14"
3/4" 34 17"
h/2
1" 55 22"
1" 48 18 L/4
1" - 70
TYPICAL BEAM DETAIL
3T/8
12" 12"
T/5
T/4
T
3"
9"
1
3
9"
#4 dowel bars @ 18"c/c
BRICK/BLOCK MASONRY
TYP. DETAIL OF CONSTRUCTION
DETAIL OF COLUMN WALL TIE DETAIL OF WINDOW JOINT IN RAFT & SLABS
PROJECTION
9"
6" THICH
FLOOR SLAB 2#3@AFTER EIGHT COURSE
BEAM TOP BARS
PRIMARY BEAM
BEAM HOOPS
1 1/2" CL.
TO END OF HOOKS BEAM BARS
ON BEAM BARS
OPEN OPEN
M
3'-"0 3'-"0
INTERIOR BEAM HOOPS SECONDARY BEAM INTERIOR BEAM HOOPS
BEAM BOTTOM BARS
(SMALLER SECTION BEAM)
SECTION AT M-M
BEAM HOOPS
COLUMN HOOPS
1 1/2" CL.COVER
TO END OF HOOKS
ON BEAM BARS BEAM BARS
1 1/2" CL.
TO END OF HOOKS
ON BEAM BARS
COL. HOOPS
Y Y
X X
Column ties are Column ties are
necessary in necessary in
this region this region
INTERIOR BEAM HOOPS
2#4
BEAM HOOPS
2#4
A
C-2 C-1 C-2
17'
B
C-2 C-3 C-2
20'-9"
60'
20'-9"
BASEMENT FLOOR
COLUMNS KEY PLAN
1 2 3
40'
19'-3" 19'-3"
A
C-2 C-1 C-2
17'
B
C-2 C-3 C-2
20'-9"
60'
C
20'-9"
GROUND FLOOR
COLUMNS KEY PLAN
1 2 3
40'
19'-3" 19'-3"
A
C-2 C-1 C-2
17'
B
C-2 C-3 C-2
20'-9"
60'
O.T.S
20'-9"
FIRST FLOOR
COLUMNS KEY PLAN
1 2 3
40'
19'-3" 19'-3"
A
C-2 C-1 C-2
17'
B
C-2 C-3 C-2
20'-9"
60'
O.T.S
20'-9"
SECOND FLOOR
COLUMNS KEY PLAN
1 2 3
40'
19'-3" 19'-3"
A
17'
B B
B
20'-9"
A A
60'
21" THICK
RAFT
C
STR-05
B B
20'-9"
10' 10'
A
#4@5"c/c #4@5"c/c
#4@5"c/c
#4@5"c/c
10'
10'
(10'x10') (10'x10')
17'
B 10' B
(10'x10')
#6@4"c/c
B
10'
#6@4"c/c
21" THICK
20'-9"
RAFT
A A
60'
10'
(10'x10')
#6@4"c/c
C
10'
STR-06
#6@4"c/c
B B
20'-9"
(10'x10') (10'x10')
#4@5"c/c
#4@5"c/c
10'
10'
#4@5"c/c #4@5"c/c
D
10' 10'
#4@8"c/c
17'
B B
21" THICK
20'-9"
RAFT
A A
60'
STR-07
#4@8"c/c
B B
20'-9"
40'
#6@5"c/c
18'-9"
17'
B B
40'
#6@5"c/c
18'-9"
20'-9"
A A
60'
#6@10"c/c
59'-6"
STR-08
21" THICK
B RAFT B
22'-6"
20'-9"
#6@5"c/c
40'
3"
2'-3"
1'-9"
1'-9"
21" th. RAFT 21" th. RAFT
2'-3"
3"
3"
3"
2'-3"
1'-9"
1'-9"
21" th. RAFT 21" th. RAFT
2'-3"
3"
3"
+0'-0" From
9" TH. WALL
Road Level
Architect
6"
LANDING SLAB
As Per
#4@9"c/c (H) #4@12"c/c (H)
15"
9"
#3@6"c/c
3-#6
9" WIDE
WATER
STOPER P.C.C (1:4:8) TYPICAL REINFORCEMENT DETAIL OF STAIR CASE
BASEMEVTFLOOR
3" 3"
2'-3"
1'-9"
P.C.C (1:4:8)
6"
#3@6"c/c #3@6"c/c #3@6"c/c
#3@6"c/c
4'
3'
12-#8 12-#8 8-#8
1'-6"
1'-6"
1'-6"
1'-3"
8-#6
4-#6 4-#6 4-#6
6"
1'-3"
1'-6" 1'-6" 1'-6"
PLAN OF SUMP PIT
1'-6"
1'-6"
1'-3"
8-#6 B.F.F.L
4-#6 4-#6 4-#6
1'-3"
RAFT RAFT
1'-6" 1'-6" 1'-6"
#4@6"c/c
#3@6"c/c #3@6"c/c #3@6"c/c #3@6"c/c
#4@10"c/c
1'
#6@6"c/c
12-#8 12-#8 12-#8 8-#8
2'
2'
2'
2'
4-#6 4-#6 4-#6 4-#6
1'-6"
#6@6"c/c
3"
1' 1' 1' 1'
IN LET
6" TH. SLAB OUT LET
2'
F.L FREE BOARD F.L
RAFT RAFT
5'
#4@6"c/c V #4@6"c/c V
P.C.C (1:4:8)
GF-B1
GF-B2
17'
GF-B1 GF-B1
B
GF-B1
GF-B1
GF-B2
20'-9"
60'
GF-B1 GF-B1
C
STR-13
GF-B1
GF-B1
GF-B2
20'-9"
GF-B1 GF-B1
D
BASEMENT FLOOR
BEAMS KEY PLAN
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
1 2 3
40'
19'-3" 19'-3"
#4@5"c/c #4@5"c/c
17'
#4@6"c/c
#4@6"c/c
#4@5"c/c #4@5"c/c
20'-9"
60'
#4@5"c/c
#4@5"c/c
C
STR-14
#4@5"c/c #4@5"c/c
20'-9"
#4@5"c/c
#4@5"c/c
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
1 2 3
40'
19'-3" 19'-3"
A
#4@5"c/c #4@5"c/c
4'
4'
#4@5"c/c #4@5"c/c #4@5"c/c
17'
#4@5"c/c #4@5"c/c
5'-3"
5'-3"
B
6'
6'
#4@5"c/c #4@5"c/c #4@5"c/c
20'-9"
6'
6'
C
STR-15
#4@5"c/c #4@5"c/c
6'
6'
#4@5"c/c #4@5"c/c
5'
5'
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
*SPACING OF DISTRIBUTION BARS FOR NEGATIVE REINFORCEMENT MUST BE KEPT AS #3@12"c/c.
1 2 3
40'
19'-3" 19'-3"
B1
B1
B2
A
GF-B1 GF-B1
GF-B1
GF-B1
GF-B2
17'
GF-B1 GF-B1
B
GF-B1
GF-B1
GF-B3
GF-B2
20'-9"
60'
STR-16
C
GF-B1 GF-B1
GF-B1
GF-B1
GF-B2
20'-9"
GF-B1 GF-B1
D
B1
B1
B2
#4@5"c/c #4@5"c/c
17'
#4@6"c/c
#4@6"c/c
#4@7"c/c #4@5"c/c
20'-9"
60'
#4@5"c/c
#4@6"c/c
STR-17
#4@5"c/c #4@5"c/c
20'-9"
#4@5"c/c
#4@5"c/c
BOTTOM BARS
3'
3'
A
#4@5"c/c #4@5"c/c
4'
4'
#4@5"c/c #4@5"c/c #4@5"c/c
17'
#4@5"c/c #4@5"c/c
5'-3"
5'-3"
B
6'
6'
#4@5"c/c #4@5"c/c #4@5"c/c
20'-9"
6'
6'
C
STR-18
#4@5"c/c #4@5"c/c
6'
6'
#4@5"c/c #4@5"c/c
5'
5'
D
3'
3'
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
*SPACING OF DISTRIBUTION BARS FOR NEGATIVE REINFORCEMENT MUST BE KEPT AS #3@12"c/c.
1 2 3
40'
19'-3" 19'-3"
B1
B1
B2
A
GF-B1 GF-B1 GF-B1
GF-B1
GF-B2
17'
GF-B1 GF-B1
B
CB-1
GF-B1
GF-B3
GF-B2
20'-9"
GF-B1
CB-1
60'
CB-1
C
STR-19
GF-B1 GF-B1
GF-B1
GF-B1
GF-B2
20'-9"
GF-B1 GF-B1
D
B1
B1
B2
FIRST FLOOR
BEAMS KEY PLAN
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
1 2 3
40'
19'-3" 19'-3"
#4@5"c/c #4@5"c/c
17'
#4@6"c/c
#4@6"c/c
B
#4@5"c/c
#4@7"c/c #4@5"c/c
20'-9"
#4@5"c/c
60'
#4@6"c/c
#4@5"c/c
C
STR-20
#4@5"c/c #4@5"c/c
20'-9"
#4@5"c/c
#4@5"c/c
3'
3'
A
#4@5"c/c #4@5"c/c
4'
4'
#4@5"c/c #4@5"c/c #4@5"c/c
17'
#4@5"c/c #4@5"c/c
5'-3"
5'-3"
B
#4@5"c/c
6'
6'
4'-6"
#4@5"c/c #4@5"c/c
20'-9"
#4@5"c/c
6'
6'
4'-6"
#4@5"c/c #4@5"c/c
6'
6'
STR-21
#4@5"c/c #4@5"c/c
5'
5'
D
3'
3'
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
*SPACING OF DISTRIBUTION BARS FOR NEGATIVE REINFORCEMENT MUST BE KEPT AS #3@12"c/c.
1 2 3
40'
19'-3" 19'-3"
B1
B1
B2
A
GF-B1 GF-B1
GF-B1
GF-B1
GF-B2
17'
GF-B1 GF-B1
B
CB-1
GF-B1
GF-B3
GF-B2
20'-9"
GF-B1
CB-1
60'
CB-1
C
STR-22
GF-B1 GF-B1
GF-B1
GF-B1
GF-B2
20'-9"
GF-B1 GF-B1
D
B1
B1
B2
SECOND FLOOR
BEAMS KEY PLAN
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
1 2 3
40'
19'-3" 19'-3"
#4@5"c/c #4@5"c/c
17'
#4@6"c/c
#4@6"c/c
B
#4@5"c/c
#4@7"c/c #4@5"c/c
20'-9"
#4@5"c/c
60'
#4@6"c/c
#4@5"c/c
C
STR-23
#4@5"c/c #4@5"c/c
20'-9"
#4@5"c/c
#4@5"c/c
3'
3'
A
#4@5"c/c #4@5"c/c
4'
4'
#4@5"c/c #4@5"c/c #4@5"c/c
17'
#4@5"c/c #4@5"c/c
5'-3"
5'-3"
B
#4@5"c/c
6'
6'
4'-6"
#4@5"c/c #4@5"c/c
20'-9"
#4@5"c/c
6'
6'
4'-6"
#4@5"c/c #4@5"c/c
6'
6'
STR-24
#4@5"c/c #4@5"c/c
5'
5'
D
3'
3'
NOTE:
*ALL SLABS ARE 6" THICK EXCEPT MENTIONED.
*STAIRS & PODIUMS WILL BE CONSTRUCTED ACCORDINGLY.
*SPACING OF DISTRIBUTION BARS FOR NEGATIVE REINFORCEMENT MUST BE KEPT AS #3@12"c/c.
L
L/3 L/3 L/3 1'-3" 1'-3"
7-#6 3-#6 4-#6 3-#6 7-#6 7-#6 3-#6 4-#6
7-#6
(EXTRA) (EXTRA) (EXTRA)
6"
6"
6"
1'-9"
1'-9"
#3@5"c/c #3@5"c/c #3@5"c/c
1'-3"
1'-3"
1'-3"
5-#6 1 2 5-#6 1 5-#6 5-#6 1 5-#6 7-#6
2-#6(EXTRA)
3/4*L
L
L/3 L/3 L/3 1' 1'
7-#6 3-#6 4-#6 3-#6 7-#6 7-#6 3-#6 4-#6
7-#6
(EXTRA) (EXTRA) (EXTRA)
6"
6"
6"
1'-9"
1'-9"
#3@5"c/c #3@5"c/c #3@5"c/c
1'-3"
1'-3"
1'-3"
5-#6 3 4 5-#6 3 5-#6 5-#6 3 5-#6 7-#6
2-#6(EXTRA)
3/4*L
L
L/3 L/3 L/3 1' 1'
5-#6 2-#6 3-#6 2-#6 5-#6 5-#6 2-#6
5-#6 3-#6
(EXTRA) (EXTRA) (EXTRA)
6"
6"
6"
1'-6"
1'-6"
#3@6"c/c #3@6"c/c #3@6"c/c
1'
1'
1'
3-#6 5 6 3-#6 5 3-#6 3-#6 5 3-#6 5-#6
2-#6(EXTRA)
3/4*L
9"
1
4"
2 9" 9" 4-#4
2-#4 3-#4 4-#4
9"
#3@9"c/c
6"
6"
6"