Professional Documents
Culture Documents
Adventages Disvantages and Risk
Adventages Disvantages and Risk
Adventages Disvantages and Risk
© FECAP
822
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
140 10.000
9.000
120
8.000
100 7.000
Nº Companies
Billions (R$)
80 6.000
5.000
60 4.000
40 3.000
2.000
20
1.000
0 0
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
In order to obser ve public works 2000 to 2008, between 42% and 52% of revenue
importance for the construction sector economy, originated from works and/or services execution
it is sufficient to analyze the IBGE (2011) data came from constructions for bodies or companies
shown in Figure 2, which showed that, from belonging to the federal, state or local government.
823
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
2008 127
46%
2007 97
42%
2006 85
46%
2005 75
44%
2004 71
45%
2003 53
46%
2002 53
52%
2001 40
46% Value of works and/or services executed (billions R$)
2000 33
52% Public works (percentages on values of works/services executed)
Public sector works are related to highway, by construction expropriation and 3) planned
railway, urban work and special art work financial resources availability. On original project
construction (bridges, viaducts, tunnels, etc.), adaptations, the author stated that two facts often
electricity, telecommunications, water, gas and contribute to aggravate the situation: the fact
sanitation supply provision infrastructure works that the project does not contain all prescribed
and civil works, such as schools, hospitals, prisons, elements by the current legislation and that the
administrative buildings and dwellings financed fact the project is not updated when the respective
with public funds. work is in progress.
Such works are contracted through a Nevertheless, some authors (Konchar &
lowest overall price or lowest unit price public Sanvido, 1998; Palaneeswaran & Kumaraswamy,
bidding process type. Originally contracted prices, 2000; Songer & Molenaar, 1996) assign a great
if not majored by overbillings and overpricing deal of design alterations and adaptations to
(TCU, 2009), are majored by amendments or the lack of interaction between design and
by economic and financial rebalancing. Contract construction teams. The work contracting
price increase due to value amendment amount method used by most Brazilian public entities is
is caused by intentional solution changes, project named design-bid-build (DBB) by these authors.
errors and technical specification failures, which This method relates to a traditional system to
alter the initially budgeted services/material, or contract enterprises in which the owner separately
their amounts. When this happens, it is also signs contracts with design and construction
inevitable to have a deadline amendment. companies (Konchar & Sanvido, 1998). With
Work execution delays take place, according lack of technical personnel in its staff, the public
to Amaral (2000), due to three factors: 1) original entity performs the bidding process with all
project need for alterations and adaptations, relevant documentation based on a draft project,
2) properties that will be affected in some way in order to hire the company that will develop
824
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
the basic and executive projects and, in possession fully benefit from the advantages provided by
of these, performs the bidding process that will DB. The same panorama is verified in countries
contract the respective work executor. Except for such as the UK, Korea, Japan and Oman. When
works carried out by public-private partnerships, considering DB many advantages compared
all other public work contracts must conform to to DBB, it is possible that the same happens
what is prescribed by Public Procurement Law no. in Brazil, initially on a trial basis and, after
8.666/1993 (2004) and its amendments. advantages confirmation, definitively. However,
Some authors state that DBB contracting there can be no implantation without method
type can lead to some problems, such as: 1) benefits, risks and critical points refined study.
dealing with two contracts (one for design Given this need, this study aims to identify
and another one for construction) increases industry executives’ perception concerning
design-build contracting method use, advantages,
the possibility of project alteration when the
risks and disadvantages, in order to make it
work is being executed due to the occurrence
possible to be adopted by the Brazilian public
of any unplanned event in project phase, what
sector. From this study, it is possible to propose
would result in extra cost (Songer & Molenaar,
coping strategies which are necessary in case this
1996), and 2) more time for work completion
approach is adopted. For this, advantages, risks
would be needed (Konchar & Sanvido, 1998;
and disadvantages mentioned in the researched
Palaneeswaran & Kumaraswamy, 2000). Similar
literature will be addressed, as well as the ones
problems are common in enterprises contracted likely to happen according to the opinion of 19
by the Brazilian Public Administration regarding professionals from the construction industry. It
works. should be noted that the focus of this research
An alternative to DBB is the Design- will be on these aspects occurrence between public
build (DB) method. In this model, an entity or works design and construction phases.
consortium is contractually responsible for the work In order to reach the main objective, the
design and execution (Hale, Shrestha, Gibson, & study was divided into the following sections:
Migliaccio, 2009; Songer & Molenaar, 1996). section 2, concerning the DB contracting method,
Konchar and Sanvido (1998) and Palaneeswaran its main characteristics, advantages, disadvantages
and Kumaraswamy (2000) stated that the primary and inherent risks; section 3, regarding the
reason to select the DB method is its potential to used research method; section 4, concerning
reduce total development time, given the overlap in results; and section 5, regarding final conclusions
a certain stage of design and construction phases. and considerations, including research limitations
This time reduction would also result in cost and future study suggestions.
reduction. These, among other advantages, have
enabled the method to be well accepted compared
to other possible ones. 2 D e s i g n - b u i l d con t rac t ing
Although used in private sector and public- method
private partnerships, design and construction
DB contracting method finds obstacles in the Design-build is an enterprise contracting
Brazilian legislation regarding its possibility of system in which the contracting party, or owner,
being adopted by the public sector. Basic – and hires a company to perform both design and
executive in some cases – design mandatory construction under a single contract (Konchar &
requirement prior to work contracting prevents Sanvido, 1998; Molenaar & Gransberg, 2001).
its use. However, studies such as the ones by Arditi and Lee (2003) added that this method
Molenaar and Gransberg (2001), for example, facilitates innovative and flexible approaches use,
approach similar situations in some US states, such as construction and new material technologies
which are adapting their legislation in order to knowledge gradual introduction.
825
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
Contractually, DB provides a single Park et al., 2009; Yates, 1995) incidence, less
responsibility point for design and construction administrative work, clarification requests and
services, which is true from the contracting changes (Yates, 1995), better constructability1,
party’s perspective, but not from the contracted more innovation and better decision-making (
company, which may subcontract services of Molenaar et al., 1999; Yates, 1995). Concerning
which they have no expertise, or join a companies’ design alterations, Perkins (2009) stated that there
consortium (Chang, Shen, & Ibbs, 2010; Park, Ji, are two significant advantages in the DB method:
Lee, & Kim, 2009; Puerto, Gransberg, & Shane, design errors cease to be a construction phase
2008; Oyegoke, Dickinson, Khalfan, Mcdermott, alteration source and the joint work of designer,
& Rowlinson, 2009). However, some contracting constructor and contracting party enables skills
parties require these subcontracts plan. sharing in cost reduction and deadline shortening.
In addition to the single responsibility Songer and Molenaar (1996) identified that
point, the method has other features. Park et the main reason to use the DB contract, according
al. (2009) mentioned the method characteristic to interviewees from public and private sectors,
of being more often applied in large and complex was the short duration, followed by, in assigned
enterprises, once they allow, among other importance order: cost fixation and reduction,
benefits, good coordination and communication. constructability and innovation, schedule securing,
According to other authors, the main advantages claims reduction and design complexity level.
of DB contracting method rest in the fact that it The authors highlighted that, although the short
provides better time (Hale et al., 2009; Konchar duration appears as the main motivation, any of the
& Sanvido, 1998; Molenaar, Songer, & Barash, aforementioned factors can become preponderant in
1999; Park et al., 2009; Yates, 1995), cost particular enterprises. In order to fully enjoy these
(Konchar & Sanvido, 1998; Park et al., 2009; benefits, it is necessary, among other initiatives,
Yates, 1995) and quality (Park et al., 2009) to observe the DB method own selection process,
performance, less claims, conflicts, disputes and which is called two-steps, as shown in Figure 3
legal actions (Molenaar, Songer, & Barash, 1999; (Migliaccio & Shrestha, 2009b).
826
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
Prior to the Request for Qualifications final landmark is the receiving of proposals from
(RFQ), Migliaccio, Gibson, & O’Connor pre-qualified companies in sealed envelopes, one
(2009a) reported the study of feasibility, cost- for competition according to technique criterion,
benefit relations, funds/financing sources, and another one for competition according to
among others. RFQ stage objective is to select price criterion.
proponents who have the required qualifications In the proposal evaluation stage - RFP3 -,
to execute the enterprise, in order to assure the the best value evaluation procedure is adopted, in
participants number is between three and five, which technical and price criteria are weighed at
a reasonable number for the contracting party’s the contracting party’s discretion. Each envelope
hiring staff, considering the following phases’ goes to the respective evaluation committee, which
administrative workload. This phase result is cannot comment anything about it, not even
the list of pre-qualified candidates to continue within committees, until the scores are assigned.
in the bidding process. This stage result is the announcement of the best
In the RFP – Request for Proposals value contracting proposal. Some companies
– phase, proponent instructions, DB draft in the US public sector have a sub-phase, the
contract, technical requirements development evaluation stage, in which they negotiate prices
(environmental impact and preliminar y and allow proponents to mend the irregularities
engineering) and its attachments are set. noted in their proposals. Only after that the grades
Subsequently, there is the proposal request draft are calculated, and the winner, announced.
release for industry acknowledgement, which In the last phase – contract finalization –
may suggest changes by submitting a written the committee can negotiate alternative technical
document or discussing in meetings (two to concepts proposed by a pre-qualified company
three rounds, depending on the project). At or several pre-qualified companies, but which
the same time, technical review committees and had not won the bidding process, provided that
subcommittees are formed with assigned roles the (negotiation) procedure has been previously
and responsibilities, and the rules to evaluate approved in the proposal request preparation
proposals are designed. In this stage, the stage. Once alternative technical concepts are
complete proposal request is originated and, after negotiated, the company is compensated and the
competent authorities’ approval, it is released for commission remakes the final price, comprising
companies that take part in the list of pre-qualified the change. After negotiation, the commission
candidates. concludes the winning company hiring and, after
In the proposal development stage - competent authority approval, the contract goes
RFP2 -, pre-qualified companies interact with to the administration phase.
the commission through clarification requests, Regarding each phase duration, Migliaccio
answered in meetings (usually two or three and Shrestha (2009b) conducted a study with a
meetings, but it may also be more meetings in sample of 19 highway work enterprises performed
the case of more complex enterprises). In this according to the DB method, with a cost range
phase, pre-qualified companies may suggest between $ 9 million and $ 1.3 billion, conducted
alternative technical concepts, which are evaluated between 1997 and 2006, with the results shown
by committees and subcommittees and, when in Table 1.
accepted, alter the proposal request. This stage
827
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
Adapted from “Procurement of design-build services: two-phase selection for highway projects,” G. C. Migliaccio, G. E.
Gibson, E. and J. T. O’Connor, 2009a, Journal of Management in Engineering, 25, 29-39. “Analysis of design-build procurement
activities durations for highway projects ,” G. C. Migliaccio, and P. P. Shrestha, 2009b. Proceedings of the ASCE Construction
Research Congress, Seattle, WA, USA, p. 229-238.
In the study by Rosner, Thal, and West and innovative management approaches
(2009), with data from 278 DB enterprises and use. Regarding contracting party involvement
557 DBB enterprises performed between 1996 in the scope definition stage and in cost, deadline
and 2006, it was found that the DB method and quality control throughout the enterprise,
significantly improved regarding total time Molenaar and Songer (1998) claimed that the
extrapolation and enterprises cost throughout the absence of this may result in nonconformity in
years. This suggests that the know-how acquired relation to initially established specifications. Park
by the contracting party improves time and cost et al. (2009) cited the existence of a contracting
method metrics. One should also consider that party system to measure and control contracted
certain procedures standardization with method party performance as a critical success point in
extensive use is time and resource-efficient. the DB method.
Concerning the risk, the DB contracting
method is better applied, according to some
3 D e s i g n - b u i l d me t h od authors (Konchar & Sanvido, 1998; Park et
disadvantages and risks al., 2009), to large and complex enterprises.
However, it is important to mention three
Aiming at a possible method implantation, perspectives, according to which Miller and
it is necessary to know success critical points, Lessard (2001) suggested their intensity analysis
negative aspects and inherent risks. in enterprises of this sort ballast coping and
In order to fully enjoy the benefits, it training strategies. These perspectives are related
is necessary to pay attention to critical success to completion, market, social and institutional
points in the DB method which, if ignored, can risks, which in turn vary simultaneously in
configure specification nonconformity and cost intensity, according to the authors, depending on
and deadlines extrapolation risks. Lam, Chan the enterprise type. It is pertinent to note that the
and Chan (2008) cited contracting party’s (the «risk formation» term deals with the possibility
staff or consultants) and construction team’s of the risks being caused to provide a positive
competence, management action effectiveness repercussion on the enterprise.
(communication, control and management Enterprise completing risks can be:
systems and organizational structure), working technical - those that are usually related to designs
relations among teams, contracting party’s that generate the enterprises, or used technologies;
contributions (experience and knowledge), of construction - those which contracting party,
contracting party’s deadlines and costs focus, contracted party and sponsors are subjected in the
828
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
829
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
and Miller and Hobbs (2005), proposed by the area; failures and nonconformities - quality
PMBOK® Guide (PMI, 2008), stated that all area; low performance, poor specifications,
project management knowledge areas may be noncompliance with deadlines – purchasing/
potential sources of risk generation. Thus, in hiring area (PMI, 2008).
each of the other eight knowledge areas (besides Based on the approaches described in
the risk area), described in the PMBOK® Guide, Miller and in the PMBOK® Guide, risks inherent
risks can occur due to: environmental threats and to DB enterprises that are restricted to contracting
opportunities - integration area; flawed definitions party and contracted party were researched in the
- scope area; tight or unfeasible schedules – literature. The chart below shows disadvantages
deadline area; tight or unfeasible budgets - cost and risks associated with DB contracting method,
area; diseases, absenteeism, high turnover, classified according to risk sources covered in this
resignation - human resources area; failures or section, and mentioning the studies in which they
deficiencies in communication - communication were cited.
830
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
Thereafter, a semi-structured interview was at collecting the opinion of respondents who had
conducted for field research, with objective and a higher number of amendments in contracts
subjective questions, through which interviewees’ signed by the body which was object of study,
opinions were collected regarding problems since supposedly they would be more familiar
observed between design and construction, the with problems between design and construction
possibility or not of DB method solving such that result in amendments; 2) more sizeable
problems, and Public Administration risks, contracts, aimed at collecting the opinion of those
advantages and disadvantages in adopting this hired for higher values, once these were in charge
method. The Brazilian procurement law prohibits of executing supposedly more complex works. In
DB method application, i.e., it does not allow order to maintain the source confidentiality,
hiring a company to draft a project (basic and companies were named as presented in Chart
executive project) and conduct the construction 2. The three construction companies, selected
execution. Thus, respondents could not be asked according to the largest number of amendments,
about method practical issues, but only about were named ECQ1, ECQ2 and ECQ3. Designers,
issues that, according to their perceptions, could selected by bulkier contracts, received the
occur in case the method was adopted. EPV1, EPV2, and EPV3 designation, and so
Nineteen interviews were conducted: forth. Project, construction and supervision
three with public body fiscals and 16 with groups, contracting party and contracted party
engineers from companies hired by the body, diversity and data collection form, which was
and selected based on prior documentary by documentary and field research in the form
research in bidding processes carried out between of interview, with objective and subjective
2006 and 2010. Companies were categorized questions, allowed a problem analysis through
according to the nature of services provided in different points of view, and different opinions
construction companies (works performing), exploration on the matter in question (Markoni
designing (contracted to draft the basic and & Lakatos, 2009). It is important to emphasize
executive designs) and supervising (contracted to that respondents have not restricted their answers
monitor work execution, as specified in the basic only to the public body, which was the source
and executive projects). The sample of respondents of the study, as they provided similar services to
was defined as shown in Chart 2. other public bodies from different government
Two respondents selection criteria were levels; therefore, there is the possibility of results
used: 1) higher number of amendments, aimed generalization.
831
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
After transcribing the interviews, the (Bardin, 2011). Later, registration units were
content analysis was applied to the transcriptions. organized into thematic categories related to DB
The idea of theme was used in register units method advantages and disadvantages foreseen by
prior identification, which is a signification unit respondents. The procedures for this study are
that naturally emerges from an analyzed text outlined in the following figure.
Figure 4 –Figure
Procedure totoconduct
4 - Procedure conduct the the research
research
832
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
just after being concluded due to failure in its the scope. Among DB method disadvantages,
execution, or that showed problems some cases Arditi and Lee (2003), Park et al. (2009) and
even in its design phase, all widely known, Chang et al. (2010) mentioned the difficulty of
suggest that such concerns are well-grounded. the contracted party to manage the enterprise
In addition, the lack of expertise in projects and ensure quality. Without proper structure,
would make the building companies adjust including the clear definition of the several
prices according to those risks, and decisions on procedures involved when monitoring a DB
the project would be made by the construction enterprise, there will be consequences such as
company in first place and not by the requesting low project quality, poor communication, lack of
body, as it currently happens. Regarding the contracting body prerogative in project definition,
control that the construction company has on high prices, time-consuming administrative
the enterprise in the DB method, Molenaar and processes, among other interferences. On the other
Songer (1998) emphasized that the contracting hand, the several stories about procurement and
party’s involvement is of paramount importance public work execution frauds, so recurrent, may
to minimize it. have led ECQ1 to explicitly state that strong and
With regard to the structure the bodies effective management absence by the contracting
should have to exert proper control, respondents body may lead to illicit acts occurrence (see the
mentioned active and qualified inspection, Fairness in procedures/commitment topic in
detailed project analysis and objectivity to define Table 2).
833
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
The need to adjust the companies to the due to legal issues, and due to the fact that required
new demand would, in respondents’ opinion, documentation for the negotiations sometimes
lead to extinction, merger, restructuring and even is not in the owner’s possession. Thus, how to
subcontracting among segment companies, which foresee and plan for these cases? In other cases,
is ratified by Puerto et al. (2008), Park et al. (2009), environmental permits specifically, it is discovered
Oyegoke et al. (2009) and Chang et al. (2010), during the execution, due to the identification
when they mention that companies contracted by of a rock formation that was not verified in the
DB method may subcontract services for which design, that the road should have a different route
they have no expertise. Concerning the difficulties and go through an environmental preservation
found by companies, Park et al. (2009) cited area. So, how to anticipate and be prepared to
the fact that there are few trained or qualified face such a situation? You must agree with FISC1
companies as a DB problem. Chang et al. (2010) regarding these points. However, having had
cited the lack of experience with construction previous planning, facts are likely to happen as
and with design by the designer and the builder, the mentioned ones referred as emerging risks,
respectively, concerning the qualification issue and should certainly be foreseen, with procedures
required from these companies. The assertion that to be taken in case they happen, and the necessary
construction companies would hire designers lies time to solve them. Besides, contracted design
in the fact that nowadays, at least in the studied data in loco verification by the inspection team
sample, companies clearly have distinct expertises, or by the body technical team would enable the
design or construction, what would lead them to, identification of aspects which went unnoticed by
designers, such as an improper rock formation.
a priori, subcontracting.
ECQ1, due to DB enterprise complexity,
EPV and FISC2 designers mentioned
mentioned that the method adoption would
error identification problems. Nowadays, the
cause further intervention by regulatory agencies,
supervisor analyzes and adapts the design prepared
and EPQ 3 emphasized the need for fairness
by the designer to the reality of the work. Thus,
and commitment by both involved parties,
they identify some mistakes which went
contracting and contracted. These statements
unnoticed by those who drew the design. Then,
have to do with work price and/or basic budget
it was hypothesized that when drawing up and
spreadsheets elaboration. Nowadays, the designer
executing the project, the construction company
company drafts the work basic budget and,
could not notice some errors. Designers who
when taking part in the bidding, the contracting
were interviewed see supervision companies’
company must organize their pricing spreadsheet
performance from a positive point of view when
in line with such a budget. However, after the
revising projects, because errors can be identified
bidding is won, many constructing companies
and corrected. In the DB method, revisions
require pricing spreadsheet readjustment, what
should be carried out by the contracting party’s involves service items quantity increases and
technical team. The absence of this team could decreases on the grounds of adapting services to
collaborate for error non-identification on the the local reality. Nowadays, with the design and
design prepared by the contracted party. the construction being carried out by different
ECV 1 pertinently noted that the DB companies, regulatory agency actions have
method would not be the solution to the identified spreadsheet preparation irregularities
problems caused by several delays. The origin of with respect to arbitrary prices and quantities. In
these problems lies in the lack of planning and the case of a single company, similar practices
control by administration. As FISC1 mentions could become more difficult to be identified, and
(FISC1 transcription, answer 22), there are therefore attract more careful audits performed by
expropriations which take a long time to be made regulatory agencies.
834
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
835
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
performance, quality and scope by the contracting the study in another public entity would allow
party, deficiencies that must be corrected before different conclusions. However, considering
the method in question adoption, since, above all, that the observed restrictions are inherent to the
due control exercise is a critical success factor. By great majority of public bodies in the country, it
generalizing the limitations mentioned for all is unlikely to happen. However, more studies on
public bodies, it would not be advisable to have the method, in a private scope or in public-private
any initiative in implanting the DB method in partnerships could be conducted, whether or
public enterprises contracting in the Brazilian not to confirm the advantages and disadvantages
context without first eliminating or minimizing verified in the studies of the consulted authors. In
their risks and weaknesses. In this sense, these addition, most of related studies could confirm,
findings will be useful to adopt preventive refute or add possible disadvantages and risks
measures. to DB method adoption. In contexts using the
The results may still contribute not only DB contracting method, it would be possible to
to a possible method implantation even in verify whether the time spent in the selection and
different contexts from the public, but also for contracting process influences work execution
the improvement of processes concerning works time reduction.
design and execution. In addition, this study offers
contribution as a suggestion to make the legislation
flexible according to potential gains from the DB NOTA
implantation, especially due to known delays and 1. Constructability: construction knowledge introduction
from the first design stages (Songer & Molenaar, 1997).
overpricing in the various Brazilian public work
enterprises, namely: World Cup/2014, Growth
Acceleration Program (PAC-1 and PAC-2), My References
House, My Life program (MCMV), among
others. Amaral, A. C. C. do. (2000). Problemas na
As used research method limitations, it is execução de obras públicas. Retrieved December, 15,
visualized, a priori, study performance with a state 2000, from http://www.conlicitacao.com.br/
public entity which would hinder the conclusion oquee/artigos /ramos_de_atividade/cintra_do_
generalization drawn from the study. However, in amaral_2006_09_22.02.php.
order to answer questions, respondents were based
not only on their experiences with enterprises Arditi, D., Lee, D.-E. (2003). Assessing the
carried out by the bodies which were object of corporate service quality performance of
this study, but also in other experiences acquired design-build contractors using quality function
in similar enterprises in various bodies. The deployment. Construction Management and
intentional sample composed of three (3) Economics, 21(2), 175-185.
professionals of each company category is also
a limiting factor, since the selected companies Bardin, L. (2011). Análise de conteúdo (279 pp.).
may not be the most representative of the studied São Paulo: Edições 70.
universe. Despite this, as noted in Table 2,
respondents selection was detailed considering Lei n. 8.666, de 21 de junho de 1993. (2004).
the amount of amendments and higher contracted Dispõe sobre normas de licitações e contratos da
amounts, and diversified considering construction Administração Pública e dá outras providências
companies, designers, supervisors and inspectors (134 pp.). São Paulo: Nova Dimensão Jurídica:
of the studied public entity works. São Paulo. 134 pp.
With regard to the DB method identified
Chang, A. S., Shen, F.-Y., Ibbs, W. (2010,
restrictions implantation, it is possible that
December). Design and construction coordination
836
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Advantages, disadvantages and risks in the adoption of design-build contracting method in the Brazilian public sector
problems and planning for design-build project ______; Lessard, D. (2001). Understanding and
new users. Canadian Journal of Civil Engineering, managing risks in large engineering projects.
37(12), 1525-1534. International Journal of Project Management,
19(8), 437-443.
Creswell, J. W. (2007). Projeto de pesquisa: métodos
qualitativo, quantitativo e misto (2a ed., 248 pp.). Molenaar, K. R., Gransberg, D. D. (2001).
Porto Alegre: Artmed. 248 pp. Design-builder selection for small highway
projects. Journal of Management in Engineering,
Hale, D. R., Shrestha, P. P., Gibson, G. E., 17(4), 214-223.
Migliaccio, G. C. (2009). Empirical comparison
of design/build and design/bid/build project ______; Songer, A. D., Barash, M. (1999, March/
delivery methods. Journal of Construction Engineering April). Public-sector design/build evolution and
and Management, 135(7), 579-587. performance. Journal of Management in Engineering,
15(2), 54-62.
IBGE. (2011). Pesquisa Anual da Indústria da
Construção. Retrieved March 09, 2011, from ______; Songer, A. D. (1998). Model for public
http://www.ibge.gov.br/home/pesquisa/pesquisa_ sector design-build project selection. Journal of
google.shtm?cx=009791019813784313549%3A Construction Engineering and Management, 124(6),
onz63jzsr68&cof=FORID%3A9&ie=ISO-8859- 467-479.
1&q=PAIC&sa=Pesquisar&siteurl=ww w.ibge.
gov.br%2F&ref=&ss=636j134930j4. Oyegoke, A. S., Dickinson, M., Khalfan, M.
M. A., Mcdermott, P., Rowlinson, S. (2009).
Konchar, M., Sanvido, V. (1998). Comparison of Construction project procurement routes: an
U.S. project delivery systems. Journal of Construction
in-depth critique. International Journal of Managing
Engineering and Management, 124(6), 435-444.
Projects in Business, 2(3), 338-354.
Lam, E. W. M., Chan, A. P. C., Chan, D. W. M.
Palaneeswaran, E., Kumaraswamy, M. M. (2000).
(2008, May). Determinants of successful design-
Contractor selection for design/build projects.
build projects. Journal of Construction Engineering and
Journal of Construction Engineering and Management,
Management, 134(5), 333-341.
126(5), 331-339.
Markoni, M. A., Lakatos, E. M. (2009).
Park, M., Ji, S.-H., Lee, H.-S., Kim, W. (2009,
Fundamentos de metodologia científica (6th ed.). São
November). Strategies for design-build in Korea
Paulo: Atlas.
using system dynamics modeling. Journal of
Migliaccio, G. C., Gibson, G. E., O’Connor, J. Construction Engineering and Management, 135(11),
T. (2009a, January). Procurement of design-build 1125-1137.
services: two-phase selection for highway projects.
Perkins, R. A. (2009, July). Sources of changes
Journal of Management in Engineering, 25(1), 29-39.
in design-build contracts for a governmental
______; Shrestha, P. P. (2009b). Analysis of owner. Journal of Construction Engineering and
design-build procurement activities durations Management, 135(7), 588-593.
for highway projects (pp. 229-238). Proceedings
of the ASCE Construction Research Congress, Seattle, PMI. (2008). PMBoK - guia do conjunto de conhecimentos
WA, USA. em gerenciamento de projetos (4th ed.). New York:
Project Management Institute (PMI).
Miller, R., Hobbs, B. (2005, September).
Governance regimes for large complex projects. Puerto, C. L. D., Gransberg, D. D., Shane, J.
Project Management Journal, 36(3), 42-50. S. (2008, January). Comparative analysis of
837
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Ana Elisabete Cavalcanti de Albuquerque / Marcos André de Mendes Primo / Felipe Augusto Pereira
owner goals for design/build projects. Journal of ______; Molenaar, K. R. (1996, November/
Management in Engineering, 24(1), 32-39. December). Selecting design-build: public and
private sector owner attitudes. Journal of Management
Rosner, J. W., Thal, Jr., Alfred E., West, C. J. in Engineering, 12(6), 47-53.
(2009, August). Analysis of the design-build
delivery method in air force construction projects. TCU. (2009). Obras públicas: recomendações
Journal of Construction Engineering and Management, básicas para a contratação e fiscalização de obras de
135(8), 710-717. edificações públicas (2a ed., 94 pp.). Brasília: TCU,
SECOB. 94 pp.
Songer, A. D., Molenaar, K. R. (1997, March).
Project characteristics for successful public-sector Yates, J. K. (1995).Use of design/build in E/C
design-build. Journal of Construction Engineering and industry. Journal of Management in Engineering, 11(6),
Management, 123(1), 34-40. 33-38.
838
Rev. bus. manag., São Paulo, Vol. 17, No. 54, pp. 822-838, Jan./Mar. 2015
Reproduced with permission of the copyright owner. Further reproduction prohibited without
permission.