Detail Cost Estimation of Roads (Complete)
Detail Cost Estimation of Roads (Complete)
-n=;=_ -n=;=_
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
0
SUMMARY OF COST
Name of the road:…………………………….
Chainage:0+000 to ….
S.N. Description of works Amount (NRs)
A General Item 21,867,400.08
B Site Clearance and Earthworks 545,897,060.82
C Structural Works 768,534,118.05
D Cross Drainage Works 53,640,636.53
E Pavement Works 392,399,538.00
F Drain Works 132,148,480.49
G Miscellenous Works 173,616,829.56
Base Cost (A+B+C+D+E+F+G) 2,088,104,063.53
VAT @13% of Base Cost 271,453,528.25
Contingency @ 5% of Base Cost 104,405,203.17
Total Cost including VAT & Contingency 2,463,962,794.95
Price adjustment Contingency @ 10% of Base Cost 208,810,406.35
Physical Contingency @ 10% of Base cost 208,810,406.35
Grand Total Cost 2,881,583,607.65
Cost Per Km of the road inclusive of VAT and contingency at Base Cost 88,631,755.21
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
0
SUMMARY OF COST
Remarks
1.05%
26.14%
36.81%
2.57%
18.79%
6.33%
8.31%
100%(I)
II=13% of I
III=5% 0f I
IV=I+II+III
V
VI
VII=IV+V+VI
VIII=IV/27.8 km
(a) Plain cement concrete, 1:3:6 or richer mix Cum 10.00 1,353.58 13,535.80
(b) Reinforced cement concrete work Cum 5.00 1,893.72 9,468.60
(c) Random rubble masonry in cement mortar Cum 35.00 1,371.05 47,986.75
(d)Dismantling of RCC pipes (excluding excavation and
rm 50.00 464.03 23,201.50
refilling). upto 600 mm dia.
Remarks
Remarks
Remarks
Remarks
I
II=13% of I
III=5% 0f I
IV=I+II+III
V
VI
VII=IV+V+VI
VIII=IV/27.8 km
For stone masonry retaining and breast wall Calculation refer attached sheet 22529.14
Total 22529.14
Providing and Placing machine mixed cement concrete
C.5 M10/40 including compaction, curing, testing all complete. Cum Calculation refer attached sheet 656.87
(SS/SP-2000)
Total 7502.08
Carry out backfilling works behind the structures with
C.7 approved suitable filler material spreading in layers, watering Cum 11011.18
and compaction all complete (SS/SP-900)
Total 11011.18
D Cross Drainage Works
Excavation for foundation in all types of soil including rock in
D.1 all conditions including dewatering, relevant lift and safe Cum
disposal all complete. (SS/SP-900)
Pipe culvert (90 cm) 77 77.27 5949.79
Slab culvert 3m 2 130.82 261.64
Total 6211.43
Providing, laying and levelling of dry stone soling works in
D.2 Cum
the foundation all complete (SS/SP-2600).
Slab culvert 3m 2 4.50 9.00
Total 9.00
Providing and Placing machine mixed cement concrete
D.3 M15/40 including compaction, curing, testing all complete. Cum
(SS/SP-2000)
Pipe culvert (90 cm) 77 11.93 918.61
Slab culvert 3m 2 37.47 74.94
Total 993.55
Providing and laying Random rubble stone masonry in
D.5 cement mortar [ cement(1) : sand(4)] including scaffolding, Cum
curing, preparation of mortar,finishing etc.all complete.
(SS/SP-2600)
Pipe culvert (90 cm) 77 24.28 1869.56
Slab culvert 3m 2 108.66 217.32
Total 2086.88
Providing and laying reinforcement including cutting,
D.6 bending,binding,fixing in position etc.all complete. (SS/SP- Kg
2600)
Slab culvert 3m 2 858.15 1716.30
Total 1716.30
Providing , Preparing and Installing form work including
necessary supports and removing after completion for
D.7 Sqm
foundation and footings (a) using timber ( soft wood) - Class
F1 finish.
Pipe culvert (90 cm) 77 5.06 389.62
Slab culvert 3m 2 82.14 164.28
Total 553.90
Proving and laying RCC pipes with or without collars jointed
with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1
D.8 Rm
cement : 2 fine sand ) including transportation all complete.
(SS/SP 700)
Pipe culvert (90 cm) 77 12.50 962.50
Pipe culvert (60 cm) 5 12.50 62.50
Total 1025.00
Carry out backfilling works behind the structures with
D.9 common excavated material spreading in layers, watering Cum
and compaction all complete.(SS/SP-900.)
Pipe culvert (90 cm) 77 31.49 2424.73
Slab culvert 3m 2 35.16 70.32
Total 2495.05
Carry out backfilling works behind the structures with
D.10 approved suitable filler material spreading in layers, watering Cum
and compaction all complete.(SS/SP-900.)
Pipe culvert (90 cm) 77 5.55 427.35
Slab culvert 3m 2 11.10 22.20
Total 449.55
Length
s
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
k
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m )
2
Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m )3
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
0+000 0.00 4.04 - - 0.02 - - - - - - - - 95 - 5 - 0 - Ordinary Soil
0+020 20.00 21.46 12.75 255.00 0.29 0.16 3.20 - - - - - - 95 242.25 5 12.75 0 - Ordinary Soil
0+040 20.00 26.25 23.86 477.20 - 0.15 3.00 - - - - - - 95 453.34 5 23.86 0 - Ordinary Soil
0+060 20.00 93.07 59.66 1,193.20 - - - - - - - - - 95 1,133.54 5 59.66 0 - Ordinary Soil
0+080 20.00 70.08 81.58 1,631.60 1.29 0.65 13.00 - 10.00 11.47 114.70 4.01 40.10 95 1,550.02 5 81.58 0 - Ordinary Soil
0+100 20.00 70.70 70.39 1,407.80 - 0.65 13.00 - 20.00 20.28 405.60 0.66 13.20 95 1,337.41 5 70.39 0 - Ordinary Soil
0+120 20.00 87.61 79.16 1,583.20 - - - - 20.00 22.44 448.80 0.66 13.20 95 1,504.04 5 79.16 0 - Ordinary Soil
0+140 20.00 138.57 113.09 2,261.80 - - - - 20.00 34.20 684.00 0.68 13.60 95 2,148.71 5 113.09 0 - Ordinary Soil
0+160 20.00 145.44 142.01 2,840.20 - - - - 20.00 61.80 1,236.00 1.64 32.80 95 2,698.19 5 142.01 0 - Ordinary Soil
0+180 20.00 168.93 157.19 3,143.80 - - - - 20.00 69.42 1,388.40 1.55 31.00 95 2,986.61 5 157.19 0 - Ordinary Soil
0+200 20.00 188.70 178.82 3,576.40 - - - - 20.00 96.39 1,927.80 1.55 31.00 95 3,397.58 5 178.82 0 - Ordinary Soil
0+220 20.00 136.89 162.80 3,256.00 - - - - 20.00 55.63 1,112.60 1.55 31.00 95 3,093.20 5 162.80 0 - Ordinary Soil
0+240 20.00 103.79 120.34 2,406.80 - - - - 20.00 39.98 799.60 1.50 30.00 95 2,286.46 5 120.34 0 - Ordinary Soil
0+260 20.00 82.30 93.05 1,861.00 - - - - 20.00 27.95 559.00 0.66 13.20 95 1,767.95 5 93.05 0 - Ordinary Soil
0+280 20.00 75.42 78.86 1,577.20 - - - - 20.00 24.87 497.40 0.66 13.20 95 1,498.34 5 78.86 0 - Ordinary Soil
0+300 20.00 65.19 70.31 1,406.20 - - - - 20.00 22.49 449.80 0.65 13.00 95 1,335.89 5 70.31 0 - Ordinary Soil
0+320 20.00 58.90 62.05 1,241.00 - - - - 20.00 20.64 412.80 0.72 14.40 95 1,178.95 5 62.05 0 - Ordinary Soil
0+340 20.00 37.83 48.37 967.40 - - - - 20.00 10.26 205.20 - - 95 919.03 5 48.37 0 - Ordinary Soil
0+360 20.00 50.96 44.40 888.00 - - - - 20.00 12.70 254.00 0.92 18.40 95 843.60 5 44.40 0 - Ordinary Soil
0+380 20.00 30.62 40.79 815.80 - - - - 20.00 9.65 193.00 - - 95 775.01 5 40.79 0 - Ordinary Soil
0+400 20.00 31.78 31.20 624.00 0.34 0.17 3.40 - 20.00 10.45 209.00 0.91 18.20 95 592.80 5 31.20 0 - Ordinary Soil
0+420 20.00 39.21 35.50 710.00 - 0.17 3.40 - 20.00 12.91 258.20 0.92 18.40 95 674.50 5 35.50 0 - Ordinary Soil
0+440 20.00 32.46 35.84 716.80 1.48 0.74 14.80 - 20.00 12.61 252.20 1.08 21.60 95 680.96 5 35.84 0 - Ordinary Soil
0+460 20.00 26.47 29.47 589.40 0.45 0.97 19.40 - 20.00 11.68 233.60 0.41 8.20 95 559.93 5 29.47 0 - Ordinary Soil
0+480 20.00 36.41 31.44 628.80 - 0.23 4.60 - 20.00 10.72 214.40 - - 95 597.36 5 31.44 0 - Ordinary Soil
0+500 20.00 28.44 32.43 648.60 0.05 0.03 0.60 - 20.00 11.74 234.80 0.56 11.20 95 616.17 5 32.43 0 - Ordinary Soil
0+520 20.00 22.02 25.23 504.60 0.40 0.23 4.60 - 20.00 9.61 192.20 0.27 5.40 95 479.37 5 25.23 0 - Ordinary Soil
0+540 20.00 20.98 21.50 430.00 0.99 0.70 14.00 - 20.00 11.94 238.80 0.95 19.00 95 408.50 5 21.50 0 - Ordinary Soil
0+560 20.00 13.68 17.33 346.60 9.40 5.20 104.00 - 20.00 4.84 96.80 0.52 10.40 95 329.27 5 17.33 0 - Ordinary Soil
0+580 20.00 15.18 14.43 288.60 3.50 6.45 129.00 - 20.00 1.02 20.40 0.01 0.20 95 274.17 5 14.43 0 - Ordinary Soil
0+600 20.00 162.12 88.65 1,773.00 - 1.75 35.00 - 20.00 29.30 586.00 0.89 17.80 95 1,684.35 5 88.65 0 - Ordinary Soil
0+620 20.00 228.19 195.16 3,903.20 - - - - 20.00 96.75 1,935.00 0.70 14.00 95 3,708.04 5 195.16 0 - Ordinary Soil
0+640 20.00 76.68 152.44 3,048.80 - - - - 20.00 32.17 643.40 0.67 13.40 95 2,896.36 5 152.44 0 - Ordinary Soil
0+660 20.00 37.44 57.06 1,141.20 0.02 0.01 0.20 - 20.00 16.82 336.40 22.61 452.20 95 1,084.14 5 57.06 0 - Ordinary Soil
0+680 20.00 33.65 35.55 711.00 8.81 4.42 88.40 - 20.00 2.50 50.00 0.28 5.60 95 675.45 5 35.55 0 - Ordinary Soil
0+700 20.00 34.79 34.22 684.40 2.57 5.69 113.80 - 20.00 5.64 112.80 1.40 28.00 95 650.18 5 34.22 0 - Ordinary Soil
0+720 20.00 47.91 41.35 827.00 0.32 1.45 29.00 - 20.00 3.25 65.00 0.61 12.20 95 785.65 5 41.35 0 - Ordinary Soil
0+740 20.00 49.90 48.91 978.20 0.42 0.37 7.40 - 20.00 2.77 55.40 0.51 10.20 95 929.29 5 48.91 0 - Ordinary Soil
15 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
0+760 20.00 40.22 45.06 901.20 1.59 1.01 20.20 - 20.00 1.65 33.00 0.17 3.40 95 856.14 5 45.06 0 - Ordinary Soil
0+780 20.00 44.72 42.47 849.40 0.45 1.02 20.40 - 10.00 3.10 31.00 0.53 5.30 95 806.93 5 42.47 0 - Ordinary Soil
0+800 20.00 95.30 70.01 1,400.20 - 0.23 4.60 - - - - - - 95 1,330.19 5 70.01 0 - Ordinary Soil
0+820 20.00 138.92 117.11 2,342.20 - - - - - - - - - 95 2,225.09 5 117.11 0 - Ordinary Soil
0+840 20.00 153.93 146.43 2,928.60 - - - - 10.00 42.59 425.90 0.67 6.70 95 2,782.17 5 146.43 0 - Ordinary Soil
0+860 20.00 237.90 195.92 3,918.40 - - - - 20.00 85.93 1,718.60 3.11 62.20 95 3,722.48 5 195.92 0 - Ordinary Soil
0+880 20.00 310.62 274.26 5,485.20 - - - - 20.00 122.95 2,459.00 1.64 32.80 95 5,210.94 5 274.26 0 - Ordinary Soil
0+900 20.00 293.76 302.19 6,043.80 - - - - 20.00 128.93 2,578.60 1.78 35.60 95 5,741.61 5 302.19 0 - Ordinary Soil
0+920 20.00 279.62 286.69 5,733.80 - - - - 20.00 119.61 2,392.20 1.63 32.60 95 5,447.11 5 286.69 0 - Ordinary Soil
0+940 20.00 297.02 288.32 5,766.40 0.01 0.01 0.20 - 20.00 150.20 3,004.00 1.38 27.60 95 5,478.08 5 288.32 0 - Ordinary Soil
0+960 20.00 276.33 286.68 5,733.60 0.01 0.01 0.20 - 20.00 131.19 2,623.80 1.38 27.60 95 5,446.92 5 286.68 0 - Ordinary Soil
0+980 20.00 231.89 254.11 5,082.20 - 0.01 0.20 - 10.00 120.91 1,209.10 1.36 13.60 95 4,828.09 5 254.11 0 - Ordinary Soil
1+000 20.00 345.53 288.71 5,774.20 - - - - - - - - - 95 5,485.49 5 288.71 0 - Ordinary Soil
1+020 20.00 321.47 333.50 6,670.00 - - - - - - - - - 95 6,336.50 5 333.50 0 - Ordinary Soil
1+040 20.00 275.52 298.50 5,970.00 - - - - - - - - - 95 5,671.50 5 298.50 0 - Ordinary Soil
1+060 20.00 263.11 269.32 5,386.40 - - - - - - - - - 95 5,117.08 5 269.32 0 - Ordinary Soil
1+080 20.00 212.02 237.57 4,751.40 - - - - - - - - - 95 4,513.83 5 237.57 0 - Ordinary Soil
1+100 20.00 194.68 203.35 4,067.00 - - - - - - - - - 95 3,863.65 5 203.35 0 - Ordinary Soil
1+120 20.00 121.49 158.09 3,161.80 - - - - - - - - - 95 3,003.71 5 158.09 0 - Ordinary Soil
1+140 20.00 79.73 100.61 2,012.20 - - - - - - - - - 95 1,911.59 5 100.61 0 - Ordinary Soil
1+160 20.00 58.33 69.03 1,380.60 - - - - - - - - - 95 1,311.57 5 69.03 0 - Ordinary Soil
1+180 20.00 57.48 57.91 1,158.20 - - - - - - - - - 95 1,100.29 5 57.91 0 - Ordinary Soil
1+200 20.00 24.80 41.14 822.80 0.97 0.49 9.80 - 10.00 2.36 23.60 0.33 3.30 95 781.66 5 41.14 0 - Ordinary Soil
1+220 20.00 18.52 21.66 433.20 0.30 0.64 12.80 - 20.00 3.56 71.20 0.67 13.40 95 411.54 5 21.66 0 - Ordinary Soil
1+240 20.00 12.46 15.49 309.80 0.61 0.46 9.20 - 20.00 2.60 52.00 0.42 8.40 95 294.31 5 15.49 0 - Ordinary Soil
1+260 20.00 13.86 13.16 263.20 3.98 2.30 46.00 - 20.00 3.95 79.00 0.64 12.80 95 250.04 5 13.16 0 - Ordinary Soil
1+280 20.00 11.15 12.51 250.20 3.40 3.69 73.80 - 20.00 2.18 43.60 0.48 9.60 95 237.69 5 12.51 0 - Ordinary Soil
1+300 20.00 1.04 6.10 122.00 0.49 1.95 39.00 - 10.00 6.37 63.70 1.75 17.50 95 115.90 5 6.10 0 - Ordinary Soil
1+320 20.00 23.99 12.52 250.40 0.15 0.32 6.40 - - - - - - 95 237.88 5 12.52 0 - Ordinary Soil
1+340 20.00 51.97 37.98 759.60 - 0.08 1.60 - - - - - - 95 721.62 5 37.98 0 - Ordinary Soil
1+360 20.00 18.19 35.08 701.60 0.19 0.10 2.00 - - - - - - 95 666.52 5 35.08 0 - Ordinary Soil
1+380 20.00 14.38 16.29 325.80 11.81 6.00 120.00 - 10.00 5.24 52.40 0.72 7.20 95 309.51 5 16.29 0 - Ordinary Soil
1+400 20.00 2.14 8.26 165.20 10.44 11.13 222.60 57.40 10.00 0.50 5.00 - - 95 156.94 5 8.26 0 - Ordinary Soil
1+420 20.00 52.71 27.43 548.60 - 5.22 104.40 - - - - - - 95 521.17 5 27.43 0 - Ordinary Soil
1+440 20.00 52.42 52.57 1,051.40 0.02 0.01 0.20 - - - - - - 95 998.83 5 52.57 0 - Ordinary Soil
1+460 20.00 0.08 26.25 525.00 5.99 3.01 60.20 - 7.00 1.30 9.10 0.01 0.07 95 498.75 5 26.25 0 - Ordinary Soil
1+480 20.00 - 0.04 0.80 5.81 5.90 118.00 117.20 - - - - - 95 0.76 5 0.04 0 - Ordinary Soil
1+500 20.00 - - - 6.21 6.01 120.20 120.20 7.00 0.87 6.09 0.11 0.77 95 - 5 - 0 - Ordinary Soil
1+520 20.00 1.07 0.54 10.80 1.88 4.05 81.00 70.20 - - - - - 95 10.26 5 0.54 0 - Ordinary Soil
1+540 20.00 2.89 1.98 39.60 4.65 3.27 65.40 25.80 - - - - - 95 37.62 5 1.98 0 - Ordinary Soil
1+560 20.00 0.84 1.87 37.40 3.77 4.21 84.20 46.80 - - - - - 95 35.53 5 1.87 0 - Ordinary Soil
1+580 20.00 14.20 7.52 150.40 - 1.89 37.80 - - - - - - 95 142.88 5 7.52 0 - Ordinary Soil
1+600 20.00 16.13 15.17 303.40 - - - - - - - - - 95 288.23 5 15.17 0 - Ordinary Soil
16 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
1+620 20.00 25.34 20.74 414.80 - - - - - - - - - 95 394.06 5 20.74 0 - Ordinary Soil
1+640 20.00 35.76 30.55 611.00 - - - - - - - - - 95 580.45 5 30.55 0 - Ordinary Soil
1+660 20.00 58.92 47.34 946.80 - - - - - - - - - 95 899.46 5 47.34 0 - Ordinary Soil
1+680 20.00 82.18 70.55 1,411.00 - - - - - - - - - 95 1,340.45 5 70.55 0 - Ordinary Soil
1+700 20.00 100.98 91.58 1,831.60 - - - - - - - - - 95 1,740.02 5 91.58 0 - Ordinary Soil
1+720 20.00 77.10 89.04 1,780.80 - - - - - - - - - 95 1,691.76 5 89.04 0 - Ordinary Soil
1+740 20.00 49.35 63.23 1,264.60 - - - - - - - - - 95 1,201.37 5 63.23 0 - Ordinary Soil
1+760 20.00 61.09 55.22 1,104.40 0.01 0.01 0.20 - - - - - - 95 1,049.18 5 55.22 0 - Ordinary Soil
1+780 20.00 88.78 74.94 1,498.80 - 0.01 0.20 - - - - - - 95 1,423.86 5 74.94 0 - Ordinary Soil
1+800 20.00 107.27 98.03 1,960.60 - - - - - - - - - 95 1,862.57 5 98.03 0 - Ordinary Soil
1+820 20.00 113.79 110.53 2,210.60 - - - - - - - - - 95 2,100.07 5 110.53 0 - Ordinary Soil
1+840 20.00 154.97 134.38 2,687.60 - - - - - - - - - 95 2,553.22 5 134.38 0 - Ordinary Soil
1+860 20.00 156.59 155.78 3,115.60 - - - - - - - - - 95 2,959.82 5 155.78 0 - Ordinary Soil
1+880 20.00 110.88 133.74 2,674.80 - - - - - - - - - 95 2,541.06 5 133.74 0 - Ordinary Soil
1+900 20.00 67.68 89.28 1,785.60 - - - - - - - - - 95 1,696.32 5 89.28 0 - Ordinary Soil
1+920 20.00 100.35 84.02 1,680.40 - - - - - - - - - 95 1,596.38 5 84.02 0 - Ordinary Soil
1+940 20.00 123.37 111.86 2,237.20 - - - - - - - - - 95 2,125.34 5 111.86 0 - Ordinary Soil
1+960 20.00 159.77 141.57 2,831.40 - - - - - - - - - 95 2,689.83 5 141.57 0 - Ordinary Soil
1+980 20.00 175.08 167.43 3,348.60 - - - - - - - - - 95 3,181.17 5 167.43 0 - Ordinary Soil
2+000 20.00 144.55 159.82 3,196.40 - - - - - - - - - 95 3,036.58 5 159.82 0 - Ordinary Soil
2+020 20.00 144.11 144.33 2,886.60 - - - - - - - - - 95 2,742.27 5 144.33 0 - Ordinary Soil
2+040 20.00 129.39 136.75 2,735.00 - - - - - - - - - 95 2,598.25 5 136.75 0 - Ordinary Soil
2+060 20.00 105.61 117.50 2,350.00 - - - - - - - - - 95 2,232.50 5 117.50 0 - Ordinary Soil
2+080 20.00 103.29 104.45 2,089.00 - - - - - - - - - 95 1,984.55 5 104.45 0 - Ordinary Soil
2+100 20.00 95.25 99.27 1,985.40 - - - - - - - - - 95 1,886.13 5 99.27 0 - Ordinary Soil
2+120 20.00 109.40 102.33 2,046.60 - - - - - - - - - 95 1,944.27 5 102.33 0 - Ordinary Soil
2+140 20.00 89.26 99.33 1,986.60 - - - - - - - - - 95 1,887.27 5 99.33 0 - Ordinary Soil
2+160 20.00 72.88 81.07 1,621.40 - - - - - - - - - 95 1,540.33 5 81.07 0 - Ordinary Soil
2+180 20.00 185.75 129.32 2,586.40 - - - - - - - - - 95 2,457.08 5 129.32 0 - Ordinary Soil
2+200 20.00 163.89 174.82 3,496.40 - - - - 10.00 37.62 376.20 0.67 6.70 95 3,321.58 5 174.82 0 - Ordinary Soil
2+220 20.00 100.35 132.12 2,642.40 - - - - 20.00 22.38 447.60 0.66 13.20 95 2,510.28 5 132.12 0 - Ordinary Soil
2+240 20.00 79.37 89.86 1,797.20 - - - - 20.00 16.75 335.00 0.74 14.80 95 1,707.34 5 89.86 0 - Ordinary Soil
2+260 20.00 81.95 80.66 1,613.20 - - - - 10.00 17.44 174.40 0.86 8.60 95 1,532.54 5 80.66 0 - Ordinary Soil
2+280 20.00 102.26 92.11 1,842.20 - - - - - - - - - 95 1,750.09 5 92.11 0 - Ordinary Soil
2+300 20.00 97.16 99.71 1,994.20 - - - - - - - - - 95 1,894.49 5 99.71 0 - Ordinary Soil
2+320 20.00 74.89 86.03 1,720.60 - - - - - - - - - 95 1,634.57 5 86.03 0 - Ordinary Soil
2+340 20.00 47.05 60.97 1,219.40 - - - - - - - - - 95 1,158.43 5 60.97 0 - Ordinary Soil
2+360 20.00 53.77 50.41 1,008.20 - - - - - - - - - 95 957.79 5 50.41 0 - Ordinary Soil
2+380 20.00 46.84 50.31 1,006.20 - - - - - - - - - 95 955.89 5 50.31 0 - Ordinary Soil
2+400 20.00 38.90 42.87 857.40 0.01 0.01 0.20 - - - - - - 95 814.53 5 42.87 0 - Ordinary Soil
2+420 20.00 17.92 28.41 568.20 0.02 0.02 0.40 - - - - - - 95 539.79 5 28.41 0 - Ordinary Soil
2+440 20.00 4.49 11.21 224.20 1.17 0.60 12.00 - 10.00 1.38 13.80 0.29 2.90 95 212.99 5 11.21 0 - Ordinary Soil
2+460 20.00 2.07 3.28 65.60 4.81 2.99 59.80 - 20.00 1.32 26.40 0.21 4.20 95 62.32 5 3.28 0 - Ordinary Soil
17 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
2+480 20.00 10.85 6.46 129.20 3.31 4.06 81.20 - 10.00 1.53 15.30 0.27 2.70 95 122.74 5 6.46 0 - Ordinary Soil
2+500 20.00 151.63 81.24 1,624.80 - 1.66 33.20 - - - - - - 95 1,543.56 5 81.24 0 - Ordinary Soil
2+520 20.00 170.48 161.06 3,221.20 - - - - - - - - - 95 3,060.14 5 161.06 0 - Ordinary Soil
2+540 20.00 117.23 143.86 2,877.20 - - - - - - - - - 95 2,733.34 5 143.86 0 - Ordinary Soil
2+560 20.00 67.05 92.14 1,842.80 - - - - - - - - - 95 1,750.66 5 92.14 0 - Ordinary Soil
2+580 20.00 42.53 54.79 1,095.80 - - - - - - - - - 95 1,041.01 5 54.79 0 - Ordinary Soil
2+600 20.00 18.93 30.73 614.60 - - - - - - - - - 95 583.87 5 30.73 0 - Ordinary Soil
2+620 20.00 3.51 11.22 224.40 2.66 1.33 26.60 - 10.00 1.72 17.20 0.36 3.60 95 213.18 5 11.22 0 - Ordinary Soil
2+640 20.00 0.53 2.02 40.40 6.20 4.43 88.60 48.20 10.00 2.73 27.30 0.58 5.80 95 38.38 5 2.02 0 - Ordinary Soil
2+660 20.00 9.09 4.81 96.20 10.16 8.18 163.60 67.40 - - - - - 95 91.39 5 4.81 0 - Ordinary Soil
2+680 20.00 30.06 19.58 391.60 - 5.08 101.60 - - - - - - 95 372.02 5 19.58 0 - Ordinary Soil
2+700 20.00 37.67 33.87 677.40 - - - - - - - - - 95 643.53 5 33.87 0 - Ordinary Soil
2+720 20.00 27.98 32.83 656.60 - - - - - - - - - 95 623.77 5 32.83 0 - Ordinary Soil
2+740 20.00 17.21 22.60 452.00 0.27 0.14 2.80 - 10.00 1.54 15.40 0.37 3.70 95 429.40 5 22.60 0 - Ordinary Soil
2+760 20.00 9.28 13.25 265.00 2.79 1.53 30.60 - 20.00 2.53 50.60 0.56 11.20 95 251.75 5 13.25 0 - Ordinary Soil
2+780 20.00 3.37 6.33 126.60 2.37 2.58 51.60 - 20.00 1.65 33.00 0.43 8.60 95 120.27 5 6.33 0 - Ordinary Soil
2+800 20.00 10.54 6.96 139.20 1.10 1.74 34.80 - 20.00 0.99 19.80 0.17 3.40 95 132.24 5 6.96 0 - Ordinary Soil
2+820 20.00 7.11 8.83 176.60 6.20 3.65 73.00 - 20.00 5.21 104.20 0.84 16.80 95 167.77 5 8.83 0 - Ordinary Soil
2+840 20.00 5.91 6.51 130.20 5.88 6.04 120.80 - 20.00 2.43 48.60 0.24 4.80 95 123.69 5 6.51 0 - Ordinary Soil
2+860 20.00 14.03 9.97 199.40 10.45 8.17 163.40 - 10.00 13.23 132.30 3.19 31.90 95 189.43 5 9.97 0 - Ordinary Soil
2+880 20.00 36.42 25.23 504.60 1.98 6.22 124.40 - - - - - - 95 479.37 5 25.23 0 - Ordinary Soil
2+900 20.00 49.06 42.74 854.80 - 0.99 19.80 - - - - - - 95 812.06 5 42.74 0 - Ordinary Soil
2+920 20.00 51.49 50.28 1,005.60 - - - - - - - - - 95 955.32 5 50.28 0 - Ordinary Soil
2+940 20.00 28.97 40.23 804.60 4.13 2.07 41.40 - 10.00 5.04 50.40 0.98 9.80 95 764.37 5 40.23 0 - Ordinary Soil
2+960 20.00 38.93 33.95 679.00 3.16 3.65 73.00 - 10.00 6.65 66.50 1.40 14.00 95 645.05 5 33.95 0 - Ordinary Soil
2+980 20.00 174.52 106.73 2,134.60 - 1.58 31.60 - - - - - - 95 2,027.87 5 106.73 0 - Ordinary Soil
3+000 20.00 217.17 195.85 3,917.00 - - - - 10.00 83.38 833.80 0.69 6.90 95 3,721.15 5 195.85 0 - Ordinary Soil
3+020 20.00 205.49 211.33 4,226.60 - - - - 20.00 53.42 1,068.40 0.69 13.80 95 4,015.27 5 211.33 0 - Ordinary Soil
3+040 20.00 115.05 160.27 3,205.40 - - - - 20.00 29.28 585.60 0.66 13.20 95 3,045.13 5 160.27 0 - Ordinary Soil
3+060 20.00 61.81 88.43 1,768.60 - - - - 20.00 26.46 529.20 0.80 16.00 95 1,680.17 5 88.43 0 - Ordinary Soil
3+080 20.00 61.54 61.68 1,233.60 - - - - 20.00 26.45 529.00 0.66 13.20 95 1,171.92 5 61.68 0 - Ordinary Soil
3+100 20.00 92.79 77.17 1,543.40 - - - - 20.00 25.03 500.60 0.66 13.20 95 1,466.23 5 77.17 0 - Ordinary Soil
3+120 20.00 99.40 96.10 1,922.00 - - - - 20.00 27.10 542.00 0.66 13.20 95 1,825.90 5 96.10 0 - Ordinary Soil
3+140 20.00 89.59 94.50 1,890.00 0.01 0.01 0.20 - 20.00 27.48 549.60 0.65 13.00 95 1,795.50 5 94.50 0 - Ordinary Soil
3+160 20.00 75.86 82.73 1,654.60 - 0.01 0.20 - 10.00 27.96 279.60 0.66 6.60 95 1,571.87 5 82.73 0 - Ordinary Soil
3+180 20.00 88.64 82.25 1,645.00 - - - - - - - - - 95 1,562.75 5 82.25 0 - Ordinary Soil
3+200 20.00 64.36 76.50 1,530.00 - - - - - - - - - 95 1,453.50 5 76.50 0 - Ordinary Soil
3+220 20.00 60.69 62.53 1,250.60 - - - - - - - - - 95 1,188.07 5 62.53 0 - Ordinary Soil
3+240 20.00 39.86 50.28 1,005.60 0.34 0.17 3.40 - - - - - - 95 955.32 5 50.28 0 - Ordinary Soil
3+260 20.00 42.04 40.95 819.00 - 0.17 3.40 - - - - - - 95 778.05 5 40.95 0 - Ordinary Soil
3+280 20.00 30.90 36.47 729.40 0.34 0.17 3.40 - 10.00 1.26 12.60 0.29 2.90 95 692.93 5 36.47 0 - Ordinary Soil
3+300 20.00 16.66 23.78 475.60 1.92 1.13 22.60 - 20.00 2.96 59.20 0.81 16.20 95 451.82 5 23.78 0 - Ordinary Soil
3+320 20.00 13.05 14.86 297.20 1.33 1.63 32.60 - 20.00 1.90 38.00 0.48 9.60 95 282.34 5 14.86 0 - Ordinary Soil
18 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
3+340 20.00 16.63 14.84 296.80 0.12 0.73 14.60 - 20.00 1.69 33.80 0.46 9.20 95 281.96 5 14.84 0 - Ordinary Soil
3+360 20.00 18.38 17.51 350.20 1.88 1.00 20.00 - 20.00 3.58 71.60 1.06 21.20 95 332.69 5 17.51 0 - Ordinary Soil
3+380 20.00 22.09 20.24 404.80 0.06 0.97 19.40 - 20.00 1.33 26.60 0.34 6.80 95 384.56 5 20.24 0 - Ordinary Soil
3+400 20.00 24.67 23.38 467.60 2.85 1.46 29.20 - 10.00 1.74 17.40 0.38 3.80 95 444.22 5 23.38 0 - Ordinary Soil
3+420 20.00 52.51 38.59 771.80 - 1.43 28.60 - - - - - - 95 733.21 5 38.59 0 - Ordinary Soil
3+440 20.00 36.60 44.56 891.20 1.00 0.50 10.00 - 10.00 1.98 19.80 0.29 2.90 95 846.64 5 44.56 0 - Ordinary Soil
3+460 20.00 31.08 33.84 676.80 0.08 0.54 10.80 - 10.00 1.65 16.50 0.48 4.80 95 642.96 5 33.84 0 - Ordinary Soil
3+480 20.00 48.47 39.78 795.60 - 0.04 0.80 - - - - - - 95 755.82 5 39.78 0 - Ordinary Soil
3+500 20.00 47.47 47.97 959.40 - - - - - - - - - 95 911.43 5 47.97 0 - Ordinary Soil
3+520 20.00 60.63 54.05 1,081.00 - - - - - - - - - 95 1,026.95 5 54.05 0 - Ordinary Soil
3+540 20.00 48.08 54.36 1,087.20 2.02 1.01 20.20 - - - - - - 95 1,032.84 5 54.36 0 - Ordinary Soil
3+560 20.00 56.47 52.28 1,045.60 - 1.01 20.20 - - - - - - 95 993.32 5 52.28 0 - Ordinary Soil
3+580 20.00 41.40 48.94 978.80 - - - - - - - - - 95 929.86 5 48.94 0 - Ordinary Soil
3+600 20.00 10.59 26.00 520.00 0.70 0.35 7.00 - 7.00 0.62 4.34 0.08 0.56 95 494.00 5 26.00 0 - Ordinary Soil
3+620 20.00 56.69 33.64 672.80 - 0.35 7.00 - - - - - - 95 639.16 5 33.64 0 - Ordinary Soil
3+640 20.00 250.82 153.76 3,075.20 - - - - - - - - - 95 2,921.44 5 153.76 0 - Ordinary Soil
3+660 20.00 258.46 254.64 5,092.80 - - - - - - - - - 95 4,838.16 5 254.64 0 - Ordinary Soil
3+680 20.00 142.50 200.48 4,009.60 - - - - 10.00 52.56 525.60 0.69 6.90 95 3,809.12 5 200.48 0 - Ordinary Soil
3+700 20.00 184.31 163.41 3,268.20 - - - - 20.00 47.46 949.20 0.76 15.20 95 3,104.79 5 163.41 0 - Ordinary Soil
3+720 20.00 118.76 151.54 3,030.80 - - - - 20.00 39.96 799.20 0.67 13.40 95 2,879.26 5 151.54 0 - Ordinary Soil
3+740 20.00 156.46 137.61 2,752.20 - - - - 20.00 42.14 842.80 0.67 13.40 95 2,614.59 5 137.61 0 - Ordinary Soil
3+760 20.00 128.40 142.43 2,848.60 - - - - 20.00 38.97 779.40 0.67 13.40 95 2,706.17 5 142.43 0 - Ordinary Soil
3+780 20.00 111.15 119.78 2,395.60 - - - - 20.00 28.23 564.60 0.65 13.00 95 2,275.82 5 119.78 0 - Ordinary Soil
3+800 20.00 107.07 109.11 2,182.20 - - - - 20.00 24.91 498.20 0.80 16.00 95 2,073.09 5 109.11 0 - Ordinary Soil
3+820 20.00 74.88 90.98 1,819.60 - - - - 20.00 23.38 467.60 0.80 16.00 95 1,728.62 5 90.98 0 - Ordinary Soil
3+840 20.00 94.23 84.56 1,691.20 - - - - 20.00 23.64 472.80 0.66 13.20 95 1,606.64 5 84.56 0 - Ordinary Soil
3+860 20.00 91.92 93.08 1,861.60 - - - - 20.00 22.04 440.80 0.68 13.60 95 1,768.52 5 93.08 0 - Ordinary Soil
3+880 20.00 116.26 104.09 2,081.80 - - - - 10.00 22.63 226.30 0.64 6.40 95 1,977.71 5 104.09 0 - Ordinary Soil
3+900 20.00 110.29 113.28 2,265.60 - - - - - - - - - 95 2,152.32 5 113.28 0 - Ordinary Soil
3+920 20.00 107.17 108.73 2,174.60 - - - - - - - - - 95 2,065.87 5 108.73 0 - Ordinary Soil
3+940 20.00 103.29 105.23 2,104.60 - - - - - - - - - 95 1,999.37 5 105.23 0 - Ordinary Soil
3+960 20.00 76.06 89.68 1,793.60 0.01 0.01 0.20 - - - - - - 95 1,703.92 5 89.68 0 - Ordinary Soil
3+980 20.00 49.29 62.68 1,253.60 - 0.01 0.20 - - - - - - 95 1,190.92 5 62.68 0 - Ordinary Soil
4+000 20.00 75.34 62.32 1,246.40 3.70 1.85 37.00 - 10.00 43.38 433.80 1.45 14.50 95 1,184.08 5 62.32 0 - Ordinary Soil
4+020 20.00 25.01 50.18 1,003.60 6.45 5.08 101.60 - 20.00 20.19 403.80 2.05 41.00 95 953.42 5 50.18 0 - Ordinary Soil
4+040 20.00 19.13 22.07 441.40 1.14 3.80 76.00 - 20.00 4.77 95.40 1.00 20.00 95 419.33 5 22.07 0 - Ordinary Soil
4+060 20.00 9.61 14.37 287.40 2.44 1.79 35.80 - 20.00 3.26 65.20 0.52 10.40 95 273.03 5 14.37 0 - Ordinary Soil
4+080 20.00 9.28 9.45 189.00 7.89 5.17 103.40 - 10.00 3.58 35.80 0.47 4.70 95 179.55 5 9.45 0 - Ordinary Soil
4+100 20.00 8.07 8.68 173.60 9.19 8.54 170.80 - - - - - - 95 164.92 5 8.68 0 - Ordinary Soil
4+120 20.00 8.49 8.28 165.60 9.32 9.26 185.20 19.60 10.00 6.46 64.60 1.18 11.80 95 157.32 5 8.28 0 - Ordinary Soil
4+140 20.00 33.26 20.88 417.60 1.42 5.37 107.40 - 10.00 4.38 43.80 0.91 9.10 95 396.72 5 20.88 0 - Ordinary Soil
4+160 20.00 51.66 42.46 849.20 - 0.71 14.20 - - - - - - 95 806.74 5 42.46 0 - Ordinary Soil
4+180 20.00 32.83 42.25 845.00 2.88 1.44 28.80 - 10.00 6.58 65.80 1.46 14.60 95 802.75 5 42.25 0 - Ordinary Soil
19 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
4+200 20.00 66.73 49.78 995.60 0.34 1.61 32.20 - 10.00 6.04 60.40 1.65 16.50 95 945.82 5 49.78 0 - Ordinary Soil
4+220 20.00 89.37 78.05 1,561.00 - 0.17 3.40 - - - - - - 95 1,482.95 5 78.05 0 - Ordinary Soil
4+240 20.00 81.76 85.57 1,711.40 - - - - - - - - - 95 1,625.83 5 85.57 0 - Ordinary Soil
4+260 20.00 125.55 103.66 2,073.20 - - - - - - - - - 95 1,969.54 5 103.66 0 - Ordinary Soil
4+280 20.00 200.55 163.05 3,261.00 - - - - 10.00 53.30 533.00 0.69 6.90 95 3,097.95 5 163.05 0 - Ordinary Soil
4+300 20.00 203.66 202.11 4,042.20 - - - - 20.00 52.81 1,056.20 0.83 16.60 95 3,840.09 5 202.11 0 - Ordinary Soil
4+320 20.00 206.31 204.99 4,099.80 - - - - 20.00 65.34 1,306.80 0.69 13.80 95 3,894.81 5 204.99 0 - Ordinary Soil
4+340 20.00 219.72 213.02 4,260.40 - - - - 20.00 72.04 1,440.80 0.65 13.00 95 4,047.38 5 213.02 0 - Ordinary Soil
4+360 20.00 202.62 211.17 4,223.40 - - - - 20.00 115.57 2,311.40 0.69 13.80 95 4,012.23 5 211.17 0 - Ordinary Soil
4+380 20.00 200.91 201.77 4,035.40 - - - - 20.00 139.15 2,783.00 1.57 31.40 95 3,833.63 5 201.77 0 - Ordinary Soil
4+400 20.00 218.48 209.70 4,194.00 - - - - 20.00 153.98 3,079.60 1.54 30.80 95 3,984.30 5 209.70 0 - Ordinary Soil
4+420 20.00 232.37 225.43 4,508.60 - - - - 20.00 172.39 3,447.80 1.56 31.20 95 4,283.17 5 225.43 0 - Ordinary Soil
4+440 20.00 306.43 269.40 5,388.00 - - - - 20.00 210.66 4,213.20 1.82 36.40 95 5,118.60 5 269.40 0 - Ordinary Soil
4+460 20.00 298.77 302.60 6,052.00 - - - - 20.00 215.08 4,301.60 2.77 55.40 95 5,749.40 5 302.60 0 - Ordinary Soil
4+480 20.00 295.45 297.11 5,942.20 - - - - 20.00 281.57 5,631.40 8.25 165.00 95 5,645.09 5 297.11 0 - Ordinary Soil
4+500 20.00 260.18 277.82 5,556.40 - - - - 20.00 259.13 5,182.60 5.25 105.00 95 5,278.58 5 277.82 0 - Ordinary Soil
4+520 20.00 258.77 259.48 5,189.60 - - - - 20.00 244.79 4,895.80 4.08 81.60 95 4,930.12 5 259.48 0 - Ordinary Soil
4+540 20.00 231.29 245.03 4,900.60 - - - - 20.00 178.69 3,573.80 1.43 28.60 95 4,655.57 5 245.03 0 - Ordinary Soil
4+560 20.00 211.65 221.47 4,429.40 - - - - 20.00 154.59 3,091.80 1.58 31.60 95 4,207.93 5 221.47 0 - Ordinary Soil
4+580 20.00 244.69 228.17 4,563.40 - - - - 20.00 118.88 2,377.60 1.55 31.00 95 4,335.23 5 228.17 0 - Ordinary Soil
4+600 20.00 259.51 252.10 5,042.00 0.01 0.01 0.20 - 20.00 130.27 2,605.40 1.56 31.20 95 4,789.90 5 252.10 0 - Ordinary Soil
4+620 20.00 227.96 243.74 4,874.80 - 0.01 0.20 - 20.00 157.72 3,154.40 1.58 31.60 95 4,631.06 5 243.74 0 - Ordinary Soil
4+640 20.00 218.73 223.35 4,467.00 - - - - 20.00 185.16 3,703.20 16.28 325.60 95 4,243.65 5 223.35 0 - Ordinary Soil
4+660 20.00 281.15 249.94 4,998.80 - - - - 20.00 214.23 4,284.60 33.65 673.00 95 4,748.86 5 249.94 0 - Ordinary Soil
4+680 20.00 249.00 265.08 5,301.60 - - - - 20.00 194.84 3,896.80 7.42 148.40 95 5,036.52 5 265.08 0 - Ordinary Soil
4+700 20.00 206.26 227.63 4,552.60 - - - - 20.00 148.30 2,966.00 0.65 13.00 95 4,324.97 5 227.63 0 - Ordinary Soil
4+720 20.00 186.46 196.36 3,927.20 - - - - 20.00 142.17 2,843.40 2.66 53.20 95 3,730.84 5 196.36 0 - Ordinary Soil
4+740 20.00 167.18 176.82 3,536.40 - - - - 20.00 106.52 2,130.40 1.57 31.40 95 3,359.58 5 176.82 0 - Ordinary Soil
4+760 20.00 167.75 167.47 3,349.40 - - - - 20.00 70.37 1,407.40 0.65 13.00 95 3,181.93 5 167.47 0 - Ordinary Soil
4+780 20.00 179.27 173.51 3,470.20 - - - - 20.00 51.38 1,027.60 0.64 12.80 95 3,296.69 5 173.51 0 - Ordinary Soil
4+800 20.00 175.99 177.63 3,552.60 - - - - 20.00 45.61 912.20 0.65 13.00 95 3,374.97 5 177.63 0 - Ordinary Soil
4+820 20.00 175.79 175.89 3,517.80 - - - - 20.00 52.33 1,046.60 0.73 14.60 95 3,341.91 5 175.89 0 - Ordinary Soil
4+840 20.00 120.58 148.19 2,963.80 - - - - 20.00 37.41 748.20 0.68 13.60 95 2,815.61 5 148.19 0 - Ordinary Soil
4+860 20.00 79.92 100.25 2,005.00 - - - - 20.00 20.61 412.20 0.89 17.80 95 1,904.75 5 100.25 0 - Ordinary Soil
4+880 20.00 57.07 68.50 1,370.00 - - - - 20.00 14.16 283.20 0.93 18.60 95 1,301.50 5 68.50 0 - Ordinary Soil
4+900 20.00 35.56 46.32 926.40 - - - - 20.00 9.59 191.80 0.90 18.00 95 880.08 5 46.32 0 - Ordinary Soil
4+920 20.00 35.93 35.75 715.00 - - - - 20.00 10.57 211.40 1.00 20.00 95 679.25 5 35.75 0 - Ordinary Soil
4+940 20.00 25.31 30.62 612.40 0.27 0.14 2.80 - 20.00 8.25 165.00 - - 95 581.78 5 30.62 0 - Ordinary Soil
4+960 20.00 28.46 26.89 537.80 0.19 0.23 4.60 - 20.00 8.11 162.20 0.91 18.20 95 510.91 5 26.89 0 - Ordinary Soil
4+980 20.00 25.88 27.17 543.40 - 0.10 2.00 - 20.00 7.70 154.00 - - 95 516.23 5 27.17 0 - Ordinary Soil
5+000 20.00 22.68 24.28 485.60 0.39 0.20 4.00 - 20.00 8.81 176.20 0.27 5.40 95 461.32 5 24.28 0 - Ordinary Soil
5+020 20.00 30.63 26.66 533.20 - 0.20 4.00 - 20.00 8.06 161.20 1.04 20.80 95 506.54 5 26.66 0 - Ordinary Soil
5+040 20.00 37.61 34.12 682.40 - - - - 20.00 10.64 212.80 1.05 21.00 95 648.28 5 34.12 0 - Ordinary Soil
20 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
5+060 20.00 33.66 35.64 712.80 - - - - 20.00 8.78 175.60 1.05 21.00 95 677.16 5 35.64 0 - Ordinary Soil
5+080 20.00 63.05 48.36 967.20 - - - - 20.00 21.18 423.60 0.76 15.20 95 918.84 5 48.36 0 - Ordinary Soil
5+100 20.00 81.17 72.11 1,442.20 - - - - 20.00 25.60 512.00 0.78 15.60 95 1,370.09 5 72.11 0 - Ordinary Soil
5+120 20.00 70.93 76.05 1,521.00 - - - - 20.00 28.04 560.80 0.89 17.80 95 1,444.95 5 76.05 0 - Ordinary Soil
5+140 20.00 62.91 66.92 1,338.40 - - - - 20.00 18.52 370.40 0.77 15.40 95 1,271.48 5 66.92 0 - Ordinary Soil
5+160 20.00 75.18 69.05 1,381.00 0.01 0.01 0.20 - 20.00 26.26 525.20 0.92 18.40 95 1,311.95 5 69.05 0 - Ordinary Soil
5+180 20.00 55.74 65.46 1,309.20 - 0.01 0.20 - 10.00 14.64 146.40 0.86 8.60 95 1,243.74 5 65.46 0 - Ordinary Soil
5+200 20.00 34.16 44.95 899.00 - - - - - - - - - 95 854.05 5 44.95 0 - Ordinary Soil
5+220 20.00 38.99 36.58 731.60 - - - - - - - - - 95 695.02 5 36.58 0 - Ordinary Soil
5+240 20.00 22.46 30.73 614.60 - - - - 10.00 1.11 11.10 0.24 2.40 95 583.87 5 30.73 0 - Ordinary Soil
5+260 20.00 15.41 18.94 378.80 1.55 0.78 15.60 - 20.00 1.97 39.40 0.24 4.80 95 359.86 5 18.94 0 - Ordinary Soil
5+280 20.00 25.00 20.21 404.20 5.71 3.63 72.60 - 20.00 3.61 72.20 0.50 10.00 95 383.99 5 20.21 0 - Ordinary Soil
5+300 20.00 19.68 22.34 446.80 4.98 5.35 107.00 - 20.00 3.61 72.20 0.51 10.20 95 424.46 5 22.34 0 - Ordinary Soil
5+320 20.00 11.98 15.83 316.60 7.29 6.14 122.80 - 20.00 4.59 91.80 0.77 15.40 95 300.77 5 15.83 0 - Ordinary Soil
5+340 20.00 23.04 17.51 350.20 5.99 6.64 132.80 - 20.00 5.65 113.00 1.07 21.40 95 332.69 5 17.51 0 - Ordinary Soil
5+360 20.00 19.21 21.13 422.60 1.83 3.91 78.20 - 10.00 1.27 12.70 0.27 2.70 95 401.47 5 21.13 0 - Ordinary Soil
5+380 20.00 24.89 22.05 441.00 2.08 1.96 39.20 - - - - - - 95 418.95 5 22.05 0 - Ordinary Soil
5+400 20.00 32.03 28.46 569.20 1.57 1.83 36.60 - 10.00 4.18 41.80 0.85 8.50 95 540.74 5 28.46 0 - Ordinary Soil
5+420 20.00 2.55 17.29 345.80 8.60 5.09 101.80 - 20.00 6.14 122.80 1.14 22.80 95 328.51 5 17.29 0 - Ordinary Soil
5+440 20.00 36.68 19.62 392.40 - 4.30 86.00 - 20.00 0.75 15.00 0.12 2.40 95 372.78 5 19.62 0 - Ordinary Soil
5+460 20.00 31.31 34.00 680.00 0.29 0.15 3.00 - 20.00 2.41 48.20 0.76 15.20 95 646.00 5 34.00 0 - Ordinary Soil
5+480 20.00 52.20 41.76 835.20 0.06 0.18 3.60 - 20.00 21.38 427.60 0.89 17.80 95 793.44 5 41.76 0 - Ordinary Soil
5+500 20.00 26.53 39.37 787.40 0.09 0.08 1.60 - 20.00 0.49 9.80 0.07 1.40 95 748.03 5 39.37 0 - Ordinary Soil
5+520 20.00 10.81 18.67 373.40 7.09 3.59 71.80 - 10.00 6.67 66.70 1.37 13.70 95 354.73 5 18.67 0 - Ordinary Soil
5+540 20.00 133.07 71.94 1,438.80 - 3.55 71.00 - - - - - - 95 1,366.86 5 71.94 0 - Ordinary Soil
5+560 20.00 73.92 103.50 2,070.00 0.11 0.06 1.20 - 10.00 2.11 21.10 0.67 6.70 95 1,966.50 5 103.50 0 - Ordinary Soil
5+580 20.00 15.90 44.91 898.20 2.22 1.17 23.40 - 20.00 6.77 135.40 1.63 32.60 95 853.29 5 44.91 0 - Ordinary Soil
5+600 20.00 10.27 13.09 261.80 1.07 1.65 33.00 - 10.00 4.34 43.40 1.00 10.00 95 248.71 5 13.09 0 - Ordinary Soil
5+620 20.00 90.61 50.44 1,008.80 - 0.54 10.80 - - - - - - 95 958.36 5 50.44 0 - Ordinary Soil
5+640 20.00 29.74 60.18 1,203.60 2.93 1.47 29.40 - 10.00 3.45 34.50 0.50 5.00 95 1,143.42 5 60.18 0 - Ordinary Soil
5+660 20.00 35.84 32.79 655.80 6.13 4.53 90.60 - 20.00 6.57 131.40 1.51 30.20 95 623.01 5 32.79 0 - Ordinary Soil
5+680 20.00 23.36 29.60 592.00 6.67 6.40 128.00 - 20.00 16.76 335.20 4.90 98.00 95 562.40 5 29.60 0 - Ordinary Soil
5+700 20.00 22.99 23.18 463.60 7.26 6.97 139.40 - 20.00 20.00 400.00 6.90 138.00 95 440.42 5 23.18 0 - Ordinary Soil
5+720 20.00 - 11.50 230.00 65.54 36.40 728.00 498.00 20.00 8.94 178.80 0.11 2.20 95 218.50 5 11.50 0 - Ordinary Soil
5+740 20.00 47.15 23.58 471.60 0.52 33.03 660.60 189.00 20.00 5.71 114.20 1.51 30.20 95 448.02 5 23.58 0 - Ordinary Soil
5+760 20.00 20.21 33.68 673.60 6.96 3.74 74.80 - 20.00 15.49 309.80 4.35 87.00 95 639.92 5 33.68 0 - Ordinary Soil
5+780 20.00 10.26 15.24 304.80 14.28 10.62 212.40 - 20.00 12.71 254.20 2.80 56.00 95 289.56 5 15.24 0 - Ordinary Soil
5+800 20.00 59.20 34.73 694.60 5.22 9.75 195.00 - 20.00 7.31 146.20 1.72 34.40 95 659.87 5 34.73 0 - Ordinary Soil
5+820 20.00 94.18 76.69 1,533.80 1.84 3.53 70.60 - 20.00 11.80 236.00 3.65 73.00 95 1,457.11 5 76.69 0 - Ordinary Soil
5+840 20.00 30.61 62.40 1,248.00 6.05 3.95 79.00 - 20.00 12.16 243.20 3.21 64.20 95 1,185.60 5 62.40 0 - Ordinary Soil
5+860 20.00 51.01 40.81 816.20 1.66 3.86 77.20 - 20.00 11.62 232.40 3.83 76.60 95 775.39 5 40.81 0 - Ordinary Soil
5+880 20.00 65.31 58.16 1,163.20 0.88 1.27 25.40 - 20.00 4.95 99.00 1.15 23.00 95 1,105.04 5 58.16 0 - Ordinary Soil
5+900 20.00 20.38 42.85 857.00 7.09 3.99 79.80 - 20.00 4.34 86.80 0.50 10.00 95 814.15 5 42.85 0 - Ordinary Soil
21 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
5+920 20.00 11.38 15.88 317.60 9.31 8.20 164.00 - 20.00 2.63 52.60 0.20 4.00 95 301.72 5 15.88 0 - Ordinary Soil
5+940 20.00 81.74 46.56 931.20 - 4.66 93.20 - 20.00 0.51 10.20 0.04 0.80 95 884.64 5 46.56 0 - Ordinary Soil
5+960 20.00 76.61 79.18 1,583.60 0.40 0.20 4.00 - 10.00 2.84 28.40 0.94 9.40 95 1,504.42 5 79.18 0 - Ordinary Soil
5+980 20.00 55.77 66.19 1,323.80 - 0.20 4.00 - - - - - - 95 1,257.61 5 66.19 0 - Ordinary Soil
6+000 20.00 29.22 42.50 850.00 1.44 0.72 14.40 - 10.00 2.93 29.30 0.84 8.40 95 807.50 5 42.50 0 - Ordinary Soil
6+020 20.00 12.19 20.71 414.20 9.44 5.44 108.80 - 20.00 14.89 297.80 3.93 78.60 95 393.49 5 20.71 0 - Ordinary Soil
6+040 20.00 17.81 15.00 300.00 4.75 7.10 142.00 - 20.00 6.00 120.00 1.09 21.80 95 285.00 5 15.00 0 - Ordinary Soil
6+060 20.00 25.96 21.89 437.80 0.60 2.68 53.60 - 20.00 1.30 26.00 0.28 5.60 95 415.91 5 21.89 0 - Ordinary Soil
6+080 20.00 23.45 24.71 494.20 2.24 1.42 28.40 - 20.00 2.33 46.60 0.65 13.00 95 469.49 5 24.71 0 - Ordinary Soil
6+100 20.00 58.70 41.08 821.60 - 1.12 22.40 - 20.00 1.18 23.60 0.23 4.60 95 780.52 5 41.08 0 - Ordinary Soil
6+120 20.00 47.76 53.23 1,064.60 1.40 0.70 14.00 - 20.00 2.45 49.00 0.66 13.20 95 1,011.37 5 53.23 0 - Ordinary Soil
6+140 20.00 53.40 50.58 1,011.60 0.20 0.80 16.00 - 20.00 1.48 29.60 0.39 7.80 95 961.02 5 50.58 0 - Ordinary Soil
6+160 20.00 13.84 33.62 672.40 10.80 5.50 110.00 - 20.00 9.20 184.00 2.12 42.40 95 638.78 5 33.62 0 - Ordinary Soil
6+180 20.00 3.79 8.82 176.40 24.63 17.72 354.40 178.00 20.00 11.73 234.60 2.13 42.60 95 167.58 5 8.82 0 - Ordinary Soil
6+200 20.00 21.70 12.75 255.00 2.91 13.77 275.40 20.40 20.00 5.78 115.60 1.33 26.60 95 242.25 5 12.75 0 - Ordinary Soil
6+220 20.00 14.78 18.24 364.80 5.79 4.35 87.00 - 20.00 4.33 86.60 0.66 13.20 95 346.56 5 18.24 0 - Ordinary Soil
6+240 20.00 28.08 21.43 428.60 0.06 2.93 58.60 - 20.00 1.30 26.00 0.33 6.60 95 407.17 5 21.43 0 - Ordinary Soil
6+260 20.00 11.73 19.91 398.20 5.05 2.56 51.20 - 20.00 2.47 49.40 0.12 2.40 95 378.29 5 19.91 0 - Ordinary Soil
6+280 20.00 0.29 6.01 120.20 7.30 6.18 123.60 3.40 20.00 2.29 45.80 0.20 4.00 95 114.19 5 6.01 0 - Ordinary Soil
6+300 20.00 - 0.15 3.00 16.81 12.06 241.20 238.20 20.00 4.23 84.60 0.51 10.20 95 2.85 5 0.15 0 - Ordinary Soil
6+320 20.00 - - - 40.75 28.78 575.60 575.60 20.00 6.85 137.00 1.10 22.00 95 - 5 - 0 - Ordinary Soil
6+340 20.00 - - - 57.16 48.96 979.20 979.20 20.00 11.86 237.20 3.05 61.00 95 - 5 - 0 - Ordinary Soil
6+360 20.00 - - - 61.26 59.21 1,184.20 1,184.20 10.00 7.82 78.20 1.53 15.30 95 - 5 - 0 - Ordinary Soil
6+380 20.00 - - - 126.07 93.67 1,873.40 1,873.40 - - - - - 95 - 5 - 0 - Ordinary Soil
6+400 20.00 - - - 168.86 147.47 2,949.40 2,949.40 - - - - - 95 - 5 - 0 - Ordinary Soil
6+420 20.00 - - - 172.41 170.64 3,412.80 3,412.80 - - - - - 95 - 5 - 0 - Ordinary Soil
6+440 20.00 - - - 212.31 192.36 3,847.20 3,847.20 - - - - - 95 - 5 - 0 - Ordinary Soil
6+460 20.00 - - - 180.83 196.57 3,931.40 3,931.40 - - - - - 95 - 5 - 0 - Ordinary Soil
6+480 20.00 - - - 71.09 125.96 2,519.20 2,519.20 10.00 8.80 88.00 0.75 7.50 95 - 5 - 0 - Ordinary Soil
6+500 20.00 32.55 16.28 325.60 5.93 38.51 770.20 444.60 20.00 17.49 349.80 5.42 108.40 95 309.32 5 16.28 0 - Ordinary Soil
6+520 20.00 0.28 16.42 328.40 23.75 14.84 296.80 - 20.00 11.69 233.80 2.37 47.40 95 311.98 5 16.42 0 - Ordinary Soil
6+540 20.00 4.49 2.39 47.80 18.21 20.98 419.60 371.80 20.00 17.52 350.40 4.45 89.00 95 45.41 5 2.39 0 - Ordinary Soil
6+560 20.00 11.62 8.06 161.20 4.47 11.34 226.80 65.60 10.00 4.63 46.30 0.88 8.80 95 153.14 5 8.06 0 - Ordinary Soil
6+580 20.00 34.04 22.83 456.60 - 2.24 44.80 - - - - - - 95 433.77 5 22.83 0 - Ordinary Soil
6+600 20.00 35.30 34.67 693.40 0.16 0.08 1.60 - - - - - - 95 658.73 5 34.67 0 - Ordinary Soil
6+620 20.00 4.04 19.67 393.40 8.96 4.56 91.20 - 10.00 1.46 14.60 0.01 0.10 95 373.73 5 19.67 0 - Ordinary Soil
6+640 20.00 - 2.02 40.40 15.93 12.45 249.00 208.60 20.00 5.73 114.60 0.77 15.40 95 38.38 5 2.02 0 - Ordinary Soil
6+660 20.00 22.00 11.00 220.00 0.02 7.98 159.60 - 10.00 1.93 19.30 0.57 5.70 95 209.00 5 11.00 0 - Ordinary Soil
6+680 20.00 54.44 38.22 764.40 - 0.01 0.20 - - - - - - 95 726.18 5 38.22 0 - Ordinary Soil
6+700 20.00 99.87 77.16 1,543.20 - - - - 10.00 107.70 1,077.00 1.58 15.80 95 1,466.04 5 77.16 0 - Ordinary Soil
6+720 20.00 42.02 70.95 1,419.00 0.01 0.01 0.20 - 20.00 25.09 501.80 0.90 18.00 95 1,348.05 5 70.95 0 - Ordinary Soil
6+740 20.00 14.42 28.22 564.40 0.25 0.13 2.60 - 20.00 17.56 351.20 1.65 33.00 95 536.18 5 28.22 0 - Ordinary Soil
6+760 20.00 32.69 23.56 471.20 - 0.13 2.60 - 20.00 29.79 595.80 0.67 13.40 95 447.64 5 23.56 0 - Ordinary Soil
22 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
6+780 20.00 26.8012 29.75 595.00 0.003 - - - 20.00 26.71 534.20 0.66 13.20 95 565.25 5 29.75 0 - Ordinary Soil
6+800 20.00 28.72 27.76 555.20 - - - - 20.00 29.60 592.00 0.80 16.00 95 527.44 5 27.76 0 - Ordinary Soil
6+820 20.00 28.43 28.58 571.60 - - - - 20.00 28.72 574.40 0.70 14.00 95 543.02 5 28.58 0 - Ordinary Soil
6+840 20.00 44.06 36.25 725.00 - - - - 20.00 33.50 670.00 0.79 15.80 95 688.75 5 36.25 0 - Ordinary Soil
6+860 20.00 37.81 40.94 818.80 - - - - 20.00 31.70 634.00 0.66 13.20 95 777.86 5 40.94 0 - Ordinary Soil
6+880 20.00 59.42 48.62 972.40 - - - - 20.00 42.26 845.20 0.68 13.60 95 923.78 5 48.62 0 - Ordinary Soil
6+900 20.00 74.80 67.11 1,342.20 - - - - 20.00 50.55 1,011.00 0.69 13.80 95 1,275.09 5 67.11 0 - Ordinary Soil
6+920 20.00 72.26 73.53 1,470.60 - - - - 20.00 49.51 990.20 0.69 13.80 95 1,397.07 5 73.53 0 - Ordinary Soil
6+940 20.00 58.26 65.26 1,305.20 - - - - 20.00 74.35 1,487.00 0.69 13.80 95 1,239.94 5 65.26 0 - Ordinary Soil
6+960 20.00 79.33 68.80 1,376.00 - - - - 20.00 125.16 2,503.20 1.60 32.00 95 1,307.20 5 68.80 0 - Ordinary Soil
6+980 20.00 85.36 82.35 1,647.00 - - - - 20.00 146.05 2,921.00 1.60 32.00 95 1,564.65 5 82.35 0 - Ordinary Soil
7+000 20.00 91.57 88.47 1,769.40 - - - - 20.00 153.23 3,064.60 1.73 34.60 95 1,680.93 5 88.47 0 - Ordinary Soil
7+020 20.00 120.16 105.87 2,117.40 - - - - 20.00 121.84 2,436.80 1.60 32.00 95 2,011.53 5 105.87 0 - Ordinary Soil
7+040 20.00 85.82 102.99 2,059.80 - - - - 20.00 93.36 1,867.20 2.83 56.60 95 1,956.81 5 102.99 0 - Ordinary Soil
7+060 20.00 101.95 93.89 1,877.80 - - - - 20.00 119.29 2,385.80 1.63 32.60 95 1,783.91 5 93.89 0 - Ordinary Soil
7+080 20.00 124.52 105.17 2,103.40 - - - - 20.00 153.99 3,079.80 1.44 28.80 95 1,998.23 5 105.17 0 - Ordinary Soil
7+100 20.00 142.30 122.13 2,442.60 - - - - 20.00 185.32 3,706.40 1.55 31.00 95 2,320.47 5 122.13 0 - Ordinary Soil
7+120 20.00 125.50 125.01 2,500.20 0.02 0.01 0.20 - 20.00 222.57 4,451.40 1.68 33.60 95 2,375.19 5 125.01 0 - Ordinary Soil
7+140 20.00 152.87 147.59 2,951.80 - - - - 20.00 279.81 5,596.20 3.09 61.80 95 2,804.21 5 147.59 0 - Ordinary Soil
7+160 20.00 147.40 136.45 2,729.00 - 0.01 0.20 - 10.00 317.47 3,174.70 6.91 69.10 95 2,592.55 5 136.45 0 - Ordinary Soil
7+180 20.00 280.74 216.81 4,336.20 - - - - - - - - - 95 4,119.39 5 216.81 0 - Ordinary Soil
7+200 20.00 273.47 210.44 4,208.80 - - - - - - - - - 95 3,998.36 5 210.44 0 - Ordinary Soil
7+220 20.00 349.04 314.89 6,297.80 - - - - - - - - - 95 5,982.91 5 314.89 0 - Ordinary Soil
7+240 20.00 343.48 308.48 6,169.60 - - - - - - - - - 95 5,861.12 5 308.48 0 - Ordinary Soil
7+260 20.00 349.52 349.28 6,985.60 - - - - - - - - - 95 6,636.32 5 349.28 0 - Ordinary Soil
7+280 20.00 356.63 350.06 7,001.20 - - - - - - - - - 95 6,651.14 5 350.06 0 - Ordinary Soil
7+300 20.00 375.73 362.63 7,252.60 - - - - - - - - - 95 6,889.97 5 362.63 0 - Ordinary Soil
7+320 20.00 376.24 366.44 7,328.80 - - - - - - - - - 95 6,962.36 5 366.44 0 - Ordinary Soil
7+340 20.00 381.43 378.58 7,571.60 - - - - - - - - - 95 7,193.02 5 378.58 0 - Ordinary Soil
7+360 20.00 413.65 394.95 7,899.00 - - - - - - - - - 95 7,504.05 5 394.95 0 - Ordinary Soil
7+380 20.00 395.84 388.64 7,772.80 - - - - - - - - - 95 7,384.16 5 388.64 0 - Ordinary Soil
7+400 20.00 458.15 435.90 8,718.00 - - - - - - - - - 95 8,282.10 5 435.90 0 - Ordinary Soil
7+420 20.00 520.54 458.19 9,163.80 - - - - - - - - - 95 8,705.61 5 458.19 0 - Ordinary Soil
7+440 20.00 523.58 490.87 9,817.40 - - - - - - - - - 95 9,326.53 5 490.87 0 - Ordinary Soil
7+460 20.00 491.16 505.85 10,117.00 - - - - - - - - - 95 9,611.15 5 505.85 0 - Ordinary Soil
7+480 20.00 509.23 516.41 10,328.20 - - - - - - - - - 95 9,811.79 5 516.41 0 - Ordinary Soil
7+500 20.00 564.29 527.73 10,554.60 - - - - - - - - - 95 10,026.87 5 527.73 0 - Ordinary Soil
7+520 20.00 540.48 524.86 10,497.20 - - - - - - - - - 95 9,972.34 5 524.86 0 - Ordinary Soil
7+540 20.00 471.61 517.95 10,359.00 - - - - - - - - - 95 9,841.05 5 517.95 0 - Ordinary Soil
7+560 20.00 551.84 546.16 10,923.20 - - - - - - - - - 95 10,377.04 5 546.16 0 - Ordinary Soil
7+580 20.00 553.28 512.45 10,249.00 - - - - - - - - - 95 9,736.55 5 512.45 0 - Ordinary Soil
7+600 20.00 555.13 553.49 11,069.80 - - - - - - - - - 95 10,516.31 5 553.49 0 - Ordinary Soil
7+620 20.00 538.54 545.91 10,918.20 - - - - - - - - - 95 10,372.29 5 545.91 0 - Ordinary Soil
23 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
7+640 20.00 536.41 545.77 10,915.40 - - - - - - - - - 95 10,369.63 5 545.77 0 - Ordinary Soil
7+660 20.00 514.70 526.62 10,532.40 - - - - - - - - - 95 10,005.78 5 526.62 0 - Ordinary Soil
7+680 20.00 533.10 534.76 10,695.20 - - - - - - - - - 95 10,160.44 5 534.76 0 - Ordinary Soil
7+700 20.00 525.30 520.00 10,400.00 - - - - - - - - - 95 9,880.00 5 520.00 0 - Ordinary Soil
7+720 20.00 539.82 536.46 10,729.20 - - - - - - - - - 95 10,192.74 5 536.46 0 - Ordinary Soil
7+740 20.00 737.30 631.30 12,626.00 - - - - - - - - - 95 11,994.70 5 631.30 0 - Ordinary Soil
7+760 20.00 738.40 639.11 12,782.20 - - - - - - - - - 95 12,143.09 5 639.11 0 - Ordinary Soil
7+780 20.00 668.14 702.72 14,054.40 - - - - - - - - - 95 13,351.68 5 702.72 0 - Ordinary Soil
7+800 20.00 601.15 669.78 13,395.60 - - - - - - - - - 95 12,725.82 5 669.78 0 - Ordinary Soil
7+820 20.00 602.05 635.10 12,702.00 - - - - - - - - - 95 12,066.90 5 635.10 0 - Ordinary Soil
7+840 20.00 618.61 609.88 12,197.60 - - - - - - - - - 95 11,587.72 5 609.88 0 - Ordinary Soil
7+860 20.00 615.22 608.64 12,172.80 - - - - - - - - - 95 11,564.16 5 608.64 0 - Ordinary Soil
7+880 20.00 634.77 626.69 12,533.80 - - - - - - - - - 95 11,907.11 5 626.69 0 - Ordinary Soil
7+900 20.00 662.03 638.63 12,772.60 - - - - - - - - - 95 12,133.97 5 638.63 0 - Ordinary Soil
7+920 20.00 746.72 690.75 13,815.00 - - - - - - - - - 95 13,124.25 5 690.75 0 - Ordinary Soil
7+940 20.00 679.53 670.78 13,415.60 - - - - - - - - - 95 12,744.82 5 670.78 0 - Ordinary Soil
7+960 20.00 683.29 715.01 14,300.20 - - - - - - - - - 95 13,585.19 5 715.01 0 - Ordinary Soil
7+980 20.00 728.17 703.85 14,077.00 - - - - - - - - - 95 13,373.15 5 703.85 0 - Ordinary Soil
8+000 20.00 740.84 712.07 14,241.40 - - - - - - - - - 95 13,529.33 5 712.07 0 - Ordinary Soil
8+020 20.00 789.39 758.78 15,175.60 - - - - - - - - - 95 14,416.82 5 758.78 0 - Ordinary Soil
8+040 20.00 810.61 775.73 15,514.60 - - - - - - - - - 95 14,738.87 5 775.73 0 - Ordinary Soil
8+060 20.00 817.57 803.48 16,069.60 - - - - - - - - - 95 15,266.12 5 803.48 0 - Ordinary Soil
8+080 20.00 837.40 824.01 16,480.20 - - - - - - - - - 95 15,656.19 5 824.01 0 - Ordinary Soil
8+100 20.00 812.04 814.81 16,296.20 - - - - - - - - - 95 15,481.39 5 814.81 0 - Ordinary Soil
8+120 20.00 793.09 815.25 16,305.00 - - - - - - - - - 95 15,489.75 5 815.25 0 - Ordinary Soil
8+140 20.00 755.68 783.86 15,677.20 - - - - - - - - - 95 14,893.34 5 783.86 0 - Ordinary Soil
8+160 20.00 738.00 765.55 15,311.00 - - - - - - - - - 95 14,545.45 5 765.55 0 - Ordinary Soil
8+180 20.00 825.03 790.36 15,807.20 - - - - - - - - - 95 15,016.84 5 790.36 0 - Ordinary Soil
8+200 20.00 820.19 779.10 15,582.00 - - - - - - - - - 95 14,802.90 5 779.10 0 - Ordinary Soil
8+220 20.00 884.48 854.76 17,095.20 - - - - - - - - - 95 16,240.44 5 854.76 0 - Ordinary Soil
8+240 20.00 799.06 809.63 16,192.60 - - - - - - - - - 95 15,382.97 5 809.63 0 - Ordinary Soil
8+260 20.00 787.89 836.19 16,723.80 - - - - - - - - - 95 15,887.61 5 836.19 0 - Ordinary Soil
8+280 20.00 761.42 780.24 15,604.80 - - - - - - - - - 95 14,824.56 5 780.24 0 - Ordinary Soil
8+300 20.00 821.06 804.48 16,089.60 0.01 0.01 0.20 - - - - - - 95 15,285.12 5 804.48 0 - Ordinary Soil
8+320 20.00 803.73 782.58 15,651.60 - - - - - - - - - 95 14,869.02 5 782.58 0 - Ordinary Soil
8+340 20.00 693.04 757.05 15,141.00 - 0.01 0.20 - - - - - - 95 14,383.95 5 757.05 0 - Ordinary Soil
8+360 20.00 887.73 845.73 16,914.60 - - - - - - - - - 95 16,068.87 5 845.73 0 - Ordinary Soil
8+380 20.00 803.32 748.18 14,963.60 - - - - - - - - - 95 14,215.42 5 748.18 0 - Ordinary Soil
8+400 20.00 834.76 861.25 17,225.00 - - - - - - - - - 95 16,363.75 5 861.25 0 - Ordinary Soil
8+420 20.00 781.40 792.36 15,847.20 - - - - - - - - - 95 15,054.84 5 792.36 0 - Ordinary Soil
8+440 20.00 776.86 805.81 16,116.20 - - - - - - - - - 95 15,310.39 5 805.81 0 - Ordinary Soil
8+460 20.00 928.10 854.75 17,095.00 - - - - - - - - - 95 16,240.25 5 854.75 0 - Ordinary Soil
8+480 20.00 947.08 861.97 17,239.40 - - - - - - - - - 95 16,377.43 5 861.97 0 - Ordinary Soil
24 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
8+500 20.00 853.41 890.76 17,815.20 - - - - - - - - - 95 16,924.44 5 890.76 0 - Ordinary Soil
8+520 20.00 862.98 905.03 18,100.60 - - - - - - - - - 95 17,195.57 5 905.03 0 - Ordinary Soil
8+540 20.00 873.57 863.49 17,269.80 - - - - - - - - - 95 16,406.31 5 863.49 0 - Ordinary Soil
8+560 20.00 907.34 885.16 17,703.20 - - - - - - - - - 95 16,818.04 5 885.16 0 - Ordinary Soil
8+580 20.00 908.68 891.13 17,822.60 - - - - - - - - - 95 16,931.47 5 891.13 0 - Ordinary Soil
8+600 20.00 946.49 926.92 18,538.40 - - - - - - - - - 95 17,611.48 5 926.92 0 - Ordinary Soil
8+620 20.00 952.36 930.52 18,610.40 - - - - - - - - - 95 17,679.88 5 930.52 0 - Ordinary Soil
8+640 20.00 891.92 919.21 18,384.20 - - - - - - - - - 95 17,464.99 5 919.21 0 - Ordinary Soil
8+660 20.00 888.74 920.55 18,411.00 - - - - - - - - - 95 17,490.45 5 920.55 0 - Ordinary Soil
8+680 20.00 936.70 914.31 18,286.20 - - - - - - - - - 95 17,371.89 5 914.31 0 - Ordinary Soil
8+700 20.00 873.70 881.22 17,624.40 - - - - - - - - - 95 16,743.18 5 881.22 0 - Ordinary Soil
8+720 20.00 947.16 941.93 18,838.60 - - - - - - - - - 95 17,896.67 5 941.93 0 - Ordinary Soil
8+740 20.00 836.45 855.08 17,101.60 - - - - - - - - - 95 16,246.52 5 855.08 0 - Ordinary Soil
8+760 20.00 925.96 936.56 18,731.20 - - - - - - - - - 95 17,794.64 5 936.56 0 - Ordinary Soil
8+780 20.00 1,007.90 922.18 18,443.60 - - - - - - - - - 95 17,521.42 5 922.18 0 - Ordinary Soil
8+800 20.00 1,016.65 971.31 19,426.20 - - - - - - - - - 95 18,454.89 5 971.31 0 - Ordinary Soil
8+820 20.00 940.71 974.31 19,486.20 - - - - - - - - - 95 18,511.89 5 974.31 0 - Ordinary Soil
8+840 20.00 971.79 994.22 19,884.40 - - - - - - - - - 95 18,890.18 5 994.22 0 - Ordinary Soil
8+860 20.00 1,073.70 1,007.21 20,144.20 - - - - - - - - - 95 19,136.99 5 1,007.21 0 - Ordinary Soil
8+880 20.00 1,062.44 1,017.12 20,342.40 - - - - - - - - - 95 19,325.28 5 1,017.12 0 - Ordinary Soil
8+900 20.00 1,042.50 1,058.10 21,162.00 - - - - - - - - - 95 20,103.90 5 1,058.10 0 - Ordinary Soil
8+920 20.00 975.73 1,019.09 20,381.80 - - - - - - - - - 95 19,362.71 5 1,019.09 0 - Ordinary Soil
8+940 20.00 1,084.79 1,063.65 21,273.00 - - - - - - - - - 95 20,209.35 5 1,063.65 0 - Ordinary Soil
8+960 20.00 1,016.27 996.00 19,920.00 - - - - - - - - - 95 18,924.00 5 996.00 0 - Ordinary Soil
8+980 20.00 998.48 1,041.64 20,832.80 - - - - - - - - - 95 19,791.16 5 1,041.64 0 - Ordinary Soil
9+000 20.00 997.94 1,007.11 20,142.20 - - - - - - - - - 95 19,135.09 5 1,007.11 0 - Ordinary Soil
9+020 20.00 1,079.63 1,039.06 20,781.20 0.01 0.01 0.20 - - - - - - 95 19,742.14 5 1,039.06 0 - Ordinary Soil
9+040 20.00 1,096.84 1,047.39 20,947.80 - - - - - - - - - 95 19,900.41 5 1,047.39 0 - Ordinary Soil
9+060 20.00 1,040.30 1,059.97 21,199.40 - 0.01 0.20 - - - - - - 95 20,139.43 5 1,059.97 0 - Ordinary Soil
9+080 20.00 970.52 1,033.68 20,673.60 - - - - - - - - - 95 19,639.92 5 1,033.68 0 - Ordinary Soil
9+100 20.00 973.24 1,006.77 20,135.40 - - - - - - - - - 95 19,128.63 5 1,006.77 0 - Ordinary Soil
9+120 20.00 1,097.02 1,033.77 20,675.40 - - - - - - - - - 95 19,641.63 5 1,033.77 0 - Ordinary Soil
9+140 20.00 1,085.24 1,029.24 20,584.80 - - - - - - - - - 95 19,555.56 5 1,029.24 0 - Ordinary Soil
9+160 20.00 1,063.88 1,080.45 21,609.00 - - - - - - - - - 95 20,528.55 5 1,080.45 0 - Ordinary Soil
9+180 20.00 993.47 1,039.36 20,787.20 - - - - - - - - - 95 19,747.84 5 1,039.36 0 - Ordinary Soil
9+200 20.00 974.60 1,019.24 20,384.80 - - - - - - - - - 95 19,365.56 5 1,019.24 0 - Ordinary Soil
9+220 20.00 1,029.28 1,011.38 20,227.60 - - - - - - - - - 95 19,216.22 5 1,011.38 0 - Ordinary Soil
9+240 20.00 991.86 983.23 19,664.60 - - - - - - - - - 95 18,681.37 5 983.23 0 - Ordinary Soil
9+260 20.00 1,024.32 1,026.80 20,536.00 - - - - - - - - - 95 19,509.20 5 1,026.80 0 - Ordinary Soil
9+280 20.00 962.29 977.08 19,541.60 - - - - - - - - - 95 18,564.52 5 977.08 0 - Ordinary Soil
9+300 20.00 1,040.21 1,032.27 20,645.40 - - - - - - - - - 95 19,613.13 5 1,032.27 0 - Ordinary Soil
9+320 20.00 1,091.17 1,026.73 20,534.60 - - - - - - - - - 95 19,507.87 5 1,026.73 0 - Ordinary Soil
9+340 20.00 1,084.88 1,062.55 21,251.00 - - - - - - - - - 95 20,188.45 5 1,062.55 0 - Ordinary Soil
25 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
9+360 20.00 1,046.08 1,068.63 21,372.60 - - - - - - - - - 95 20,303.97 5 1,068.63 0 - Ordinary Soil
9+380 20.00 924.40 1,004.64 20,092.80 - - - - - - - - - 95 19,088.16 5 1,004.64 0 - Ordinary Soil
9+400 20.00 1,015.40 1,030.74 20,614.80 - - - - - - - - - 95 19,584.06 5 1,030.74 0 - Ordinary Soil
9+420 20.00 1,178.37 1,051.39 21,027.80 - - - - - - - - - 95 19,976.41 5 1,051.39 0 - Ordinary Soil
9+440 20.00 1,183.85 1,099.63 21,992.60 - - - - - - - - - 95 20,892.97 5 1,099.63 0 - Ordinary Soil
9+460 20.00 1,076.73 1,127.55 22,551.00 - - - - - - - - - 95 21,423.45 5 1,127.55 0 - Ordinary Soil
9+480 20.00 1,134.14 1,159.00 23,180.00 - - - - - - - - - 95 22,021.00 5 1,159.00 0 - Ordinary Soil
9+500 20.00 1,020.61 1,048.67 20,973.40 - - - - - - - - - 95 19,924.73 5 1,048.67 0 - Ordinary Soil
9+520 20.00 1,070.77 1,102.46 22,049.20 - - - - - - - - - 95 20,946.74 5 1,102.46 0 - Ordinary Soil
9+540 20.00 1,069.04 1,044.83 20,896.60 - - - - - - - - - 95 19,851.77 5 1,044.83 0 - Ordinary Soil
9+560 20.00 1,076.99 1,073.88 21,477.60 - - - - - - - - - 95 20,403.72 5 1,073.88 0 - Ordinary Soil
9+580 20.00 1,071.40 1,070.22 21,404.40 - - - - - - - - - 95 20,334.18 5 1,070.22 0 - Ordinary Soil
9+600 20.00 939.50 1,008.25 20,165.00 - - - - - - - - - 95 19,156.75 5 1,008.25 0 - Ordinary Soil
9+620 20.00 669.02 870.21 17,404.20 - - - - - - - - - 95 16,533.99 5 870.21 0 - Ordinary Soil
9+640 20.00 1,120.64 1,030.07 20,601.40 - - - - - - - - - 95 19,571.33 5 1,030.07 0 - Ordinary Soil
9+660 20.00 1,083.42 876.22 17,524.40 - - - - - - - - - 95 16,648.18 5 876.22 0 - Ordinary Soil
9+680 20.00 1,003.17 1,061.91 21,238.20 - - - - - - - - - 95 20,176.29 5 1,061.91 0 - Ordinary Soil
9+700 20.00 990.32 1,036.87 20,737.40 - - - - - - - - - 95 19,700.53 5 1,036.87 0 - Ordinary Soil
9+720 20.00 1,007.09 1,005.13 20,102.60 - - - - - - - - - 95 19,097.47 5 1,005.13 0 - Ordinary Soil
9+740 20.00 1,019.17 1,004.75 20,095.00 - - - - - - - - - 95 19,090.25 5 1,004.75 0 - Ordinary Soil
9+760 20.00 973.08 990.09 19,801.80 - - - - - - - - - 95 18,811.71 5 990.09 0 - Ordinary Soil
9+780 20.00 1,026.77 1,022.97 20,459.40 - - - - - - - - - 95 19,436.43 5 1,022.97 0 - Ordinary Soil
9+800 20.00 1,030.31 1,001.70 20,034.00 - - - - - - - - - 95 19,032.30 5 1,001.70 0 - Ordinary Soil
9+820 20.00 970.31 998.54 19,970.80 - - - - - - - - - 95 18,972.26 5 998.54 0 - Ordinary Soil
9+840 20.00 847.80 939.06 18,781.20 - - - - - - - - - 95 17,842.14 5 939.06 0 - Ordinary Soil
9+860 20.00 984.66 977.49 19,549.80 0.07 0.04 0.80 - - - - - - 95 18,572.31 5 977.49 0 - Ordinary Soil
9+880 20.00 989.09 918.45 18,369.00 - - - - - - - - - 95 17,450.55 5 918.45 0 - Ordinary Soil
9+900 20.00 1,056.48 1,020.57 20,411.40 - 0.04 0.80 - - - - - - 95 19,390.83 5 1,020.57 0 - Ordinary Soil
9+920 20.00 1,034.14 1,011.62 20,232.40 - - - - - - - - - 95 19,220.78 5 1,011.62 0 - Ordinary Soil
9+940 20.00 1,045.98 1,051.23 21,024.60 - - - - - - - - - 95 19,973.37 5 1,051.23 0 - Ordinary Soil
9+960 20.00 937.77 985.96 19,719.20 - - - - - - - - - 95 18,733.24 5 985.96 0 - Ordinary Soil
9+980 20.00 931.20 988.59 19,771.80 - - - - - - - - - 95 18,783.21 5 988.59 0 - Ordinary Soil
10+000 20.00 1,112.13 1,024.95 20,499.00 - - - - - - - - - 95 19,474.05 5 1,024.95 0 - Ordinary Soil
10+020 20.00 1,110.48 1,020.84 20,416.80 - - - - - - - - - 95 19,395.96 5 1,020.84 0 - Ordinary Soil
10+040 20.00 1,162.36 1,137.25 22,745.00 - - - - - - - - - 95 21,607.75 5 1,137.25 0 - Ordinary Soil
10+060 20.00 996.26 1,053.37 21,067.40 - - - - - - - - - 95 20,014.03 5 1,053.37 0 - Ordinary Soil
10+080 20.00 1,000.47 1,081.42 21,628.40 - - - - - - - - - 95 20,546.98 5 1,081.42 0 - Ordinary Soil
10+100 20.00 1,015.27 1,005.77 20,115.40 - - - - - - - - - 95 19,109.63 5 1,005.77 0 - Ordinary Soil
10+120 20.00 1,122.83 1,061.65 21,233.00 - - - - - - - - - 95 20,171.35 5 1,061.65 0 - Ordinary Soil
10+140 20.00 1,108.96 1,062.12 21,242.40 - - - - - - - - - 95 20,180.28 5 1,062.12 0 - Ordinary Soil
10+160 20.00 1,111.38 1,117.11 22,342.20 - - - - - - - - - 95 21,225.09 5 1,117.11 0 - Ordinary Soil
10+180 20.00 1,125.62 1,117.29 22,345.80 - - - - - - - - - 95 21,228.51 5 1,117.29 0 - Ordinary Soil
10+200 20.00 1,143.73 1,127.56 22,551.20 - - - - - - - - - 95 21,423.64 5 1,127.56 0 - Ordinary Soil
26 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
10+220 20.00 1,157.22 1,141.42 22,828.40 - - - - - - - - - 95 21,686.98 5 1,141.42 0 - Ordinary Soil
10+240 20.00 1,152.54 1,148.14 22,962.80 - - - - - - - - - 95 21,814.66 5 1,148.14 0 - Ordinary Soil
10+260 20.00 1,147.54 1,152.38 23,047.60 - - - - - - - - - 95 21,895.22 5 1,152.38 0 - Ordinary Soil
10+280 20.00 1,138.47 1,145.51 22,910.20 - - - - - - - - - 95 21,764.69 5 1,145.51 0 - Ordinary Soil
10+300 20.00 1,119.41 1,133.48 22,669.60 - - - - - - - - - 95 21,536.12 5 1,133.48 0 - Ordinary Soil
10+320 20.00 1,103.78 1,121.13 22,422.60 0.05 0.03 0.60 - - - - - - 95 21,301.47 5 1,121.13 0 - Ordinary Soil
10+340 20.00 1,121.29 1,120.35 22,407.00 - - - - - - - - - 95 21,286.65 5 1,120.35 0 - Ordinary Soil
10+360 20.00 1,102.67 1,103.23 22,064.60 - 0.03 0.60 - - - - - - 95 20,961.37 5 1,103.23 0 - Ordinary Soil
10+380 20.00 1,054.24 1,087.77 21,755.40 - - - - - - - - - 95 20,667.63 5 1,087.77 0 - Ordinary Soil
10+400 20.00 1,050.80 1,076.74 21,534.80 - - - - - - - - - 95 20,458.06 5 1,076.74 0 - Ordinary Soil
10+420 20.00 1,056.63 1,055.44 21,108.80 - - - - - - - - - 95 20,053.36 5 1,055.44 0 - Ordinary Soil
10+440 20.00 986.22 1,018.51 20,370.20 - - - - - - - - - 95 19,351.69 5 1,018.51 0 - Ordinary Soil
10+460 20.00 1,086.62 1,071.63 21,432.60 - - - - - - - - - 95 20,360.97 5 1,071.63 0 - Ordinary Soil
10+480 20.00 1,130.21 1,058.22 21,164.40 - - - - - - - - - 95 20,106.18 5 1,058.22 0 - Ordinary Soil
10+500 20.00 1,131.99 1,109.31 22,186.20 - - - - - - - - - 95 21,076.89 5 1,109.31 0 - Ordinary Soil
10+520 20.00 1,076.56 1,103.39 22,067.80 0.01 0.01 0.20 - - - - - - 95 20,964.41 5 1,103.39 0 - Ordinary Soil
10+540 20.00 1,080.88 1,106.44 22,128.80 - - - - - - - - - 95 21,022.36 5 1,106.44 0 - Ordinary Soil
10+560 20.00 1,105.88 1,091.22 21,824.40 - 0.01 0.20 - - - - - - 95 20,733.18 5 1,091.22 0 - Ordinary Soil
10+580 20.00 1,021.77 1,051.33 21,026.60 - - - - - - - - - 95 19,975.27 5 1,051.33 0 - Ordinary Soil
10+600 20.00 1,027.68 1,066.78 21,335.60 - - - - - - - - - 95 20,268.82 5 1,066.78 0 - Ordinary Soil
10+620 20.00 1,035.25 1,028.51 20,570.20 - - - - - - - - - 95 19,541.69 5 1,028.51 0 - Ordinary Soil
10+640 20.00 1,042.52 1,035.10 20,702.00 - - - - - - - - - 95 19,666.90 5 1,035.10 0 - Ordinary Soil
10+660 20.00 1,041.63 1,038.44 20,768.80 - - - - - - - - - 95 19,730.36 5 1,038.44 0 - Ordinary Soil
10+680 20.00 901.69 972.11 19,442.20 - - - - - - - - - 95 18,470.09 5 972.11 0 - Ordinary Soil
10+700 20.00 845.80 943.72 18,874.40 - - - - - - - - - 95 17,930.68 5 943.72 0 - Ordinary Soil
10+720 20.00 1,118.44 1,010.07 20,201.40 - - - - - - - - - 95 19,191.33 5 1,010.07 0 - Ordinary Soil
10+740 20.00 1,080.88 963.34 19,266.80 - - - - - - - - - 95 18,303.46 5 963.34 0 - Ordinary Soil
10+760 20.00 1,077.53 1,097.99 21,959.80 - - - - - - - - - 95 20,861.81 5 1,097.99 0 - Ordinary Soil
10+780 20.00 1,078.85 1,079.87 21,597.40 - - - - - - - - - 95 20,517.53 5 1,079.87 0 - Ordinary Soil
10+800 20.00 1,061.57 1,069.55 21,391.00 - - - - - - - - - 95 20,321.45 5 1,069.55 0 - Ordinary Soil
10+820 20.00 1,059.66 1,069.26 21,385.20 - - - - - - - - - 95 20,315.94 5 1,069.26 0 - Ordinary Soil
10+840 20.00 1,101.21 1,081.39 21,627.80 - - - - - - - - - 95 20,546.41 5 1,081.39 0 - Ordinary Soil
10+860 20.00 1,098.29 1,078.98 21,579.60 - - - - - - - - - 95 20,500.62 5 1,078.98 0 - Ordinary Soil
10+880 20.00 1,029.97 1,065.59 21,311.80 0.01 0.01 0.20 - - - - - - 95 20,246.21 5 1,065.59 0 - Ordinary Soil
10+900 20.00 1,005.63 1,051.96 21,039.20 - - - - - - - - - 95 19,987.24 5 1,051.96 0 - Ordinary Soil
10+920 20.00 930.76 980.37 19,607.40 - 0.01 0.20 - - - - - - 95 18,627.03 5 980.37 0 - Ordinary Soil
10+940 20.00 971.34 988.49 19,769.80 - - - - - - - - - 95 18,781.31 5 988.49 0 - Ordinary Soil
10+960 20.00 997.97 964.37 19,287.40 - - - - - - - - - 95 18,323.03 5 964.37 0 - Ordinary Soil
10+980 20.00 961.94 966.64 19,332.80 - - - - - - - - - 95 18,366.16 5 966.64 0 - Ordinary Soil
11+000 20.00 901.95 949.96 18,999.20 - - - - - - - - - 95 18,049.24 5 949.96 0 - Ordinary Soil
11+020 20.00 906.46 934.20 18,684.00 - - - - - - - - - 95 17,749.80 5 934.20 0 - Ordinary Soil
11+040 20.00 875.91 888.93 17,778.60 - - - - - - - - - 95 16,889.67 5 888.93 0 - Ordinary Soil
11+060 20.00 849.61 878.04 17,560.80 - - - - - - - - - 95 16,682.76 5 878.04 0 - Ordinary Soil
27 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
11+080 20.00 871.28 873.60 17,472.00 - - - - - - - - - 95 16,598.40 5 873.60 0 - Ordinary Soil
11+100 20.00 844.24 846.93 16,938.60 - - - - - - - - - 95 16,091.67 5 846.93 0 - Ordinary Soil
11+120 20.00 824.53 847.91 16,958.20 - - - - - - - - - 95 16,110.29 5 847.91 0 - Ordinary Soil
11+140 20.00 810.55 827.40 16,548.00 - - - - - - - - - 95 15,720.60 5 827.40 0 - Ordinary Soil
11+160 20.00 720.43 772.48 15,449.60 - - - - - - - - - 95 14,677.12 5 772.48 0 - Ordinary Soil
11+180 20.00 654.89 732.72 14,654.40 - - - - - - - - - 95 13,921.68 5 732.72 0 - Ordinary Soil
11+200 20.00 680.85 700.64 14,012.80 - - - - - - - - - 95 13,312.16 5 700.64 0 - Ordinary Soil
11+220 20.00 614.46 634.68 12,693.60 - - - - - - - - - 95 12,058.92 5 634.68 0 - Ordinary Soil
11+240 20.00 595.04 637.95 12,759.00 - - - - - - - - - 95 12,121.05 5 637.95 0 - Ordinary Soil
11+260 20.00 561.94 588.20 11,764.00 - - - - - - - - - 95 11,175.80 5 588.20 0 - Ordinary Soil
11+280 20.00 533.79 564.42 11,288.40 - - - - - - - - - 95 10,723.98 5 564.42 0 - Ordinary Soil
11+300 20.00 546.28 554.11 11,082.20 - - - - - - - - - 95 10,528.09 5 554.11 0 - Ordinary Soil
11+320 20.00 550.45 542.12 10,842.40 - - - - - - - - - 95 10,300.28 5 542.12 0 - Ordinary Soil
11+340 20.00 457.02 501.65 10,033.00 - - - - - - - - - 95 9,531.35 5 501.65 0 - Ordinary Soil
11+360 20.00 460.17 505.31 10,106.20 - - - - - - - - - 95 9,600.89 5 505.31 0 - Ordinary Soil
11+380 20.00 436.79 446.91 8,938.20 - - - - - - - - - 95 8,491.29 5 446.91 0 - Ordinary Soil
11+400 20.00 241.60 350.89 7,017.80 - - - - - - - - - 95 6,666.91 5 350.89 0 - Ordinary Soil
11+420 20.00 418.27 427.53 8,550.60 0.01 0.01 0.20 - - - - - - 95 8,123.07 5 427.53 0 - Ordinary Soil
11+440 20.00 447.33 344.47 6,889.40 - - - - - - - - - 95 6,544.93 5 344.47 0 - Ordinary Soil
11+460 20.00 437.53 427.90 8,558.00 - 0.01 0.20 - - - - - - 95 8,130.10 5 427.90 0 - Ordinary Soil
11+480 20.00 407.78 427.56 8,551.20 0.01 0.01 0.20 - - - - - - 95 8,123.64 5 427.56 0 - Ordinary Soil
11+500 20.00 353.13 395.33 7,906.60 - - - - - - - - - 95 7,511.27 5 395.33 0 - Ordinary Soil
11+520 20.00 359.50 383.64 7,672.80 - 0.01 0.20 - - - - - - 95 7,289.16 5 383.64 0 - Ordinary Soil
11+540 20.00 295.91 324.52 6,490.40 - - - - - - - - - 95 6,165.88 5 324.52 0 - Ordinary Soil
11+560 20.00 359.47 359.49 7,189.80 - - - - - - - - - 95 6,830.31 5 359.49 0 - Ordinary Soil
11+580 20.00 291.55 293.73 5,874.60 - - - - - - - - - 95 5,580.87 5 293.73 0 - Ordinary Soil
11+600 20.00 275.22 317.35 6,347.00 - - - - - - - - - 95 6,029.65 5 317.35 0 - Ordinary Soil
11+620 20.00 242.38 266.97 5,339.40 - - - - - - - - - 95 5,072.43 5 266.97 0 - Ordinary Soil
11+640 20.00 213.27 244.25 4,885.00 - - - - - - - - - 95 4,640.75 5 244.25 0 - Ordinary Soil
11+660 20.00 225.53 233.96 4,679.20 - - - - - - - - - 95 4,445.24 5 233.96 0 - Ordinary Soil
11+680 20.00 268.59 240.93 4,818.60 - - - - - - - - - 95 4,577.67 5 240.93 0 - Ordinary Soil
11+700 20.00 266.80 246.17 4,923.40 - - - - - - - - - 95 4,677.23 5 246.17 0 - Ordinary Soil
11+720 20.00 235.28 251.94 5,038.80 - - - - - - - - - 95 4,786.86 5 251.94 0 - Ordinary Soil
11+740 20.00 264.23 265.52 5,310.40 0.01 0.01 0.20 - - - - - - 95 5,044.88 5 265.52 0 - Ordinary Soil
11+760 20.00 212.04 223.66 4,473.20 - - - - - - - - - 95 4,249.54 5 223.66 0 - Ordinary Soil
11+780 20.00 278.08 271.16 5,423.20 - 0.01 0.20 - - - - - - 95 5,152.04 5 271.16 0 - Ordinary Soil
11+800 20.00 274.53 243.29 4,865.80 - - - - - - - - - 95 4,622.51 5 243.29 0 - Ordinary Soil
11+820 20.00 301.48 289.78 5,795.60 - - - - - - - - - 95 5,505.82 5 289.78 0 - Ordinary Soil
11+840 20.00 326.56 300.55 6,011.00 - - - - - - - - - 95 5,710.45 5 300.55 0 - Ordinary Soil
11+860 20.00 338.69 320.09 6,401.80 - - - - - - - - - 95 6,081.71 5 320.09 0 - Ordinary Soil
11+880 20.00 409.67 368.12 7,362.40 - - - - - - - - - 95 6,994.28 5 368.12 0 - Ordinary Soil
11+900 20.00 458.41 398.55 7,971.00 - - - - - - - - - 95 7,572.45 5 398.55 0 - Ordinary Soil
11+920 20.00 519.38 464.53 9,290.60 - - - - - - - - - 95 8,826.07 5 464.53 0 - Ordinary Soil
28 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
11+940 20.00 562.08 510.25 10,205.00 0.02 0.01 0.20 - - - - - - 95 9,694.75 5 510.25 0 - Ordinary Soil
11+960 20.00 536.56 527.97 10,559.40 - - - - - - - - - 95 10,031.43 5 527.97 0 - Ordinary Soil
11+980 20.00 588.42 575.25 11,505.00 - 0.01 0.20 - - - - - - 95 10,929.75 5 575.25 0 - Ordinary Soil
12+000 20.00 547.27 541.92 10,838.40 - - - - - - - - - 95 10,296.48 5 541.92 0 - Ordinary Soil
12+020 20.00 458.79 523.61 10,472.20 - - - - - - - - - 95 9,948.59 5 523.61 0 - Ordinary Soil
12+040 20.00 520.71 533.99 10,679.80 - - - - - - - - - 95 10,145.81 5 533.99 0 - Ordinary Soil
12+060 20.00 586.61 522.70 10,454.00 - - - - - - - - - 95 9,931.30 5 522.70 0 - Ordinary Soil
12+080 20.00 589.18 554.95 11,099.00 - - - - - - - - - 95 10,544.05 5 554.95 0 - Ordinary Soil
12+100 20.00 556.09 571.35 11,427.00 0.01 0.01 0.20 - - - - - - 95 10,855.65 5 571.35 0 - Ordinary Soil
12+120 20.00 522.02 555.60 11,112.00 - - - - - - - - - 95 10,556.40 5 555.60 0 - Ordinary Soil
12+140 20.00 511.98 534.04 10,680.80 - 0.01 0.20 - - - - - - 95 10,146.76 5 534.04 0 - Ordinary Soil
12+160 20.00 503.27 512.65 10,253.00 - - - - - - - - - 95 9,740.35 5 512.65 0 - Ordinary Soil
12+180 20.00 402.82 457.40 9,148.00 0.01 0.01 0.20 - - - - - - 95 8,690.60 5 457.40 0 - Ordinary Soil
12+200 20.00 446.15 474.71 9,494.20 - - - - - - - - - 95 9,019.49 5 474.71 0 - Ordinary Soil
12+220 20.00 373.55 388.19 7,763.80 - 0.01 0.20 - - - - - - 95 7,375.61 5 388.19 0 - Ordinary Soil
12+240 20.00 475.99 461.07 9,221.40 - - - - - - - - - 95 8,760.33 5 461.07 0 - Ordinary Soil
12+260 20.00 500.41 436.98 8,739.60 - - - - - - - - - 95 8,302.62 5 436.98 0 - Ordinary Soil
12+280 20.00 440.52 458.26 9,165.20 - - - - - - - - - 95 8,706.94 5 458.26 0 - Ordinary Soil
12+300 20.00 426.32 463.37 9,267.40 - - - - - - - - - 95 8,804.03 5 463.37 0 - Ordinary Soil
12+320 20.00 418.73 429.63 8,592.60 - - - - - - - - - 95 8,162.97 5 429.63 0 - Ordinary Soil
12+340 20.00 412.82 419.57 8,391.40 - - - - - - - - - 95 7,971.83 5 419.57 0 - Ordinary Soil
12+360 20.00 372.97 395.85 7,917.00 - - - - - - - - - 95 7,521.15 5 395.85 0 - Ordinary Soil
12+380 20.00 297.79 355.31 7,106.20 - - - - - - - - - 95 6,750.89 5 355.31 0 - Ordinary Soil
12+400 20.00 313.94 343.46 6,869.20 0.01 0.01 0.20 - - - - - - 95 6,525.74 5 343.46 0 - Ordinary Soil
12+420 20.00 308.39 303.09 6,061.80 - - - - - - - - - 95 5,758.71 5 303.09 0 - Ordinary Soil
12+440 20.00 257.70 285.82 5,716.40 - 0.01 0.20 - - - - - - 95 5,430.58 5 285.82 0 - Ordinary Soil
12+460 20.00 287.53 297.96 5,959.20 - - - - - - - - - 95 5,661.24 5 297.96 0 - Ordinary Soil
12+480 20.00 238.60 248.15 4,963.00 - - - - - - - - - 95 4,714.85 5 248.15 0 - Ordinary Soil
12+500 20.00 287.96 287.75 5,755.00 - - - - - - - - - 95 5,467.25 5 287.75 0 - Ordinary Soil
12+520 20.00 309.94 274.27 5,485.40 - - - - - - - - - 95 5,211.13 5 274.27 0 - Ordinary Soil
12+540 20.00 318.25 303.11 6,062.20 0.01 0.01 0.20 - - - - - - 95 5,759.09 5 303.11 0 - Ordinary Soil
12+560 20.00 329.43 319.69 6,393.80 - - - - - - - - - 95 6,074.11 5 319.69 0 - Ordinary Soil
12+580 20.00 342.33 330.29 6,605.80 - 0.01 0.20 - - - - - - 95 6,275.51 5 330.29 0 - Ordinary Soil
12+600 20.00 309.48 319.46 6,389.20 - - - - - - - - - 95 6,069.74 5 319.46 0 - Ordinary Soil
12+620 20.00 287.06 314.70 6,294.00 - - - - - - - - - 95 5,979.30 5 314.70 0 - Ordinary Soil
12+640 20.00 255.44 282.46 5,649.20 - - - - - - - - - 95 5,366.74 5 282.46 0 - Ordinary Soil
12+660 20.00 235.32 261.19 5,223.80 - - - - - - - - - 95 4,962.61 5 261.19 0 - Ordinary Soil
12+680 20.00 182.92 219.18 4,383.60 - - - - - - - - - 95 4,164.42 5 219.18 0 - Ordinary Soil
12+700 20.00 342.32 288.82 5,776.40 - - - - - - - - - 95 5,487.58 5 288.82 0 - Ordinary Soil
12+720 20.00 391.01 286.97 5,739.40 - - - - - - - - - 95 5,452.43 5 286.97 0 - Ordinary Soil
12+740 20.00 394.23 368.28 7,365.60 - - - - - - - - - 95 6,997.32 5 368.28 0 - Ordinary Soil
12+760 20.00 355.02 373.02 7,460.40 - - - - - - - - - 95 7,087.38 5 373.02 0 - Ordinary Soil
12+780 20.00 360.73 377.48 7,549.60 - - - - - - - - - 95 7,172.12 5 377.48 0 - Ordinary Soil
29 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
12+800 20.00 354.35 354.69 7,093.80 - - - - - - - - - 95 6,739.11 5 354.69 0 - Ordinary Soil
12+820 20.00 336.82 348.78 6,975.60 - - - - - - - - - 95 6,626.82 5 348.78 0 - Ordinary Soil
12+840 20.00 359.86 357.11 7,142.20 - - - - - - - - - 95 6,785.09 5 357.11 0 - Ordinary Soil
12+860 20.00 404.72 370.77 7,415.40 - - - - - - - - - 95 7,044.63 5 370.77 0 - Ordinary Soil
12+880 20.00 368.79 364.33 7,286.60 - - - - - - - - - 95 6,922.27 5 364.33 0 - Ordinary Soil
12+900 20.00 349.69 377.21 7,544.20 - - - - - - - - - 95 7,166.99 5 377.21 0 - Ordinary Soil
12+920 20.00 349.19 358.99 7,179.80 - - - - - - - - - 95 6,820.81 5 358.99 0 - Ordinary Soil
12+940 20.00 336.02 342.86 6,857.20 - - - - - - - - - 95 6,514.34 5 342.86 0 - Ordinary Soil
12+960 20.00 355.90 352.55 7,051.00 - - - - - - - - - 95 6,698.45 5 352.55 0 - Ordinary Soil
12+980 20.00 362.87 349.45 6,989.00 - - - - - - - - - 95 6,639.55 5 349.45 0 - Ordinary Soil
13+000 20.00 384.00 369.95 7,399.00 - - - - - - - - - 95 7,029.05 5 369.95 0 - Ordinary Soil
13+020 20.00 309.65 336.26 6,725.20 - - - - - - - - - 95 6,388.94 5 336.26 0 - Ordinary Soil
13+040 20.00 340.78 362.39 7,247.80 - - - - - - - - - 95 6,885.41 5 362.39 0 - Ordinary Soil
13+060 20.00 324.85 317.25 6,345.00 - - - - - - - - - 95 6,027.75 5 317.25 0 - Ordinary Soil
13+080 20.00 316.74 328.76 6,575.20 - - - - - - - - - 95 6,246.44 5 328.76 0 - Ordinary Soil
13+100 20.00 285.95 305.40 6,108.00 - - - - - - - - - 95 5,802.60 5 305.40 0 - Ordinary Soil
13+120 20.00 196.30 256.52 5,130.40 - - - - - - - - - 95 4,873.88 5 256.52 0 - Ordinary Soil
13+140 20.00 155.50 220.73 4,414.60 - - - - - - - - - 95 4,193.87 5 220.73 0 - Ordinary Soil
13+160 20.00 156.82 176.56 3,531.20 - - - - - - - - - 95 3,354.64 5 176.56 0 - Ordinary Soil
13+180 20.00 208.72 182.11 3,642.20 - - - - - - - - - 95 3,460.09 5 182.11 0 - Ordinary Soil
13+200 20.00 199.93 178.38 3,567.60 - - - - - - - - - 95 3,389.22 5 178.38 0 - Ordinary Soil
13+220 20.00 170.87 189.80 3,796.00 - - - - - - - - - 95 3,606.20 5 189.80 0 - Ordinary Soil
13+240 20.00 163.42 181.68 3,633.60 - - - - - - - - - 95 3,451.92 5 181.68 0 - Ordinary Soil
13+260 20.00 225.54 198.21 3,964.20 - - - - - - - - - 95 3,765.99 5 198.21 0 - Ordinary Soil
13+280 20.00 201.03 182.23 3,644.60 - - - - - - - - - 95 3,462.37 5 182.23 0 - Ordinary Soil
13+300 20.00 192.17 208.86 4,177.20 - - - - - - - - - 95 3,968.34 5 208.86 0 - Ordinary Soil
13+320 20.00 220.30 210.67 4,213.40 - - - - - - - - - 95 4,002.73 5 210.67 0 - Ordinary Soil
13+340 20.00 198.45 195.31 3,906.20 - - - - - - - - - 95 3,710.89 5 195.31 0 - Ordinary Soil
13+360 20.00 223.33 221.82 4,436.40 - - - - - - - - - 95 4,214.58 5 221.82 0 - Ordinary Soil
13+380 20.00 193.30 195.88 3,917.60 - - - - - - - - - 95 3,721.72 5 195.88 0 - Ordinary Soil
13+400 20.00 185.70 204.52 4,090.40 - - - - - - - - - 95 3,885.88 5 204.52 0 - Ordinary Soil
13+420 20.00 159.61 176.46 3,529.20 - - - - - - - - - 95 3,352.74 5 176.46 0 - Ordinary Soil
13+440 20.00 171.50 178.60 3,572.00 - - - - - - - - - 95 3,393.40 5 178.60 0 - Ordinary Soil
13+460 20.00 66.25 112.93 2,258.60 - - - - - - - - - 95 2,145.67 5 112.93 0 - Ordinary Soil
13+480 20.00 70.78 121.14 2,422.80 - - - - - - - - - 95 2,301.66 5 121.14 0 - Ordinary Soil
13+500 20.00 215.86 141.06 2,821.20 - - - - - - - - - 95 2,680.14 5 141.06 0 - Ordinary Soil
13+520 20.00 186.19 128.49 2,569.80 - - - - - - - - - 95 2,441.31 5 128.49 0 - Ordinary Soil
13+540 20.00 175.08 195.47 3,909.40 - - - - - - - - - 95 3,713.93 5 195.47 0 - Ordinary Soil
13+560 20.00 187.35 186.77 3,735.40 - - - - - - - - - 95 3,548.63 5 186.77 0 - Ordinary Soil
13+580 20.00 151.55 163.32 3,266.40 - - - - - - - - - 95 3,103.08 5 163.32 0 - Ordinary Soil
13+600 20.00 189.67 188.51 3,770.20 - - - - - - - - - 95 3,581.69 5 188.51 0 - Ordinary Soil
13+620 20.00 217.06 184.31 3,686.20 - - - - - - - - - 95 3,501.89 5 184.31 0 - Ordinary Soil
13+640 20.00 156.77 173.22 3,464.40 - - - - - - - - - 95 3,291.18 5 173.22 0 - Ordinary Soil
30 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
13+660 20.00 162.56 189.81 3,796.20 - - - - - - - - - 95 3,606.39 5 189.81 0 - Ordinary Soil
13+680 20.00 116.38 136.58 2,731.60 0.01 0.01 0.20 - - - - - - 95 2,595.02 5 136.58 0 - Ordinary Soil
13+700 20.00 99.33 130.95 2,619.00 - - - - - - - - - 95 2,488.05 5 130.95 0 - Ordinary Soil
13+720 20.00 92.39 104.39 2,087.80 - 0.01 0.20 - - - - - - 95 1,983.41 5 104.39 0 - Ordinary Soil
13+740 20.00 77.41 88.37 1,767.40 - - - - - - - - - 95 1,679.03 5 88.37 0 - Ordinary Soil
13+760 20.00 80.02 86.21 1,724.20 - - - - - - - - - 95 1,637.99 5 86.21 0 - Ordinary Soil
13+780 20.00 51.43 64.42 1,288.40 - - - - - - - - - 95 1,223.98 5 64.42 0 - Ordinary Soil
13+800 20.00 41.76 60.89 1,217.80 - - - - - - - - - 95 1,156.91 5 60.89 0 - Ordinary Soil
13+820 20.00 12.16 31.80 636.00 9.72 4.86 97.20 - - - - - - 95 604.20 5 31.80 0 - Ordinary Soil
13+840 20.00 14.72 28.24 564.80 10.13 5.07 101.40 - 10.00 17.67 176.70 5.19 51.90 95 536.56 5 28.24 0 - Ordinary Soil
13+860 20.00 13.35 12.76 255.20 8.12 8.92 178.40 - 20.00 14.28 285.60 4.07 81.40 95 242.44 5 12.76 0 - Ordinary Soil
13+880 20.00 14.11 14.42 288.40 3.67 6.90 138.00 - 20.00 9.06 181.20 2.35 47.00 95 273.98 5 14.42 0 - Ordinary Soil
13+900 20.00 11.98 12.67 253.40 0.90 4.51 90.20 - 10.00 2.72 27.20 0.76 7.60 95 240.73 5 12.67 0 - Ordinary Soil
13+920 20.00 38.96 26.54 530.80 - 1.84 36.80 - - - - - - 95 504.26 5 26.54 0 - Ordinary Soil
13+940 20.00 - 5.99 119.80 31.44 16.17 323.40 203.60 10.00 4.12 41.20 0.68 6.80 95 113.81 5 5.99 0 - Ordinary Soil
13+960 20.00 - 19.48 389.60 16.32 8.16 163.20 - 20.00 12.23 244.60 2.76 55.20 95 370.12 5 19.48 0 - Ordinary Soil
13+980 20.00 - - - 14.80 23.12 462.40 462.40 10.00 5.74 57.40 0.85 8.50 95 - 5 - 0 - Ordinary Soil
14+000 20.00 10.52 5.26 105.20 11.66 13.99 279.80 174.60 - - - - - 95 99.94 5 5.26 0 - Ordinary Soil
14+020 20.00 49.13 24.57 491.40 0.34 7.57 151.40 - - - - - - 95 466.83 5 24.57 0 - Ordinary Soil
14+040 20.00 54.45 32.49 649.80 0.29 5.98 119.60 - - - - - - 95 617.31 5 32.49 0 - Ordinary Soil
14+060 20.00 31.63 40.38 807.60 2.89 1.62 32.40 - - - - - - 95 767.22 5 40.38 0 - Ordinary Soil
14+080 20.00 11.46 32.96 659.20 - 0.15 3.00 - - - - - - 95 626.24 5 32.96 0 - Ordinary Soil
14+100 20.00 13.94 22.79 455.80 - 1.45 29.00 - 10.00 1.29 12.90 0.26 2.60 95 433.01 5 22.79 0 - Ordinary Soil
14+120 20.00 9.55 10.51 210.20 - - - - 20.00 1.20 24.00 0.23 4.60 95 199.69 5 10.51 0 - Ordinary Soil
14+140 20.00 7.96 10.95 219.00 3.27 1.64 32.80 - 20.00 2.76 55.20 0.41 8.20 95 208.05 5 10.95 0 - Ordinary Soil
14+160 20.00 7.29 8.42 168.40 4.44 2.22 44.40 - 20.00 9.13 182.60 2.24 44.80 95 159.98 5 8.42 0 - Ordinary Soil
14+180 20.00 10.97 9.47 189.40 19.43 11.35 227.00 37.60 20.00 16.33 326.60 3.52 70.40 95 179.93 5 9.47 0 - Ordinary Soil
14+200 20.00 6.69 6.99 139.80 12.81 8.63 172.60 32.80 20.00 18.84 376.80 6.20 124.00 95 132.81 5 6.99 0 - Ordinary Soil
14+220 20.00 3.93 7.45 149.00 23.95 21.69 433.80 284.80 20.00 10.34 206.80 2.25 45.00 95 141.55 5 7.45 0 - Ordinary Soil
14+240 20.00 26.55 16.62 332.40 3.82 8.32 166.40 - 10.00 8.46 84.60 2.25 22.50 95 315.78 5 16.62 0 - Ordinary Soil
14+260 20.00 7.34 5.64 112.80 84.90 54.43 1,088.60 975.80 - - - - - 95 107.16 5 5.64 0 - Ordinary Soil
14+280 20.00 6.50 16.53 330.60 57.32 30.57 611.40 280.80 10.00 4.63 46.30 0.93 9.30 95 314.07 5 16.53 0 - Ordinary Soil
14+300 20.00 1.41 4.38 87.60 65.67 75.29 1,505.80 1,418.20 20.00 37.27 745.40 16.67 333.40 95 83.22 5 4.38 0 - Ordinary Soil
14+320 20.00 6.47 6.49 129.80 15.54 36.43 728.60 598.80 20.00 21.52 430.40 7.17 143.40 95 123.31 5 6.49 0 - Ordinary Soil
14+340 20.00 1.61 1.51 30.20 32.77 49.22 984.40 954.20 20.00 9.81 196.20 3.58 71.60 95 28.69 5 1.51 0 - Ordinary Soil
14+360 20.00 12.52 9.50 190.00 11.34 13.44 268.80 78.80 20.00 5.66 113.20 0.80 16.00 95 180.50 5 9.50 0 - Ordinary Soil
14+380 20.00 20.59 11.10 222.00 1.88 17.33 346.60 124.60 10.00 2.72 27.20 0.70 7.00 95 210.90 5 11.10 0 - Ordinary Soil
14+400 20.00 28.62 20.57 411.40 - 5.67 113.40 - - - - - - 95 390.83 5 20.57 0 - Ordinary Soil
14+420 20.00 14.96 17.78 355.60 - 0.94 18.80 - 10.00 1.67 16.70 0.40 4.00 95 337.82 5 17.78 0 - Ordinary Soil
14+440 20.00 9.62 19.12 382.40 4.17 2.09 41.80 - 20.00 9.43 188.60 2.33 46.60 95 363.28 5 19.12 0 - Ordinary Soil
14+460 20.00 5.97 10.47 209.40 1.53 0.77 15.40 - 20.00 2.53 50.60 0.64 12.80 95 198.93 5 10.47 0 - Ordinary Soil
14+480 20.00 2.05 5.84 116.80 3.49 3.83 76.60 - 10.00 1.07 10.70 0.17 1.70 95 110.96 5 5.84 0 - Ordinary Soil
14+500 20.00 1.48 3.73 74.60 4.02 2.78 55.60 - - - - - - 95 70.87 5 3.73 0 - Ordinary Soil
31 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
14+520 20.00 3.32 2.69 53.80 0.13 1.81 36.20 - - - - - - 95 51.11 5 2.69 0 - Ordinary Soil
14+540 20.00 3.90 2.69 53.80 5.00 4.51 90.20 36.40 - - - - - 95 51.11 5 2.69 0 - Ordinary Soil
14+560 20.00 10.62 6.97 139.40 1.16 0.65 13.00 - - - - - - 95 132.43 5 6.97 0 - Ordinary Soil
14+580 20.00 4.08 3.99 79.80 6.53 5.77 115.40 35.60 - - - - - 95 75.81 5 3.99 0 - Ordinary Soil
14+600 20.00 27.56 19.09 381.80 1.92 1.54 30.80 - - - - - - 95 362.71 5 19.09 0 - Ordinary Soil
14+620 20.00 20.33 12.21 244.20 3.64 5.09 101.80 - - - - - - 95 231.99 5 12.21 0 - Ordinary Soil
14+640 20.00 26.70 27.13 542.60 5.78 3.85 77.00 - 10.00 6.20 62.00 1.33 13.30 95 515.47 5 27.13 0 - Ordinary Soil
14+660 20.00 14.59 17.46 349.20 9.51 6.58 131.60 - 20.00 3.91 78.20 0.47 9.40 95 331.74 5 17.46 0 - Ordinary Soil
14+680 20.00 9.23 17.97 359.40 12.73 9.26 185.20 - 20.00 4.11 82.20 0.28 5.60 95 341.43 5 17.97 0 - Ordinary Soil
14+700 20.00 16.40 15.50 310.00 4.05 6.78 135.60 - 20.00 9.62 192.40 2.37 47.40 95 294.50 5 15.50 0 - Ordinary Soil
14+720 20.00 12.75 10.99 219.80 6.40 9.57 191.40 - 20.00 2.66 53.20 0.19 3.80 95 208.81 5 10.99 0 - Ordinary Soil
14+740 20.00 26.89 21.65 433.00 1.37 2.71 54.20 - 20.00 4.58 91.60 1.02 20.40 95 411.35 5 21.65 0 - Ordinary Soil
14+760 20.00 73.41 43.08 861.60 0.45 3.43 68.60 - 20.00 5.31 106.20 1.52 30.40 95 818.52 5 43.08 0 - Ordinary Soil
14+780 20.00 8.16 17.53 350.60 17.13 9.25 185.00 - 20.00 7.78 155.60 1.53 30.60 95 333.07 5 17.53 0 - Ordinary Soil
14+800 20.00 30.15 51.78 1,035.60 0.28 0.37 7.40 - 10.00 1.36 13.60 0.33 3.30 95 983.82 5 51.78 0 - Ordinary Soil
14+820 20.00 36.39 22.28 445.60 - 8.57 171.40 - - - - - - 95 423.32 5 22.28 0 - Ordinary Soil
14+840 20.00 20.40 25.28 505.60 - 0.14 2.80 - 10.00 1.42 14.20 0.28 2.80 95 480.32 5 25.28 0 - Ordinary Soil
14+860 20.00 14.17 25.28 505.60 3.99 2.00 40.00 - 20.00 1.74 34.80 0.17 3.40 95 480.32 5 25.28 0 - Ordinary Soil
14+880 20.00 0.86 10.63 212.60 13.34 6.67 133.40 - 20.00 5.47 109.40 0.72 14.40 95 201.97 5 10.63 0 - Ordinary Soil
14+900 20.00 1.78 7.98 159.60 4.73 4.36 87.20 - 20.00 2.96 59.20 0.36 7.20 95 151.62 5 7.98 0 - Ordinary Soil
14+920 20.00 0.59 0.73 14.60 6.01 9.68 193.60 179.00 20.00 0.98 19.60 - - 95 13.87 5 0.73 0 - Ordinary Soil
14+940 20.00 0.39 1.09 21.80 8.20 6.47 129.40 107.60 20.00 2.24 44.80 0.18 3.60 95 20.71 5 1.09 0 - Ordinary Soil
14+960 20.00 1.49 1.04 20.80 7.49 6.75 135.00 114.20 10.00 2.25 22.50 0.17 1.70 95 19.76 5 1.04 0 - Ordinary Soil
14+980 20.00 19.18 9.79 195.80 1.93 5.07 101.40 - - - - - - 95 186.01 5 9.79 0 - Ordinary Soil
15+000 20.00 21.28 11.39 227.80 0.09 3.79 75.80 - - - - - - 95 216.41 5 11.39 0 - Ordinary Soil
15+020 20.00 11.42 15.30 306.00 2.51 2.22 44.40 - 10.00 2.13 21.30 0.18 1.80 95 290.70 5 15.30 0 - Ordinary Soil
15+040 20.00 0.07 10.68 213.60 11.22 5.66 113.20 - 20.00 2.76 55.20 0.18 3.60 95 202.92 5 10.68 0 - Ordinary Soil
15+060 20.00 - 5.71 114.20 11.00 6.76 135.20 21.00 20.00 1.64 32.80 0.03 0.60 95 108.49 5 5.71 0 - Ordinary Soil
15+080 20.00 7.62 3.85 77.00 1.37 6.30 126.00 49.00 20.00 2.49 49.80 0.65 13.00 95 73.15 5 3.85 0 - Ordinary Soil
15+100 20.00 4.89 2.45 49.00 1.97 6.49 129.80 80.80 20.00 1.04 20.80 0.18 3.60 95 46.55 5 2.45 0 - Ordinary Soil
15+120 20.00 - 3.81 76.20 23.80 12.59 251.80 175.60 20.00 3.05 61.00 0.24 4.80 95 72.39 5 3.81 0 - Ordinary Soil
15+140 20.00 6.57 5.73 114.60 8.21 5.09 101.80 - 20.00 2.72 54.40 0.24 4.80 95 108.87 5 5.73 0 - Ordinary Soil
15+160 20.00 28.10 14.05 281.00 0.24 12.02 240.40 - 10.00 1.56 15.60 0.39 3.90 95 266.95 5 14.05 0 - Ordinary Soil
15+180 20.00 30.02 18.30 366.00 - 4.11 82.20 - - - - - - 95 347.70 5 18.30 0 - Ordinary Soil
15+200 20.00 12.52 20.31 406.20 1.08 0.66 13.20 - 10.00 1.99 19.90 0.27 2.70 95 385.89 5 20.31 0 - Ordinary Soil
15+220 20.00 7.38 18.70 374.00 6.54 3.27 65.40 - 20.00 1.66 33.20 0.05 1.00 95 355.30 5 18.70 0 - Ordinary Soil
15+240 20.00 11.26 11.89 237.80 0.78 0.93 18.60 - 20.00 1.46 29.20 0.32 6.40 95 225.91 5 11.89 0 - Ordinary Soil
15+260 20.00 17.01 12.20 244.00 4.44 5.49 109.80 - 20.00 2.58 51.60 0.56 11.20 95 231.80 5 12.20 0 - Ordinary Soil
15+280 20.00 16.65 13.96 279.20 11.35 6.07 121.40 - 20.00 1.80 36.00 0.04 0.80 95 265.24 5 13.96 0 - Ordinary Soil
15+300 20.00 3.12 10.07 201.40 8.41 6.43 128.60 - 20.00 3.00 60.00 0.29 5.80 95 191.33 5 10.07 0 - Ordinary Soil
15+320 20.00 10.51 13.58 271.60 3.48 7.42 148.40 - 20.00 1.60 32.00 0.06 1.20 95 258.02 5 13.58 0 - Ordinary Soil
15+340 20.00 2.25 2.69 53.80 4.57 6.49 129.80 76.00 20.00 1.10 22.00 0.17 3.40 95 51.11 5 2.69 0 - Ordinary Soil
15+360 20.00 - 5.26 105.20 10.90 7.19 143.80 38.60 20.00 2.48 49.60 0.48 9.60 95 99.94 5 5.26 0 - Ordinary Soil
32 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
15+380 20.00 2.82 2.54 50.80 11.20 7.89 157.80 107.00 20.00 0.22 4.40 - - 95 48.26 5 2.54 0 - Ordinary Soil
15+400 20.00 15.93 7.97 159.40 5.54 8.22 164.40 5.00 20.00 2.06 41.20 0.15 3.00 95 151.43 5 7.97 0 - Ordinary Soil
15+420 20.00 21.08 11.95 239.00 0.79 6.00 120.00 - 20.00 2.46 49.20 0.37 7.40 95 227.05 5 11.95 0 - Ordinary Soil
15+440 20.00 - 7.97 159.40 19.43 12.49 249.80 90.40 20.00 1.78 35.60 0.06 1.20 95 151.43 5 7.97 0 - Ordinary Soil
15+460 20.00 2.70 11.89 237.80 10.38 5.59 111.80 - 20.00 4.35 87.00 0.49 9.80 95 225.91 5 11.89 0 - Ordinary Soil
15+480 20.00 6.22 3.11 62.20 2.85 11.14 222.80 160.60 20.00 4.26 85.20 0.66 13.20 95 59.09 5 3.11 0 - Ordinary Soil
15+500 20.00 9.81 6.26 125.20 5.74 8.06 161.20 36.00 20.00 3.27 65.40 0.37 7.40 95 118.94 5 6.26 0 - Ordinary Soil
15+520 20.00 9.68 7.95 159.00 0.94 1.90 38.00 - 20.00 2.17 43.40 0.55 11.00 95 151.05 5 7.95 0 - Ordinary Soil
15+540 20.00 15.33 12.57 251.40 2.01 3.88 77.60 - 20.00 2.12 42.40 0.22 4.40 95 238.83 5 12.57 0 - Ordinary Soil
15+560 20.00 32.52 21.10 422.00 0.43 0.69 13.80 - 10.00 1.33 13.30 0.29 2.90 95 400.90 5 21.10 0 - Ordinary Soil
15+580 20.00 52.41 33.87 677.40 - 1.01 20.20 - - - - - - 95 643.53 5 33.87 0 - Ordinary Soil
15+600 20.00 44.88 38.70 774.00 - 0.22 4.40 - - - - - - 95 735.30 5 38.70 0 - Ordinary Soil
15+620 20.00 44.17 48.29 965.80 - - - - - - - - - 95 917.51 5 48.29 0 - Ordinary Soil
15+640 20.00 7.13 26.01 520.20 3.20 1.60 32.00 - 10.00 2.19 21.90 0.46 4.60 95 494.19 5 26.01 0 - Ordinary Soil
15+660 20.00 0.50 22.34 446.80 6.76 3.38 67.60 - 20.00 3.90 78.00 0.48 9.60 95 424.46 5 22.34 0 - Ordinary Soil
15+680 20.00 1.63 4.38 87.60 5.96 4.58 91.60 4.00 20.00 1.19 23.80 - - 95 83.22 5 4.38 0 - Ordinary Soil
15+700 20.00 3.81 2.16 43.20 6.65 6.71 134.20 91.00 20.00 3.81 76.20 0.45 9.00 95 41.04 5 2.16 0 - Ordinary Soil
15+720 20.00 18.95 10.29 205.80 1.64 3.80 76.00 - 20.00 2.45 49.00 0.29 5.80 95 195.51 5 10.29 0 - Ordinary Soil
15+740 20.00 22.53 13.17 263.40 1.14 3.90 78.00 - 20.00 2.15 43.00 0.28 5.60 95 250.23 5 13.17 0 - Ordinary Soil
15+760 20.00 5.95 12.45 249.00 6.26 3.95 79.00 - 20.00 3.26 65.20 0.36 7.20 95 236.55 5 12.45 0 - Ordinary Soil
15+780 20.00 2.98 12.76 255.20 4.82 2.98 59.60 - 20.00 2.98 59.60 0.35 7.00 95 242.44 5 12.76 0 - Ordinary Soil
15+800 20.00 10.08 8.02 160.40 2.76 4.51 90.20 - 20.00 1.94 38.80 0.17 3.40 95 152.38 5 8.02 0 - Ordinary Soil
15+820 20.00 26.27 14.63 292.60 1.85 3.34 66.80 - 20.00 1.98 39.60 0.20 4.00 95 277.97 5 14.63 0 - Ordinary Soil
15+840 20.00 4.60 7.34 146.80 0.28 1.52 30.40 - 20.00 1.18 23.60 0.25 5.00 95 139.46 5 7.34 0 - Ordinary Soil
15+860 20.00 4.82 15.55 311.00 7.75 4.80 96.00 - 20.00 5.44 108.80 0.81 16.20 95 295.45 5 15.55 0 - Ordinary Soil
15+880 20.00 12.46 8.53 170.60 3.32 1.80 36.00 - 20.00 1.54 30.80 0.08 1.60 95 162.07 5 8.53 0 - Ordinary Soil
15+900 20.00 21.55 13.19 263.80 1.20 4.48 89.60 - 20.00 2.50 50.00 0.34 6.80 95 250.61 5 13.19 0 - Ordinary Soil
15+920 20.00 20.54 16.50 330.00 2.80 3.06 61.20 - 20.00 1.40 28.00 0.05 1.00 95 313.50 5 16.50 0 - Ordinary Soil
15+940 20.00 9.31 15.43 308.60 5.47 3.34 66.80 - 20.00 4.59 91.80 0.68 13.60 95 293.17 5 15.43 0 - Ordinary Soil
15+960 20.00 7.23 13.89 277.80 12.14 7.47 149.40 - 20.00 20.22 404.40 5.65 113.00 95 263.91 5 13.89 0 - Ordinary Soil
15+980 20.00 1.35 5.33 106.60 22.12 13.80 276.00 169.40 20.00 12.51 250.20 2.68 53.60 95 101.27 5 5.33 0 - Ordinary Soil
16+000 20.00 24.60 15.92 318.40 2.45 7.30 146.00 - 20.00 6.94 138.80 1.60 32.00 95 302.48 5 15.92 0 - Ordinary Soil
16+020 20.00 11.42 6.39 127.80 10.39 16.26 325.20 197.40 20.00 6.66 133.20 1.14 22.80 95 121.41 5 6.39 0 - Ordinary Soil
16+040 20.00 20.02 22.31 446.20 7.52 4.99 99.80 - 20.00 11.53 230.60 2.76 55.20 95 423.89 5 22.31 0 - Ordinary Soil
16+060 20.00 33.07 22.25 445.00 4.13 7.26 145.20 - 20.00 5.91 118.20 1.15 23.00 95 422.75 5 22.25 0 - Ordinary Soil
16+080 20.00 28.75 24.39 487.80 4.26 5.89 117.80 - 20.00 6.14 122.80 1.13 22.60 95 463.41 5 24.39 0 - Ordinary Soil
16+100 20.00 4.50 18.79 375.80 8.45 6.29 125.80 - 20.00 7.38 147.60 1.29 25.80 95 357.01 5 18.79 0 - Ordinary Soil
16+120 20.00 1.17 14.96 299.20 13.99 9.13 182.60 - 20.00 9.11 182.20 1.72 34.40 95 284.24 5 14.96 0 - Ordinary Soil
16+140 20.00 0.01 2.26 45.20 67.68 38.07 761.40 716.20 10.00 2.42 24.20 0.30 3.00 95 42.94 5 2.26 0 - Ordinary Soil
16+160 20.00 - 0.59 11.80 102.19 58.09 1,161.80 1,150.00 - - - - - 95 11.21 5 0.59 0 - Ordinary Soil
16+180 20.00 - 0.01 0.20 103.97 85.83 1,716.60 1,716.40 - - - - - 95 0.19 5 0.01 0 - Ordinary Soil
16+200 20.00 21.39 10.70 214.00 0.20 51.20 1,024.00 810.00 7.00 0.79 5.53 0.13 0.91 95 203.30 5 10.70 0 - Ordinary Soil
16+220 20.00 87.83 43.92 878.40 - 51.99 1,039.80 161.40 - - - - - 95 834.48 5 43.92 0 - Ordinary Soil
33 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
16+240 20.00 19.31 20.35 407.00 3.89 2.05 41.00 - 10.00 6.02 60.20 1.19 11.90 95 386.65 5 20.35 0 - Ordinary Soil
16+260 20.00 12.94 50.39 1,007.80 4.19 2.10 42.00 - 20.00 6.35 127.00 1.23 24.60 95 957.41 5 50.39 0 - Ordinary Soil
16+280 20.00 4.06 11.69 233.80 15.58 9.74 194.80 - 20.00 16.94 338.80 4.20 84.00 95 222.11 5 11.69 0 - Ordinary Soil
16+300 20.00 5.56 9.25 185.00 16.77 10.48 209.60 24.60 20.00 14.66 293.20 3.47 69.40 95 175.75 5 9.25 0 - Ordinary Soil
16+320 20.00 26.56 15.31 306.20 5.85 10.72 214.40 - 20.00 12.24 244.80 3.24 64.80 95 290.89 5 15.31 0 - Ordinary Soil
16+340 20.00 53.83 29.70 594.00 2.14 9.46 189.20 - 20.00 7.28 145.60 1.72 34.40 95 564.30 5 29.70 0 - Ordinary Soil
16+360 20.00 58.97 42.77 855.40 2.60 4.23 84.60 - 20.00 21.28 425.60 7.84 156.80 95 812.63 5 42.77 0 - Ordinary Soil
16+380 20.00 46.11 49.97 999.40 4.69 3.42 68.40 - 10.00 22.95 229.50 9.11 91.10 95 949.43 5 49.97 0 - Ordinary Soil
16+400 20.00 64.28 61.63 1,232.60 - 1.30 26.00 - - - - - - 95 1,170.97 5 61.63 0 - Ordinary Soil
16+420 20.00 161.67 103.89 2,077.80 - 2.35 47.00 - - - - - - 95 1,973.91 5 103.89 0 - Ordinary Soil
16+440 20.00 195.83 130.06 2,601.20 - - - - - - - - - 95 2,471.14 5 130.06 0 - Ordinary Soil
16+460 20.00 125.50 143.59 2,871.80 - - - - - - - - - 95 2,728.21 5 143.59 0 - Ordinary Soil
16+480 20.00 127.70 161.77 3,235.40 - - - - - - - - - 95 3,073.63 5 161.77 0 - Ordinary Soil
16+500 20.00 173.26 149.38 2,987.60 - - - - - - - - - 95 2,838.22 5 149.38 0 - Ordinary Soil
16+520 20.00 177.27 152.49 3,049.80 - - - - - - - - - 95 2,897.31 5 152.49 0 - Ordinary Soil
16+540 20.00 163.86 168.56 3,371.20 - - - - - - - - - 95 3,202.64 5 168.56 0 - Ordinary Soil
16+560 20.00 99.00 138.14 2,762.80 - - - - - - - - - 95 2,624.66 5 138.14 0 - Ordinary Soil
16+580 20.00 72.83 118.35 2,367.00 - - - - - - - - - 95 2,248.65 5 118.35 0 - Ordinary Soil
16+600 20.00 75.12 87.06 1,741.20 - - - - - - - - - 95 1,654.14 5 87.06 0 - Ordinary Soil
16+620 20.00 75.07 73.95 1,479.00 - - - - - - - - - 95 1,405.05 5 73.95 0 - Ordinary Soil
16+640 20.00 121.16 98.14 1,962.80 - - - - - - - - - 95 1,864.66 5 98.14 0 - Ordinary Soil
16+660 20.00 165.01 120.04 2,400.80 - - - - - - - - - 95 2,280.76 5 120.04 0 - Ordinary Soil
16+680 20.00 162.01 141.59 2,831.80 - - - - - - - - - 95 2,690.21 5 141.59 0 - Ordinary Soil
16+700 20.00 162.30 163.66 3,273.20 0.01 0.01 0.20 - - - - - - 95 3,109.54 5 163.66 0 - Ordinary Soil
16+720 20.00 103.65 132.83 2,656.60 - - - - - - - - - 95 2,523.77 5 132.83 0 - Ordinary Soil
16+740 20.00 124.10 143.20 2,864.00 - 0.01 0.20 - - - - - - 95 2,720.80 5 143.20 0 - Ordinary Soil
16+760 20.00 109.84 106.75 2,135.00 - - - - - - - - - 95 2,028.25 5 106.75 0 - Ordinary Soil
16+780 20.00 110.84 117.47 2,349.40 - - - - - - - - - 95 2,231.93 5 117.47 0 - Ordinary Soil
16+800 20.00 65.28 87.56 1,751.20 - - - - - - - - - 95 1,663.64 5 87.56 0 - Ordinary Soil
16+820 20.00 44.91 77.88 1,557.60 1.46 0.73 14.60 - 10.00 4.76 47.60 0.96 9.60 95 1,479.72 5 77.88 0 - Ordinary Soil
16+840 20.00 51.00 58.14 1,162.80 1.45 0.73 14.60 - 10.00 1.83 18.30 0.22 2.20 95 1,104.66 5 58.14 0 - Ordinary Soil
16+860 20.00 98.07 71.49 1,429.80 2.11 1.79 35.80 - - - - - - 95 1,358.31 5 71.49 0 - Ordinary Soil
16+880 20.00 49.66 50.33 1,006.60 4.97 3.21 64.20 - 10.00 9.63 96.30 3.50 35.00 95 956.27 5 50.33 0 - Ordinary Soil
16+900 20.00 32.51 65.29 1,305.80 7.18 4.65 93.00 - 20.00 7.02 140.40 2.38 47.60 95 1,240.51 5 65.29 0 - Ordinary Soil
16+920 20.00 28.57 39.12 782.40 20.39 12.68 253.60 - 20.00 0.15 3.00 - - 95 743.28 5 39.12 0 - Ordinary Soil
16+940 20.00 33.24 32.88 657.60 9.57 8.38 167.60 - 20.00 12.91 258.20 3.46 69.20 95 624.72 5 32.88 0 - Ordinary Soil
16+960 20.00 37.25 32.91 658.20 2.01 11.20 224.00 - 20.00 11.40 228.00 3.48 69.60 95 625.29 5 32.91 0 - Ordinary Soil
16+980 20.00 32.92 33.08 661.60 4.64 7.11 142.20 - 20.00 12.93 258.60 3.70 74.00 95 628.52 5 33.08 0 - Ordinary Soil
17+000 20.00 42.60 39.93 798.60 8.53 5.27 105.40 - 20.00 3.34 66.80 0.83 16.60 95 758.67 5 39.93 0 - Ordinary Soil
17+020 20.00 14.56 23.74 474.80 9.18 6.91 138.20 - 20.00 10.21 204.20 2.24 44.80 95 451.06 5 23.74 0 - Ordinary Soil
17+040 20.00 8.44 25.52 510.40 10.01 9.27 185.40 - 20.00 7.17 143.40 1.73 34.60 95 484.88 5 25.52 0 - Ordinary Soil
17+060 20.00 11.18 12.87 257.40 10.86 10.02 200.40 - 20.00 2.83 56.60 0.56 11.20 95 244.53 5 12.87 0 - Ordinary Soil
17+080 20.00 8.55 8.50 170.00 12.07 11.04 220.80 50.80 20.00 10.54 210.80 2.75 55.00 95 161.50 5 8.50 0 - Ordinary Soil
34 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
17+100 20.00 11.57 11.38 227.60 12.75 11.81 236.20 8.60 20.00 14.43 288.60 4.38 87.60 95 216.22 5 11.38 0 - Ordinary Soil
17+120 20.00 24.87 16.71 334.20 11.36 11.72 234.40 - 20.00 9.30 186.00 2.80 56.00 95 317.49 5 16.71 0 - Ordinary Soil
17+140 20.00 47.00 29.29 585.80 5.78 9.27 185.40 - 20.00 16.52 330.40 5.27 105.40 95 556.51 5 29.29 0 - Ordinary Soil
17+160 20.00 12.21 18.54 370.80 2.65 7.01 140.20 - 20.00 3.25 65.00 0.93 18.60 95 352.26 5 18.54 0 - Ordinary Soil
17+180 20.00 36.30 41.65 833.00 3.72 4.75 95.00 - 20.00 3.02 60.40 0.42 8.40 95 791.35 5 41.65 0 - Ordinary Soil
17+200 20.00 34.70 23.46 469.20 3.53 3.09 61.80 - 10.00 6.17 61.70 1.35 13.50 95 445.74 5 23.46 0 - Ordinary Soil
17+220 20.00 108.78 72.54 1,450.80 - 1.86 37.20 - - - - - - 95 1,378.26 5 72.54 0 - Ordinary Soil
17+240 20.00 156.20 95.45 1,909.00 - 1.77 35.40 - 10.00 45.23 452.30 0.68 6.80 95 1,813.55 5 95.45 0 - Ordinary Soil
17+260 20.00 107.72 108.25 2,165.00 - - - - 20.00 39.28 785.60 1.27 25.40 95 2,056.75 5 108.25 0 - Ordinary Soil
17+280 20.00 71.79 114.00 2,280.00 1.08 0.54 10.80 - 20.00 35.83 716.60 2.07 41.40 95 2,166.00 5 114.00 0 - Ordinary Soil
17+300 20.00 76.91 92.32 1,846.40 - - - - 10.00 25.30 253.00 0.66 6.60 95 1,754.08 5 92.32 0 - Ordinary Soil
17+320 20.00 18.10 44.95 899.00 2.61 1.85 37.00 - - - - - - 95 854.05 5 44.95 0 - Ordinary Soil
17+340 20.00 0.69 38.80 776.00 8.53 4.27 85.40 - - - - - - 95 737.20 5 38.80 0 - Ordinary Soil
17+360 20.00 - 9.05 181.00 21.09 11.85 237.00 56.00 - - - - - 95 171.95 5 9.05 0 - Ordinary Soil
17+380 20.00 22.50 11.60 232.00 9.47 9.00 180.00 - 10.00 2.23 22.30 0.08 0.80 95 220.40 5 11.60 0 - Ordinary Soil
17+400 20.00 28.45 14.23 284.60 2.63 11.86 237.20 - 20.00 4.05 81.00 0.62 12.40 95 270.37 5 14.23 0 - Ordinary Soil
17+420 20.00 6.85 14.68 293.60 10.61 10.04 200.80 - 10.00 5.80 58.00 0.97 9.70 95 278.92 5 14.68 0 - Ordinary Soil
17+440 20.00 41.73 35.09 701.80 0.01 1.32 26.40 - - - - - - 95 666.71 5 35.09 0 - Ordinary Soil
17+460 20.00 84.32 45.59 911.80 - 5.31 106.20 - - - - - - 95 866.21 5 45.59 0 - Ordinary Soil
17+480 20.00 15.46 28.60 572.00 14.45 7.23 144.60 - 10.00 16.81 168.10 4.16 41.60 95 543.40 5 28.60 0 - Ordinary Soil
17+500 20.00 - 42.16 843.20 30.03 15.02 300.40 - 20.00 15.32 306.40 3.43 68.60 95 801.04 5 42.16 0 - Ordinary Soil
17+520 20.00 56.52 35.99 719.80 0.10 7.28 145.60 - 10.00 2.93 29.30 0.97 9.70 95 683.81 5 35.99 0 - Ordinary Soil
17+540 20.00 96.48 48.24 964.80 - 15.02 300.40 - - - - - - 95 916.56 5 48.24 0 - Ordinary Soil
17+560 20.00 94.40 75.46 1,509.20 - 0.05 1.00 - - - - - - 95 1,433.74 5 75.46 0 - Ordinary Soil
17+580 20.00 150.64 123.56 2,471.20 - - - - 10.00 48.34 483.40 0.69 6.90 95 2,347.64 5 123.56 0 - Ordinary Soil
17+600 20.00 85.05 89.73 1,794.60 0.01 0.01 0.20 - 10.00 19.96 199.60 0.94 9.40 95 1,704.87 5 89.73 0 - Ordinary Soil
17+620 20.00 59.16 104.90 2,098.00 - - - - - - - - - 95 1,993.10 5 104.90 0 - Ordinary Soil
17+640 20.00 88.11 86.58 1,731.60 - 0.01 0.20 - 7.00 21.23 148.61 1.02 7.14 95 1,645.02 5 86.58 0 - Ordinary Soil
17+660 20.00 61.46 60.31 1,206.20 - - - - - - - - - 95 1,145.89 5 60.31 0 - Ordinary Soil
17+680 20.00 61.05 74.58 1,491.60 - - - - - - - - - 95 1,417.02 5 74.58 0 - Ordinary Soil
17+700 20.00 45.74 53.60 1,072.00 0.88 0.44 8.80 - 10.00 2.88 28.80 0.90 9.00 95 1,018.40 5 53.60 0 - Ordinary Soil
17+720 20.00 50.01 55.53 1,110.60 0.31 0.16 3.20 - 10.00 2.43 24.30 0.74 7.40 95 1,055.07 5 55.53 0 - Ordinary Soil
17+740 20.00 97.50 71.62 1,432.40 - 0.44 8.80 - - - - - - 95 1,360.78 5 71.62 0 - Ordinary Soil
17+760 20.00 97.41 73.71 1,474.20 - 0.16 3.20 - - - - - - 95 1,400.49 5 73.71 0 - Ordinary Soil
17+780 20.00 66.75 82.13 1,642.60 0.15 0.08 1.60 - 10.00 1.56 15.60 0.40 4.00 95 1,560.47 5 82.13 0 - Ordinary Soil
17+800 20.00 58.13 77.77 1,555.40 0.47 0.24 4.80 - 10.00 2.77 27.70 0.48 4.80 95 1,477.63 5 77.77 0 - Ordinary Soil
17+820 20.00 157.79 112.27 2,245.40 - 0.08 1.60 - - - - - - 95 2,133.13 5 112.27 0 - Ordinary Soil
17+840 20.00 33.63 45.88 917.60 5.23 2.85 57.00 - 10.00 7.86 78.60 1.91 19.10 95 871.72 5 45.88 0 - Ordinary Soil
17+860 20.00 26.78 92.29 1,845.80 6.96 3.48 69.60 - 20.00 7.39 147.80 1.48 29.60 95 1,753.51 5 92.29 0 - Ordinary Soil
17+880 20.00 72.58 53.11 1,062.20 0.03 2.63 52.60 - 10.00 1.93 19.30 0.57 5.70 95 1,009.09 5 53.11 0 - Ordinary Soil
17+900 20.00 59.63 43.21 864.20 - 3.48 69.60 - - - - - - 95 820.99 5 43.21 0 - Ordinary Soil
17+920 20.00 3.81 38.20 764.00 13.56 6.80 136.00 - 10.00 2.70 27.00 0.22 2.20 95 725.80 5 38.20 0 - Ordinary Soil
17+940 20.00 7.53 33.58 671.60 5.78 2.89 57.80 - 20.00 5.73 114.60 0.99 19.80 95 638.02 5 33.58 0 - Ordinary Soil
35 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
17+960 20.00 15.00 9.41 188.20 2.81 8.19 163.80 - 20.00 4.07 81.40 0.61 12.20 95 178.79 5 9.41 0 - Ordinary Soil
17+980 20.00 22.95 15.24 304.80 0.63 3.21 64.20 - 10.00 1.21 12.10 0.25 2.50 95 289.56 5 15.24 0 - Ordinary Soil
18+000 20.00 45.93 30.47 609.40 - 1.41 28.20 - - - - - - 95 578.93 5 30.47 0 - Ordinary Soil
18+020 20.00 5.52 14.24 284.80 11.54 6.09 121.80 - 10.00 9.72 97.20 1.96 19.60 95 270.56 5 14.24 0 - Ordinary Soil
18+040 20.00 - 22.97 459.40 25.60 12.80 256.00 - 20.00 13.17 263.40 2.60 52.00 95 436.43 5 22.97 0 - Ordinary Soil
18+060 20.00 15.93 10.73 214.60 2.54 7.04 140.80 - 20.00 1.87 37.40 0.41 8.20 95 203.87 5 10.73 0 - Ordinary Soil
18+080 20.00 6.60 3.30 66.00 10.54 18.07 361.40 295.40 20.00 6.47 129.40 1.05 21.00 95 62.70 5 3.30 0 - Ordinary Soil
18+100 20.00 16.75 16.34 326.80 4.94 3.74 74.80 - 20.00 4.84 96.80 0.88 17.60 95 310.46 5 16.34 0 - Ordinary Soil
18+120 20.00 39.51 23.06 461.20 1.09 5.82 116.40 - 20.00 2.64 52.80 0.74 14.80 95 438.14 5 23.06 0 - Ordinary Soil
18+140 20.00 54.11 35.43 708.60 - 2.47 49.40 - 20.00 0.48 9.60 0.05 1.00 95 673.17 5 35.43 0 - Ordinary Soil
18+160 20.00 36.16 37.84 756.80 0.49 0.79 15.80 - 20.00 2.03 40.60 0.55 11.00 95 718.96 5 37.84 0 - Ordinary Soil
18+180 20.00 12.23 33.17 663.40 8.20 4.10 82.00 - 20.00 5.72 114.40 1.05 21.00 95 630.23 5 33.17 0 - Ordinary Soil
18+200 20.00 15.57 25.87 517.40 7.66 4.08 81.60 - 20.00 6.04 120.80 1.15 23.00 95 491.53 5 25.87 0 - Ordinary Soil
18+220 20.00 17.87 15.05 301.00 4.14 6.17 123.40 - 20.00 5.71 114.20 1.12 22.40 95 285.95 5 15.05 0 - Ordinary Soil
18+240 20.00 7.75 11.66 233.20 10.68 9.17 183.40 - 20.00 5.49 109.80 0.85 17.00 95 221.54 5 11.66 0 - Ordinary Soil
18+260 20.00 22.88 20.38 407.60 1.11 2.63 52.60 - 20.00 2.45 49.00 0.65 13.00 95 387.22 5 20.38 0 - Ordinary Soil
18+280 20.00 63.30 35.53 710.60 1.68 6.18 123.60 - 20.00 2.99 59.80 0.85 17.00 95 675.07 5 35.53 0 - Ordinary Soil
18+300 20.00 155.36 89.12 1,782.40 29.68 15.40 308.00 - 20.00 0.60 12.00 0.10 2.00 95 1,693.28 5 89.12 0 - Ordinary Soil
18+320 20.00 29.48 46.39 927.80 32.90 17.29 345.80 - 20.00 1.72 34.40 0.26 5.20 95 881.41 5 46.39 0 - Ordinary Soil
18+340 20.00 49.83 102.60 2,052.00 35.07 32.38 647.60 - 20.00 2.22 44.40 0.38 7.60 95 1,949.40 5 102.60 0 - Ordinary Soil
18+360 20.00 38.97 34.23 684.60 10.34 21.62 432.40 - 20.00 9.15 183.00 1.57 31.40 95 650.37 5 34.23 0 - Ordinary Soil
18+380 20.00 - 24.92 498.40 46.66 40.87 817.40 319.00 20.00 1.11 22.20 0.26 5.20 95 473.48 5 24.92 0 - Ordinary Soil
18+400 20.00 0.98 19.98 399.60 74.64 42.49 849.80 450.20 20.00 8.44 168.80 1.91 38.20 95 379.62 5 19.98 0 - Ordinary Soil
18+420 20.00 41.78 20.89 417.80 7.23 26.95 539.00 121.20 20.00 15.40 308.00 4.49 89.80 95 396.91 5 20.89 0 - Ordinary Soil
18+440 20.00 229.73 115.36 2,307.20 - 37.32 746.40 - 20.00 1.17 23.40 0.21 4.20 95 2,191.84 5 115.36 0 - Ordinary Soil
18+460 20.00 191.66 116.72 2,334.40 4.30 5.77 115.40 - 20.00 33.33 666.60 14.13 282.60 95 2,217.68 5 116.72 0 - Ordinary Soil
18+480 20.00 123.02 176.38 3,527.60 6.96 3.48 69.60 - 20.00 15.96 319.20 7.46 149.20 95 3,351.22 5 176.38 0 - Ordinary Soil
18+500 20.00 133.59 162.63 3,252.60 - 2.15 43.00 - 20.00 41.79 835.80 0.68 13.60 95 3,089.97 5 162.63 0 - Ordinary Soil
18+520 20.00 129.83 126.43 2,528.60 - 3.48 69.60 - 20.00 39.54 790.80 0.75 15.00 95 2,402.17 5 126.43 0 - Ordinary Soil
18+540 20.00 53.88 93.74 1,874.80 - - - - 20.00 20.70 414.00 0.73 14.60 95 1,781.06 5 93.74 0 - Ordinary Soil
18+560 20.00 31.90 80.87 1,617.40 0.42 0.21 4.20 - 20.00 1.15 23.00 0.25 5.00 95 1,536.53 5 80.87 0 - Ordinary Soil
18+580 20.00 44.82 49.35 987.00 - - - - 10.00 1.05 10.50 0.23 2.30 95 937.65 5 49.35 0 - Ordinary Soil
18+600 20.00 138.57 85.24 1,704.80 - 0.21 4.20 - - - - - - 95 1,619.56 5 85.24 0 - Ordinary Soil
18+620 20.00 98.28 71.55 1,431.00 - - - - - - - - - 95 1,359.45 5 71.55 0 - Ordinary Soil
18+640 20.00 26.48 82.53 1,650.60 0.29 0.15 3.00 - - - - - - 95 1,568.07 5 82.53 0 - Ordinary Soil
18+660 20.00 3.09 50.69 1,013.80 11.16 5.58 111.60 - 10.00 4.58 45.80 0.53 5.30 95 963.11 5 50.69 0 - Ordinary Soil
18+680 20.00 5.58 16.03 320.60 17.70 9.00 180.00 - 20.00 6.16 123.20 0.75 15.00 95 304.57 5 16.03 0 - Ordinary Soil
18+700 20.00 22.48 12.79 255.80 3.22 7.19 143.80 - 20.00 6.20 124.00 1.34 26.80 95 243.01 5 12.79 0 - Ordinary Soil
18+720 20.00 11.11 8.35 167.00 4.79 11.25 225.00 58.00 20.00 6.06 121.20 1.11 22.20 95 158.65 5 8.35 0 - Ordinary Soil
18+740 20.00 13.48 17.98 359.60 7.73 5.48 109.60 - 20.00 7.65 153.00 1.42 28.40 95 341.62 5 17.98 0 - Ordinary Soil
18+760 20.00 19.72 15.42 308.40 5.05 4.92 98.40 - 20.00 8.89 177.80 2.04 40.80 95 292.98 5 15.42 0 - Ordinary Soil
18+780 20.00 16.57 15.03 300.60 7.01 7.37 147.40 - 20.00 10.97 219.40 2.76 55.20 95 285.57 5 15.03 0 - Ordinary Soil
18+800 20.00 21.87 20.80 416.00 6.25 5.65 113.00 - 10.00 7.50 75.00 1.58 15.80 95 395.20 5 20.80 0 - Ordinary Soil
36 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
18+820 20.00 91.56 54.07 1,081.40 - 3.51 70.20 - - - - - - 95 1,027.33 5 54.07 0 - Ordinary Soil
18+840 20.00 68.16 45.02 900.40 - 3.13 62.60 - - - - - - 95 855.38 5 45.02 0 - Ordinary Soil
18+860 20.00 67.28 79.42 1,588.40 - - - - - - - - - 95 1,508.98 5 79.42 0 - Ordinary Soil
18+880 20.00 51.87 60.02 1,200.40 - - - - 10.00 0.58 5.80 0.06 0.60 95 1,140.38 5 60.02 0 - Ordinary Soil
18+900 20.00 29.95 48.62 972.40 2.53 1.27 25.40 - 20.00 3.05 61.00 0.47 9.40 95 923.78 5 48.62 0 - Ordinary Soil
18+920 20.00 24.78 38.33 766.60 3.34 1.67 33.40 - 20.00 5.47 109.40 1.15 23.00 95 728.27 5 38.33 0 - Ordinary Soil
18+940 20.00 13.56 21.76 435.20 9.23 5.88 117.60 - 20.00 5.83 116.60 1.05 21.00 95 413.44 5 21.76 0 - Ordinary Soil
18+960 20.00 8.73 16.76 335.20 10.72 7.03 140.60 - 20.00 5.43 108.60 0.90 18.00 95 318.44 5 16.76 0 - Ordinary Soil
18+980 20.00 41.51 27.54 550.80 1.07 5.15 103.00 - 10.00 2.04 20.40 0.28 2.80 95 523.26 5 27.54 0 - Ordinary Soil
19+000 20.00 74.30 41.52 830.40 - 5.36 107.20 - - - - - - 95 788.88 5 41.52 0 - Ordinary Soil
19+020 20.00 55.56 48.54 970.80 0.54 0.81 16.20 - - - - - - 95 922.26 5 48.54 0 - Ordinary Soil
19+040 20.00 36.75 55.53 1,110.60 0.83 0.42 8.40 - 7.00 2.43 17.01 0.35 2.45 95 1,055.07 5 55.53 0 - Ordinary Soil
19+060 20.00 77.62 66.59 1,331.80 - 0.27 5.40 - - - - - - 95 1,265.21 5 66.59 0 - Ordinary Soil
19+080 20.00 129.78 83.27 1,665.40 - 0.42 8.40 - - - - - - 95 1,582.13 5 83.27 0 - Ordinary Soil
19+100 20.00 166.20 121.91 2,438.20 - - - - - - - - - 95 2,316.29 5 121.91 0 - Ordinary Soil
19+120 20.00 101.78 115.78 2,315.60 - - - - - - - - - 95 2,199.82 5 115.78 0 - Ordinary Soil
19+140 20.00 36.05 101.13 2,022.60 - - - - - - - - - 95 1,921.47 5 101.13 0 - Ordinary Soil
19+160 20.00 5.00 53.39 1,067.80 12.78 6.39 127.80 - 10.00 12.95 129.50 3.00 30.00 95 1,014.41 5 53.39 0 - Ordinary Soil
19+180 20.00 - 18.03 360.60 33.91 16.96 339.20 - 20.00 8.88 177.60 1.75 35.00 95 342.57 5 18.03 0 - Ordinary Soil
19+200 20.00 11.17 8.09 161.80 8.86 10.82 216.40 54.60 20.00 10.07 201.40 2.31 46.20 95 153.71 5 8.09 0 - Ordinary Soil
19+220 20.00 17.66 8.83 176.60 5.34 19.63 392.60 216.00 20.00 9.16 183.20 2.05 41.00 95 167.77 5 8.83 0 - Ordinary Soil
19+240 20.00 9.67 10.42 208.40 7.74 8.30 166.00 - 20.00 7.01 140.20 1.36 27.20 95 197.98 5 10.42 0 - Ordinary Soil
19+260 20.00 10.08 13.87 277.40 9.31 7.33 146.60 - 20.00 5.46 109.20 0.93 18.60 95 263.53 5 13.87 0 - Ordinary Soil
19+280 20.00 23.79 16.73 334.60 3.04 5.39 107.80 - 20.00 10.12 202.40 2.72 54.40 95 317.87 5 16.73 0 - Ordinary Soil
19+300 20.00 27.63 18.86 377.20 8.04 8.68 173.60 - 20.00 9.49 189.80 2.30 46.00 95 358.34 5 18.86 0 - Ordinary Soil
19+320 20.00 18.79 21.29 425.80 9.82 6.43 128.60 - 20.00 13.52 270.40 3.54 70.80 95 404.51 5 21.29 0 - Ordinary Soil
19+340 20.00 15.29 21.46 429.20 10.33 9.19 183.80 - 20.00 8.42 168.40 1.79 35.80 95 407.74 5 21.46 0 - Ordinary Soil
19+360 20.00 11.63 15.21 304.20 12.60 11.21 224.20 - 20.00 10.30 206.00 2.39 47.80 95 288.99 5 15.21 0 - Ordinary Soil
19+380 20.00 18.25 16.77 335.40 5.24 7.79 155.80 - 20.00 9.07 181.40 2.02 40.40 95 318.63 5 16.77 0 - Ordinary Soil
19+400 20.00 11.02 11.33 226.60 6.56 9.58 191.60 - 20.00 4.16 83.20 0.61 12.20 95 215.27 5 11.33 0 - Ordinary Soil
19+420 20.00 10.65 14.45 289.00 5.27 5.26 105.20 - 20.00 5.12 102.40 0.91 18.20 95 274.55 5 14.45 0 - Ordinary Soil
19+440 20.00 7.88 9.45 189.00 6.29 6.43 128.60 - 20.00 4.47 89.40 0.69 13.80 95 179.55 5 9.45 0 - Ordinary Soil
19+460 20.00 4.09 7.37 147.40 12.99 9.13 182.60 35.20 20.00 8.50 170.00 1.53 30.60 95 140.03 5 7.37 0 - Ordinary Soil
19+480 20.00 2.26 5.07 101.40 18.10 12.20 244.00 142.60 20.00 10.24 204.80 1.88 37.60 95 96.33 5 5.07 0 - Ordinary Soil
19+500 20.00 9.19 6.64 132.80 8.29 10.64 212.80 80.00 20.00 6.63 132.60 1.24 24.80 95 126.16 5 6.64 0 - Ordinary Soil
19+520 20.00 11.97 7.12 142.40 5.07 11.59 231.80 89.40 20.00 3.28 65.60 0.40 8.00 95 135.28 5 7.12 0 - Ordinary Soil
19+540 20.00 4.29 6.74 134.80 7.70 8.00 160.00 25.20 20.00 2.16 43.20 0.18 3.60 95 128.06 5 6.74 0 - Ordinary Soil
19+560 20.00 4.69 8.33 166.60 3.28 4.18 83.60 - 20.00 2.53 50.60 0.58 11.60 95 158.27 5 8.33 0 - Ordinary Soil
19+580 20.00 8.96 6.63 132.60 1.23 4.47 89.40 - 10.00 1.02 10.20 0.18 1.80 95 125.97 5 6.63 0 - Ordinary Soil
19+600 20.00 15.13 9.91 198.20 1.20 2.24 44.80 - - - - - - 95 188.29 5 9.91 0 - Ordinary Soil
19+620 20.00 5.25 7.11 142.20 2.82 2.03 40.60 - 10.00 1.98 19.80 0.17 1.70 95 135.09 5 7.11 0 - Ordinary Soil
19+640 20.00 4.92 10.03 200.60 2.94 2.07 41.40 - 20.00 1.92 38.40 0.16 3.20 95 190.57 5 10.03 0 - Ordinary Soil
19+660 20.00 5.20 5.23 104.60 2.95 2.89 57.80 - 10.00 2.15 21.50 0.20 2.00 95 99.37 5 5.23 0 - Ordinary Soil
37 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
19+680 20.00 19.50 12.21 244.20 0.01 1.48 29.60 - - - - - - 95 231.99 5 12.21 0 - Ordinary Soil
19+700 20.00 25.82 15.51 310.20 - 1.48 29.60 - - - - - - 95 294.69 5 15.51 0 - Ordinary Soil
19+720 20.00 39.17 29.34 586.80 - 0.01 0.20 - - - - - - 95 557.46 5 29.34 0 - Ordinary Soil
19+740 20.00 93.15 59.49 1,189.80 - - - - - - - - - 95 1,130.31 5 59.49 0 - Ordinary Soil
19+760 20.00 126.80 82.99 1,659.80 - - - - - - - - - 95 1,576.81 5 82.99 0 - Ordinary Soil
19+780 20.00 149.08 121.12 2,422.40 - - - - - - - - - 95 2,301.28 5 121.12 0 - Ordinary Soil
19+800 20.00 117.44 122.12 2,442.40 - - - - - - - - - 95 2,320.28 5 122.12 0 - Ordinary Soil
19+820 20.00 93.82 121.45 2,429.00 - - - - - - - - - 95 2,307.55 5 121.45 0 - Ordinary Soil
19+840 20.00 62.69 90.07 1,801.40 - - - - - - - - - 95 1,711.33 5 90.07 0 - Ordinary Soil
19+860 20.00 50.58 72.20 1,444.00 - - - - - - - - - 95 1,371.80 5 72.20 0 - Ordinary Soil
19+880 20.00 39.28 50.99 1,019.80 3.24 1.62 32.40 - - - - - - 95 968.81 5 50.99 0 - Ordinary Soil
19+900 20.00 27.97 39.28 785.60 1.32 0.66 13.20 - 7.00 2.13 14.91 0.26 1.82 95 746.32 5 39.28 0 - Ordinary Soil
19+920 20.00 75.95 57.62 1,152.40 - 1.62 32.40 - - - - - - 95 1,094.78 5 57.62 0 - Ordinary Soil
19+940 20.00 34.23 31.10 622.00 1.67 1.50 30.00 - 7.00 1.17 8.19 0.12 0.84 95 590.90 5 31.10 0 - Ordinary Soil
19+960 20.00 54.07 65.01 1,300.20 0.05 0.03 0.60 - - - - - - 95 1,235.19 5 65.01 0 - Ordinary Soil
19+980 20.00 75.50 54.87 1,097.40 0.01 0.84 16.80 - - - - - - 95 1,042.53 5 54.87 0 - Ordinary Soil
20+000 20.00 25.31 39.69 793.80 - 0.03 0.60 - - - - - - 95 754.11 5 39.69 0 - Ordinary Soil
20+020 20.00 - 37.75 755.00 28.77 14.39 287.80 - - - - - - 95 717.25 5 37.75 0 - Ordinary Soil
20+040 20.00 - 12.66 253.20 98.12 49.06 981.20 728.00 - - - - - 95 240.54 5 12.66 0 - Ordinary Soil
20+060 20.00 - - - 23.59 26.18 523.60 523.60 10.00 2.95 29.50 0.17 1.70 95 - 5 - 0 - Ordinary Soil
20+080 20.00 5.03 2.52 50.40 0.82 49.47 989.40 939.00 20.00 0.72 14.40 0.11 2.20 95 47.88 5 2.52 0 - Ordinary Soil
20+100 20.00 1.20 0.60 12.00 4.35 13.97 279.40 267.40 20.00 3.05 61.00 0.75 15.00 95 11.40 5 0.60 0 - Ordinary Soil
20+120 20.00 1.78 3.41 68.20 3.16 1.99 39.80 - 10.00 1.48 14.80 0.08 0.80 95 64.79 5 3.41 0 - Ordinary Soil
20+140 20.00 2.93 2.07 41.40 1.11 2.73 54.60 13.20 - - - - - 95 39.33 5 2.07 0 - Ordinary Soil
20+160 20.00 4.14 2.96 59.20 0.21 1.69 33.80 - - - - - - 95 56.24 5 2.96 0 - Ordinary Soil
20+180 20.00 2.93 2.93 58.60 0.48 0.80 16.00 - - - - - - 95 55.67 5 2.93 0 - Ordinary Soil
20+200 20.00 3.09 3.62 72.40 4.02 2.12 42.40 - - - - - - 95 68.78 5 3.62 0 - Ordinary Soil
20+220 20.00 1.75 2.34 46.80 6.50 3.49 69.80 23.00 10.00 1.91 19.10 0.35 3.50 95 44.46 5 2.34 0 - Ordinary Soil
20+240 20.00 2.74 2.92 58.40 3.23 3.63 72.60 14.20 20.00 1.01 20.20 0.16 3.20 95 55.48 5 2.92 0 - Ordinary Soil
20+260 20.00 12.52 7.14 142.80 0.44 3.47 69.40 - 10.00 1.46 14.60 0.33 3.30 95 135.66 5 7.14 0 - Ordinary Soil
20+280 20.00 23.24 12.99 259.80 - 1.62 32.40 - - - - - - 95 246.81 5 12.99 0 - Ordinary Soil
20+300 20.00 14.69 13.61 272.20 0.40 0.42 8.40 - 10.00 1.42 14.20 0.33 3.30 95 258.59 5 13.61 0 - Ordinary Soil
20+320 20.00 2.26 12.75 255.00 12.78 6.39 127.80 - 20.00 5.61 112.20 0.75 15.00 95 242.25 5 12.75 0 - Ordinary Soil
20+340 20.00 11.51 13.10 262.00 1.94 1.17 23.40 - 20.00 2.14 42.80 0.23 4.60 95 248.90 5 13.10 0 - Ordinary Soil
20+360 20.00 12.10 7.18 143.60 1.33 7.06 141.20 - 10.00 1.92 19.20 0.45 4.50 95 136.42 5 7.18 0 - Ordinary Soil
20+380 20.00 6.00 8.76 175.20 1.47 1.71 34.20 - - - - - - 95 166.44 5 8.76 0 - Ordinary Soil
20+400 20.00 - 6.05 121.00 11.68 6.51 130.20 9.20 10.00 1.50 15.00 0.19 1.90 95 114.95 5 6.05 0 - Ordinary Soil
20+420 20.00 - 3.00 60.00 26.41 13.94 278.80 218.80 10.00 2.31 23.10 0.06 0.60 95 57.00 5 3.00 0 - Ordinary Soil
20+440 20.00 4.48 2.24 44.80 6.55 9.12 182.40 137.60 - - - - - 95 42.56 5 2.24 0 - Ordinary Soil
20+460 20.00 10.53 5.27 105.40 1.87 14.14 282.80 177.40 - - - - - 95 100.13 5 5.27 0 - Ordinary Soil
20+480 20.00 10.15 7.32 146.40 4.15 5.35 107.00 - 10.00 2.39 23.90 0.46 4.60 95 139.08 5 7.32 0 - Ordinary Soil
20+500 20.00 14.00 12.27 245.40 4.30 3.09 61.80 - 20.00 5.97 119.40 1.19 23.80 95 233.13 5 12.27 0 - Ordinary Soil
20+520 20.00 21.25 15.70 314.00 1.92 3.04 60.80 - 20.00 3.86 77.20 0.72 14.40 95 298.30 5 15.70 0 - Ordinary Soil
38 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
20+540 20.00 7.87 10.94 218.80 10.38 7.34 146.80 - 20.00 12.84 256.80 3.06 61.20 95 207.86 5 10.94 0 - Ordinary Soil
20+560 20.00 12.89 17.07 341.40 5.86 3.89 77.80 - 10.00 8.13 81.30 1.63 16.30 95 324.33 5 17.07 0 - Ordinary Soil
20+580 20.00 64.57 36.22 724.40 - 5.19 103.80 - - - - - - 95 688.18 5 36.22 0 - Ordinary Soil
20+600 20.00 47.18 30.04 600.80 0.06 2.96 59.20 - - - - - - 95 570.76 5 30.04 0 - Ordinary Soil
20+620 20.00 13.26 38.92 778.40 8.15 4.08 81.60 - 10.00 6.26 62.60 1.12 11.20 95 739.48 5 38.92 0 - Ordinary Soil
20+640 20.00 20.19 33.69 673.80 6.75 3.41 68.20 - 20.00 3.71 74.20 0.51 10.20 95 640.11 5 33.69 0 - Ordinary Soil
20+660 20.00 11.19 12.23 244.60 6.91 7.53 150.60 - 20.00 4.51 90.20 0.64 12.80 95 232.37 5 12.23 0 - Ordinary Soil
20+680 20.00 - 10.10 202.00 28.70 17.73 354.60 152.60 20.00 9.30 186.00 1.67 33.40 95 191.90 5 10.10 0 - Ordinary Soil
20+700 20.00 2.46 6.83 136.60 21.97 14.44 288.80 152.20 20.00 12.00 240.00 2.44 48.80 95 129.77 5 6.83 0 - Ordinary Soil
20+720 20.00 4.79 2.40 48.00 16.00 22.35 447.00 399.00 20.00 5.38 107.60 0.87 17.40 95 45.60 5 2.40 0 - Ordinary Soil
20+740 20.00 0.01 1.24 24.80 22.52 22.25 445.00 420.20 20.00 6.33 126.60 1.24 24.80 95 23.56 5 1.24 0 - Ordinary Soil
20+760 20.00 - 2.40 48.00 25.12 20.56 411.20 363.20 20.00 8.78 175.60 1.44 28.80 95 45.60 5 2.40 0 - Ordinary Soil
20+780 20.00 2.34 1.18 23.60 13.43 17.98 359.60 336.00 20.00 4.33 86.60 0.58 11.60 95 22.42 5 1.18 0 - Ordinary Soil
20+800 20.00 4.01 2.01 40.20 14.86 19.99 399.80 359.60 20.00 7.26 145.20 1.28 25.60 95 38.19 5 2.01 0 - Ordinary Soil
20+820 20.00 - 1.17 23.40 25.02 19.23 384.60 361.20 20.00 10.14 202.80 2.14 42.80 95 22.23 5 1.17 0 - Ordinary Soil
20+840 20.00 - 2.01 40.20 36.07 25.47 509.40 469.20 20.00 9.34 186.80 2.27 45.40 95 38.19 5 2.01 0 - Ordinary Soil
20+860 20.00 - - - 50.58 37.80 756.00 756.00 20.00 5.86 117.20 0.93 18.60 95 - 5 - 0 - Ordinary Soil
20+880 20.00 - - - 73.34 54.71 1,094.20 1,094.20 10.00 0.44 4.40 - - 95 - 5 - 0 - Ordinary Soil
20+900 20.00 - - - 115.72 83.15 1,663.00 1,663.00 - - - - - 95 - 5 - 0 - Ordinary Soil
20+920 20.00 - - - 141.72 107.53 2,150.60 2,150.60 - - - - - 95 - 5 - 0 - Ordinary Soil
20+940 20.00 - - - 45.88 80.80 1,616.00 1,616.00 10.00 6.27 62.70 0.79 7.90 95 - 5 - 0 - Ordinary Soil
20+960 20.00 - - - 39.38 90.55 1,811.00 1,811.00 20.00 6.47 129.40 1.39 27.80 95 - 5 - 0 - Ordinary Soil
20+980 20.00 - - - 77.36 61.62 1,232.40 1,232.40 20.00 0.98 19.60 0.01 0.20 95 - 5 - 0 - Ordinary Soil
21+000 20.00 4.72 2.36 47.20 8.17 23.78 475.60 428.40 20.00 3.56 71.20 0.36 7.20 95 44.84 5 2.36 0 - Ordinary Soil
21+020 20.00 18.63 9.32 186.40 4.19 40.78 815.60 629.20 20.00 5.56 111.20 1.08 21.60 95 177.08 5 9.32 0 - Ordinary Soil
21+040 20.00 5.36 5.04 100.80 10.09 9.13 182.60 81.80 20.00 6.84 136.80 1.16 23.20 95 95.76 5 5.04 0 - Ordinary Soil
21+060 20.00 11.70 15.17 303.40 6.19 5.19 103.80 - 20.00 4.44 88.80 0.64 12.80 95 288.23 5 15.17 0 - Ordinary Soil
21+080 20.00 3.39 4.38 87.60 9.03 9.56 191.20 103.60 10.00 3.95 39.50 0.47 4.70 95 83.22 5 4.38 0 - Ordinary Soil
21+100 20.00 3.17 7.44 148.80 13.62 9.91 198.20 49.40 - - - - - 95 141.36 5 7.44 0 - Ordinary Soil
21+120 20.00 10.69 7.04 140.80 3.27 6.15 123.00 - 10.00 3.94 39.40 0.56 5.60 95 133.76 5 7.04 0 - Ordinary Soil
21+140 20.00 31.27 17.22 344.40 0.39 7.01 140.20 - 20.00 1.31 26.20 0.30 6.00 95 327.18 5 17.22 0 - Ordinary Soil
21+160 20.00 17.41 14.05 281.00 4.63 3.95 79.00 - 20.00 6.48 129.60 1.25 25.00 95 266.95 5 14.05 0 - Ordinary Soil
21+180 20.00 23.46 27.37 547.40 0.83 0.61 12.20 - 10.00 2.14 21.40 0.55 5.50 95 520.03 5 27.37 0 - Ordinary Soil
21+200 20.00 - 8.71 174.20 27.40 16.02 320.40 146.20 - - - - - 95 165.49 5 8.71 0 - Ordinary Soil
21+220 20.00 - 11.73 234.60 30.00 15.42 308.40 73.80 - - - - - 95 222.87 5 11.73 0 - Ordinary Soil
21+240 20.00 - - - 44.60 36.00 720.00 720.00 - - - - - 95 - 5 - 0 - Ordinary Soil
21+260 20.00 4.63 2.32 46.40 9.05 19.53 390.60 344.20 7.00 4.62 32.34 0.57 3.99 95 44.08 5 2.32 0 - Ordinary Soil
21+280 20.00 121.46 60.73 1,214.60 - 22.30 446.00 - - - - - - 95 1,153.87 5 60.73 0 - Ordinary Soil
21+300 20.00 236.47 120.55 2,411.00 - 4.53 90.60 - 10.00 57.59 575.90 0.68 6.80 95 2,290.45 5 120.55 0 - Ordinary Soil
21+320 20.00 126.53 124.00 2,480.00 - - - - 20.00 32.41 648.20 0.90 18.00 95 2,356.00 5 124.00 0 - Ordinary Soil
21+340 20.00 44.54 140.51 2,810.20 - - - - 20.00 15.74 314.80 0.87 17.40 95 2,669.69 5 140.51 0 - Ordinary Soil
21+360 20.00 48.26 87.40 1,748.00 - - - - 20.00 15.39 307.80 0.88 17.60 95 1,660.60 5 87.40 0 - Ordinary Soil
21+380 20.00 65.80 55.17 1,103.40 - - - - 20.00 20.27 405.40 0.89 17.80 95 1,048.23 5 55.17 0 - Ordinary Soil
39 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
21+400 20.00 44.34 46.30 926.00 - - - - 20.00 16.38 327.60 0.89 17.80 95 879.70 5 46.30 0 - Ordinary Soil
21+420 20.00 24.55 45.18 903.60 2.79 1.40 28.00 - 20.00 3.03 60.60 0.47 9.40 95 858.42 5 45.18 0 - Ordinary Soil
21+440 20.00 3.84 24.09 481.80 13.30 6.65 133.00 - 20.00 13.26 265.20 3.03 60.60 95 457.71 5 24.09 0 - Ordinary Soil
21+460 20.00 - 12.28 245.60 21.98 12.39 247.80 2.20 20.00 9.43 188.60 1.68 33.60 95 233.32 5 12.28 0 - Ordinary Soil
21+480 20.00 0.13 1.99 39.80 16.75 15.03 300.60 260.80 20.00 6.71 134.20 1.22 24.40 95 37.81 5 1.99 0 - Ordinary Soil
21+500 20.00 - - - 23.66 22.82 456.40 456.40 20.00 14.36 287.20 2.99 59.80 95 - 5 - 0 - Ordinary Soil
21+520 20.00 0.48 0.31 6.20 16.95 16.85 337.00 330.80 20.00 12.42 248.40 2.58 51.60 95 5.89 5 0.31 0 - Ordinary Soil
21+540 20.00 9.31 4.66 93.20 6.86 15.26 305.20 212.00 10.00 4.29 42.90 0.62 6.20 95 88.54 5 4.66 0 - Ordinary Soil
21+560 20.00 68.11 34.30 686.00 - 8.48 169.60 - - - - - - 95 651.70 5 34.30 0 - Ordinary Soil
21+580 20.00 96.71 53.01 1,060.20 - 3.43 68.60 - - - - - - 95 1,007.19 5 53.01 0 - Ordinary Soil
21+600 20.00 344.62 206.37 4,127.40 - - - - - - - - - 95 3,921.03 5 206.37 0 - Ordinary Soil
21+620 20.00 338.60 217.66 4,353.20 - - - - - - - - - 95 4,135.54 5 217.66 0 - Ordinary Soil
21+640 20.00 201.08 272.85 5,457.00 0.01 0.01 0.20 - - - - - - 95 5,184.15 5 272.85 0 - Ordinary Soil
21+660 20.00 163.12 250.86 5,017.20 - - - - - - - - - 95 4,766.34 5 250.86 0 - Ordinary Soil
21+680 20.00 156.46 178.77 3,575.40 - 0.01 0.20 - - - - - - 95 3,396.63 5 178.77 0 - Ordinary Soil
21+700 20.00 145.33 154.23 3,084.60 0.01 0.01 0.20 - - - - - - 95 2,930.37 5 154.23 0 - Ordinary Soil
21+720 20.00 181.97 169.22 3,384.40 - - - - - - - - - 95 3,215.18 5 169.22 0 - Ordinary Soil
21+740 20.00 164.15 154.74 3,094.80 - 0.01 0.20 - - - - - - 95 2,940.06 5 154.74 0 - Ordinary Soil
21+760 20.00 172.52 177.25 3,545.00 - - - - - - - - - 95 3,367.75 5 177.25 0 - Ordinary Soil
21+780 20.00 123.81 143.98 2,879.60 - - - - 10.00 40.57 405.70 0.68 6.80 95 2,735.62 5 143.98 0 - Ordinary Soil
21+800 20.00 84.92 128.72 2,574.40 - - - - 20.00 31.84 636.80 0.75 15.00 95 2,445.68 5 128.72 0 - Ordinary Soil
21+820 20.00 29.71 76.76 1,535.20 2.99 1.50 30.00 - 20.00 6.13 122.60 1.29 25.80 95 1,458.44 5 76.76 0 - Ordinary Soil
21+840 20.00 8.83 46.88 937.60 9.00 4.50 90.00 - 20.00 10.94 218.80 2.45 49.00 95 890.72 5 46.88 0 - Ordinary Soil
21+860 20.00 0.78 15.25 305.00 20.75 11.87 237.40 - 20.00 15.23 304.60 3.33 66.60 95 289.75 5 15.25 0 - Ordinary Soil
21+880 20.00 - 4.42 88.40 38.91 23.96 479.20 390.80 20.00 14.43 288.60 2.66 53.20 95 83.98 5 4.42 0 - Ordinary Soil
21+900 20.00 - 0.39 7.80 32.79 26.77 535.40 527.60 20.00 14.57 291.40 2.89 57.80 95 7.41 5 0.39 0 - Ordinary Soil
21+920 20.00 0.84 0.42 8.40 16.34 27.63 552.60 544.20 20.00 7.58 151.60 1.28 25.60 95 7.98 5 0.42 0 - Ordinary Soil
21+940 20.00 12.39 6.20 124.00 5.62 19.21 384.20 260.20 10.00 4.95 49.50 0.84 8.40 95 117.80 5 6.20 0 - Ordinary Soil
21+960 20.00 50.12 25.48 509.60 0.58 8.46 169.20 - - - - - - 95 484.12 5 25.48 0 - Ordinary Soil
21+980 20.00 247.14 129.77 2,595.40 - 2.81 56.20 - - - - - - 95 2,465.63 5 129.77 0 - Ordinary Soil
22+000 20.00 260.19 155.16 3,103.20 - 0.29 5.80 - 10.00 101.02 1,010.20 0.66 6.60 95 2,948.04 5 155.16 0 - Ordinary Soil
22+020 20.00 225.13 236.14 4,722.80 - - - - 20.00 69.17 1,383.40 0.65 13.00 95 4,486.66 5 236.14 0 - Ordinary Soil
22+040 20.00 102.11 181.15 3,623.00 - - - - 20.00 32.60 652.00 0.67 13.40 95 3,441.85 5 181.15 0 - Ordinary Soil
22+060 20.00 34.38 129.76 2,595.20 0.50 0.25 5.00 - 20.00 2.17 43.40 0.62 12.40 95 2,465.44 5 129.76 0 - Ordinary Soil
22+080 20.00 0.16 51.14 1,022.80 23.04 11.52 230.40 - 20.00 8.42 168.40 1.45 29.00 95 971.66 5 51.14 0 - Ordinary Soil
22+100 20.00 - 17.19 343.80 29.79 15.15 303.00 - 20.00 9.48 189.60 1.83 36.60 95 326.61 5 17.19 0 - Ordinary Soil
22+120 20.00 - 0.08 1.60 40.35 31.70 634.00 632.40 20.00 3.39 67.80 0.55 11.00 95 1.52 5 0.08 0 - Ordinary Soil
22+140 20.00 - - - 46.86 38.33 766.60 766.60 20.00 2.23 44.60 0.32 6.40 95 - 5 - 0 - Ordinary Soil
22+160 20.00 - - - 23.46 31.91 638.20 638.20 10.00 5.50 55.00 0.71 7.10 95 - 5 - 0 - Ordinary Soil
22+180 20.00 156.56 78.28 1,565.60 - 23.43 468.60 - - - - - - 95 1,487.32 5 78.28 0 - Ordinary Soil
22+200 20.00 138.38 69.19 1,383.80 - 11.73 234.60 - 10.00 40.86 408.60 0.67 6.70 95 1,314.61 5 69.19 0 - Ordinary Soil
22+220 20.00 91.59 124.08 2,481.60 - - - - 20.00 31.67 633.40 0.67 13.40 95 2,357.52 5 124.08 0 - Ordinary Soil
22+240 20.00 28.81 83.60 1,672.00 1.00 0.50 10.00 - 20.00 2.23 44.60 0.60 12.00 95 1,588.40 5 83.60 0 - Ordinary Soil
40 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
22+260 20.00 2.04 46.82 936.40 14.84 7.42 148.40 - 20.00 8.00 160.00 1.37 27.40 95 889.58 5 46.82 0 - Ordinary Soil
22+280 20.00 3.15 15.98 319.60 15.41 8.21 164.20 - 20.00 7.16 143.20 1.29 25.80 95 303.62 5 15.98 0 - Ordinary Soil
22+300 20.00 11.04 6.54 130.80 8.17 11.51 230.20 99.40 20.00 6.34 126.80 1.25 25.00 95 124.26 5 6.54 0 - Ordinary Soil
22+320 20.00 6.29 4.72 94.40 11.65 13.53 270.60 176.20 20.00 9.35 187.00 1.84 36.80 95 89.68 5 4.72 0 - Ordinary Soil
22+340 20.00 17.23 14.14 282.80 4.51 6.34 126.80 - 20.00 5.51 110.20 1.03 20.60 95 268.66 5 14.14 0 - Ordinary Soil
22+360 20.00 47.50 26.90 538.00 0.84 6.25 125.00 - 10.00 5.45 54.50 1.26 12.60 95 511.10 5 26.90 0 - Ordinary Soil
22+380 20.00 221.89 119.56 2,391.20 - 2.26 45.20 - - - - - - 95 2,271.64 5 119.56 0 - Ordinary Soil
22+400 20.00 292.64 170.07 3,401.40 - 0.42 8.40 - 10.00 130.50 1,305.00 1.64 16.40 95 3,231.33 5 170.07 0 - Ordinary Soil
22+420 20.00 213.61 217.75 4,355.00 - - - - 20.00 81.70 1,634.00 0.69 13.80 95 4,137.25 5 217.75 0 - Ordinary Soil
22+440 20.00 181.25 236.95 4,739.00 - - - - 20.00 57.21 1,144.20 0.64 12.80 95 4,502.05 5 236.95 0 - Ordinary Soil
22+460 20.00 157.00 185.31 3,706.20 - - - - 20.00 51.61 1,032.20 0.64 12.80 95 3,520.89 5 185.31 0 - Ordinary Soil
22+480 20.00 124.20 152.73 3,054.60 - - - - 20.00 33.20 664.00 0.91 18.20 95 2,901.87 5 152.73 0 - Ordinary Soil
22+500 20.00 56.45 106.73 2,134.60 - - - - 20.00 18.86 377.20 0.76 15.20 95 2,027.87 5 106.73 0 - Ordinary Soil
22+520 20.00 22.99 73.60 1,472.00 3.42 1.71 34.20 - 20.00 6.70 134.00 1.38 27.60 95 1,398.40 5 73.60 0 - Ordinary Soil
22+540 20.00 15.16 35.81 716.20 8.53 4.27 85.40 - 20.00 10.98 219.60 2.48 49.60 95 680.39 5 35.81 0 - Ordinary Soil
22+560 20.00 0.86 11.93 238.60 23.65 13.54 270.80 32.20 20.00 18.94 378.80 4.39 87.80 95 226.67 5 11.93 0 - Ordinary Soil
22+580 20.00 25.02 20.09 401.80 0.33 4.43 88.60 - 20.00 1.42 28.40 0.33 6.60 95 381.71 5 20.09 0 - Ordinary Soil
22+600 20.00 238.68 119.77 2,395.40 - 11.83 236.60 - 20.00 60.53 1,210.60 0.70 14.00 95 2,275.63 5 119.77 0 - Ordinary Soil
22+620 20.00 161.73 93.38 1,867.60 - 0.17 3.40 - 20.00 70.66 1,413.20 0.69 13.80 95 1,774.22 5 93.38 0 - Ordinary Soil
22+640 20.00 195.14 216.91 4,338.20 - - - - 20.00 54.96 1,099.20 0.72 14.40 95 4,121.29 5 216.91 0 - Ordinary Soil
22+660 20.00 111.79 136.76 2,735.20 - - - - 10.00 33.82 338.20 0.75 7.50 95 2,598.44 5 136.76 0 - Ordinary Soil
22+680 20.00 62.33 128.74 2,574.80 - - - - - - - - - 95 2,446.06 5 128.74 0 - Ordinary Soil
22+700 20.00 25.62 68.71 1,374.20 2.45 1.23 24.60 - 10.00 7.09 70.90 1.63 16.30 95 1,305.49 5 68.71 0 - Ordinary Soil
22+720 20.00 20.22 41.28 825.60 3.71 1.86 37.20 - 20.00 6.22 124.40 1.24 24.80 95 784.32 5 41.28 0 - Ordinary Soil
22+740 20.00 6.92 16.27 325.40 11.98 7.22 144.40 - 20.00 8.67 173.40 1.66 33.20 95 309.13 5 16.27 0 - Ordinary Soil
22+760 20.00 - 10.11 202.20 30.29 17.00 340.00 137.80 20.00 14.95 299.00 3.06 61.20 95 192.09 5 10.11 0 - Ordinary Soil
22+780 20.00 - 3.46 69.20 32.09 22.04 440.80 371.60 20.00 12.14 242.80 2.59 51.80 95 65.74 5 3.46 0 - Ordinary Soil
22+800 20.00 0.23 0.12 2.40 28.05 29.17 583.40 581.00 10.00 15.93 159.30 3.43 34.30 95 2.28 5 0.12 0 - Ordinary Soil
22+820 20.00 117.03 58.52 1,170.40 - 16.05 321.00 - - - - - - 95 1,111.88 5 58.52 0 - Ordinary Soil
22+840 20.00 193.11 96.67 1,933.40 - 14.03 280.60 - 10.00 67.76 677.60 0.69 6.90 95 1,836.73 5 96.67 0 - Ordinary Soil
22+860 20.00 204.41 160.72 3,214.40 - - - - 20.00 56.55 1,131.00 0.68 13.60 95 3,053.68 5 160.72 0 - Ordinary Soil
22+880 20.00 176.08 184.60 3,692.00 0.01 0.01 0.20 - 20.00 49.65 993.00 0.68 13.60 95 3,507.40 5 184.60 0 - Ordinary Soil
22+900 20.00 199.87 202.14 4,042.80 - - - - 20.00 55.58 1,111.60 0.69 13.80 95 3,840.66 5 202.14 0 - Ordinary Soil
22+920 20.00 226.99 201.54 4,030.80 - 0.01 0.20 - 20.00 61.11 1,222.20 0.69 13.80 95 3,829.26 5 201.54 0 - Ordinary Soil
22+940 20.00 167.03 183.45 3,669.00 - - - - 20.00 92.79 1,855.80 1.62 32.40 95 3,485.55 5 183.45 0 - Ordinary Soil
22+960 20.00 164.32 195.66 3,913.20 - - - - 20.00 92.32 1,846.40 1.61 32.20 95 3,717.54 5 195.66 0 - Ordinary Soil
22+980 20.00 220.30 193.67 3,873.40 0.01 0.01 0.20 - 20.00 82.96 1,659.20 1.80 36.00 95 3,679.73 5 193.67 0 - Ordinary Soil
23+000 20.00 200.75 182.54 3,650.80 - - - - 20.00 73.81 1,476.20 1.76 35.20 95 3,468.26 5 182.54 0 - Ordinary Soil
23+020 20.00 200.21 210.26 4,205.20 - 0.01 0.20 - 20.00 76.20 1,524.00 1.61 32.20 95 3,994.94 5 210.26 0 - Ordinary Soil
23+040 20.00 174.02 187.39 3,747.80 - - - - 20.00 98.59 1,971.80 1.62 32.40 95 3,560.41 5 187.39 0 - Ordinary Soil
23+060 20.00 216.63 208.42 4,168.40 - - - - 20.00 92.02 1,840.40 1.63 32.60 95 3,959.98 5 208.42 0 - Ordinary Soil
23+080 20.00 225.44 199.73 3,994.60 - - - - 20.00 99.91 1,998.20 1.63 32.60 95 3,794.87 5 199.73 0 - Ordinary Soil
23+100 20.00 261.99 239.31 4,786.20 - - - - 10.00 136.80 1,368.00 1.37 13.70 95 4,546.89 5 239.31 0 - Ordinary Soil
41 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
23+120 20.00 110.45 167.95 3,359.00 - - - - - - - - - 95 3,191.05 5 167.95 0 - Ordinary Soil
23+140 20.00 69.09 165.54 3,310.80 - - - - - - - - - 95 3,145.26 5 165.54 0 - Ordinary Soil
23+160 20.00 25.69 68.07 1,361.40 0.25 0.13 2.60 - - - - - - 95 1,293.33 5 68.07 0 - Ordinary Soil
23+180 20.00 116.93 93.01 1,860.20 0.01 0.01 0.20 - - - - - - 95 1,767.19 5 93.01 0 - Ordinary Soil
23+200 20.00 116.80 71.25 1,425.00 - 0.13 2.60 - - - - - - 95 1,353.75 5 71.25 0 - Ordinary Soil
23+220 20.00 111.39 114.16 2,283.20 - 0.01 0.20 - - - - - - 95 2,169.04 5 114.16 0 - Ordinary Soil
23+240 20.00 98.53 107.67 2,153.40 - - - - - - - - - 95 2,045.73 5 107.67 0 - Ordinary Soil
23+260 20.00 121.95 116.67 2,333.40 - - - - - - - - - 95 2,216.73 5 116.67 0 - Ordinary Soil
23+280 20.00 91.28 94.91 1,898.20 - - - - - - - - - 95 1,803.29 5 94.91 0 - Ordinary Soil
23+300 20.00 35.16 78.56 1,571.20 1.32 0.66 13.20 - 10.00 4.95 49.50 1.04 10.40 95 1,492.64 5 78.56 0 - Ordinary Soil
23+320 20.00 5.25 48.27 965.40 9.71 4.86 97.20 - 20.00 6.68 133.60 1.21 24.20 95 917.13 5 48.27 0 - Ordinary Soil
23+340 20.00 3.00 19.08 381.60 14.58 7.95 159.00 - 20.00 13.48 269.60 2.99 59.80 95 362.52 5 19.08 0 - Ordinary Soil
23+360 20.00 12.80 9.03 180.60 6.36 8.04 160.80 - 20.00 8.37 167.40 1.67 33.40 95 171.57 5 9.03 0 - Ordinary Soil
23+380 20.00 12.40 7.70 154.00 7.09 10.84 216.80 62.80 20.00 8.05 161.00 1.57 31.40 95 146.30 5 7.70 0 - Ordinary Soil
23+400 20.00 22.46 17.63 352.60 1.18 3.77 75.40 - 20.00 2.16 43.20 0.56 11.20 95 334.97 5 17.63 0 - Ordinary Soil
23+420 20.00 46.46 29.43 588.60 0.05 3.57 71.40 - 20.00 1.80 36.00 0.51 10.20 95 559.17 5 29.43 0 - Ordinary Soil
23+440 20.00 9.26 15.86 317.20 6.07 3.63 72.60 - 20.00 7.87 157.40 1.66 33.20 95 301.34 5 15.86 0 - Ordinary Soil
23+460 20.00 - 23.23 464.60 51.82 25.94 518.80 54.20 10.00 5.43 54.30 0.70 7.00 95 441.37 5 23.23 0 - Ordinary Soil
23+480 20.00 - 4.63 92.60 88.50 47.29 945.80 853.20 - - - - - 95 87.97 5 4.63 0 - Ordinary Soil
23+500 20.00 11.07 5.54 110.80 0.71 26.27 525.40 414.60 7.00 2.31 16.17 0.62 4.34 95 105.26 5 5.54 0 - Ordinary Soil
23+520 20.00 38.19 19.10 382.00 2.43 45.47 909.40 527.40 - - - - - 95 362.90 5 19.10 0 - Ordinary Soil
23+540 20.00 47.85 29.46 589.20 - 0.36 7.20 - - - - - - 95 559.74 5 29.46 0 - Ordinary Soil
23+560 20.00 77.73 57.96 1,159.20 - 1.22 24.40 - - - - - - 95 1,101.24 5 57.96 0 - Ordinary Soil
23+580 20.00 72.85 60.35 1,207.00 - - - - - - - - - 95 1,146.65 5 60.35 0 - Ordinary Soil
23+600 20.00 35.45 56.59 1,131.80 0.03 0.02 0.40 - - - - - - 95 1,075.21 5 56.59 0 - Ordinary Soil
23+620 20.00 35.82 54.34 1,086.80 - - - - - - - - - 95 1,032.46 5 54.34 0 - Ordinary Soil
23+640 20.00 203.09 119.27 2,385.40 0.01 0.02 0.40 - - - - - - 95 2,266.13 5 119.27 0 - Ordinary Soil
23+660 20.00 230.19 133.01 2,660.20 - - - - - - - - - 95 2,527.19 5 133.01 0 - Ordinary Soil
23+680 20.00 168.94 186.02 3,720.40 - 0.01 0.20 - - - - - - 95 3,534.38 5 186.02 0 - Ordinary Soil
23+700 20.00 1.60 115.90 2,318.00 8.07 4.04 80.80 - 7.00 3.73 26.11 0.45 3.15 95 2,202.10 5 115.90 0 - Ordinary Soil
23+720 20.00 - 84.47 1,689.40 - - - - - - - - - 95 1,604.93 5 84.47 0 - Ordinary Soil
23+740 20.00 25.78 13.69 273.80 1.08 4.58 91.60 - 10.00 1.63 16.30 0.38 3.80 95 260.11 5 13.69 0 - Ordinary Soil
23+760 20.00 32.68 16.34 326.80 0.61 0.31 6.20 - 20.00 2.09 41.80 0.58 11.60 95 310.46 5 16.34 0 - Ordinary Soil
23+780 20.00 9.62 17.70 354.00 5.32 3.20 64.00 - 20.00 2.34 46.80 0.48 9.60 95 336.30 5 17.70 0 - Ordinary Soil
23+800 20.00 1.59 17.14 342.80 15.42 8.02 160.40 - 20.00 3.81 76.20 0.47 9.40 95 325.66 5 17.14 0 - Ordinary Soil
23+820 20.00 5.14 7.38 147.60 11.19 8.26 165.20 17.60 20.00 5.99 119.80 0.96 19.20 95 140.22 5 7.38 0 - Ordinary Soil
23+840 20.00 17.87 9.73 194.60 2.83 9.13 182.60 - 20.00 3.47 69.40 0.50 10.00 95 184.87 5 9.73 0 - Ordinary Soil
23+860 20.00 25.12 15.13 302.60 1.77 6.48 129.60 - 20.00 4.50 90.00 0.84 16.80 95 287.47 5 15.13 0 - Ordinary Soil
23+880 20.00 24.43 21.15 423.00 2.13 2.48 49.60 - 20.00 3.95 79.00 0.67 13.40 95 401.85 5 21.15 0 - Ordinary Soil
23+900 20.00 0.18 12.65 253.00 21.24 11.51 230.20 - 20.00 10.24 204.80 1.65 33.00 95 240.35 5 12.65 0 - Ordinary Soil
23+920 20.00 - 12.22 244.40 49.98 26.06 521.20 276.80 20.00 3.66 73.20 0.14 2.80 95 232.18 5 12.22 0 - Ordinary Soil
23+940 20.00 3.59 1.89 37.80 10.82 16.03 320.60 282.80 10.00 8.97 89.70 1.74 17.40 95 35.91 5 1.89 0 - Ordinary Soil
23+960 20.00 49.45 24.73 494.60 - 24.99 499.80 5.20 - - - - - 95 469.87 5 24.73 0 - Ordinary Soil
42 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
23+980 20.00 32.04 17.82 356.40 0.06 5.44 108.80 - - - - - - 95 338.58 5 17.82 0 - Ordinary Soil
24+000 20.00 1.21 25.33 506.60 7.14 3.57 71.40 - - - - - - 95 481.27 5 25.33 0 - Ordinary Soil
24+020 20.00 2.75 17.40 348.00 20.80 10.43 208.60 - 7.00 2.50 17.50 0.05 0.35 95 330.60 5 17.40 0 - Ordinary Soil
24+040 20.00 93.57 47.39 947.80 - 3.57 71.40 - - - - - - 95 900.41 5 47.39 0 - Ordinary Soil
24+060 20.00 137.18 69.97 1,399.40 - 10.40 208.00 - - - - - - 95 1,329.43 5 69.97 0 - Ordinary Soil
24+080 20.00 144.07 118.82 2,376.40 - - - - - - - - - 95 2,257.58 5 118.82 0 - Ordinary Soil
24+100 20.00 85.96 111.57 2,231.40 - - - - - - - - - 95 2,119.83 5 111.57 0 - Ordinary Soil
24+120 20.00 34.65 89.36 1,787.20 0.25 0.13 2.60 - - - - - - 95 1,697.84 5 89.36 0 - Ordinary Soil
24+140 20.00 3.81 44.89 897.80 0.82 0.41 8.20 - - - - - - 95 852.91 5 44.89 0 - Ordinary Soil
24+160 20.00 0.12 17.39 347.80 1.32 0.79 15.80 - - - - - - 95 330.41 5 17.39 0 - Ordinary Soil
24+180 20.00 8.83 6.32 126.40 - 0.41 8.20 - - - - - - 95 120.08 5 6.32 0 - Ordinary Soil
24+200 20.00 10.15 5.14 102.80 0.08 0.70 14.00 - - - - - - 95 97.66 5 5.14 0 - Ordinary Soil
24+220 20.00 93.12 50.98 1,019.60 - - - - - - - - - 95 968.62 5 50.98 0 - Ordinary Soil
24+240 20.00 246.97 128.56 2,571.20 0.01 0.05 1.00 - - - - - - 95 2,442.64 5 128.56 0 - Ordinary Soil
24+260 20.00 190.54 141.83 2,836.60 - - - - - - - - - 95 2,694.77 5 141.83 0 - Ordinary Soil
24+280 20.00 148.07 197.52 3,950.40 - 0.01 0.20 - - - - - - 95 3,752.88 5 197.52 0 - Ordinary Soil
24+300 20.00 122.18 156.36 3,127.20 - - - - - - - - - 95 2,970.84 5 156.36 0 - Ordinary Soil
24+320 20.00 125.03 136.55 2,731.00 - - - - - - - - - 95 2,594.45 5 136.55 0 - Ordinary Soil
24+340 20.00 152.65 137.42 2,748.40 0.01 0.01 0.20 - - - - - - 95 2,610.98 5 137.42 0 - Ordinary Soil
24+360 20.00 25.28 75.16 1,503.20 0.78 0.39 7.80 - 7.00 3.48 24.36 1.09 7.63 95 1,428.04 5 75.16 0 - Ordinary Soil
24+380 20.00 37.01 94.83 1,896.60 0.02 0.02 0.40 - - - - - - 95 1,801.77 5 94.83 0 - Ordinary Soil
24+400 20.00 82.24 53.76 1,075.20 - 0.39 7.80 - - - - - - 95 1,021.44 5 53.76 0 - Ordinary Soil
24+420 20.00 62.29 49.65 993.00 - 0.01 0.20 - - - - - - 95 943.35 5 49.65 0 - Ordinary Soil
24+440 20.00 46.56 64.40 1,288.00 - - - - - - - - - 95 1,223.60 5 64.40 0 - Ordinary Soil
24+460 20.00 30.21 46.25 925.00 0.13 0.07 1.40 - 10.00 1.63 16.30 0.44 4.40 95 878.75 5 46.25 0 - Ordinary Soil
24+480 20.00 25.33 35.95 719.00 1.12 0.56 11.20 - 20.00 3.03 60.60 0.88 17.60 95 683.05 5 35.95 0 - Ordinary Soil
24+500 20.00 22.57 26.39 527.80 0.77 0.45 9.00 - 20.00 2.07 41.40 0.54 10.80 95 501.41 5 26.39 0 - Ordinary Soil
24+520 20.00 16.21 20.77 415.40 3.33 2.23 44.60 - 20.00 2.53 50.60 0.63 12.60 95 394.63 5 20.77 0 - Ordinary Soil
24+540 20.00 29.27 25.92 518.40 0.83 0.80 16.00 - 10.00 3.30 33.00 1.02 10.20 95 492.48 5 25.92 0 - Ordinary Soil
24+560 20.00 45.50 30.86 617.20 1.62 2.48 49.60 - - - - - - 95 586.34 5 30.86 0 - Ordinary Soil
24+580 20.00 96.29 62.78 1,255.60 - 0.42 8.40 - - - - - - 95 1,192.82 5 62.78 0 - Ordinary Soil
24+600 20.00 138.39 91.95 1,839.00 0.01 0.82 16.40 - - - - - - 95 1,747.05 5 91.95 0 - Ordinary Soil
24+620 20.00 59.85 78.07 1,561.40 - - - - 10.00 0.89 8.90 0.14 1.40 95 1,483.33 5 78.07 0 - Ordinary Soil
24+640 20.00 12.20 75.30 1,506.00 2.34 1.18 23.60 - 10.00 2.56 25.60 0.62 6.20 95 1,430.70 5 75.30 0 - Ordinary Soil
24+660 20.00 24.35 42.10 842.00 0.30 0.15 3.00 - - - - - - 95 799.90 5 42.10 0 - Ordinary Soil
24+680 20.00 43.66 27.93 558.60 - 1.17 23.40 - - - - - - 95 530.67 5 27.93 0 - Ordinary Soil
24+700 20.00 62.18 43.27 865.40 - 0.15 3.00 - - - - - - 95 822.13 5 43.27 0 - Ordinary Soil
24+720 20.00 20.35 32.01 640.20 1.92 0.96 19.20 - 10.00 2.28 22.80 0.56 5.60 95 608.19 5 32.01 0 - Ordinary Soil
24+740 20.00 34.18 48.18 963.60 0.18 0.09 1.80 - 20.00 1.65 33.00 0.44 8.80 95 915.42 5 48.18 0 - Ordinary Soil
24+760 20.00 19.65 20.00 400.00 0.44 1.18 23.60 - 10.00 1.30 13.00 0.28 2.80 95 380.00 5 20.00 0 - Ordinary Soil
24+780 20.00 60.30 47.24 944.80 - 0.09 1.80 - - - - - - 95 897.56 5 47.24 0 - Ordinary Soil
24+800 20.00 35.63 27.64 552.80 0.33 0.39 7.80 - 10.00 1.25 12.50 0.29 2.90 95 525.16 5 27.64 0 - Ordinary Soil
24+820 20.00 42.32 51.31 1,026.20 0.12 0.06 1.20 - 10.00 1.59 15.90 0.41 4.10 95 974.89 5 51.31 0 - Ordinary Soil
43 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
24+840 20.00 60.55 48.09 961.80 - 0.17 3.40 - - - - - - 95 913.71 5 48.09 0 - Ordinary Soil
24+860 20.00 17.96 30.14 602.80 3.10 1.61 32.20 - 10.00 2.60 26.00 0.68 6.80 95 572.66 5 30.14 0 - Ordinary Soil
24+880 20.00 0.04 30.30 606.00 17.27 8.64 172.80 - 20.00 6.11 122.20 0.80 16.00 95 575.70 5 30.30 0 - Ordinary Soil
24+900 20.00 - 8.98 179.60 34.09 18.60 372.00 192.40 20.00 10.44 208.80 1.39 27.80 95 170.62 5 8.98 0 - Ordinary Soil
24+920 20.00 13.89 6.97 139.40 10.80 14.04 280.80 141.40 10.00 13.98 139.80 3.41 34.10 95 132.43 5 6.97 0 - Ordinary Soil
24+940 20.00 73.67 36.84 736.80 - 17.05 341.00 - - - - - - 95 699.96 5 36.84 0 - Ordinary Soil
24+960 20.00 40.44 27.17 543.40 0.98 5.89 117.80 - - - - - - 95 516.23 5 27.17 0 - Ordinary Soil
24+980 20.00 80.08 76.88 1,537.60 0.04 0.02 0.40 - 10.00 1.72 17.20 0.50 5.00 95 1,460.72 5 76.88 0 - Ordinary Soil
25+000 20.00 77.24 58.84 1,176.80 0.01 0.50 10.00 - 20.00 2.05 41.00 0.56 11.20 95 1,117.96 5 58.84 0 - Ordinary Soil
25+020 20.00 77.68 78.88 1,577.60 0.09 0.07 1.40 - 20.00 1.45 29.00 0.41 8.20 95 1,498.72 5 78.88 0 - Ordinary Soil
25+040 20.00 50.43 63.84 1,276.80 3.18 1.60 32.00 - 20.00 6.03 120.60 1.29 25.80 95 1,212.96 5 63.84 0 - Ordinary Soil
25+060 20.00 9.68 43.68 873.60 9.03 4.56 91.20 - 20.00 6.84 136.80 1.19 23.80 95 829.92 5 43.68 0 - Ordinary Soil
25+080 20.00 24.55 37.49 749.80 1.10 2.14 42.80 - 20.00 1.95 39.00 0.28 5.60 95 712.31 5 37.49 0 - Ordinary Soil
25+100 20.00 29.36 19.52 390.40 7.27 8.15 163.00 - 20.00 5.35 107.00 1.10 22.00 95 370.88 5 19.52 0 - Ordinary Soil
25+120 20.00 14.19 19.37 387.40 1.53 1.32 26.40 - 20.00 3.91 78.20 1.23 24.60 95 368.03 5 19.37 0 - Ordinary Soil
25+140 20.00 5.37 17.37 347.40 3.84 5.56 111.20 - 20.00 1.35 27.00 0.23 4.60 95 330.03 5 17.37 0 - Ordinary Soil
25+160 20.00 0.31 7.25 145.00 7.14 4.34 86.80 - 20.00 2.87 57.40 0.61 12.20 95 137.75 5 7.25 0 - Ordinary Soil
25+180 20.00 3.38 4.38 87.60 3.82 3.83 76.60 - 20.00 1.40 28.00 0.24 4.80 95 83.22 5 4.38 0 - Ordinary Soil
25+200 20.00 0.98 0.65 13.00 7.84 7.49 149.80 136.80 20.00 4.22 84.40 0.67 13.40 95 12.35 5 0.65 0 - Ordinary Soil
25+220 20.00 26.47 14.93 298.60 0.20 2.01 40.20 - 10.00 1.42 14.20 0.36 3.60 95 283.67 5 14.93 0 - Ordinary Soil
25+240 20.00 67.52 34.25 685.00 - 3.92 78.40 - - - - - - 95 650.75 5 34.25 0 - Ordinary Soil
25+260 20.00 81.94 54.21 1,084.20 - 0.10 2.00 - - - - - - 95 1,029.99 5 54.21 0 - Ordinary Soil
25+280 20.00 69.56 68.54 1,370.80 - - - - - - - - - 95 1,302.26 5 68.54 0 - Ordinary Soil
25+300 20.00 77.82 79.88 1,597.60 - - - - - - - - - 95 1,517.72 5 79.88 0 - Ordinary Soil
25+320 20.00 101.44 85.50 1,710.00 - - - - - - - - - 95 1,624.50 5 85.50 0 - Ordinary Soil
25+340 20.00 111.07 94.45 1,889.00 - - - - - - - - - 95 1,794.55 5 94.45 0 - Ordinary Soil
25+360 20.00 83.55 92.50 1,850.00 - - - - - - - - - 95 1,757.50 5 92.50 0 - Ordinary Soil
25+380 20.00 62.12 86.60 1,732.00 - - - - - - - - - 95 1,645.40 5 86.60 0 - Ordinary Soil
25+400 20.00 50.11 66.83 1,336.60 - - - - - - - - - 95 1,269.77 5 66.83 0 - Ordinary Soil
25+420 20.00 38.87 50.50 1,010.00 - - - - - - - - - 95 959.50 5 50.50 0 - Ordinary Soil
25+440 20.00 40.69 45.40 908.00 - - - - - - - - - 95 862.60 5 45.40 0 - Ordinary Soil
25+460 20.00 42.28 40.58 811.60 - - - - - - - - - 95 771.02 5 40.58 0 - Ordinary Soil
25+480 20.00 128.10 84.40 1,688.00 - - - - - - - - - 95 1,603.60 5 84.40 0 - Ordinary Soil
25+500 20.00 151.54 96.91 1,938.20 - - - - - - - - - 95 1,841.29 5 96.91 0 - Ordinary Soil
25+520 20.00 148.50 138.30 2,766.00 - - - - - - - - - 95 2,627.70 5 138.30 0 - Ordinary Soil
25+540 20.00 136.07 143.81 2,876.20 - - - - - - - - - 95 2,732.39 5 143.81 0 - Ordinary Soil
25+560 20.00 122.08 135.29 2,705.80 - - - - - - - - - 95 2,570.51 5 135.29 0 - Ordinary Soil
25+580 20.00 166.13 151.10 3,022.00 - - - - - - - - - 95 2,870.90 5 151.10 0 - Ordinary Soil
25+600 20.00 221.35 171.72 3,434.40 - - - - - - - - - 95 3,262.68 5 171.72 0 - Ordinary Soil
25+620 20.00 213.30 189.72 3,794.40 - - - - - - - - - 95 3,604.68 5 189.72 0 - Ordinary Soil
25+640 20.00 196.15 208.75 4,175.00 - - - - - - - - - 95 3,966.25 5 208.75 0 - Ordinary Soil
25+660 20.00 212.05 212.68 4,253.60 0.01 0.01 0.20 - - - - - - 95 4,040.92 5 212.68 0 - Ordinary Soil
25+680 20.00 218.03 207.09 4,141.80 - - - - - - - - - 95 3,934.71 5 207.09 0 - Ordinary Soil
44 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
25+700 20.00 272.77 242.41 4,848.20 - 0.01 0.20 - - - - - - 95 4,605.79 5 242.41 0 - Ordinary Soil
25+720 20.00 304.52 261.28 5,225.60 - - - - - - - - - 95 4,964.32 5 261.28 0 - Ordinary Soil
25+740 20.00 336.92 304.85 6,097.00 - - - - - - - - - 95 5,792.15 5 304.85 0 - Ordinary Soil
25+760 20.00 326.80 315.66 6,313.20 - - - - - - - - - 95 5,997.54 5 315.66 0 - Ordinary Soil
25+780 20.00 332.77 334.85 6,697.00 - - - - - - - - - 95 6,362.15 5 334.85 0 - Ordinary Soil
25+800 20.00 395.93 361.37 7,227.40 - - - - - - - - - 95 6,866.03 5 361.37 0 - Ordinary Soil
25+820 20.00 399.29 366.03 7,320.60 - - - - - - - - - 95 6,954.57 5 366.03 0 - Ordinary Soil
25+840 20.00 588.57 492.25 9,845.00 - - - - - - - - - 95 9,352.75 5 492.25 0 - Ordinary Soil
25+860 20.00 489.84 444.57 8,891.40 - - - - - - - - - 95 8,446.83 5 444.57 0 - Ordinary Soil
25+880 20.00 433.44 511.01 10,220.20 - - - - - - - - - 95 9,709.19 5 511.01 0 - Ordinary Soil
25+900 20.00 384.09 436.97 8,739.40 - - - - - - - - - 95 8,302.43 5 436.97 0 - Ordinary Soil
25+920 20.00 356.70 395.07 7,901.40 - - - - - - - - - 95 7,506.33 5 395.07 0 - Ordinary Soil
25+940 20.00 551.79 467.94 9,358.80 - - - - - - - - - 95 8,890.86 5 467.94 0 - Ordinary Soil
25+960 20.00 493.40 425.05 8,501.00 - - - - - - - - - 95 8,075.95 5 425.05 0 - Ordinary Soil
25+980 20.00 459.98 505.89 10,117.80 - - - - - - - - - 95 9,611.91 5 505.89 0 - Ordinary Soil
26+000 20.00 340.54 416.97 8,339.40 - - - - - - - - - 95 7,922.43 5 416.97 0 - Ordinary Soil
26+020 20.00 450.64 455.31 9,106.20 - - - - - - - - - 95 8,650.89 5 455.31 0 - Ordinary Soil
26+040 20.00 376.94 358.74 7,174.80 - - - - - - - - - 95 6,816.06 5 358.74 0 - Ordinary Soil
26+060 20.00 318.31 384.48 7,689.60 - - - - - - - - - 95 7,305.12 5 384.48 0 - Ordinary Soil
26+080 20.00 326.30 351.62 7,032.40 0.01 0.01 0.20 - - - - - - 95 6,680.78 5 351.62 0 - Ordinary Soil
26+100 20.00 302.65 310.48 6,209.60 - - - - - - - - - 95 5,899.12 5 310.48 0 - Ordinary Soil
26+120 20.00 259.39 292.85 5,857.00 - 0.01 0.20 - 10.00 80.61 806.10 0.70 7.00 95 5,564.15 5 292.85 0 - Ordinary Soil
26+140 20.00 310.74 306.70 6,134.00 - - - - 20.00 78.17 1,563.40 0.70 14.00 95 5,827.30 5 306.70 0 - Ordinary Soil
26+160 20.00 287.67 273.53 5,470.60 - - - - 20.00 66.38 1,327.60 0.69 13.80 95 5,197.07 5 273.53 0 - Ordinary Soil
26+180 20.00 210.28 260.51 5,210.20 - - - - 20.00 49.38 987.60 0.68 13.60 95 4,949.69 5 260.51 0 - Ordinary Soil
26+200 20.00 168.26 227.97 4,559.40 - - - - 20.00 39.96 799.20 0.67 13.40 95 4,331.43 5 227.97 0 - Ordinary Soil
26+220 20.00 140.01 175.15 3,503.00 - - - - 10.00 31.02 310.20 0.67 6.70 95 3,327.85 5 175.15 0 - Ordinary Soil
26+240 20.00 157.26 162.76 3,255.20 - - - - - - - - - 95 3,092.44 5 162.76 0 - Ordinary Soil
26+260 20.00 110.35 125.18 2,503.60 - - - - - - - - - 95 2,378.42 5 125.18 0 - Ordinary Soil
26+280 20.00 47.06 102.16 2,043.20 - - - - - - - - - 95 1,941.04 5 102.16 0 - Ordinary Soil
26+300 20.00 23.06 66.71 1,334.20 - - - - - - - - - 95 1,267.49 5 66.71 0 - Ordinary Soil
26+320 20.00 16.06 31.56 631.20 - - - - - - - - - 95 599.64 5 31.56 0 - Ordinary Soil
26+340 20.00 26.26 24.66 493.20 - - - - - - - - - 95 468.54 5 24.66 0 - Ordinary Soil
26+360 20.00 4.08 10.07 201.40 0.58 0.29 5.80 - - - - - - 95 191.33 5 10.07 0 - Ordinary Soil
26+380 20.00 0.61 13.44 268.80 3.98 1.99 39.80 - 7.00 0.89 6.23 0.12 0.84 95 255.36 5 13.44 0 - Ordinary Soil
26+400 20.00 6.85 5.47 109.40 0.64 0.61 12.20 - - - - - - 95 103.93 5 5.47 0 - Ordinary Soil
26+420 20.00 28.53 14.57 291.40 - 1.99 39.80 - - - - - - 95 276.83 5 14.57 0 - Ordinary Soil
26+440 20.00 23.46 15.16 303.20 - 0.32 6.40 - - - - - - 95 288.04 5 15.16 0 - Ordinary Soil
26+460 20.00 7.13 17.83 356.60 0.94 0.47 9.40 - - - - - - 95 338.77 5 17.83 0 - Ordinary Soil
26+480 20.00 0.02 11.74 234.80 12.25 6.13 122.60 - 7.00 4.41 30.87 0.47 3.29 95 223.06 5 11.74 0 - Ordinary Soil
26+500 20.00 26.33 16.73 334.60 - 0.47 9.40 - - - - - - 95 317.87 5 16.73 0 - Ordinary Soil
26+520 20.00 40.26 20.14 402.80 - 6.13 122.60 - - - - - - 95 382.66 5 20.14 0 - Ordinary Soil
26+540 20.00 41.23 33.78 675.60 - - - - - - - - - 95 641.82 5 33.78 0 - Ordinary Soil
45 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
26+560 20.00 59.44 49.85 997.00 - - - - - - - - - 95 947.15 5 49.85 0 - Ordinary Soil
26+580 20.00 92.72 66.98 1,339.60 - - - - - - - - - 95 1,272.62 5 66.98 0 - Ordinary Soil
26+600 20.00 82.69 71.07 1,421.40 - - - - - - - - - 95 1,350.33 5 71.07 0 - Ordinary Soil
26+620 20.00 52.26 72.49 1,449.80 - - - - - - - - - 95 1,377.31 5 72.49 0 - Ordinary Soil
26+640 20.00 15.61 49.15 983.00 - - - - - - - - - 95 933.85 5 49.15 0 - Ordinary Soil
26+660 20.00 5.10 28.68 573.60 4.44 2.22 44.40 - - - - - - 95 544.92 5 28.68 0 - Ordinary Soil
26+680 20.00 7.71 11.66 233.20 - - - - - - - - - 95 221.54 5 11.66 0 - Ordinary Soil
26+700 20.00 30.72 17.91 358.20 0.01 2.23 44.60 - - - - - - 95 340.29 5 17.91 0 - Ordinary Soil
26+720 20.00 24.39 16.05 321.00 - - - - - - - - - 95 304.95 5 16.05 0 - Ordinary Soil
26+740 20.00 37.25 33.99 679.80 - 0.01 0.20 - - - - - - 95 645.81 5 33.99 0 - Ordinary Soil
26+760 20.00 53.08 38.74 774.80 - - - - - - - - - 95 736.06 5 38.74 0 - Ordinary Soil
26+780 20.00 82.02 59.64 1,192.80 - - - - - - - - - 95 1,133.16 5 59.64 0 - Ordinary Soil
26+800 20.00 81.64 67.36 1,347.20 - - - - - - - - - 95 1,279.84 5 67.36 0 - Ordinary Soil
26+820 20.00 89.69 85.86 1,717.20 - - - - - - - - - 95 1,631.34 5 85.86 0 - Ordinary Soil
26+840 20.00 110.62 96.13 1,922.60 - - - - - - - - - 95 1,826.47 5 96.13 0 - Ordinary Soil
26+860 20.00 98.45 94.07 1,881.40 - - - - - - - - - 95 1,787.33 5 94.07 0 - Ordinary Soil
26+880 20.00 67.19 88.91 1,778.20 - - - - - - - - - 95 1,689.29 5 88.91 0 - Ordinary Soil
26+900 20.00 45.06 71.76 1,435.20 - - - - - - - - - 95 1,363.44 5 71.76 0 - Ordinary Soil
26+920 20.00 32.29 49.74 994.80 - - - - - - - - - 95 945.06 5 49.74 0 - Ordinary Soil
26+940 20.00 44.40 44.73 894.60 - - - - - - - - - 95 849.87 5 44.73 0 - Ordinary Soil
26+960 20.00 14.57 23.43 468.60 3.89 1.95 39.00 - 10.00 2.39 23.90 0.54 5.40 95 445.17 5 23.43 0 - Ordinary Soil
26+980 20.00 2.34 23.37 467.40 5.83 2.92 58.40 - 20.00 2.40 48.00 0.56 11.20 95 444.03 5 23.37 0 - Ordinary Soil
27+000 20.00 14.42 14.50 290.00 1.24 2.57 51.40 - 20.00 2.74 54.80 0.37 7.40 95 275.50 5 14.50 0 - Ordinary Soil
27+020 20.00 12.13 7.24 144.80 2.56 4.20 84.00 - 10.00 2.14 21.40 0.21 2.10 95 137.56 5 7.24 0 - Ordinary Soil
27+040 20.00 16.48 15.45 309.00 0.11 0.68 13.60 - - - - - - 95 293.55 5 15.45 0 - Ordinary Soil
27+060 20.00 11.71 11.92 238.40 0.26 1.41 28.20 - - - - - - 95 226.48 5 11.92 0 - Ordinary Soil
27+080 20.00 1.29 8.89 177.80 5.65 2.88 57.60 - 10.00 1.50 15.00 0.03 0.30 95 168.91 5 8.89 0 - Ordinary Soil
27+100 20.00 7.44 9.58 191.60 12.89 6.58 131.60 - 20.00 2.73 54.60 0.18 3.60 95 182.02 5 9.58 0 - Ordinary Soil
27+120 20.00 6.02 3.66 73.20 8.12 6.89 137.80 64.60 20.00 4.97 99.40 0.64 12.80 95 69.54 5 3.66 0 - Ordinary Soil
27+140 20.00 9.05 8.25 165.00 7.14 10.02 200.40 35.40 10.00 5.13 51.30 0.79 7.90 95 156.75 5 8.25 0 - Ordinary Soil
27+160 20.00 31.30 18.66 373.20 0.05 4.09 81.80 - - - - - - 95 354.54 5 18.66 0 - Ordinary Soil
27+180 20.00 21.73 15.39 307.80 1.14 4.14 82.80 - 10.00 3.05 30.50 0.86 8.60 95 292.41 5 15.39 0 - Ordinary Soil
27+200 20.00 15.53 23.42 468.40 2.45 1.25 25.00 - 20.00 2.02 40.40 0.44 8.80 95 444.98 5 23.42 0 - Ordinary Soil
27+220 20.00 14.43 18.08 361.60 0.53 0.84 16.80 - 20.00 1.48 29.60 0.33 6.60 95 343.52 5 18.08 0 - Ordinary Soil
27+240 20.00 7.73 11.63 232.60 1.09 1.77 35.40 - 20.00 1.26 25.20 0.25 5.00 95 220.97 5 11.63 0 - Ordinary Soil
27+260 20.00 1.61 8.02 160.40 10.00 5.27 105.40 - 20.00 4.83 96.60 0.60 12.00 95 152.38 5 8.02 0 - Ordinary Soil
27+280 20.00 26.38 17.06 341.20 2.91 2.00 40.00 - 10.00 1.69 16.90 0.32 3.20 95 324.14 5 17.06 0 - Ordinary Soil
27+300 20.00 27.67 14.64 292.80 - 5.00 100.00 - - - - - - 95 278.16 5 14.64 0 - Ordinary Soil
27+320 20.00 2.09 14.24 284.80 4.47 3.69 73.80 - 10.00 1.86 18.60 0.12 1.20 95 270.56 5 14.24 0 - Ordinary Soil
27+340 20.00 8.92 18.30 366.00 4.70 2.35 47.00 - 20.00 1.13 22.60 - - 95 347.70 5 18.30 0 - Ordinary Soil
27+360 20.00 29.81 15.95 319.00 2.65 3.56 71.20 - 20.00 1.00 20.00 - - 95 303.05 5 15.95 0 - Ordinary Soil
27+380 20.00 16.15 12.54 250.80 4.68 4.69 93.80 - 20.00 5.52 110.40 1.04 20.80 95 238.26 5 12.54 0 - Ordinary Soil
27+400 20.00 6.25 18.03 360.60 1.06 1.86 37.20 - 20.00 1.02 20.40 0.18 3.60 95 342.57 5 18.03 0 - Ordinary Soil
46 of 323
EARTHWORK CALCULATIONS FOR ROADWAY
Name of the road:…………………………….
Chainage:0+000 to ….
Earthwork in Roadway Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
Excess filling
ge
Length
ks
Road way Cutting Filling Cutting Back filling Ordinary Soil Soft Rock Hard Rock
Length (m)
na
ar
Av area Volume Area Av area Volume Area Area Volume Volume
m
i
ha
Area (m2) Volume (m3) L (m) Vol (m3) Vol (m3) Volume (m3)
Re
(m2) (m3) (m2) (m2) (m3) (m2) (m2) (m3) (m3)
C
% % %
27+420 20.00 11.09 13.62 272.40 5.22 4.95 99.00 - 20.00 2.41 48.20 0.46 9.20 95 258.78 5 13.62 0 - Ordinary Soil
27+440 20.00 6.20 6.23 124.60 1.90 1.48 29.60 - 20.00 1.41 28.20 0.28 5.60 95 118.37 5 6.23 0 - Ordinary Soil
27+460 20.00 3.11 7.10 142.00 6.21 5.72 114.40 - 20.00 2.78 55.60 0.27 5.40 95 134.90 5 7.10 0 - Ordinary Soil
27+480 20.00 3.73 4.97 99.40 10.95 6.43 128.60 29.20 20.00 1.84 36.80 0.08 1.60 95 94.43 5 4.97 0 - Ordinary Soil
27+500 20.00 0.01 1.56 31.20 14.98 10.60 212.00 180.80 20.00 1.48 29.60 0.37 7.40 95 29.64 5 1.56 0 - Ordinary Soil
27+520 20.00 7.80 5.77 115.40 8.10 9.53 190.60 75.20 20.00 8.01 160.20 1.52 30.40 95 109.63 5 5.77 0 - Ordinary Soil
27+540 20.00 36.08 18.05 361.00 0.74 7.86 157.20 - 20.00 2.58 51.60 0.40 8.00 95 342.95 5 18.05 0 - Ordinary Soil
27+560 20.00 49.36 28.58 571.60 0.74 4.42 88.40 - 20.00 5.53 110.60 1.33 26.60 95 543.02 5 28.58 0 - Ordinary Soil
27+580 20.00 58.61 47.35 947.00 0.78 0.76 15.20 - 20.00 9.12 182.40 2.78 55.60 95 899.65 5 47.35 0 - Ordinary Soil
27+600 20.00 14.63 32.00 640.00 11.77 6.26 125.20 - 20.00 13.78 275.60 3.21 64.20 95 608.00 5 32.00 0 - Ordinary Soil
27+620 20.00 13.85 36.23 724.60 3.32 2.05 41.00 - 10.00 4.10 41.00 0.59 5.90 95 688.37 5 36.23 0 - Ordinary Soil
27+640 20.00 14.88 14.76 295.20 0.17 5.97 119.40 - - - - - - 95 280.44 5 14.76 0 - Ordinary Soil
27+660 20.00 15.33 14.59 291.80 - 1.66 33.20 - - - - - - 95 277.21 5 14.59 0 - Ordinary Soil
27+680 20.00 17.33 16.11 322.20 - 0.09 1.80 - - - - - - 95 306.09 5 16.11 0 - Ordinary Soil
27+700 20.00 19.95 17.64 352.80 - - - - - - - - - 95 335.16 5 17.64 0 - Ordinary Soil
27+720 20.00 6.45 11.89 237.80 0.03 0.02 0.40 - - - - - - 95 225.91 5 11.89 0 - Ordinary Soil
27+740 20.00 7.01 13.48 269.60 0.20 0.10 2.00 - - - - - - 95 256.12 5 13.48 0 - Ordinary Soil
27+760 20.00 4.96 5.71 114.20 2.43 1.23 24.60 - - - - - - 95 108.49 5 5.71 0 - Ordinary Soil
27+780 20.00 7.41 7.21 144.20 2.95 1.58 31.60 - - - - - - 95 136.99 5 7.21 0 - Ordinary Soil
27+800 20.00 9.44 7.20 144.00 0.76 1.60 32.00 - 7.00 1.29 9.03 0.26 1.82 95 136.80 5 7.20 0 - Ordinary Soil
Total 27800.00 5823363.00 125749.00 66772.60 273146.98 15730.26 5532194.85 291168.15 0.00
47 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Road
Planning and Design Branch
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³) fill area (m³) Fill) KM. KM. M3-KM
(m³)
1 0+000 4.04 0.02 - 1+200 1.20 0.20 -
2 0+020 21.46 255.00 0.29 3.10 251.90 1+200 1.18 0.18 45.34
3 0+040 26.25 477.10 - 2.90 474.20 1+200 1.16 0.16 75.87
4 0+060 93.07 1,193.20 - - 1,193.20 1+200 1.14 0.14 167.05
5 0+080 81.55 1,746.20 5.30 53.00 1,693.20 1+200 1.12 0.12 203.18
6 0+100 90.98 1,725.30 0.66 59.60 1,665.70 1+200 1.10 0.10 166.57
7 0+120 110.05 2,010.30 0.66 13.20 1,997.10 1+200 1.08 0.08 159.77
8 0+140 172.77 2,828.20 0.68 13.40 2,814.80 1+200 1.06 0.06 168.89
9 0+160 207.24 3,800.10 1.64 23.20 3,776.90 1+200 1.04 0.04 151.08
10 0+180 238.35 4,455.90 1.55 31.90 4,424.00 1+200 1.02 0.02 88.48
11 0+200 285.09 5,234.40 1.55 31.00 5,203.40 1+200 1.00 - -
12 0+220 192.52 4,776.10 1.55 31.00 4,745.10 1+200 0.98 - -
13 0+240 143.77 3,362.90 1.50 30.50 3,332.40 1+200 0.96 - -
14 0+260 110.25 2,540.20 0.66 21.60 2,518.60 1+200 0.94 - -
15 0+280 100.29 2,105.40 0.66 13.20 2,092.20 1+200 0.92 - -
16 0+300 87.68 1,879.70 0.65 13.10 1,866.60 1+200 0.90 - -
17 0+320 79.54 1,672.20 0.72 13.70 1,658.50 1+200 0.88 - -
18 0+340 48.09 1,276.30 - 7.20 1,269.10 1+200 0.86 - -
19 0+360 63.66 1,117.50 0.92 9.20 1,108.30 1+200 0.84 - -
20 0+380 40.27 1,039.30 - 9.20 1,030.10 1+200 0.82 - -
21 0+400 42.23 825.00 1.25 12.50 812.50 1+200 0.80 - -
22 0+420 52.12 943.50 0.92 21.70 921.80 1+200 0.78 - -
23 0+440 45.07 971.90 2.55 34.70 937.20 1+200 0.76 - -
24 0+460 38.15 832.20 0.86 34.10 798.10 1+200 0.74 - -
25 0+480 47.13 852.80 - 8.60 844.20 1+200 0.72 - -
26 0+500 40.18 873.10 0.61 6.10 867.00 1+200 0.70 - -
27 0+520 31.63 718.10 0.67 12.80 705.30 1+200 0.68 - -
28 0+540 32.92 645.50 1.94 26.10 619.40 1+200 0.66 - -
29 0+560 18.52 514.40 9.92 118.60 395.80 1+200 0.64 - -
30 0+580 16.20 347.20 3.51 134.30 212.90 1+200 0.62 - -
31 0+600 191.42 2,076.20 0.89 44.00 2,032.20 1+200 0.60 - -
32 0+620 324.94 5,163.60 0.70 15.90 5,147.70 1+200 0.58 - -
33 0+640 108.85 4,337.90 0.67 13.70 4,324.20 1+200 0.56 - -
34 0+660 54.26 1,631.10 22.63 233.00 1,398.10 1+200 0.54 - -
35 0+680 36.15 904.10 9.09 317.20 586.90 1+200 0.52 - -
36 0+700 40.43 765.80 3.97 130.60 635.20 1+200 0.50 - -
37 0+720 51.16 915.90 0.93 49.00 866.90 1+200 0.48 - -
38 0+740 52.67 1,038.30 0.93 18.60 1,019.70 1+200 0.46 - -
39 0+760 41.87 945.40 1.76 26.90 918.50 1+200 0.44 - -
40 0+780 47.82 896.90 0.98 27.40 869.50 1+200 0.42 - -
41 0+800 95.30 1,431.20 - 9.80 1,421.40 1+200 0.40 - -
42 0+820 138.92 2,342.20 - - 2,342.20 1+200 0.38 - -
43 0+840 196.52 3,354.40 0.67 6.70 3,347.70 1+200 0.36 - -
44 0+860 323.83 5,203.50 3.11 37.80 5,165.70 1+200 0.34 - -
45 0+880 433.57 7,574.00 1.64 47.50 7,526.50 1+200 0.32 - -
46 0+900 422.69 8,562.60 1.78 34.20 8,528.40 1+200 0.30 - -
47 0+920 399.23 8,219.20 1.63 34.10 8,185.10 1+200 0.28 - -
48 0+940 447.22 8,464.50 1.38 30.10 8,434.40 1+200 0.26 - -
49 0+960 407.52 8,547.40 1.39 27.70 8,519.70 1+200 0.24 - -
50 0+980 352.80 7,603.20 1.36 27.50 7,575.70 1+200 0.22 - -
51 1+000 345.53 6,983.30 - 13.60 6,969.70 1+200 0.20 - -
52 1+020 321.47 6,670.00 - - 6,670.00 1+200 0.18 - -
53 1+040 275.52 5,969.90 - - 5,969.90 1+200 0.16 - -
54 1+060 263.11 5,386.30 - - 5,386.30 1+200 0.14 - -
55 1+080 212.02 4,751.30 - - 4,751.30 1+200 0.12 - -
56 1+100 194.68 4,067.00 - - 4,067.00 1+200 0.10 - -
57 1+120 121.49 3,161.70 - - 3,161.70 1+200 0.08 - -
58 1+140 79.73 2,012.20 - - 2,012.20 1+200 0.06 - -
59 1+160 58.33 1,380.60 - - 1,380.60 1+200 0.04 - -
60 1+180 57.48 1,158.10 - - 1,158.10 1+200 0.02 - -
61 1+200 27.16 846.40 1.30 13.00 833.40 1+200 - - - Disposal site
62 1+220 22.08 492.40 0.97 22.70 469.70 1+200 0.02 - -
48 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
63 1+240 15.06 371.40 1.03 20.00 351.40 1+200 0.04 - -
64 1+260 17.81 328.70 4.62 56.50 272.20 1+200 0.06 - -
65 1+280 13.33 311.40 3.88 85.00 226.40 1+200 0.08 - -
66 1+300 7.41 207.40 2.24 61.20 146.20 1+200 0.10 - -
67 1+320 23.99 314.00 0.15 23.90 290.10 1+200 0.12 - -
68 1+340 51.97 759.60 - 1.50 758.10 1+200 0.14 - -
69 1+360 18.19 701.60 0.19 1.90 699.70 1+200 0.16 - -
70 1+380 19.62 378.10 12.53 127.20 250.90 1+200 0.18 - -
71 1+400 2.64 222.60 10.44 229.70 (7.10) 1+200 0.20 - -
72 1+420 52.71 553.50 - 104.40 449.10 1+200 0.22 - -
73 1+440 52.42 1,051.30 0.02 0.20 1,051.10 1+200 0.24 - -
74 1+460 1.38 538.00 6.00 60.20 477.80 1+200 0.26 - -
75 1+480 - 13.80 5.81 118.10 (104.30) 1+200 0.28 - -
76 1+500 0.87 8.70 6.32 121.30 (112.60) 1+200 0.30 - -
77 1+520 1.07 19.40 1.88 82.00 (62.60) 1+200 0.32 - -
78 1+540 2.89 39.60 4.65 65.30 (25.70) 1+200 0.34 - -
79 1+560 0.84 37.30 3.77 84.20 (46.90) 1+200 0.36 - -
80 1+580 14.20 150.40 - 37.70 112.70 1+200 0.38 - -
81 1+600 16.13 303.30 - - 303.30 1+200 0.40 - -
82 1+620 25.34 414.70 - - 414.70 1+200 0.42 - -
83 1+640 35.76 611.00 - - 611.00 1+200 0.44 - -
84 1+660 58.92 946.80 - - 946.80 1+200 0.46 - -
85 1+680 82.18 1,411.00 - - 1,411.00 1+200 0.48 - -
86 1+700 100.98 1,831.60 - - 1,831.60 1+200 0.50 - -
87 1+720 77.10 1,780.80 - - 1,780.80 1+200 0.52 - -
88 1+740 49.35 1,264.50 - - 1,264.50 1+200 0.54 - -
89 1+760 61.09 1,104.40 0.01 0.10 1,104.30 1+200 0.56 - -
90 1+780 88.78 1,498.70 - 0.10 1,498.60 1+200 0.58 - -
91 1+800 107.27 1,960.50 - - 1,960.50 1+200 0.60 - -
92 1+820 113.79 2,210.60 - - 2,210.60 1+200 0.62 - -
93 1+840 154.97 2,687.60 - - 2,687.60 1+200 0.64 - -
94 1+860 156.59 3,115.60 - - 3,115.60 1+200 0.66 - -
95 1+880 110.88 2,674.70 - - 2,674.70 1+200 0.68 - -
96 1+900 67.68 1,785.60 - - 1,785.60 1+200 0.70 - -
97 1+920 100.35 1,680.30 - - 1,680.30 1+200 0.72 - -
98 1+940 123.37 2,237.20 - - 2,237.20 1+200 0.74 - -
99 1+960 159.77 2,831.40 - - 2,831.40 1+200 0.76 - -
100 1+980 175.08 3,348.50 - - 3,348.50 1+200 0.78 - -
101 2+000 144.55 3,196.30 - - 3,196.30 1+200 0.80 - -
102 2+020 144.11 2,886.60 - - 2,886.60 1+200 0.82 - -
103 2+040 129.39 2,735.00 - - 2,735.00 1+200 0.84 - -
104 2+060 105.61 2,350.00 - - 2,350.00 1+200 0.86 - -
105 2+080 103.29 2,089.00 - - 2,089.00 1+200 0.88 - -
106 2+100 95.25 1,985.40 - - 1,985.40 1+200 0.90 - -
107 2+120 109.40 2,046.50 - - 2,046.50 1+200 0.92 - -
108 2+140 89.26 1,986.60 - - 1,986.60 1+200 0.94 - -
109 2+160 72.88 1,621.40 - - 1,621.40 3+160 1.00 - -
110 2+180 185.75 2,586.30 - - 2,586.30 3+160 0.98 - -
111 2+200 201.51 3,872.60 0.67 6.70 3,865.90 3+160 0.96 - -
112 2+220 122.73 3,242.40 0.66 13.30 3,229.10 3+160 0.94 - -
113 2+240 96.12 2,188.50 0.74 14.00 2,174.50 3+160 0.92 - -
114 2+260 99.39 1,955.10 0.86 16.00 1,939.10 3+160 0.90 - -
115 2+280 102.26 2,016.50 - 8.60 2,007.90 3+160 0.88 - -
116 2+300 97.16 1,994.20 - - 1,994.20 3+160 0.86 - -
117 2+320 74.89 1,720.50 - - 1,720.50 3+160 0.84 - -
118 2+340 47.05 1,219.40 - - 1,219.40 3+160 0.82 - -
119 2+360 53.77 1,008.20 - - 1,008.20 3+160 0.80 - -
120 2+380 46.84 1,006.10 - - 1,006.10 3+160 0.78 - -
121 2+400 38.90 857.40 0.01 0.10 857.30 3+160 0.76 - -
122 2+420 17.92 568.20 0.02 0.30 567.90 3+160 0.74 - -
123 2+440 5.87 237.90 1.46 14.80 223.10 3+160 0.72 - -
124 2+460 3.39 92.60 5.02 64.80 27.80 3+160 0.70 - -
125 2+480 12.38 157.70 3.58 86.00 71.70 3+160 0.68 - -
126 2+500 151.63 1,640.10 - 35.80 1,604.30 3+160 0.66 - -
127 2+520 170.48 3,221.10 - - 3,221.10 3+160 0.64 - -
128 2+540 117.23 2,877.10 - - 2,877.10 3+160 0.62 - -
129 2+560 67.05 1,842.80 - - 1,842.80 3+160 0.60 - -
130 2+580 42.53 1,095.80 - - 1,095.80 3+160 0.58 - -
131 2+600 18.93 614.60 - - 614.60 3+160 0.56 - -
132 2+620 5.23 241.60 3.02 30.20 211.40 3+160 0.54 - -
133 2+640 3.26 84.90 6.78 98.00 (13.10) 3+160 0.52 - -
134 2+660 9.09 123.50 10.16 169.40 (45.90) 3+160 0.50 - -
135 2+680 30.06 391.50 - 101.60 289.90 3+160 0.48 - -
136 2+700 37.67 677.30 - - 677.30 3+160 0.46 - -
137 2+720 27.98 656.50 - - 656.50 3+160 0.44 - -
49 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
138 2+740 18.75 467.30 0.64 6.40 460.90 3+160 0.42 - -
139 2+760 11.81 305.60 3.35 39.90 265.70 3+160 0.40 - -
140 2+780 5.02 168.30 2.80 61.50 106.80 3+160 0.38 - -
141 2+800 11.53 165.50 1.27 40.70 124.80 3+160 0.36 - -
142 2+820 12.32 238.50 7.04 83.10 155.40 3+160 0.34 - -
143 2+840 8.34 206.60 6.12 131.60 75.00 3+160 0.32 - -
144 2+860 27.26 356.00 13.64 197.60 158.40 3+160 0.30 - -
145 2+880 36.42 636.80 1.98 156.20 480.60 3+160 0.28 - -
146 2+900 49.06 854.80 - 19.80 835.00 3+160 0.26 - -
147 2+920 51.49 1,005.50 - - 1,005.50 3+160 0.24 - -
148 2+940 34.01 855.00 5.11 51.10 803.90 3+160 0.22 - -
149 2+960 45.58 795.90 4.56 96.70 699.20 3+160 0.20 - -
150 2+980 174.52 2,201.00 - 45.60 2,155.40 3+160 0.18 - -
151 3+000 300.55 4,750.70 0.69 6.90 4,743.80 3+160 0.16 - -
152 3+020 258.91 5,594.60 0.69 13.80 5,580.80 3+160 0.14 - -
153 3+040 144.33 4,032.40 0.66 13.50 4,018.90 3+160 0.12 - -
154 3+060 88.27 2,326.00 0.80 14.60 2,311.40 3+160 0.10 - -
155 3+080 87.99 1,762.60 0.66 14.60 1,748.00 3+160 0.08 - -
156 3+100 117.82 2,058.10 0.66 13.20 2,044.90 3+160 0.06 - -
157 3+120 126.50 2,443.20 0.66 13.20 2,430.00 3+160 0.04 - -
158 3+140 117.07 2,435.70 0.66 13.20 2,422.50 3+160 0.02 - -
159 3+160 103.82 2,208.90 0.66 13.20 2,195.70 3+160 - - - Disposal site
160 3+180 88.64 1,924.60 - 6.60 1,918.00 3+160 0.02 - -
161 3+200 64.36 1,530.00 - - 1,530.00 3+160 0.04 - -
162 3+220 60.69 1,250.50 - - 1,250.50 3+160 0.06 - -
163 3+240 39.86 1,005.50 0.34 3.40 1,002.10 3+160 0.08 - -
164 3+260 42.04 819.00 - 3.40 815.60 3+160 0.10 - -
165 3+280 32.16 742.00 0.63 6.30 735.70 3+160 0.12 - -
166 3+300 19.62 517.80 2.72 33.50 484.30 3+160 0.14 - -
167 3+320 14.95 345.70 1.81 45.30 300.40 3+160 0.16 - -
168 3+340 18.32 332.70 0.58 23.90 308.80 3+160 0.18 - -
169 3+360 21.96 402.80 2.94 35.20 367.60 3+160 0.20 - -
170 3+380 23.42 453.80 0.40 33.40 420.40 3+160 0.22 - -
171 3+400 26.41 498.30 3.23 36.30 462.00 3+160 0.24 - -
172 3+420 52.51 789.20 - 32.30 756.90 3+160 0.26 - -
173 3+440 38.58 910.90 1.29 12.90 898.00 3+160 0.28 - -
174 3+460 32.73 713.10 0.56 18.50 694.60 3+160 0.30 - -
175 3+480 48.47 812.00 - 5.60 806.40 3+160 0.32 - -
176 3+500 47.47 959.40 - - 959.40 3+160 0.34 - -
177 3+520 60.63 1,081.00 - - 1,081.00 3+160 0.36 - -
178 3+540 48.08 1,087.10 2.02 20.20 1,066.90 3+160 0.38 - -
179 3+560 56.47 1,045.50 - 20.20 1,025.30 3+160 0.40 - -
180 3+580 41.40 978.70 - - 978.70 3+160 0.42 - -
181 3+600 11.21 526.10 0.78 7.80 518.30 3+160 0.44 - -
182 3+620 56.69 679.00 - 7.80 671.20 3+160 0.46 - -
183 3+640 250.82 3,075.10 - - 3,075.10 3+160 0.48 - -
184 3+660 258.46 5,092.80 - - 5,092.80 3+160 0.50 - -
185 3+680 195.06 4,535.20 0.69 6.90 4,528.30 3+160 0.52 - -
186 3+700 231.77 4,268.30 0.76 14.50 4,253.80 3+160 0.54 - -
187 3+720 158.72 3,904.90 0.67 14.30 3,890.60 3+160 0.56 - -
188 3+740 198.60 3,573.20 0.67 13.40 3,559.80 3+160 0.58 - -
189 3+760 167.37 3,659.70 0.67 13.40 3,646.30 3+160 0.60 - -
190 3+780 139.38 3,067.50 0.65 13.20 3,054.30 3+160 0.62 - -
191 3+800 131.98 2,713.60 0.80 14.50 2,699.10 3+160 0.64 - -
192 3+820 98.26 2,302.40 0.80 16.00 2,286.40 3+160 0.66 - -
193 3+840 117.87 2,161.30 0.66 14.60 2,146.70 3+160 0.68 - -
194 3+860 113.96 2,318.30 0.68 13.40 2,304.90 3+160 0.70 - -
195 3+880 138.89 2,528.50 0.64 13.20 2,515.30 3+160 0.72 - -
196 3+900 110.29 2,491.80 - 6.40 2,485.40 3+160 0.74 - -
197 3+920 107.17 2,174.60 - - 2,174.60 3+160 0.76 - -
198 3+940 103.29 2,104.60 - - 2,104.60 3+160 0.78 - -
199 3+960 76.06 1,793.50 0.01 0.10 1,793.40 3+160 0.80 - -
200 3+980 49.29 1,253.50 - 0.10 1,253.40 3+160 0.82 - -
201 4+000 118.72 1,680.10 5.15 51.50 1,628.60 3+160 0.84 - -
202 4+020 45.20 1,639.20 8.49 136.40 1,502.80 3+160 0.86 - -
203 4+040 23.90 691.00 2.14 106.30 584.70 3+160 0.88 - -
204 4+060 12.87 367.70 2.96 51.00 316.70 3+160 0.90 - -
205 4+080 12.86 257.30 8.36 113.20 144.10 3+160 0.92 - -
206 4+100 8.07 209.30 9.19 175.50 33.80 3+160 0.94 - -
207 4+120 14.95 230.20 10.50 196.90 33.30 3+160 0.96 - -
208 4+140 37.64 525.90 2.33 128.30 397.60 3+160 0.98 - -
209 4+160 51.66 893.00 - 23.30 869.70 3+160 1.00 - -
210 4+180 39.41 910.70 4.33 43.30 867.40 5+180 1.00 - -
211 4+200 72.77 1,121.80 1.99 63.20 1,058.60 5+180 0.98 - -
212 4+220 89.37 1,621.40 - 19.90 1,601.50 5+180 0.96 - -
50 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
213 4+240 81.76 1,711.30 - - 1,711.30 5+180 0.94 - -
214 4+260 125.55 2,073.10 - - 2,073.10 5+180 0.92 - -
215 4+280 253.85 3,794.00 0.69 6.90 3,787.10 5+180 0.90 - -
216 4+300 256.47 5,103.20 0.83 15.20 5,088.00 5+180 0.88 - -
217 4+320 271.65 5,281.20 0.69 15.20 5,266.00 5+180 0.86 - -
218 4+340 291.76 5,634.10 0.65 13.40 5,620.70 5+180 0.84 - -
219 4+360 318.19 6,099.50 0.69 13.40 6,086.10 5+180 0.82 - -
220 4+380 340.06 6,582.50 1.57 22.60 6,559.90 5+180 0.80 - -
221 4+400 372.46 7,125.20 1.54 31.10 7,094.10 5+180 0.78 - -
222 4+420 404.76 7,772.20 1.56 31.00 7,741.20 5+180 0.76 - -
223 4+440 517.09 9,218.50 1.82 33.80 9,184.70 5+180 0.74 - -
224 4+460 513.85 10,309.40 2.77 45.90 10,263.50 5+180 0.72 - -
225 4+480 577.02 10,908.70 8.25 110.20 10,798.50 5+180 0.70 - -
226 4+500 519.31 10,963.30 5.25 135.00 10,828.30 5+180 0.68 - -
227 4+520 503.56 10,228.70 4.08 93.30 10,135.40 5+180 0.66 - -
228 4+540 409.98 9,135.40 1.43 55.10 9,080.30 5+180 0.64 - -
229 4+560 366.24 7,762.20 1.58 30.10 7,732.10 5+180 0.62 - -
230 4+580 363.57 7,298.10 1.55 31.30 7,266.80 5+180 0.60 - -
231 4+600 389.78 7,533.50 1.57 31.20 7,502.30 5+180 0.58 - -
232 4+620 385.68 7,754.60 1.58 31.50 7,723.10 5+180 0.56 - -
233 4+640 403.89 7,895.70 16.28 178.60 7,717.10 5+180 0.54 - -
234 4+660 495.38 8,992.70 33.65 499.30 8,493.40 5+180 0.52 - -
235 4+680 443.84 9,392.20 7.42 410.70 8,981.50 5+180 0.50 - -
236 4+700 354.56 7,984.00 0.65 80.70 7,903.30 5+180 0.48 - -
237 4+720 328.63 6,831.90 2.66 33.10 6,798.80 5+180 0.46 - -
238 4+740 273.70 6,023.30 1.57 42.30 5,981.00 5+180 0.44 - -
239 4+760 238.12 5,118.20 0.65 22.20 5,096.00 5+180 0.42 - -
240 4+780 230.65 4,687.70 0.64 12.90 4,674.80 5+180 0.40 - -
241 4+800 221.60 4,522.50 0.65 12.90 4,509.60 5+180 0.38 - -
242 4+820 228.12 4,497.20 0.73 13.80 4,483.40 5+180 0.36 - -
243 4+840 157.99 3,861.10 0.68 14.10 3,847.00 5+180 0.34 - -
244 4+860 100.53 2,585.20 0.89 15.70 2,569.50 5+180 0.32 - -
245 4+880 71.23 1,717.60 0.93 18.20 1,699.40 5+180 0.30 - -
246 4+900 45.15 1,163.80 0.90 18.30 1,145.50 5+180 0.28 - -
247 4+920 46.50 916.50 1.00 19.00 897.50 5+180 0.26 - -
248 4+940 33.56 800.60 0.27 12.70 787.90 5+180 0.24 - -
249 4+960 36.57 701.30 1.09 13.60 687.70 5+180 0.22 - -
250 4+980 33.58 701.50 - 10.90 690.60 5+180 0.20 - -
251 5+000 31.49 650.70 0.66 6.60 644.10 5+180 0.18 - -
252 5+020 38.69 701.80 1.04 17.00 684.80 5+180 0.16 - -
253 5+040 48.25 869.40 1.05 20.90 848.50 5+180 0.14 - -
254 5+060 42.44 906.90 1.05 21.00 885.90 5+180 0.12 - -
255 5+080 84.23 1,266.70 0.76 18.10 1,248.60 5+180 0.10 - -
256 5+100 106.77 1,910.00 0.78 15.40 1,894.60 5+180 0.08 - -
257 5+120 98.97 2,057.40 0.89 16.70 2,040.70 5+180 0.06 - -
258 5+140 81.43 1,804.00 0.77 16.60 1,787.40 5+180 0.04 - -
259 5+160 101.44 1,828.70 0.93 17.00 1,811.70 5+180 0.02 - -
260 5+180 70.38 1,718.20 0.86 17.90 1,700.30 5+180 - - - Disposal site
261 5+200 34.16 1,045.40 - 8.60 1,036.80 5+180 0.02 - -
262 5+220 38.99 731.50 - - 731.50 5+180 0.04 - -
263 5+240 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.06 - Err:509
264 5+260 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.08 - Err:509
265 5+280 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.10 - Err:509
266 5+300 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.12 - Err:509
267 5+320 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.14 - Err:509
268 5+340 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.16 - Err:509
269 5+360 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.18 - Err:509
270 5+380 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.20 - Err:509
271 5+400 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.22 - Err:509
272 5+420 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.24 - Err:509
273 5+440 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.26 - Err:509
274 5+460 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.28 - Err:509
275 5+480 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.30 - Err:509
276 5+500 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.32 - Err:509
277 5+520 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.34 - Err:509
278 5+540 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.36 - Err:509
279 5+560 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.38 - Err:509
280 5+580 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.40 - Err:509
281 5+600 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.42 - Err:509
282 5+620 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.44 - Err:509
283 5+640 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.46 - Err:509
284 5+660 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.48 - Err:509
285 5+680 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.50 - Err:509
286 5+700 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.52 - Err:509
287 5+720 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.54 - Err:509
51 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
288 5+740 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.56 - Err:509
289 5+760 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.58 - Err:509
290 5+780 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.60 - Err:509
291 5+800 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.62 - Err:509
292 5+820 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.64 - Err:509
293 5+840 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.66 - Err:509
294 5+860 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.68 - Err:509
295 5+880 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.70 - Err:509
296 5+900 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.72 - Err:509
297 5+920 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.74 - Err:509
298 5+940 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.76 - Err:509
299 5+960 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.78 - Err:509
300 5+980 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.80 - Err:509
301 6+000 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.82 - Err:509
302 6+020 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.84 - Err:509
303 6+040 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.86 - Err:509
304 6+060 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.88 - Err:509
305 6+080 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.90 - Err:509
306 6+100 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.92 - Err:509
307 6+120 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.94 - Err:509
308 6+140 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.96 - Err:509
309 6+160 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 0.98 - Err:509
310 6+180 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.00 - Err:509
311 6+200 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.02 0.02 Err:509
312 6+220 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.04 0.04 Err:509
313 6+240 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.06 0.06 Err:509
314 6+260 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.08 0.08 Err:509
315 6+280 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.10 0.10 Err:509
316 6+300 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.12 0.12 Err:509
317 6+320 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.14 0.14 Err:509
318 6+340 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.16 0.16 Err:509
319 6+360 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.18 0.18 Err:509
320 6+380 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.20 0.20 Err:509
321 6+400 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.22 0.22 Err:509
322 6+420 Err:509 Err:509 Err:509 Err:509 Err:509 5+180 1.24 0.24 Err:509
323 6+440 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.26 0.26 Err:509
324 6+460 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.24 0.24 Err:509
325 6+480 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.22 0.22 Err:509
326 6+500 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.20 0.20 Err:509
327 6+520 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.18 0.18 Err:509
328 6+540 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.16 0.16 Err:509
329 6+560 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.14 0.14 Err:509
330 6+580 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.12 0.12 Err:509
331 6+600 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.10 0.10 Err:509
332 6+620 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.08 0.08 Err:509
333 6+640 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.06 0.06 Err:509
334 6+660 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.04 0.04 Err:509
335 6+680 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.02 0.02 Err:509
336 6+700 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.00 - Err:509
337 6+720 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.98 - Err:509
338 6+740 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.96 - Err:509
339 6+760 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.94 - Err:509
340 6+780 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.92 - Err:509
341 6+800 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.90 - Err:509
342 6+820 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.88 - Err:509
343 6+840 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.86 - Err:509
344 6+860 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.84 - Err:509
345 6+880 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.82 - Err:509
346 6+900 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.80 - Err:509
347 6+920 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.78 - Err:509
348 6+940 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.76 - Err:509
349 6+960 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.74 - Err:509
350 6+980 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.72 - Err:509
351 7+000 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.70 - Err:509
352 7+020 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.68 - Err:509
353 7+040 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.66 - Err:509
354 7+060 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.64 - Err:509
355 7+080 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.62 - Err:509
356 7+100 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.60 - Err:509
357 7+120 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.58 - Err:509
358 7+140 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.56 - Err:509
359 7+160 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.54 - Err:509
360 7+180 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.52 - Err:509
361 7+200 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.50 - Err:509
362 7+220 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.48 - Err:509
52 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
363 7+240 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.46 - Err:509
364 7+260 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.44 - Err:509
365 7+280 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.42 - Err:509
366 7+300 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.40 - Err:509
367 7+320 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.38 - Err:509
368 7+340 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.36 - Err:509
369 7+360 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.34 - Err:509
370 7+380 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.32 - Err:509
371 7+400 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.30 - Err:509
372 7+420 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.28 - Err:509
373 7+440 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.26 - Err:509
374 7+460 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.24 - Err:509
375 7+480 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.22 - Err:509
376 7+500 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.20 - Err:509
377 7+520 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.18 - Err:509
378 7+540 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.16 - Err:509
379 7+560 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.14 - Err:509
380 7+580 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.12 - Err:509
381 7+600 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.10 - Err:509
382 7+620 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.08 - Err:509
383 7+640 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.06 - Err:509
384 7+660 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.04 - Err:509
385 7+680 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.02 - Err:509
386 7+700 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 - - Err:509 Disposal site
387 7+720 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.02 - Err:509
388 7+740 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.04 - Err:509
389 7+760 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.06 - Err:509
390 7+780 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.08 - Err:509
391 7+800 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.10 - Err:509
392 7+820 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.12 - Err:509
393 7+840 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.14 - Err:509
394 7+860 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.16 - Err:509
395 7+880 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.18 - Err:509
396 7+900 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.20 - Err:509
397 7+920 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.22 - Err:509
398 7+940 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.24 - Err:509
399 7+960 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.26 - Err:509
400 7+980 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.28 - Err:509
401 8+000 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.30 - Err:509
402 8+020 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.32 - Err:509
403 8+040 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.34 - Err:509
404 8+060 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.36 - Err:509
405 8+080 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.38 - Err:509
406 8+100 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.40 - Err:509
407 8+120 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.42 - Err:509
408 8+140 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.44 - Err:509
409 8+160 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.46 - Err:509
410 8+180 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.48 - Err:509
411 8+200 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.50 - Err:509
412 8+220 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.52 - Err:509
413 8+240 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.54 - Err:509
414 8+260 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.56 - Err:509
415 8+280 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.58 - Err:509
416 8+300 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.60 - Err:509
417 8+320 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.62 - Err:509
418 8+340 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.64 - Err:509
419 8+360 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.66 - Err:509
420 8+380 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.68 - Err:509
421 8+400 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.70 - Err:509
422 8+420 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.72 - Err:509
423 8+440 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.74 - Err:509
424 8+460 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.76 - Err:509
425 8+480 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.78 - Err:509
426 8+500 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.80 - Err:509
427 8+520 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.82 - Err:509
428 8+540 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.84 - Err:509
429 8+560 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.86 - Err:509
430 8+580 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.88 - Err:509
431 8+600 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.90 - Err:509
432 8+620 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.92 - Err:509
433 8+640 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.94 - Err:509
434 8+660 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.96 - Err:509
435 8+680 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 0.98 - Err:509
436 8+700 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.00 - Err:509
437 8+720 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.02 0.02 Err:509
53 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
438 8+740 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.04 0.04 Err:509
439 8+760 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.06 0.06 Err:509
440 8+780 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.08 0.08 Err:509
441 8+800 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.10 0.10 Err:509
442 8+820 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.12 0.12 Err:509
443 8+840 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.14 0.14 Err:509
444 8+860 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.16 0.16 Err:509
445 8+880 Err:509 Err:509 Err:509 Err:509 Err:509 7+700 1.18 0.18 Err:509
446 8+900 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.10 0.10 Err:509
447 8+920 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.08 0.08 Err:509
448 8+940 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.06 0.06 Err:509
449 8+960 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.04 0.04 Err:509
450 8+980 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.02 0.02 Err:509
451 9+000 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.00 - Err:509
452 9+020 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.98 - Err:509
453 9+040 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.96 - Err:509
454 9+060 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.94 - Err:509
455 9+080 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.92 - Err:509
456 9+100 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.90 - Err:509
457 9+120 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.88 - Err:509
458 9+140 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.86 - Err:509
459 9+160 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.84 - Err:509
460 9+180 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.82 - Err:509
461 9+200 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.80 - Err:509
462 9+220 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.78 - Err:509
463 9+240 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.76 - Err:509
464 9+260 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.74 - Err:509
465 9+280 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.72 - Err:509
466 9+300 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.70 - Err:509
467 9+320 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.68 - Err:509
468 9+340 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.66 - Err:509
469 9+360 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.64 - Err:509
470 9+380 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.62 - Err:509
471 9+400 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.60 - Err:509
472 9+420 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.58 - Err:509
473 9+440 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.56 - Err:509
474 9+460 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.54 - Err:509
475 9+480 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.52 - Err:509
476 9+500 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.50 - Err:509
477 9+520 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.48 - Err:509
478 9+540 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.46 - Err:509
479 9+560 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.44 - Err:509
480 9+580 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.42 - Err:509
481 9+600 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.40 - Err:509
482 9+620 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.38 - Err:509
483 9+640 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.36 - Err:509
484 9+660 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.34 - Err:509
485 9+680 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.32 - Err:509
486 9+700 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.30 - Err:509
487 9+720 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.28 - Err:509
488 9+740 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.26 - Err:509
489 9+760 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.24 - Err:509
490 9+780 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.22 - Err:509
491 9+800 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.20 - Err:509
492 9+820 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.18 - Err:509
493 9+840 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.16 - Err:509
494 9+860 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.14 - Err:509
495 9+880 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.12 - Err:509
496 9+900 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.10 - Err:509
497 9+920 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.08 - Err:509
498 9+940 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.06 - Err:509
499 9+960 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.04 - Err:509
500 9+980 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.02 - Err:509
501 10+000 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 - - Err:509 Disposal site
502 10+020 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.02 - Err:509
503 10+040 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.04 - Err:509
504 10+060 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.06 - Err:509
505 10+080 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.08 - Err:509
506 10+100 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.10 - Err:509
507 10+120 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.12 - Err:509
508 10+140 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.14 - Err:509
509 10+160 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.16 - Err:509
510 10+180 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.18 - Err:509
511 10+200 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.20 - Err:509
512 10+220 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.22 - Err:509
54 of 323
Total
Surplus/ Net Hauled
Cut Fill waste Volume Hauled Distance Hauled Quntity
Remarks
Distance
Chainage of
SN Chainage
Quantity (Cut- Tipping Area
Quantity Quantity
Cut area (m³)
fill area
(m³)
Fill) KM. KM. M3-KM
(m³)
513 10+240 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.24 - Err:509
514 10+260 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.26 - Err:509
515 10+280 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.28 - Err:509
516 10+300 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.30 - Err:509
517 10+320 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.32 - Err:509
518 10+340 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.34 - Err:509
519 10+360 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.36 - Err:509
520 10+380 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.38 - Err:509
521 10+400 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.40 - Err:509
522 10+420 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.42 - Err:509
523 10+440 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.44 - Err:509
524 10+460 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.46 - Err:509
525 10+480 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.48 - Err:509
526 10+500 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.50 - Err:509
527 10+520 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.52 - Err:509
528 10+540 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.54 - Err:509
529 10+560 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.56 - Err:509
530 10+580 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.58 - Err:509
531 10+600 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.60 - Err:509
532 10+620 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.62 - Err:509
533 10+640 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.64 - Err:509
534 10+660 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.66 - Err:509
535 10+680 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.68 - Err:509
536 10+700 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.70 - Err:509
537 10+720 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.72 - Err:509
538 10+740 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.74 - Err:509
539 10+760 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.76 - Err:509
540 10+780 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.78 - Err:509
541 10+800 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.80 - Err:509
542 10+820 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.82 - Err:509
543 10+840 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.84 - Err:509
544 10+860 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.86 - Err:509
545 10+880 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.88 - Err:509
546 10+900 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.90 - Err:509
547 10+920 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.92 - Err:509
548 10+940 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.94 - Err:509
549 10+960 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.96 - Err:509
550 10+980 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 0.98 - Err:509
551 11+000 Err:509 Err:509 Err:509 Err:509 Err:509 10+000 1.00 - Err:509
552 11+020 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.98 - Err:509
553 11+040 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.96 - Err:509
554 11+060 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.94 - Err:509
555 11+080 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.92 - Err:509
556 11+100 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.90 - Err:509
557 11+120 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.88 - Err:509
558 11+140 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.86 - Err:509
559 11+160 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.84 - Err:509
560 11+180 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.82 - Err:509
561 11+200 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.80 - Err:509
562 11+220 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.78 - Err:509
563 11+240 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.76 - Err:509
564 11+260 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.74 - Err:509
565 11+280 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.72 - Err:509
566 11+300 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.70 - Err:509
567 11+320 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.68 - Err:509
568 11+340 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.66 - Err:509
569 11+360 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.64 - Err:509
570 11+380 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.62 - Err:509
571 11+400 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.60 - Err:509
572 11+420 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.58 - Err:509
573 11+440 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.56 - Err:509
574 11+460 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.54 - Err:509
575 11+480 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.52 - Err:509
576 11+500 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.50 - Err:509
577 11+520 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.48 - Err:509
578 11+540 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.46 - Err:509
579 11+560 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.44 - Err:509
580 11+580 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.42 - Err:509
581 11+600 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.40 - Err:509
582 11+620 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.38 - Err:509
583 11+640 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.36 - Err:509
584 11+660 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.34 - Err:509
585 11+680 Err:509 Err:509 Err:509 Err:509 Err:509 12+000 0.32 - Err:509
Total Total Haulage Qty -
55 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
56 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
0+000 10 0.66 6.60 95 6.27 5 0.33 0 0.00
0+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+040 20 0.60 12.60 95 11.97 5 0.63 0 0.00
0+060 20 0.60 12.00 95 11.40 5 0.60 0 0.00
0+080 20 0.66 12.60 95 11.97 5 0.63 0 0.00
0+100 20 0.51 11.10 95 10.55 5 0.56 0 0.00
0+120 20 1.17 16.80 95 15.96 5 0.84 0 0.00
0+140 20 1.17 23.40 95 22.23 5 1.17 0 0.00
0+160 20 0.96 21.30 95 20.24 5 1.07 0 0.00
0+180 20 0.97 19.30 95 18.34 5 0.97 0 0.00
0+200 20 1.02 19.90 95 18.91 5 1.00 0 0.00
0+220 20 0.98 20.00 95 19.00 5 1.00 0 0.00
0+240 20 0.98 19.60 95 18.62 5 0.98 0 0.00
0+260 20 1.07 20.50 95 19.48 5 1.03 0 0.00
0+280 20 1.06 21.30 95 20.24 5 1.07 0 0.00
0+300 20 1.17 22.30 95 21.19 5 1.12 0 0.00
0+320 20 1.16 23.30 95 22.14 5 1.17 0 0.00
0+340 20 1.11 22.70 95 21.57 5 1.14 0 0.00
0+360 20 1.17 22.80 95 21.66 5 1.14 0 0.00
0+380 20 0.51 16.80 95 15.96 5 0.84 0 0.00
0+400 20 0.51 10.20 95 9.69 5 0.51 0 0.00
0+420 20 0.51 10.20 95 9.69 5 0.51 0 0.00
0+440 20 0.50 10.10 95 9.60 5 0.51 0 0.00
0+460 20 0.51 10.10 95 9.60 5 0.51 0 0.00
0+480 20 0.50 10.10 95 9.60 5 0.51 0 0.00
0+500 20 0.52 10.20 95 9.69 5 0.51 0 0.00
0+520 20 0.51 10.30 95 9.79 5 0.52 0 0.00
0+540 20 0.51 10.20 95 9.69 5 0.51 0 0.00
0+560 20 0.66 11.70 95 11.12 5 0.59 0 0.00
0+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+600 20 1.17 18.30 95 17.39 5 0.92 0 0.00
0+620 20 1.17 23.40 95 22.23 5 1.17 0 0.00
0+640 20 1.17 23.40 95 22.23 5 1.17 0 0.00
0+660 20 0.92 20.90 95 19.86 5 1.05 0 0.00
0+680 20 0.66 15.80 95 15.01 5 0.79 0 0.00
0+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+720 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+740 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
0+800 20 1.32 19.80 95 18.81 5 0.99 0 0.00
0+820 20 0.80 21.20 95 20.14 5 1.06 0 0.00
0+840 20 0.59 13.90 95 13.21 5 0.70 0 0.00
0+860 20 1.02 16.10 95 15.30 5 0.81 0 0.00
0+880 20 0.96 19.80 95 18.81 5 0.99 0 0.00
0+900 20 1.02 19.80 95 18.81 5 0.99 0 0.00
0+920 20 1.02 20.40 95 19.38 5 1.02 0 0.00
0+940 20 1.02 20.40 95 19.38 5 1.02 0 0.00
0+960 20 1.02 20.40 95 19.38 5 1.02 0 0.00
0+980 20 1.02 20.40 95 19.38 5 1.02 0 0.00
1+000 20 1.32 23.40 95 22.23 5 1.17 0 0.00
1+020 20 1.26 25.80 95 24.51 5 1.29 0 0.00
1+040 20 1.26 25.20 95 23.94 5 1.26 0 0.00
1+060 20 1.32 25.80 95 24.51 5 1.29 0 0.00
1+080 20 1.26 25.80 95 24.51 5 1.29 0 0.00
57 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
1+100 20 1.32 25.80 95 24.51 5 1.29 0 0.00
1+120 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+180 20 1.20 25.20 95 23.94 5 1.26 0 0.00
1+200 20 0.66 18.60 95 17.67 5 0.93 0 0.00
1+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+300 20 0.64 13.00 95 12.35 5 0.65 0 0.00
1+320 20 0.66 13.00 95 12.35 5 0.65 0 0.00
1+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
1+400 20 0.60 12.60 95 11.97 5 0.63 0 0.00
1+420 20 1.32 19.20 95 18.24 5 0.96 0 0.00
1+440 20 0.66 19.80 95 18.81 5 0.99 0 0.00
1+460 20 0.36 10.20 95 9.69 5 0.51 0 0.00
1+480 20 - 3.60 95 3.42 5 0.18 0 0.00
1+500 20 - - 95 - 5 0.00 0 0.00
1+520 20 0.52 5.20 95 4.94 5 0.26 0 0.00
1+540 20 0.66 11.80 95 11.21 5 0.59 0 0.00
1+560 20 - 6.60 95 6.27 5 0.33 0 0.00
1+580 20 1.32 13.20 95 12.54 5 0.66 0 0.00
1+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+620 20 1.20 25.20 95 23.94 5 1.26 0 0.00
1+640 20 1.32 25.20 95 23.94 5 1.26 0 0.00
1+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+680 20 1.26 25.80 95 24.51 5 1.29 0 0.00
1+700 20 1.20 24.60 95 23.37 5 1.23 0 0.00
1+720 20 1.32 25.20 95 23.94 5 1.26 0 0.00
1+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+780 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+800 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+820 20 1.26 25.80 95 24.51 5 1.29 0 0.00
1+840 20 1.26 25.20 95 23.94 5 1.26 0 0.00
1+860 20 1.32 25.80 95 24.51 5 1.29 0 0.00
1+880 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+900 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+920 20 1.32 26.40 95 25.08 5 1.32 0 0.00
1+940 20 1.26 25.80 95 24.51 5 1.29 0 0.00
1+960 20 1.26 25.20 95 23.94 5 1.26 0 0.00
1+980 20 1.32 25.80 95 24.51 5 1.29 0 0.00
2+000 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+020 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+060 20 1.26 25.80 95 24.51 5 1.29 0 0.00
2+080 20 1.32 25.80 95 24.51 5 1.29 0 0.00
2+100 20 1.26 25.80 95 24.51 5 1.29 0 0.00
2+120 20 1.32 25.80 95 24.51 5 1.29 0 0.00
2+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+180 20 1.26 25.80 95 24.51 5 1.29 0 0.00
58 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
2+200 20 1.12 23.80 95 22.61 5 1.19 0 0.00
2+220 20 1.17 22.90 95 21.76 5 1.15 0 0.00
2+240 20 1.16 23.30 95 22.14 5 1.17 0 0.00
2+260 20 1.17 23.30 95 22.14 5 1.17 0 0.00
2+280 20 1.32 24.90 95 23.66 5 1.25 0 0.00
2+300 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+320 20 1.20 25.20 95 23.94 5 1.26 0 0.00
2+340 20 1.32 25.20 95 23.94 5 1.26 0 0.00
2+360 20 1.26 25.80 95 24.51 5 1.29 0 0.00
2+380 20 1.26 25.20 95 23.94 5 1.26 0 0.00
2+400 20 1.32 25.80 95 24.51 5 1.29 0 0.00
2+420 20 0.66 19.80 95 18.81 5 0.99 0 0.00
2+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+500 20 1.32 19.80 95 18.81 5 0.99 0 0.00
2+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+560 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+580 20 1.32 26.40 95 25.08 5 1.32 0 0.00
2+600 20 0.66 19.80 95 18.81 5 0.99 0 0.00
2+620 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+640 20 0.60 12.60 95 11.97 5 0.63 0 0.00
2+660 20 0.66 12.60 95 11.97 5 0.63 0 0.00
2+680 20 1.26 19.20 95 18.24 5 0.96 0 0.00
2+700 20 1.26 25.20 95 23.94 5 1.26 0 0.00
2+720 20 0.60 18.60 95 17.67 5 0.93 0 0.00
2+740 20 0.60 12.00 95 11.40 5 0.60 0 0.00
2+760 20 0.66 12.60 95 11.97 5 0.63 0 0.00
2+780 20 0.36 10.20 95 9.69 5 0.51 0 0.00
2+800 20 0.66 10.20 95 9.69 5 0.51 0 0.00
2+820 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+840 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+880 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
2+980 20 1.32 19.80 95 18.81 5 0.99 0 0.00
3+000 20 1.17 24.90 95 23.66 5 1.25 0 0.00
3+020 20 1.07 22.40 95 21.28 5 1.12 0 0.00
3+040 20 1.17 22.40 95 21.28 5 1.12 0 0.00
3+060 20 1.18 23.50 95 22.33 5 1.18 0 0.00
3+080 20 1.17 23.50 95 22.33 5 1.18 0 0.00
3+100 20 1.17 23.40 95 22.23 5 1.17 0 0.00
3+120 20 1.17 23.40 95 22.23 5 1.17 0 0.00
3+140 20 1.17 23.40 95 22.23 5 1.17 0 0.00
3+160 20 1.17 23.40 95 22.23 5 1.17 0 0.00
3+180 20 1.32 24.90 95 23.66 5 1.25 0 0.00
3+200 20 0.60 19.20 95 18.24 5 0.96 0 0.00
3+220 20 0.66 12.60 95 11.97 5 0.63 0 0.00
3+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+280 20 0.60 12.60 95 11.97 5 0.63 0 0.00
59 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
3+300 20 0.60 12.00 95 11.40 5 0.60 0 0.00
3+320 20 0.66 12.60 95 11.97 5 0.63 0 0.00
3+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+380 20 0.60 12.60 95 11.97 5 0.63 0 0.00
3+400 20 0.66 12.60 95 11.97 5 0.63 0 0.00
3+420 20 1.32 19.80 95 18.81 5 0.99 0 0.00
3+440 20 0.66 19.80 95 18.81 5 0.99 0 0.00
3+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+500 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+540 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
3+580 20 0.60 12.60 95 11.97 5 0.63 0 0.00
3+600 20 0.66 12.60 95 11.97 5 0.63 0 0.00
3+620 20 1.32 19.80 95 18.81 5 0.99 0 0.00
3+640 20 1.26 25.80 95 24.51 5 1.29 0 0.00
3+660 20 1.32 25.80 95 24.51 5 1.29 0 0.00
3+680 20 1.17 24.90 95 23.66 5 1.25 0 0.00
3+700 20 1.12 22.90 95 21.76 5 1.15 0 0.00
3+720 20 1.17 22.90 95 21.76 5 1.15 0 0.00
3+740 20 1.06 22.30 95 21.19 5 1.12 0 0.00
3+760 20 1.06 21.20 95 20.14 5 1.06 0 0.00
3+780 20 1.11 21.70 95 20.62 5 1.09 0 0.00
3+800 20 1.12 22.30 95 21.19 5 1.12 0 0.00
3+820 20 1.18 23.00 95 21.85 5 1.15 0 0.00
3+840 20 1.07 22.50 95 21.38 5 1.13 0 0.00
3+860 20 1.17 22.40 95 21.28 5 1.12 0 0.00
3+880 20 1.11 22.80 95 21.66 5 1.14 0 0.00
3+900 20 1.32 24.30 95 23.09 5 1.22 0 0.00
3+920 20 1.32 26.40 95 25.08 5 1.32 0 0.00
3+940 20 1.32 26.40 95 25.08 5 1.32 0 0.00
3+960 20 1.26 25.80 95 24.51 5 1.29 0 0.00
3+980 20 0.66 19.20 95 18.24 5 0.96 0 0.00
4+000 20 0.47 11.30 95 10.74 5 0.57 0 0.00
4+020 20 0.51 9.80 95 9.31 5 0.49 0 0.00
4+040 20 0.66 11.70 95 11.12 5 0.59 0 0.00
4+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+140 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+180 20 0.60 12.60 95 11.97 5 0.63 0 0.00
4+200 20 0.66 12.60 95 11.97 5 0.63 0 0.00
4+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
4+240 20 1.20 18.60 95 17.67 5 0.93 0 0.00
4+260 20 1.26 24.60 95 23.37 5 1.23 0 0.00
4+280 20 1.17 24.30 95 23.09 5 1.22 0 0.00
4+300 20 1.12 22.90 95 21.76 5 1.15 0 0.00
4+320 20 1.17 22.90 95 21.76 5 1.15 0 0.00
4+340 20 1.12 22.90 95 21.76 5 1.15 0 0.00
4+360 20 0.97 20.90 95 19.86 5 1.05 0 0.00
4+380 20 1.02 19.90 95 18.91 5 1.00 0 0.00
60 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
4+400 20 1.02 20.40 95 19.38 5 1.02 0 0.00
4+420 20 1.03 20.50 95 19.48 5 1.03 0 0.00
4+440 20 1.02 20.50 95 19.48 5 1.03 0 0.00
4+460 20 0.99 20.10 95 19.10 5 1.01 0 0.00
4+480 20 1.02 20.10 95 19.10 5 1.01 0 0.00
4+500 20 1.03 20.50 95 19.48 5 1.03 0 0.00
4+520 20 1.02 20.50 95 19.48 5 1.03 0 0.00
4+540 20 0.92 19.40 95 18.43 5 0.97 0 0.00
4+560 20 1.02 19.40 95 18.43 5 0.97 0 0.00
4+580 20 0.93 19.50 95 18.53 5 0.98 0 0.00
4+600 20 1.02 19.50 95 18.53 5 0.98 0 0.00
4+620 20 1.02 20.40 95 19.38 5 1.02 0 0.00
4+640 20 1.03 20.50 95 19.48 5 1.03 0 0.00
4+660 20 0.98 20.10 95 19.10 5 1.01 0 0.00
4+680 20 1.02 20.00 95 19.00 5 1.00 0 0.00
4+700 20 1.02 20.40 95 19.38 5 1.02 0 0.00
4+720 20 1.02 20.40 95 19.38 5 1.02 0 0.00
4+740 20 1.02 20.40 95 19.38 5 1.02 0 0.00
4+760 20 1.17 21.90 95 20.81 5 1.10 0 0.00
4+780 20 1.17 23.40 95 22.23 5 1.17 0 0.00
4+800 20 1.13 23.00 95 21.85 5 1.15 0 0.00
4+820 20 1.12 22.50 95 21.38 5 1.13 0 0.00
4+840 20 1.11 22.30 95 21.19 5 1.12 0 0.00
4+860 20 1.11 22.20 95 21.09 5 1.11 0 0.00
4+880 20 1.17 22.80 95 21.66 5 1.14 0 0.00
4+900 20 1.17 23.40 95 22.23 5 1.17 0 0.00
4+920 20 0.50 16.70 95 15.87 5 0.84 0 0.00
4+940 20 0.51 10.10 95 9.60 5 0.51 0 0.00
4+960 20 0.50 10.10 95 9.60 5 0.51 0 0.00
4+980 20 0.51 10.10 95 9.60 5 0.51 0 0.00
5+000 20 0.51 10.20 95 9.69 5 0.51 0 0.00
5+020 20 0.51 10.20 95 9.69 5 0.51 0 0.00
5+040 20 0.51 10.20 95 9.69 5 0.51 0 0.00
5+060 20 0.51 10.20 95 9.69 5 0.51 0 0.00
5+080 20 1.06 15.70 95 14.92 5 0.79 0 0.00
5+100 20 1.12 21.80 95 20.71 5 1.09 0 0.00
5+120 20 1.11 22.30 95 21.19 5 1.12 0 0.00
5+140 20 1.05 21.60 95 20.52 5 1.08 0 0.00
5+160 20 0.51 15.60 95 14.82 5 0.78 0 0.00
5+180 20 0.51 10.20 95 9.69 5 0.51 0 0.00
5+200 20 0.66 11.70 95 11.12 5 0.59 0 0.00
5+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+400 20 0.60 12.60 95 11.97 5 0.63 0 0.00
5+420 20 0.66 12.60 95 11.97 5 0.63 0 0.00
5+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+480 20 0.51 11.70 95 11.12 5 0.59 0 0.00
61 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
5+500 20 0.66 11.70 95 11.12 5 0.59 0 0.00
5+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+540 20 0.60 12.60 95 11.97 5 0.63 0 0.00
5+560 20 0.60 12.00 95 11.40 5 0.60 0 0.00
5+580 20 0.66 12.60 95 11.97 5 0.63 0 0.00
5+600 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+620 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+640 20 0.60 12.60 95 11.97 5 0.63 0 0.00
5+660 20 0.66 12.60 95 11.97 5 0.63 0 0.00
5+680 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+720 20 - 6.60 95 6.27 5 0.33 0 0.00
5+740 20 0.66 6.60 95 6.27 5 0.33 0 0.00
5+760 20 0.60 12.60 95 11.97 5 0.63 0 0.00
5+780 20 0.66 12.60 95 11.97 5 0.63 0 0.00
5+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+820 20 0.60 12.60 95 11.97 5 0.63 0 0.00
5+840 20 0.60 12.00 95 11.40 5 0.60 0 0.00
5+860 20 0.66 12.60 95 11.97 5 0.63 0 0.00
5+880 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
5+960 20 0.60 12.60 95 11.97 5 0.63 0 0.00
5+980 20 0.66 12.60 95 11.97 5 0.63 0 0.00
6+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+040 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+120 20 0.60 12.60 95 11.97 5 0.63 0 0.00
6+140 20 0.60 12.00 95 11.40 5 0.60 0 0.00
6+160 20 0.66 12.60 95 11.97 5 0.63 0 0.00
6+180 20 0.60 12.60 95 11.97 5 0.63 0 0.00
6+200 20 0.66 12.60 95 11.97 5 0.63 0 0.00
6+220 20 0.60 12.60 95 11.97 5 0.63 0 0.00
6+240 20 0.60 12.00 95 11.40 5 0.60 0 0.00
6+260 20 0.60 12.00 95 11.40 5 0.60 0 0.00
6+280 20 0.65 12.50 95 11.88 5 0.63 0 0.00
6+300 20 - 6.50 95 6.18 5 0.33 0 0.00
6+320 20 - - 95 - 5 0.00 0 0.00
6+340 20 - - 95 - 5 0.00 0 0.00
6+360 20 - - 95 - 5 0.00 0 0.00
6+380 20 - - 95 - 5 0.00 0 0.00
6+400 20 - - 95 - 5 0.00 0 0.00
6+420 20 - - 95 - 5 0.00 0 0.00
6+440 20 - - 95 - 5 0.00 0 0.00
6+460 20 - - 95 - 5 0.00 0 0.00
6+480 20 - - 95 - 5 0.00 0 0.00
6+500 20 0.66 6.60 95 6.27 5 0.33 0 0.00
6+520 20 0.57 12.30 95 11.69 5 0.62 0 0.00
6+540 20 0.66 12.30 95 11.69 5 0.62 0 0.00
6+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
62 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
6+600 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+620 20 0.66 13.20 95 12.54 5 0.66 0 0.00
6+640 20 0.35 10.10 95 9.60 5 0.51 0 0.00
6+660 20 0.66 10.10 95 9.60 5 0.51 0 0.00
6+680 20 1.32 19.80 95 18.81 5 0.99 0 0.00
6+700 20 0.98 23.00 95 21.85 5 1.15 0 0.00
6+720 20 1.12 21.00 95 19.95 5 1.05 0 0.00
6+740 20 0.51 16.30 95 15.49 5 0.82 0 0.00
6+760 20 0.465 9.75 95 9.26 5 0.49 0 0.00
6+780 20 0.51 9.75 95 9.26 5 0.49 0 0.00
6+800 20 0.51 10.20 95 9.69 5 0.51 0 0.00
6+820 20 0.505 10.15 95 9.64 5 0.51 0 0.00
6+840 20 0.52 10.25 95 9.74 5 0.51 0 0.00
6+860 20 1.17 16.90 95 16.06 5 0.85 0 0.00
6+880 20 1.123 22.93 95 21.78 5 1.15 0 0.00
6+900 20 1.17 22.93 95 21.78 5 1.15 0 0.00
6+920 20 1.11 22.80 95 21.66 5 1.14 0 0.00
6+940 20 1.02 21.30 95 20.24 5 1.07 0 0.00
6+960 20 1.02 20.40 95 19.38 5 1.02 0 0.00
6+980 20 0.93 19.50 95 18.53 5 0.98 0 0.00
7+000 20 1.03 19.60 95 18.62 5 0.98 0 0.00
7+020 20 1.02 20.50 95 19.48 5 1.03 0 0.00
7+040 20 0.975 19.95 95 18.95 5 1.00 0 0.00
7+060 20 1.015 19.90 95 18.91 5 1.00 0 0.00
7+080 20 0.968 19.83 95 18.84 5 0.99 0 0.00
7+100 20 0.985 19.53 95 18.55 5 0.98 0 0.00
7+120 20 1.02 20.05 95 19.05 5 1.00 0 0.00
7+140 20 1.02 20.40 95 19.38 5 1.02 0 0.00
7+160 20 1.02 20.40 95 19.38 5 1.02 0 0.00
7+180 20 1.32 23.40 95 22.23 5 1.17 0 0.00
7+200 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+220 20 1.26 25.20 95 23.94 5 1.26 0 0.00
7+240 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+300 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+320 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+340 20 1.2 25.20 95 23.94 5 1.26 0 0.00
7+360 20 1.32 25.20 95 23.94 5 1.26 0 0.00
7+380 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+400 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+420 20 1.26 25.20 95 23.94 5 1.26 0 0.00
7+440 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+480 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+500 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+560 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+580 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+600 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+620 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+640 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+680 20 1.32 26.40 95 25.08 5 1.32 0 0.00
63 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
7+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+780 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+800 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+820 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+840 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+860 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+880 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+900 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+920 20 1.26 25.80 95 24.51 5 1.29 0 0.00
7+940 20 1.32 25.80 95 24.51 5 1.29 0 0.00
7+960 20 1.32 26.40 95 25.08 5 1.32 0 0.00
7+980 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+000 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+020 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+080 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+100 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+120 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+180 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+200 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+220 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+240 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+300 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+320 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+340 20 0.99 23.10 95 21.95 5 1.16 0 0.00
8+360 20 1.26 22.50 95 21.38 5 1.13 0 0.00
8+380 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+400 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+420 20 1.2 25.20 95 23.94 5 1.26 0 0.00
8+440 20 1.32 25.20 95 23.94 5 1.26 0 0.00
8+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+480 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+500 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+540 20 1.2 25.20 95 23.94 5 1.26 0 0.00
8+560 20 1.26 24.60 95 23.37 5 1.23 0 0.00
8+580 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+600 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+620 20 1.26 25.20 95 23.94 5 1.26 0 0.00
8+640 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+660 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+680 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+720 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+740 20 1.2 24.60 95 23.37 5 1.23 0 0.00
8+760 20 1.32 25.20 95 23.94 5 1.26 0 0.00
8+780 20 1.32 26.40 95 25.08 5 1.32 0 0.00
64 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
8+800 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+820 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+840 20 1.32 26.40 95 25.08 5 1.32 0 0.00
8+860 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+880 20 1.32 25.80 95 24.51 5 1.29 0 0.00
8+900 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+920 20 1.2 24.60 95 23.37 5 1.23 0 0.00
8+940 20 1.32 25.20 95 23.94 5 1.26 0 0.00
8+960 20 1.26 25.80 95 24.51 5 1.29 0 0.00
8+980 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+000 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+020 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+040 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+080 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+120 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+140 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+160 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+180 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+200 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+220 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+240 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+280 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+300 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+320 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+340 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+360 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+380 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+400 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+420 20 1.26 25.20 95 23.94 5 1.26 0 0.00
9+440 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+480 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+500 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+520 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+560 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+580 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+600 20 0.765 20.85 95 19.81 5 1.04 0 0.00
9+620 20 0.66 14.25 95 13.54 5 0.71 0 0.00
9+640 20 1.26 19.20 95 18.24 5 0.96 0 0.00
9+660 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+680 20 1.2 25.20 95 23.94 5 1.26 0 0.00
9+700 20 1.32 25.20 95 23.94 5 1.26 0 0.00
9+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+740 20 1.2 25.20 95 23.94 5 1.26 0 0.00
9+760 20 1.32 25.20 95 23.94 5 1.26 0 0.00
9+780 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+800 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+820 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+840 20 1.178 24.38 95 23.16 5 1.22 0 0.00
9+860 20 1.2 23.78 95 22.59 5 1.19 0 0.00
9+880 20 1.32 25.20 95 23.94 5 1.26 0 0.00
65 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
9+900 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+920 20 1.26 25.80 95 24.51 5 1.29 0 0.00
9+940 20 1.32 25.80 95 24.51 5 1.29 0 0.00
9+960 20 1.32 26.40 95 25.08 5 1.32 0 0.00
9+980 20 1.155 24.75 95 23.51 5 1.24 0 0.00
10+000 20 1.26 24.15 95 22.94 5 1.21 0 0.00
10+020 20 1.32 25.80 95 24.51 5 1.29 0 0.00
10+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+060 20 1.26 25.80 95 24.51 5 1.29 0 0.00
10+080 20 1.32 25.80 95 24.51 5 1.29 0 0.00
10+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+120 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+180 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+200 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+220 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+240 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+300 20 1.2 25.20 95 23.94 5 1.26 0 0.00
10+320 20 1.32 25.20 95 23.94 5 1.26 0 0.00
10+340 20 1.26 25.80 95 24.51 5 1.29 0 0.00
10+360 20 1.26 25.20 95 23.94 5 1.26 0 0.00
10+380 20 1.32 25.80 95 24.51 5 1.29 0 0.00
10+400 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+420 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+440 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+480 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+500 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+520 20 1.26 25.80 95 24.51 5 1.29 0 0.00
10+540 20 1.32 25.80 95 24.51 5 1.29 0 0.00
10+560 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+580 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+640 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+680 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+700 20 1.018 23.38 95 22.21 5 1.17 0 0.00
10+720 20 1.32 23.38 95 22.21 5 1.17 0 0.00
10+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+760 20 1.26 25.80 95 24.51 5 1.29 0 0.00
10+780 20 1.26 25.20 95 23.94 5 1.26 0 0.00
10+800 20 1.32 25.80 95 24.51 5 1.29 0 0.00
10+820 20 1.2 25.20 95 23.94 5 1.26 0 0.00
10+840 20 1.32 25.20 95 23.94 5 1.26 0 0.00
10+860 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+880 20 1.26 25.80 95 24.51 5 1.29 0 0.00
10+900 20 1.2 24.60 95 23.37 5 1.23 0 0.00
10+920 20 1.26 24.60 95 23.37 5 1.23 0 0.00
10+940 20 1.32 25.80 95 24.51 5 1.29 0 0.00
10+960 20 1.32 26.40 95 25.08 5 1.32 0 0.00
10+980 20 1.32 26.40 95 25.08 5 1.32 0 0.00
66 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
11+000 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+020 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+080 20 1.26 25.80 95 24.51 5 1.29 0 0.00
11+100 20 1.26 25.20 95 23.94 5 1.26 0 0.00
11+120 20 1.32 25.80 95 24.51 5 1.29 0 0.00
11+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+180 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+200 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+220 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+240 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+300 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+320 20 1.26 25.80 95 24.51 5 1.29 0 0.00
11+340 20 1.32 25.80 95 24.51 5 1.29 0 0.00
11+360 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+380 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+400 20 0.66 19.80 95 18.81 5 0.99 0 0.00
11+420 20 1.2 18.60 95 17.67 5 0.93 0 0.00
11+440 20 1.32 25.20 95 23.94 5 1.26 0 0.00
11+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+480 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+500 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+540 20 0.835 21.55 95 20.47 5 1.08 0 0.00
11+560 20 1.32 21.55 95 20.47 5 1.08 0 0.00
11+580 20 1.26 25.80 95 24.51 5 1.29 0 0.00
11+600 20 1.32 25.80 95 24.51 5 1.29 0 0.00
11+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+640 20 0.77 20.90 95 19.86 5 1.05 0 0.00
11+660 20 1.32 20.90 95 19.86 5 1.05 0 0.00
11+680 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+780 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+800 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+820 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+840 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+860 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+880 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+900 20 1.32 26.40 95 25.08 5 1.32 0 0.00
11+920 20 1.26 25.80 95 24.51 5 1.29 0 0.00
11+940 20 1.26 25.20 95 23.94 5 1.26 0 0.00
11+960 20 1.26 25.20 95 23.94 5 1.26 0 0.00
11+980 20 1.32 25.80 95 24.51 5 1.29 0 0.00
12+000 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+020 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+080 20 1.32 26.40 95 25.08 5 1.32 0 0.00
67 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
12+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+120 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+180 20 0.6 19.20 95 18.24 5 0.96 0 0.00
12+200 20 1.26 18.60 95 17.67 5 0.93 0 0.00
12+220 20 0.715 19.75 95 18.76 5 0.99 0 0.00
12+240 20 1.32 20.35 95 19.33 5 1.02 0 0.00
12+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+300 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+320 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+340 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+360 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+380 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+400 20 1.26 25.80 95 24.51 5 1.29 0 0.00
12+420 20 1.32 25.80 95 24.51 5 1.29 0 0.00
12+440 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+480 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+500 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+540 20 1.26 25.80 95 24.51 5 1.29 0 0.00
12+560 20 1.32 25.80 95 24.51 5 1.29 0 0.00
12+580 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+640 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+660 20 0.6 19.20 95 18.24 5 0.96 0 0.00
12+680 20 0.66 12.60 95 11.97 5 0.63 0 0.00
12+700 20 1.32 19.80 95 18.81 5 0.99 0 0.00
12+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+780 20 1.2 25.20 95 23.94 5 1.26 0 0.00
12+800 20 1.32 25.20 95 23.94 5 1.26 0 0.00
12+820 20 1.2 25.20 95 23.94 5 1.26 0 0.00
12+840 20 1.26 24.60 95 23.37 5 1.23 0 0.00
12+860 20 1.26 25.20 95 23.94 5 1.26 0 0.00
12+880 20 1.32 25.80 95 24.51 5 1.29 0 0.00
12+900 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+920 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+940 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+960 20 1.32 26.40 95 25.08 5 1.32 0 0.00
12+980 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+000 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+020 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+080 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+120 20 1.26 25.80 95 24.51 5 1.29 0 0.00
13+140 20 1.32 25.80 95 24.51 5 1.29 0 0.00
13+160 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+180 20 1.32 26.40 95 25.08 5 1.32 0 0.00
68 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
13+200 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+220 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+240 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+280 20 1.26 25.80 95 24.51 5 1.29 0 0.00
13+300 20 1.32 25.80 95 24.51 5 1.29 0 0.00
13+320 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+340 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+360 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+380 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+400 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+420 20 0.935 22.55 95 21.42 5 1.13 0 0.00
13+440 20 0.6 15.35 95 14.58 5 0.77 0 0.00
13+460 20 0.6 12.00 95 11.40 5 0.60 0 0.00
13+480 20 0.66 12.60 95 11.97 5 0.63 0 0.00
13+500 20 1.32 19.80 95 18.81 5 0.99 0 0.00
13+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+560 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+580 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+600 20 1.26 25.80 95 24.51 5 1.29 0 0.00
13+620 20 1.2 24.60 95 23.37 5 1.23 0 0.00
13+640 20 1.32 25.20 95 23.94 5 1.26 0 0.00
13+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+680 20 1.26 25.80 95 24.51 5 1.29 0 0.00
13+700 20 1.32 25.80 95 24.51 5 1.29 0 0.00
13+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
13+780 20 0.66 19.80 95 18.81 5 0.99 0 0.00
13+800 20 1.32 19.80 95 18.81 5 0.99 0 0.00
13+820 20 0.66 19.80 95 18.81 5 0.99 0 0.00
13+840 20 0.66 13.20 95 12.54 5 0.66 0 0.00
13+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
13+880 20 0.66 13.20 95 12.54 5 0.66 0 0.00
13+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
13+920 20 1.32 19.80 95 18.81 5 0.99 0 0.00
13+940 20 0 13.20 95 12.54 5 0.66 0 0.00
13+960 20 0 - 95 - 5 0.00 0 0.00
13+980 20 0 - 95 - 5 0.00 0 0.00
14+000 20 0.6 6.00 95 5.70 5 0.30 0 0.00
14+020 20 1.2 18.00 95 17.10 5 0.90 0 0.00
14+040 20 1.32 25.20 95 23.94 5 1.26 0 0.00
14+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
14+080 20 0.66 19.80 95 18.81 5 0.99 0 0.00
14+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+120 20 0.6 12.60 95 11.97 5 0.63 0 0.00
14+140 20 0.66 12.60 95 11.97 5 0.63 0 0.00
14+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+200 20 0.165 8.25 95 7.84 5 0.41 0 0.00
14+220 20 0.1 2.65 95 2.52 5 0.13 0 0.00
14+240 20 0.66 7.60 95 7.22 5 0.38 0 0.00
14+260 20 0 6.60 95 6.27 5 0.33 0 0.00
14+280 20 0 - 95 - 5 0.00 0 0.00
69 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
14+300 20 0 - 95 - 5 0.00 0 0.00
14+320 20 0.238 2.38 95 2.26 5 0.12 0 0.00
14+340 20 0 2.38 95 2.26 5 0.12 0 0.00
14+360 20 0.66 6.60 95 6.27 5 0.33 0 0.00
14+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+400 20 0.6 12.60 95 11.97 5 0.63 0 0.00
14+420 20 0.66 12.60 95 11.97 5 0.63 0 0.00
14+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+500 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+540 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+600 20 0.6 12.60 95 11.97 5 0.63 0 0.00
14+620 20 0.66 12.60 95 11.97 5 0.63 0 0.00
14+640 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+660 20 0.6 12.60 95 11.97 5 0.63 0 0.00
14+680 20 0.66 12.60 95 11.97 5 0.63 0 0.00
14+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+720 20 0.6 12.60 95 11.97 5 0.63 0 0.00
14+740 20 0.66 12.60 95 11.97 5 0.63 0 0.00
14+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+820 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+840 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+860 20 0.6 12.60 95 11.97 5 0.63 0 0.00
14+880 20 0.66 12.60 95 11.97 5 0.63 0 0.00
14+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
14+940 20 0.658 13.18 95 12.52 5 0.66 0 0.00
14+960 20 0.66 13.18 95 12.52 5 0.66 0 0.00
14+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+040 20 0.565 12.25 95 11.64 5 0.61 0 0.00
15+060 20 0.11 6.75 95 6.41 5 0.34 0 0.00
15+080 20 0.66 7.70 95 7.32 5 0.39 0 0.00
15+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+120 20 0 6.60 95 6.27 5 0.33 0 0.00
15+140 20 0.66 6.60 95 6.27 5 0.33 0 0.00
15+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+220 20 0.6 12.60 95 11.97 5 0.63 0 0.00
15+240 20 0.66 12.60 95 11.97 5 0.63 0 0.00
15+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+360 20 0.035 6.95 95 6.60 5 0.35 0 0.00
15+380 20 0.66 6.95 95 6.60 5 0.35 0 0.00
70 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
15+400 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+420 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+440 20 0 6.60 95 6.27 5 0.33 0 0.00
15+460 20 0.66 6.60 95 6.27 5 0.33 0 0.00
15+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+500 20 0.6 12.60 95 11.97 5 0.63 0 0.00
15+520 20 0.6 12.00 95 11.40 5 0.60 0 0.00
15+540 20 0.66 12.60 95 11.97 5 0.63 0 0.00
15+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+580 20 1.32 19.80 95 18.81 5 0.99 0 0.00
15+600 20 1.2 25.20 95 23.94 5 1.26 0 0.00
15+620 20 1.32 25.20 95 23.94 5 1.26 0 0.00
15+640 20 0.66 19.80 95 18.81 5 0.99 0 0.00
15+660 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+680 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+720 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+740 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+800 20 0.6 12.60 95 11.97 5 0.63 0 0.00
15+820 20 0.66 12.60 95 11.97 5 0.63 0 0.00
15+840 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+880 20 0.6 12.60 95 11.97 5 0.63 0 0.00
15+900 20 0.66 12.60 95 11.97 5 0.63 0 0.00
15+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
15+940 20 0.6 12.60 95 11.97 5 0.63 0 0.00
15+960 20 0.66 12.60 95 11.97 5 0.63 0 0.00
15+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+040 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+140 20 0 6.60 95 6.27 5 0.33 0 0.00
16+160 20 0 - 95 - 5 0.00 0 0.00
16+180 20 0 - 95 - 5 0.00 0 0.00
16+200 20 0.66 6.60 95 6.27 5 0.33 0 0.00
16+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+300 20 0.6 12.60 95 11.97 5 0.63 0 0.00
16+320 20 0.66 12.60 95 11.97 5 0.63 0 0.00
16+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+400 20 1.32 19.80 95 18.81 5 0.99 0 0.00
16+420 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+440 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+460 20 0.935 22.55 95 21.42 5 1.13 0 0.00
16+480 20 1.32 22.55 95 21.42 5 1.13 0 0.00
71 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
16+500 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+560 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+580 20 1.2 25.20 95 23.94 5 1.26 0 0.00
16+600 20 1.32 25.20 95 23.94 5 1.26 0 0.00
16+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+640 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+680 20 0.655 19.75 95 18.76 5 0.99 0 0.00
16+700 20 1.32 19.75 95 18.76 5 0.99 0 0.00
16+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
16+780 20 0.66 19.80 95 18.81 5 0.99 0 0.00
16+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+820 20 0.6 12.60 95 11.97 5 0.63 0 0.00
16+840 20 0.66 12.60 95 11.97 5 0.63 0 0.00
16+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+880 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
16+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+040 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+140 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+220 20 1.32 19.80 95 18.81 5 0.99 0 0.00
17+240 20 1.17 24.90 95 23.66 5 1.25 0 0.00
17+260 20 0.51 16.80 95 15.96 5 0.84 0 0.00
17+280 20 0.51 10.20 95 9.69 5 0.51 0 0.00
17+300 20 0.465 9.75 95 9.26 5 0.49 0 0.00
17+320 20 0.66 11.25 95 10.69 5 0.56 0 0.00
17+340 20 0.635 12.95 95 12.30 5 0.65 0 0.00
17+360 20 0.178 8.13 95 7.72 5 0.41 0 0.00
17+380 20 0.66 8.38 95 7.96 5 0.42 0 0.00
17+400 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+420 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+500 20 0.185 8.45 95 8.03 5 0.42 0 0.00
17+520 20 0.6 7.85 95 7.46 5 0.39 0 0.00
17+540 20 0.66 12.60 95 11.97 5 0.63 0 0.00
17+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+580 20 0.507 11.67 95 11.09 5 0.58 0 0.00
72 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
17+600 20 0.51 10.17 95 9.66 5 0.51 0 0.00
17+620 20 0.66 11.70 95 11.12 5 0.59 0 0.00
17+640 20 0.455 11.15 95 10.59 5 0.56 0 0.00
17+660 20 0.66 11.15 95 10.59 5 0.56 0 0.00
17+680 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+720 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+740 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+820 20 1.32 19.80 95 18.81 5 0.99 0 0.00
17+840 20 0.66 19.80 95 18.81 5 0.99 0 0.00
17+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+880 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
17+960 20 0.6 12.60 95 11.97 5 0.63 0 0.00
17+980 20 0.66 12.60 95 11.97 5 0.63 0 0.00
18+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+040 20 0.23 8.90 95 8.46 5 0.45 0 0.00
18+060 20 0.66 8.90 95 8.46 5 0.45 0 0.00
18+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+140 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+260 20 0.6 12.60 95 11.97 5 0.63 0 0.00
18+280 20 0.66 12.60 95 11.97 5 0.63 0 0.00
18+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+380 20 0 6.60 95 6.27 5 0.33 0 0.00
18+400 20 0 - 95 - 5 0.00 0 0.00
18+420 20 0.66 6.60 95 6.27 5 0.33 0 0.00
18+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+460 20 0.6 12.60 95 11.97 5 0.63 0 0.00
18+480 20 0.66 12.60 95 11.97 5 0.63 0 0.00
18+500 20 1.17 18.30 95 17.39 5 0.92 0 0.00
18+520 20 1.158 23.28 95 22.12 5 1.16 0 0.00
18+540 20 1.16 23.18 95 22.02 5 1.16 0 0.00
18+560 20 0.66 18.20 95 17.29 5 0.91 0 0.00
18+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+600 20 1.32 19.80 95 18.81 5 0.99 0 0.00
18+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
18+640 20 0.66 19.80 95 18.81 5 0.99 0 0.00
18+660 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+680 20 0.66 13.20 95 12.54 5 0.66 0 0.00
73 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
18+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+720 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+740 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+820 20 1.26 19.20 95 18.24 5 0.96 0 0.00
18+840 20 1.32 25.80 95 24.51 5 1.29 0 0.00
18+860 20 1.26 25.80 95 24.51 5 1.29 0 0.00
18+880 20 0.66 19.20 95 18.24 5 0.96 0 0.00
18+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+920 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
18+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+040 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+080 20 1.32 19.80 95 18.81 5 0.99 0 0.00
19+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
19+120 20 1.32 26.40 95 25.08 5 1.32 0 0.00
19+140 20 0.66 19.80 95 18.81 5 0.99 0 0.00
19+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+180 20 0.01 6.70 95 6.37 5 0.34 0 0.00
19+200 20 0.6 6.10 95 5.80 5 0.31 0 0.00
19+220 20 0.66 12.60 95 11.97 5 0.63 0 0.00
19+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+340 20 0.6 12.60 95 11.97 5 0.63 0 0.00
19+360 20 0.66 12.60 95 11.97 5 0.63 0 0.00
19+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+400 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+420 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+500 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+540 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+600 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+620 20 0.6 12.60 95 11.97 5 0.63 0 0.00
19+640 20 0.66 12.60 95 11.97 5 0.63 0 0.00
19+660 20 0.6 12.60 95 11.97 5 0.63 0 0.00
19+680 20 0.66 12.60 95 11.97 5 0.63 0 0.00
19+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+720 20 0.6 12.60 95 11.97 5 0.63 0 0.00
19+740 20 1.32 19.20 95 18.24 5 0.96 0 0.00
19+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
19+780 20 1.26 25.80 95 24.51 5 1.29 0 0.00
74 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
19+800 20 1.32 25.80 95 24.51 5 1.29 0 0.00
19+820 20 1.26 25.80 95 24.51 5 1.29 0 0.00
19+840 20 0.66 19.20 95 18.24 5 0.96 0 0.00
19+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+880 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+900 20 0.66 13.20 95 12.54 5 0.66 0 0.00
19+920 20 0.6 12.60 95 11.97 5 0.63 0 0.00
19+940 20 0.66 12.60 95 11.97 5 0.63 0 0.00
19+960 20 0.6 12.60 95 11.97 5 0.63 0 0.00
19+980 20 1.26 18.60 95 17.67 5 0.93 0 0.00
20+000 20 1.32 25.80 95 24.51 5 1.29 0 0.00
20+020 20 0.023 13.43 95 12.76 5 0.67 0 0.00
20+040 20 0 0.23 95 0.22 5 0.01 0 0.00
20+060 20 0.22 2.20 95 2.09 5 0.11 0 0.00
20+080 20 0.66 8.80 95 8.36 5 0.44 0 0.00
20+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+140 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+400 20 0.098 7.58 95 7.20 5 0.38 0 0.00
20+420 20 0 0.98 95 0.93 5 0.05 0 0.00
20+440 20 0.66 6.60 95 6.27 5 0.33 0 0.00
20+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+500 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+540 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+560 20 0.6 12.60 95 11.97 5 0.63 0 0.00
20+580 20 1.26 18.60 95 17.67 5 0.93 0 0.00
20+600 20 0.66 19.20 95 18.24 5 0.96 0 0.00
20+620 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+640 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+660 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+680 20 0.015 6.75 95 6.41 5 0.34 0 0.00
20+700 20 0.66 6.75 95 6.41 5 0.34 0 0.00
20+720 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+740 20 0.368 10.28 95 9.77 5 0.51 0 0.00
20+760 20 0 3.68 95 3.50 5 0.18 0 0.00
20+780 20 0.66 6.60 95 6.27 5 0.33 0 0.00
20+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
20+820 20 0.03 6.90 95 6.56 5 0.35 0 0.00
20+840 20 0 0.30 95 0.29 5 0.02 0 0.00
20+860 20 0 - 95 - 5 0.00 0 0.00
20+880 20 0 - 95 - 5 0.00 0 0.00
75 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
20+900 20 0 - 95 - 5 0.00 0 0.00
20+920 20 0 - 95 - 5 0.00 0 0.00
20+940 20 0 - 95 - 5 0.00 0 0.00
20+960 20 0.008 0.08 95 0.08 5 0.00 0 0.00
20+980 20 0 0.08 95 0.08 5 0.00 0 0.00
21+000 20 0.66 6.60 95 6.27 5 0.33 0 0.00
21+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+040 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+140 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+160 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+200 20 0 6.60 95 6.27 5 0.33 0 0.00
21+220 20 0 - 95 - 5 0.00 0 0.00
21+240 20 0 - 95 - 5 0.00 0 0.00
21+260 20 0.66 6.60 95 6.27 5 0.33 0 0.00
21+280 20 1.26 19.20 95 18.24 5 0.96 0 0.00
21+300 20 1.17 24.30 95 23.09 5 1.22 0 0.00
21+320 20 1.065 22.35 95 21.23 5 1.12 0 0.00
21+340 20 0.51 15.75 95 14.96 5 0.79 0 0.00
21+360 20 0.51 10.20 95 9.69 5 0.51 0 0.00
21+380 20 0.51 10.20 95 9.69 5 0.51 0 0.00
21+400 20 0.51 10.20 95 9.69 5 0.51 0 0.00
21+420 20 0.66 11.70 95 11.12 5 0.59 0 0.00
21+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+460 20 0.265 9.25 95 8.79 5 0.46 0 0.00
21+480 20 0.57 8.35 95 7.93 5 0.42 0 0.00
21+500 20 0.06 6.30 95 5.99 5 0.32 0 0.00
21+520 20 0.65 7.10 95 6.75 5 0.36 0 0.00
21+540 20 0.66 13.10 95 12.45 5 0.66 0 0.00
21+560 20 0.6 12.60 95 11.97 5 0.63 0 0.00
21+580 20 1.32 19.20 95 18.24 5 0.96 0 0.00
21+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+640 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+680 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
21+740 20 1.26 25.80 95 24.51 5 1.29 0 0.00
21+760 20 1.32 25.80 95 24.51 5 1.29 0 0.00
21+780 20 1.17 24.90 95 23.66 5 1.25 0 0.00
21+800 20 0.5 16.70 95 15.87 5 0.84 0 0.00
21+820 20 0.66 11.60 95 11.02 5 0.58 0 0.00
21+840 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+860 20 0.658 13.18 95 12.52 5 0.66 0 0.00
21+880 20 0 6.58 95 6.25 5 0.33 0 0.00
21+900 20 0 - 95 - 5 0.00 0 0.00
21+920 20 0.6 6.00 95 5.70 5 0.30 0 0.00
21+940 20 0.66 12.60 95 11.97 5 0.63 0 0.00
21+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
21+980 20 1.32 19.80 95 18.81 5 0.99 0 0.00
76 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
22+000 20 1.17 24.90 95 23.66 5 1.25 0 0.00
22+020 20 1.17 23.40 95 22.23 5 1.17 0 0.00
22+040 20 1.17 23.40 95 22.23 5 1.17 0 0.00
22+060 20 0.6 17.70 95 16.82 5 0.89 0 0.00
22+080 20 0.53 11.30 95 10.74 5 0.57 0 0.00
22+100 20 0.01 5.40 95 5.13 5 0.27 0 0.00
22+120 20 0 0.10 95 0.10 5 0.01 0 0.00
22+140 20 0 - 95 - 5 0.00 0 0.00
22+160 20 0.252 2.52 95 2.39 5 0.13 0 0.00
22+180 20 1.32 15.72 95 14.93 5 0.79 0 0.00
22+200 20 1.17 24.90 95 23.66 5 1.25 0 0.00
22+220 20 1.17 23.40 95 22.23 5 1.17 0 0.00
22+240 20 0.66 18.30 95 17.39 5 0.92 0 0.00
22+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+380 20 1.26 19.20 95 18.24 5 0.96 0 0.00
22+400 20 1.11 23.70 95 22.52 5 1.19 0 0.00
22+420 20 1.17 22.80 95 21.66 5 1.14 0 0.00
22+440 20 1.168 23.38 95 22.21 5 1.17 0 0.00
22+460 20 1.065 22.33 95 21.21 5 1.12 0 0.00
22+480 20 1.17 22.35 95 21.23 5 1.12 0 0.00
22+500 20 0.5 16.70 95 15.87 5 0.84 0 0.00
22+520 20 0.66 11.60 95 11.02 5 0.58 0 0.00
22+540 20 0.6 12.60 95 11.97 5 0.63 0 0.00
22+560 20 0.66 12.60 95 11.97 5 0.63 0 0.00
22+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+600 20 1.125 17.85 95 16.96 5 0.89 0 0.00
22+620 20 1.17 22.95 95 21.80 5 1.15 0 0.00
22+640 20 1.105 22.75 95 21.61 5 1.14 0 0.00
22+660 20 1.16 22.65 95 21.52 5 1.13 0 0.00
22+680 20 0.6 17.60 95 16.72 5 0.88 0 0.00
22+700 20 0.66 12.60 95 11.97 5 0.63 0 0.00
22+720 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+740 20 0.66 13.20 95 12.54 5 0.66 0 0.00
22+760 20 0.03 6.90 95 6.56 5 0.35 0 0.00
22+780 20 0 0.30 95 0.29 5 0.02 0 0.00
22+800 20 0.555 5.55 95 5.27 5 0.28 0 0.00
22+820 20 1.32 18.75 95 17.81 5 0.94 0 0.00
22+840 20 1.17 24.90 95 23.66 5 1.25 0 0.00
22+860 20 1.17 23.40 95 22.23 5 1.17 0 0.00
22+880 20 1.17 23.40 95 22.23 5 1.17 0 0.00
22+900 20 1.17 23.40 95 22.23 5 1.17 0 0.00
22+920 20 1.168 23.38 95 22.21 5 1.17 0 0.00
22+940 20 1.02 21.88 95 20.79 5 1.09 0 0.00
22+960 20 1.02 20.40 95 19.38 5 1.02 0 0.00
22+980 20 0.998 20.18 95 19.17 5 1.01 0 0.00
23+000 20 1 19.98 95 18.98 5 1.00 0 0.00
23+020 20 0.975 19.75 95 18.76 5 0.99 0 0.00
23+040 20 1.02 19.95 95 18.95 5 1.00 0 0.00
23+060 20 1.02 20.40 95 19.38 5 1.02 0 0.00
23+080 20 1.02 20.40 95 19.38 5 1.02 0 0.00
77 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
23+100 20 1.015 20.35 95 19.33 5 1.02 0 0.00
23+120 20 1.32 23.35 95 22.18 5 1.17 0 0.00
23+140 20 1.32 26.40 95 25.08 5 1.32 0 0.00
23+160 20 1.033 23.53 95 22.35 5 1.18 0 0.00
23+180 20 1.32 23.53 95 22.35 5 1.18 0 0.00
23+200 20 1.2 25.20 95 23.94 5 1.26 0 0.00
23+220 20 1.32 25.20 95 23.94 5 1.26 0 0.00
23+240 20 1.32 26.40 95 25.08 5 1.32 0 0.00
23+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
23+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
23+300 20 0.66 19.80 95 18.81 5 0.99 0 0.00
23+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+400 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+420 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+440 20 0.6 12.60 95 11.97 5 0.63 0 0.00
23+460 20 0 6.00 95 5.70 5 0.30 0 0.00
23+480 20 0 - 95 - 5 0.00 0 0.00
23+500 20 0.66 6.60 95 6.27 5 0.33 0 0.00
23+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+540 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+580 20 0.6 12.60 95 11.97 5 0.63 0 0.00
23+600 20 0.66 12.60 95 11.97 5 0.63 0 0.00
23+620 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+640 20 1.32 19.80 95 18.81 5 0.99 0 0.00
23+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
23+680 20 1.32 26.40 95 25.08 5 1.32 0 0.00
23+700 20 0.66 19.80 95 18.81 5 0.99 0 0.00
23+720 20 0 6.60 95 6.27 5 0.33 0 0.00
23+740 20 0.66 6.60 95 6.27 5 0.33 0 0.00
23+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+820 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+840 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+880 20 0.6 12.60 95 11.97 5 0.63 0 0.00
23+900 20 0.49 10.90 95 10.36 5 0.55 0 0.00
23+920 20 0 4.90 95 4.66 5 0.25 0 0.00
23+940 20 0.66 6.60 95 6.27 5 0.33 0 0.00
23+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
23+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+020 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+040 20 1.32 19.80 95 18.81 5 0.99 0 0.00
24+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+080 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+120 20 0.66 19.80 95 18.81 5 0.99 0 0.00
24+140 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+160 20 0.595 12.55 95 11.92 5 0.63 0 0.00
24+180 20 0.66 12.55 95 11.92 5 0.63 0 0.00
78 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
24+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+220 20 1.32 19.80 95 18.81 5 0.99 0 0.00
24+240 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+300 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+320 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+340 20 1.2 25.20 95 23.94 5 1.26 0 0.00
24+360 20 0.66 18.60 95 17.67 5 0.93 0 0.00
24+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+400 20 1.32 19.80 95 18.81 5 0.99 0 0.00
24+420 20 0.66 19.80 95 18.81 5 0.99 0 0.00
24+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+500 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+520 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+540 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+560 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+580 20 1.32 19.80 95 18.81 5 0.99 0 0.00
24+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
24+620 20 0.66 19.80 95 18.81 5 0.99 0 0.00
24+640 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+660 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+680 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+700 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+720 20 0.6 12.60 95 11.97 5 0.63 0 0.00
24+740 20 0.66 12.60 95 11.97 5 0.63 0 0.00
24+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+800 20 0.6 12.60 95 11.97 5 0.63 0 0.00
24+820 20 0.6 12.00 95 11.40 5 0.60 0 0.00
24+840 20 0.66 12.60 95 11.97 5 0.63 0 0.00
24+860 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+880 20 0.507 11.67 95 11.09 5 0.58 0 0.00
24+900 20 0 5.07 95 4.82 5 0.25 0 0.00
24+920 20 0.66 6.60 95 6.27 5 0.33 0 0.00
24+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
24+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
25+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
25+020 20 0.6 12.60 95 11.97 5 0.63 0 0.00
25+040 20 0.66 12.60 95 11.97 5 0.63 0 0.00
25+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
25+080 20 0.66 13.20 95 12.54 5 0.66 0 0.00
25+100 20 0.66 13.20 95 12.54 5 0.66 0 0.00
25+120 20 0.6 12.60 95 11.97 5 0.63 0 0.00
25+140 20 0.6 12.00 95 11.40 5 0.60 0 0.00
25+160 20 0.645 12.45 95 11.83 5 0.62 0 0.00
25+180 20 0.66 13.05 95 12.40 5 0.65 0 0.00
25+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
25+220 20 0.6 12.60 95 11.97 5 0.63 0 0.00
25+240 20 1.32 19.20 95 18.24 5 0.96 0 0.00
25+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+280 20 1.32 26.40 95 25.08 5 1.32 0 0.00
79 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
25+300 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+320 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+340 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+360 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+380 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+400 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+420 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+440 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+460 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+480 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+500 20 1.26 25.80 95 24.51 5 1.29 0 0.00
25+520 20 1.32 25.80 95 24.51 5 1.29 0 0.00
25+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+560 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+580 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+640 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+660 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+680 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+780 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+800 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+820 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+840 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+860 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+880 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+900 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+920 20 0.6 19.20 95 18.24 5 0.96 0 0.00
25+940 20 1.32 19.20 95 18.24 5 0.96 0 0.00
25+960 20 1.32 26.40 95 25.08 5 1.32 0 0.00
25+980 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+000 20 1.2 25.20 95 23.94 5 1.26 0 0.00
26+020 20 1.32 25.20 95 23.94 5 1.26 0 0.00
26+040 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+060 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+080 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+100 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+120 20 1.17 24.90 95 23.66 5 1.25 0 0.00
26+140 20 1.063 22.33 95 21.21 5 1.12 0 0.00
26+160 20 1.17 22.33 95 21.21 5 1.12 0 0.00
26+180 20 1.17 23.40 95 22.23 5 1.17 0 0.00
26+200 20 1.17 23.40 95 22.23 5 1.17 0 0.00
26+220 20 1.065 22.35 95 21.23 5 1.12 0 0.00
26+240 20 1.32 23.85 95 22.66 5 1.19 0 0.00
26+260 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+280 20 1.26 25.80 95 24.51 5 1.29 0 0.00
26+300 20 1.32 25.80 95 24.51 5 1.29 0 0.00
26+320 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+340 20 1.26 25.80 95 24.51 5 1.29 0 0.00
26+360 20 0.66 19.20 95 18.24 5 0.96 0 0.00
26+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
80 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m )3
Re
% % (m3) % (m3)
26+400 20 0.66 13.20 95 12.54 5 0.66 0 0.00
26+420 20 1.32 19.80 95 18.81 5 0.99 0 0.00
26+440 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+460 20 0.66 19.80 95 18.81 5 0.99 0 0.00
26+480 20 0.488 11.48 95 10.91 5 0.57 0 0.00
26+500 20 1.32 18.08 95 17.18 5 0.90 0 0.00
26+520 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+540 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+560 20 1.26 25.80 95 24.51 5 1.29 0 0.00
26+580 20 1.32 25.80 95 24.51 5 1.29 0 0.00
26+600 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+620 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+640 20 1.26 25.80 95 24.51 5 1.29 0 0.00
26+660 20 0.66 19.20 95 18.24 5 0.96 0 0.00
26+680 20 1.32 19.80 95 18.81 5 0.99 0 0.00
26+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+720 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+740 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+760 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+780 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+800 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+820 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+840 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+860 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+880 20 1.32 26.40 95 25.08 5 1.32 0 0.00
26+900 20 1.26 25.80 95 24.51 5 1.29 0 0.00
26+920 20 0.66 19.20 95 18.24 5 0.96 0 0.00
26+940 20 0.66 13.20 95 12.54 5 0.66 0 0.00
26+960 20 0.66 13.20 95 12.54 5 0.66 0 0.00
26+980 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+000 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+020 20 0.6 12.60 95 11.97 5 0.63 0 0.00
27+040 20 0.66 12.60 95 11.97 5 0.63 0 0.00
27+060 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+080 20 0.6 12.60 95 11.97 5 0.63 0 0.00
27+100 20 0.66 12.60 95 11.97 5 0.63 0 0.00
27+120 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+140 20 0.6 12.60 95 11.97 5 0.63 0 0.00
27+160 20 0.66 12.60 95 11.97 5 0.63 0 0.00
27+180 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+200 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+220 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+240 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+260 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+280 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+300 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+320 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+340 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+360 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+380 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+400 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+420 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+440 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+460 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+480 20 0.66 13.20 95 12.54 5 0.66 0 0.00
81 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
s
Ordinary Soil Soft Rock Hard Rock
k
Chainage Length (m) Area (m2) Volume(m3)
ar
Volume Volume
m
Volume (m ) 3
Re
% % (m3) % (m3)
27+500 20 0 6.60 95 6.27 5 0.33 0 0.00
27+520 20 0.66 6.60 95 6.27 5 0.33 0 0.00
27+540 20 0.6 12.60 95 11.97 5 0.63 0 0.00
27+560 20 0.66 12.60 95 11.97 5 0.63 0 0.00
27+580 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+600 20 0.6 12.60 95 11.97 5 0.63 0 0.00
27+620 20 0.66 12.60 95 11.97 5 0.63 0 0.00
27+640 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+660 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+680 20 1.32 19.80 95 18.81 5 0.99 0 0.00
27+700 20 1.32 26.40 95 25.08 5 1.32 0 0.00
27+720 20 0.66 19.80 95 18.81 5 0.99 0 0.00
27+740 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+760 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+780 20 0.66 13.20 95 12.54 5 0.66 0 0.00
27+800 20 0.66 13.20 95 12.54 5 0.66 0 0.00
82 of 323
ks
ar
m
Re
83 of 323
ks
ar
m
Re
84 of 323
ks
ar
m
Re
85 of 323
ks
ar
m
Re
86 of 323
ks
ar
m
Re
87 of 323
ks
ar
m
Re
88 of 323
ks
ar
m
Re
89 of 323
ks
ar
m
Re
90 of 323
ks
ar
m
Re
91 of 323
ks
ar
m
Re
92 of 323
ks
ar
m
Re
93 of 323
ks
ar
m
Re
94 of 323
ks
ar
m
Re
95 of 323
ks
ar
m
Re
96 of 323
ks
ar
m
Re
97 of 323
ks
ar
m
Re
98 of 323
ks
ar
m
Re
99 of 323
ks
ar
m
Re
100 of 323
ks
ar
m
Re
101 of 323
ks
ar
m
Re
102 of 323
ks
ar
m
Re
103 of 323
ks
ar
m
Re
104 of 323
ks
ar
m
Re
105 of 323
ks
ar
m
Re
106 of 323
ks
ar
m
Re
107 of 323
ks
ar
m
Re
108 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
109 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
110 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
111 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
112 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
113 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
114 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
115 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
116 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
117 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
118 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
119 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
120 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
121 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
122 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Road
Planning Monitoring and Evaluation Unit
131 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
132 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
133 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
134 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
135 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
136 of 323
Remarks
137 of 323
Remarks
138 of 323
Remarks
139 of 323
Remarks
140 of 323
Remarks
141 of 323
Remarks
142 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
Remarks
Left side Right side Volume of 0.25m thk.
Total
Length (m) PCC for Granular Filter Geotextile (m2)
Volume (m3)
the base material (m3)
Height Area(m2) Volume (m ) 3
Height Area(m2) Volume (m ) 3
143 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
Remarks
Left side Right side Volume of 0.25m thk.
Total
Length (m) PCC for Granular Filter Geotextile (m2)
Volume (m3)
the base material (m3)
Height Area(m2) Volume (m ) 3
Height Area(m2) Volume (m )
3
144 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
Remarks
Left side Right side Volume of 0.25m thk.
Total
Length (m) PCC for Granular Filter Geotextile (m2)
Volume (m3)
the base material (m3)
Height Area(m2) Volume (m ) 3
Height Area(m2) Volume (m )
3
145 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
Remarks
Left side Right side Volume of 0.25m thk.
Total
Length (m) PCC for Granular Filter Geotextile (m2)
Volume (m3)
the base material (m3)
Height Area(m2) Volume (m ) 3
Height Area(m2) Volume (m )
3
146 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
Remarks
Left side Right side Volume of 0.25m thk.
Total
Length (m) PCC for Granular Filter Geotextile (m2)
Volume (m3)
the base material (m3)
Height Area(m2) Volume (m ) 3
Height Area(m2) Volume (m )
3
147 of 323
Masonry Retaining Structure Quantity Calculation
Name of the road:…………………………….
Chainage:0+000 to ….
Structure quantity
Retaining wall Retaining Wall
Chainage
Remarks
Left side Right side Volume of 0.25m thk.
Total
Length (m) PCC for Granular Filter Geotextile (m2)
Volume (m3)
the base material (m3)
Height Area(m2) Volume (m ) 3
Height Area(m2) Volume (m ) 3
148 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
Left Right
149 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
150 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
151 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
152 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
153 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
154 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
155 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
156 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
157 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
158 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
159 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
160 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
161 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
162 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
163 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
164 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
165 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
166 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
167 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
168 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
169 of 323
DETAIL QUANTITY CALCULATIONS FOR DRAINWORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Left Right
170 of 323
Remarks
171 of 323
Remarks
172 of 323
Remarks
173 of 323
Remarks
174 of 323
Remarks
175 of 323
Remarks
176 of 323
Remarks
177 of 323
Remarks
178 of 323
Remarks
179 of 323
Remarks
180 of 323
Remarks
181 of 323
Remarks
182 of 323
Remarks
183 of 323
Remarks
184 of 323
Remarks
185 of 323
Remarks
186 of 323
Remarks
187 of 323
Remarks
188 of 323
Remarks
189 of 323
Remarks
190 of 323
Remarks
191 of 323
Remarks
192 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
QUANTITY CALCULATION FOR TRAPEZOIDAL (Side Drain A) COVER FOR SIDE DRAIN (PER 20 Rm.)
Name of the road:…………………………….
Chainage:0+000 to ….
Item
Description of works No. Length (m) Breadth (m) Height (m)
No.
For Cover Works(1.2m x 0.5m x 0.125m) 1 no.
1 PCC work for RCC in M20/20 in cover 1 0.5 1.200 0.125
Wt(Kg) per
2 Reinforcement Work meter
12 mm dia Bottom Main bars @ 15 cm c/c (Top & Bottom) 4 1.150 0.887
10 mm dia Distribution bars @ 20 cm c/c (Top & Bottom) 6.75 0.450 0.62
Total
3 Formwork
For cover 1 0.5 1.200 0.125
193 of 323
20 Rm.)
Quantity Per no
0.075
Wt(Kg) per Rm
span
4.0802
1.88325
5.963
0.425
194 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
1 PCC work for bed in M20/20 1 1.0 1.200 0.100 0.120 0.120
PCC work for slope in M20/20 1 1.0 0.263 0.050 0.013 0.013
total M20/20= 0.133
2 MM5 Stone mesonry side wall 1 1.0 0.263 0.263 0.263
A=(0.25*0.45)+(0.5*(0.275+0.475)*0.4)
195 of 323
Unit
cum
cum
196 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0
Total - - - 77 - 2 - - -
Total no of Hume Pipe 900mm Proposed = 77
MATRICES OF CROSS DRAINAGE WORKS
Name of the road:…………………………….
Chainage:0+000 to ….
Existing Proposed Proposed
NP3 RCC Slab
Chainage Length Hume culvert
(Km) (m) pipe 0.6 0.9 0.6 (span
culvert dia dia dia 0.9 dia m) 2 3 4 5 6
WORKS
Remarks
Remarks
Chainage:0+000 to ….
NP3 RCC NP3 RCC
Chainage
Hume pipe Hume pipe Bridge Length Remarks
(Km)
Culvert Culvert
60cm dia 90cm dia
0+050 1 10m PROPOSED PC 0.6M
0+860 1 10m PROPOSED PC 0.6M
1+263 1 10m EXISTING PC
1+690 1 9m PROPOSED PC 0.6M
1+844 1 10m EXISTING BRIDGE SPAN 14M
2+660 1 9m PROPOSED PC 0.6M
2+809 1 9m EXISTING PC
3+126 1 10m EXISTING PC
3+419 1 10m EXISTING PC
3+590 1 10m PROPOSED PC 0.6M
3+714 1 10m EXISTING PC
3+877 1 10m EXISTING PC
4+099 1 9m EXISTING PC
4+137 1 9m EXISTING PC
4+469 1 9m PROPOSED PC 0.6M
4+650 1 10m PROPOSED PC 0.6M
5+590 1 10m PROPOSED PC 0.6M
6+272 1 9m EXISTING PC
6+336 1 10m EXISTING PC
6+710 1 9m PROPOSED PC 0.6M
6+824 1 10m EXISTING PC
7+038 1 9m EXISTING PC
7+230 1 10m PROPOSED PC 0.6M
7+357 1 9m EXISTING PC
7+890 1 10m PROPOSED PC 0.6M
8+272 1 10m EXISTING PC
8+306 1 10m EXISTING PC
8+660 1 9m PROPOSED PC 0.6M
8+870 1 9m PROPOSED PC 0.6M
9+370 1 9m PROPOSED PC 0.6M
9+610 1 9m PROPOSED PC 0.6M
9+970 1 9m PROPOSED PC 0.6M
10+147 1 10m EXISTING BRIDGE SPAN 10M
10+195 1 9m EXISTING PC
10+818 1 10m EXISTING PC
11+129 1 10m EXISTING PC
11+423 1 10m EXISTING PC
11+590 1 10m PROPOSED PC 0.6M
Existing 19 2
Total 17 0 0
202 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0
203 of 323
Quantity Estimate of Pipe Culvert (60 dia)
4. Back Fill
i) Carriage way 1 10.67 0.95 2.44 24.73 m³
deduction for pipe -1 10.67 0.95 - 10.14 m³
ii) U/S Head wall with Catchpit 1 4.32 0.36 1.45 2.26 m³
iii) Side walls 2 1.50 0.60 2.38 4.28 m³
21.13 m³
6. Gabion Works
i) U/S Protection works 1 4.00 1.00 1.00 4.00 m³
ii)D/S Protection 1 3.00 3.00 0.50 4.50 m³
2 3.00 1.00 0.50 3.00 m³
11.50 m³
7. Formwork
i) Below D/S Head Wall 1 9.40 0.10 0.94 m²
ii) U/S Head wall with Catchpit 1 15.88 0.10 1.59 m²
iii) for Bedding Concrete 2 12.50 0.10 2.50
5.03 m²
204 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0
4. Back Fill
i) Carriage way 1 3.38 0.95 2.25 7.22 m³
deduction for pipe -1 3.38 0.95 - 3.21 m³
ii) U/S Head wall with Catchpit 1 3.90 0.36 1.45 2.04 m³
iii) Side walls 2 1.50 0.50 2.00 3.00 m³
9.05 m³
6. Gabion Works
i) U/S Protection works 1 4.00 1.00 1.00 4.00 m³
ii)D/S Protection 1 3.00 3.00 0.50 4.50 m³
2 3.00 1.00 0.50 3.00 m³
11.50 m³
7. Formwork
i) Below D/S Head Wall 1 9.40 0.10 0.94 m²
ii) U/S Head wall with Catchpit 1 14.66 0.10 1.47 m²
iii) for Bedding Concrete 2 5.00 0.10 1.00
3.41 m²
207 of 323
Quantity Estimate of Pipe Culvert (90 dia)
4. Back Fill
i) Carriage way 1 10.67 1.30 2.44 33.85 m³
deduction for pipe -1 10.67 0.95 - 10.14 m³
ii) U/S Head wall with Catchpit 1 4.32 0.45 1.80 3.50 m³
iii) Side walls 2 1.50 0.60 2.38 4.28 m³
31.49 m³
6. Gabion Works
i) U/S Protection works 1 4.00 1.00 1.00 4.00 m³
ii)D/S Protection 1 3.00 3.00 0.50 4.50 m³
2 3.00 1.00 0.50 3.00 m³
11.50 m³
7. Formwork
i) Below D/S Head Wall 1 9.40 0.10 0.94 m²
ii) U/S Head wall with Catchpit 1 16.22 0.10 1.62 m²
iii) for Bedding Concrete 2 12.50 0.10 2.50
5.06 m²
208 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
Earthwork in Foundation
1
Excavation in Hard soil
Cum
a Main Abutment Cum 2 7.8 1.9625 1.45 45.48
b Wing Walls Cum 4 5 1.5 1.45 43.50
c Cutoff Wall Cum 2 7.902 0.3 1 4.74
c Bed
under slab Cum 1 7.8 2.4 0.5 9.36
U/s and d/s under slab Cum 2 6.451 4.3 0.5 27.74
Total 130.82 2 261.640
215 of 323
Remarks
216 of 323
Government of Nepal
Ministry of Federal Affairs & Local Development
Central Level Project Implementation Unit (CLPIU)
Earthquake emergency Assistance Project
Kupondole,Lalitpur
Chainage:0+000 to ….
Total no
Sn Description of Works unit No Length (m) Width (m) Height (m) Quantity Remarks
of PC
1 Earthwork in Foundation
Excavation in Hard soil Cum
a Head Wall Cum 1 3.6 1.55 1 5.58
b Catch Pit Cum 1 2.6 2.6 1.9 12.844
c Pipe Line Cum 1 10 1.15 1.4 16.1
Total 0 0 0
2 PCC M15 Cum
a Head Wall Cum 1 3.6 1.95 0.2 1.404
b Catch Pit Cum 1 2.6 2.6 0.1 0.68
c Pipe Line Cum 1 8.5 1 0.1 0.85
Total 0 0 0
3 RRM in 1:4 cement mortar Cum
a Head Wall Cum 1 3.6 1.025 3.5 12.92
b Catch Pit Cum 1 2.4 2.4 1.8 10.37
Additional masonry works for
site condition Cum 8.0 0.5 1.5 0.00
Total 23.29
Deduction
a Pipe portion Head wall Cum 1 0.90 (0.95*PI()*(D2)/4) 0.90
b Pipe portion Catch Pit Cum 1 0.43 (0.95*PI()*(D2)/4) 0.43
c Catch Pit Cum 1 1.00 1.2 1.5 1.8
d Inlet Drain Cum 2 0.5 0.45 0.4 0.18
Total Deduction 3.31
Total after deduction 0.00 0.00 0
Transportation and Laying of
4
Hume Pipe Rm 1 10 0.00 0.00 0
Back filling work including Pipe Line Excavation Volume-
5
compaction Cum 1 (7.45*PI()*(D2)/4) 0.00 0.00 0
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
225 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
227 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
0+720 20 7.53 1.88 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.30 187.55 20.84 3.21 114.15 11.03 2.70 DBST
0+740 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.30 187.55 20.84 3.21 114.15 11.03 2.70 DBST
0+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
0+780 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
0+800 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
0+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
0+840 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
0+860 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
0+880 20 8.03 2.01 1.88 37.60 1.61 1.51 30.20 3.00 0.53 10.60 165.30 193.40 21.49 3.31 119.10 11.58 2.81 DBST
0+900 20 7.00 1.75 1.88 37.60 1.40 1.51 30.20 3.00 0.53 10.60 165.30 193.40 21.49 3.31 119.10 11.58 2.81 DBST
0+920 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
0+940 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
0+960 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
0+980 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
1+000 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+060 20 7.76 1.94 1.85 37.00 1.55 1.48 29.60 3.00 0.53 10.60 162.60 190.24 21.14 3.25 116.42 11.29 2.75 DBST
1+080 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 162.60 190.24 21.14 3.25 116.42 11.29 2.75 DBST
1+100 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
1+120 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
1+140 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+160 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
1+180 20 7.22 1.81 1.85 37.00 1.44 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
1+200 20 7.73 1.93 1.87 37.40 1.55 1.50 30.00 3.00 0.53 10.60 164.50 192.47 21.39 3.29 118.31 11.50 2.79 DBST
1+220 20 7.00 1.75 1.84 36.80 1.40 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
1+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+280 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
1+300 20 7.59 1.90 2.03 40.60 1.52 1.62 32.40 3.00 0.53 10.60 176.90 206.97 23.00 3.54 130.58 12.86 3.07 DBST
1+320 20 8.60 2.15 2.03 40.60 1.72 1.62 32.40 3.00 0.53 10.60 176.90 206.97 23.00 3.54 130.58 12.86 3.07 DBST
1+340 20 8.46 2.12 2.14 42.80 1.69 1.71 34.20 3.00 0.53 10.60 185.60 217.15 24.13 3.71 139.19 13.82 3.26 DBST
1+360 20 8.60 2.15 2.14 42.80 1.72 1.71 34.20 3.00 0.53 10.60 185.60 217.15 24.13 3.71 139.19 13.82 3.26 DBST
1+380 20 8.79 2.20 2.18 43.60 1.76 1.74 34.80 3.00 0.53 10.60 188.90 221.01 24.56 3.78 142.46 14.18 3.33 DBST
1+400 20 8.90 2.23 2.22 44.40 1.78 1.77 35.40 3.00 0.53 10.60 191.90 224.52 24.95 3.84 145.43 14.51 3.40 DBST
1+420 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
1+440 20 7.85 1.96 2.10 42.00 1.57 1.68 33.60 3.00 0.53 10.60 182.50 213.53 23.73 3.65 136.13 13.48 3.19 DBST
1+460 20 7.56 1.89 1.93 38.60 1.51 1.54 30.80 3.00 0.53 10.60 169.10 197.85 21.98 3.38 122.86 12.00 2.90 DBST
1+480 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
1+500 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
1+520 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
1+540 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
229 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
1+560 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
1+580 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+600 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+660 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
1+680 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
1+700 20 8.53 2.13 2.09 41.80 1.71 1.68 33.60 3.00 0.53 10.60 182.30 213.29 23.70 3.65 135.93 13.45 3.19 DBST
1+720 20 7.48 1.87 2.00 40.00 1.50 1.61 32.20 3.00 0.53 10.60 175.10 204.87 22.76 3.50 128.80 12.66 3.03 DBST
1+740 20 8.60 2.15 2.01 40.20 1.72 1.61 32.20 3.00 0.53 10.60 175.80 205.69 22.85 3.52 129.49 12.74 3.04 DBST
1+760 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
1+780 20 7.09 1.77 1.96 39.20 1.42 1.57 31.40 3.00 0.53 10.60 171.90 201.12 22.35 3.44 125.63 12.31 2.96 DBST
1+800 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.90 182.40 20.27 3.12 109.79 10.55 2.60 DBST
1+820 20 8.22 2.06 1.91 38.20 1.64 1.52 30.40 3.00 0.53 10.60 167.20 195.62 21.74 3.34 120.98 11.79 2.85 DBST
1+840 20 8.90 2.23 2.15 43.00 1.78 1.71 34.20 3.00 0.53 10.60 186.20 217.85 24.21 3.72 139.79 13.88 3.27 DBST
1+860 20 8.17 2.04 2.14 42.80 1.63 1.71 34.20 3.00 0.53 10.60 185.70 217.27 24.14 3.71 139.29 13.83 3.26 DBST
1+880 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 166.70 195.04 21.67 3.33 120.48 11.74 2.84 DBST
1+900 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
1+920 20 7.50 1.88 1.82 36.40 1.50 1.45 29.00 3.00 0.53 10.60 160.00 187.20 20.80 3.20 113.85 11.00 2.70 DBST
1+940 20 8.60 2.15 2.02 40.40 1.72 1.61 32.20 3.00 0.53 10.60 176.00 205.92 22.88 3.52 129.69 12.76 3.05 DBST
1+960 20 8.57 2.14 2.15 43.00 1.71 1.72 34.40 3.00 0.53 10.60 186.70 218.44 24.27 3.73 140.28 13.94 3.28 DBST
1+980 20 7.13 1.78 1.96 39.20 1.43 1.57 31.40 3.00 0.53 10.60 172.00 201.24 22.36 3.44 125.73 12.32 2.96 DBST
2+000 20 7.00 1.75 1.77 35.40 1.40 1.42 28.40 3.00 0.53 10.60 156.30 182.87 20.32 3.13 110.19 10.59 2.61 DBST
2+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+040 20 7.21 1.80 1.78 35.60 1.44 1.42 28.40 3.00 0.53 10.60 157.10 183.81 20.42 3.14 110.98 10.68 2.63 DBST
2+060 20 7.00 1.75 1.78 35.60 1.40 1.42 28.40 3.00 0.53 10.60 157.10 183.81 20.42 3.14 110.98 10.68 2.63 DBST
2+080 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
2+100 20 7.52 1.88 1.93 38.60 1.50 1.54 30.80 3.00 0.53 10.60 169.20 197.96 22.00 3.38 122.96 12.01 2.90 DBST
2+120 20 7.90 1.98 1.93 38.60 1.58 1.54 30.80 3.00 0.53 10.60 169.20 197.96 22.00 3.38 122.96 12.01 2.90 DBST
2+140 20 7.31 1.83 1.91 38.20 1.46 1.52 30.40 3.00 0.53 10.60 167.10 195.51 21.72 3.34 120.88 11.78 2.85 DBST
2+160 20 8.90 2.23 2.03 40.60 1.78 1.62 32.40 3.00 0.53 10.60 177.10 207.21 23.02 3.54 130.78 12.88 3.07 DBST
2+180 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
2+200 20 8.25 2.06 2.15 43.00 1.65 1.72 34.40 3.00 0.53 10.60 186.50 218.21 24.25 3.73 140.09 13.92 3.28 DBST
2+220 20 7.20 1.80 1.93 38.60 1.44 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
2+240 20 7.56 1.89 1.85 37.00 1.51 1.48 29.60 3.00 0.53 10.60 162.60 190.24 21.14 3.25 116.42 11.29 2.75 DBST
2+260 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
2+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+300 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+360 20 8.13 2.03 1.89 37.80 1.63 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
2+380 20 7.00 1.75 1.89 37.80 1.40 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
230 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
2+400 20 7.61 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.10 188.49 20.94 3.22 114.94 11.12 2.72 DBST
2+420 20 7.90 1.98 1.94 38.80 1.58 1.55 31.00 3.00 0.53 10.60 170.10 199.02 22.11 3.40 123.85 12.11 2.92 DBST
2+440 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
2+460 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+480 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
2+500 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
2+520 20 7.85 1.96 2.06 41.20 1.57 1.65 33.00 3.00 0.53 10.60 179.50 210.02 23.34 3.59 133.16 13.15 3.12 DBST
2+540 20 7.00 1.75 1.86 37.20 1.40 1.49 29.80 3.00 0.53 10.60 163.50 191.30 21.26 3.27 117.32 11.39 2.77 DBST
2+560 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+580 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
2+600 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
2+620 20 7.70 1.93 1.92 38.40 1.54 1.53 30.60 3.00 0.53 10.60 168.00 196.56 21.84 3.36 121.77 11.88 2.87 DBST
2+640 20 8.54 2.14 2.04 40.80 1.71 1.63 32.60 3.00 0.53 10.60 177.40 207.56 23.06 3.55 131.08 12.91 3.08 DBST
2+660 20 8.20 2.05 2.10 42.00 1.64 1.68 33.60 3.00 0.53 10.60 182.40 213.41 23.71 3.65 136.03 13.46 3.19 DBST
2+680 20 7.36 1.84 1.95 39.00 1.47 1.56 31.20 3.00 0.53 10.60 170.60 199.60 22.18 3.41 124.34 12.17 2.93 DBST
2+700 20 7.59 1.90 1.87 37.40 1.52 1.50 30.00 3.00 0.53 10.60 164.50 192.47 21.39 3.29 118.31 11.50 2.79 DBST
2+720 20 7.39 1.85 1.88 37.60 1.48 1.50 30.00 3.00 0.53 10.60 164.80 192.82 21.42 3.30 118.60 11.53 2.80 DBST
2+740 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.90 185.91 20.66 3.18 112.76 10.88 2.67 DBST
2+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+800 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+840 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+860 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+880 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
2+900 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
2+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
2+960 20 8.81 2.20 1.98 39.60 1.76 1.58 31.60 3.00 0.53 10.60 173.10 202.53 22.50 3.46 126.82 12.44 2.98 DBST
2+980 20 8.90 2.23 2.22 44.40 1.78 1.77 35.40 3.00 0.53 10.60 192.10 224.76 24.97 3.84 145.63 14.53 3.40 DBST
3+000 20 8.87 2.22 2.23 44.60 1.77 1.78 35.60 3.00 0.53 10.60 192.70 225.46 25.05 3.85 146.22 14.60 3.41 DBST
3+020 20 7.00 1.75 1.99 39.80 1.40 1.59 31.80 3.00 0.53 10.60 173.70 203.23 22.58 3.47 127.41 12.51 3.00 DBST
3+040 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
3+060 20 7.16 1.79 1.87 37.40 1.43 1.50 30.00 3.00 0.53 10.60 164.60 192.58 21.40 3.29 118.40 11.51 2.80 DBST
3+080 20 7.00 1.75 1.77 35.40 1.40 1.42 28.40 3.00 0.53 10.60 156.60 183.22 20.36 3.13 110.48 10.63 2.62 DBST
3+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+120 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+140 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+160 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
231 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
3+240 20 7.13 1.78 1.77 35.40 1.43 1.42 28.40 3.00 0.53 10.60 156.30 182.87 20.32 3.13 110.19 10.59 2.61 DBST
3+260 20 7.80 1.95 1.87 37.40 1.56 1.50 30.00 3.00 0.53 10.60 164.30 192.23 21.36 3.29 118.11 11.47 2.79 DBST
3+280 20 7.55 1.89 1.92 38.40 1.51 1.54 30.80 3.00 0.53 10.60 168.50 197.15 21.91 3.37 122.27 11.94 2.88 DBST
3+300 20 7.46 1.87 1.88 37.60 1.49 1.50 30.00 3.00 0.53 10.60 165.10 193.17 21.46 3.30 118.90 11.56 2.81 DBST
3+320 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
3+340 20 7.64 1.91 1.89 37.80 1.53 1.51 30.20 3.00 0.53 10.60 166.00 194.22 21.58 3.32 119.79 11.66 2.83 DBST
3+360 20 8.03 2.01 1.96 39.20 1.61 1.57 31.40 3.00 0.53 10.60 171.70 200.89 22.32 3.43 125.43 12.29 2.95 DBST
3+380 20 7.75 1.94 1.98 39.60 1.55 1.58 31.60 3.00 0.53 10.60 172.80 202.18 22.46 3.46 126.52 12.41 2.98 DBST
3+400 20 8.45 2.11 2.03 40.60 1.69 1.62 32.40 3.00 0.53 10.60 177.00 207.09 23.01 3.54 130.68 12.87 3.07 DBST
3+420 20 7.38 1.85 1.98 39.60 1.48 1.59 31.80 3.00 0.53 10.60 173.30 202.76 22.53 3.47 127.02 12.46 2.99 DBST
3+440 20 7.56 1.89 1.87 37.40 1.51 1.50 30.00 3.00 0.53 10.60 164.40 192.35 21.37 3.29 118.21 11.48 2.79 DBST
3+460 20 7.54 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.00 194.22 21.58 3.32 119.79 11.66 2.83 DBST
3+480 20 7.17 1.79 1.84 36.80 1.43 1.47 29.40 3.00 0.53 10.60 162.10 189.66 21.07 3.24 115.93 11.23 2.74 DBST
3+500 20 7.00 1.75 1.77 35.40 1.40 1.42 28.40 3.00 0.53 10.60 156.70 183.34 20.37 3.13 110.58 10.64 2.62 DBST
3+520 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
3+540 20 7.73 1.93 1.84 36.80 1.55 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
3+560 20 7.38 1.85 1.89 37.80 1.48 1.52 30.40 3.00 0.53 10.60 166.10 194.34 21.59 3.32 119.89 11.67 2.83 DBST
3+580 20 7.91 1.98 1.92 38.40 1.58 1.53 30.60 3.00 0.53 10.60 167.90 196.44 21.83 3.36 121.67 11.87 2.87 DBST
3+600 20 7.50 1.88 1.93 38.60 1.50 1.54 30.80 3.00 0.53 10.60 169.10 197.85 21.98 3.38 122.86 12.00 2.90 DBST
3+620 20 8.60 2.15 2.02 40.40 1.72 1.61 32.20 3.00 0.53 10.60 176.00 205.92 22.88 3.52 129.69 12.76 3.05 DBST
3+640 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
3+660 20 7.73 1.93 2.04 40.80 1.55 1.64 32.80 3.00 0.53 10.60 178.30 208.61 23.18 3.57 131.97 13.01 3.10 DBST
3+680 20 7.00 1.75 1.84 36.80 1.40 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
3+700 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
3+720 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
3+740 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
3+760 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
3+780 20 7.41 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 159.10 186.15 20.68 3.18 112.96 10.90 2.68 DBST
3+800 20 7.56 1.89 1.87 37.40 1.51 1.50 30.00 3.00 0.53 10.60 164.70 192.70 21.41 3.29 118.50 11.52 2.80 DBST
3+820 20 7.34 1.84 1.87 37.40 1.47 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
3+840 20 7.43 1.86 1.85 37.00 1.49 1.48 29.60 3.00 0.53 10.60 162.70 190.36 21.15 3.25 116.52 11.30 2.75 DBST
3+860 20 7.48 1.87 1.87 37.40 1.50 1.50 30.00 3.00 0.53 10.60 164.10 192.00 21.33 3.28 117.91 11.45 2.79 DBST
3+880 20 7.60 1.90 1.89 37.80 1.52 1.51 30.20 3.00 0.53 10.60 165.80 193.99 21.55 3.32 119.59 11.64 2.82 DBST
3+900 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
3+920 20 7.44 1.86 1.88 37.60 1.49 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
3+940 20 8.01 2.00 1.93 38.60 1.60 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
3+960 20 8.44 2.11 2.06 41.20 1.69 1.65 33.00 3.00 0.53 10.60 179.50 210.02 23.34 3.59 133.16 13.15 3.12 DBST
3+980 20 8.02 2.01 2.06 41.20 1.60 1.65 33.00 3.00 0.53 10.60 179.60 210.13 23.35 3.59 133.25 13.16 3.13 DBST
4+000 20 7.80 1.95 1.98 39.60 1.56 1.58 31.60 3.00 0.53 10.60 173.20 202.64 22.52 3.46 126.92 12.45 2.99 DBST
4+020 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
4+040 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
4+060 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
232 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
4+080 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+120 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
4+140 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
4+160 20 7.11 1.78 1.84 36.80 1.42 1.47 29.40 3.00 0.53 10.60 162.10 189.66 21.07 3.24 115.93 11.23 2.74 DBST
4+180 20 7.42 1.86 1.82 36.40 1.48 1.45 29.00 3.00 0.53 10.60 160.30 187.55 20.84 3.21 114.15 11.03 2.70 DBST
4+200 20 7.00 1.75 1.81 36.20 1.40 1.44 28.80 3.00 0.53 10.60 159.20 186.26 20.70 3.18 113.06 10.91 2.68 DBST
4+220 20 8.12 2.03 1.89 37.80 1.62 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
4+240 20 7.00 1.75 1.89 37.80 1.40 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
4+260 20 7.77 1.94 1.85 37.00 1.55 1.48 29.60 3.00 0.53 10.60 162.70 190.36 21.15 3.25 116.52 11.30 2.75 DBST
4+280 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 162.70 190.36 21.15 3.25 116.52 11.30 2.75 DBST
4+300 20 8.26 2.07 1.91 38.20 1.65 1.53 30.60 3.00 0.53 10.60 167.60 196.09 21.79 3.35 121.37 11.84 2.86 DBST
4+320 20 7.05 1.76 1.92 38.40 1.41 1.53 30.60 3.00 0.53 10.60 168.10 196.68 21.85 3.36 121.87 11.89 2.87 DBST
4+340 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.50 181.94 20.22 3.11 109.40 10.51 2.60 DBST
4+360 20 8.04 2.01 1.88 37.60 1.61 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
4+380 20 7.35 1.84 1.93 38.60 1.47 1.54 30.80 3.00 0.53 10.60 168.90 197.61 21.96 3.38 122.66 11.98 2.89 DBST
4+400 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.50 185.45 20.61 3.17 112.37 10.84 2.66 DBST
4+420 20 7.06 1.77 1.76 35.20 1.41 1.41 28.20 3.00 0.53 10.60 155.60 182.05 20.23 3.11 109.49 10.52 2.60 DBST
4+440 20 8.60 2.15 1.96 39.20 1.72 1.57 31.40 3.00 0.53 10.60 171.60 200.77 22.31 3.43 125.33 12.28 2.95 DBST
4+460 20 8.22 2.06 2.11 42.20 1.64 1.68 33.60 3.00 0.53 10.60 183.20 214.34 23.82 3.66 136.82 13.55 3.21 DBST
4+480 20 8.50 2.13 2.10 42.00 1.70 1.67 33.40 3.00 0.53 10.60 182.20 213.17 23.69 3.64 135.83 13.44 3.18 DBST
4+500 20 7.07 1.77 1.95 39.00 1.41 1.56 31.20 3.00 0.53 10.60 170.70 199.72 22.19 3.41 124.44 12.18 2.93 DBST
4+520 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.70 182.17 20.24 3.11 109.59 10.53 2.60 DBST
4+540 20 7.29 1.82 1.79 35.80 1.46 1.43 28.60 3.00 0.53 10.60 157.90 184.74 20.53 3.16 111.77 10.77 2.65 DBST
4+560 20 7.00 1.75 1.79 35.80 1.40 1.43 28.60 3.00 0.53 10.60 157.90 184.74 20.53 3.16 111.77 10.77 2.65 DBST
4+580 20 7.10 1.78 1.77 35.40 1.42 1.41 28.20 3.00 0.53 10.60 156.00 182.52 20.28 3.12 109.89 10.56 2.61 DBST
4+600 20 7.00 1.75 1.77 35.40 1.40 1.41 28.20 3.00 0.53 10.60 156.00 182.52 20.28 3.12 109.89 10.56 2.61 DBST
4+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+640 20 7.06 1.77 1.76 35.20 1.41 1.41 28.20 3.00 0.53 10.60 155.60 182.05 20.23 3.11 109.49 10.52 2.60 DBST
4+660 20 8.60 2.15 1.96 39.20 1.72 1.57 31.40 3.00 0.53 10.60 171.60 200.77 22.31 3.43 125.33 12.28 2.95 DBST
4+680 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
4+700 20 7.45 1.86 2.01 40.20 1.49 1.61 32.20 3.00 0.53 10.60 175.50 205.34 22.82 3.51 129.20 12.71 3.04 DBST
4+720 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.50 186.62 20.74 3.19 113.36 10.95 2.68 DBST
4+740 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+800 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
4+820 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
4+840 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
4+860 20 7.30 1.83 1.79 35.80 1.46 1.43 28.60 3.00 0.53 10.60 158.00 184.86 20.54 3.16 111.87 10.78 2.65 DBST
4+880 20 7.30 1.83 1.83 36.60 1.46 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
4+900 20 7.00 1.75 1.79 35.80 1.40 1.43 28.60 3.00 0.53 10.60 158.00 184.86 20.54 3.16 111.87 10.78 2.65 DBST
233 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
4+920 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
4+940 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
4+960 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
4+980 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
5+000 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+060 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+080 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
5+100 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
5+120 20 7.95 1.99 1.93 38.60 1.59 1.54 30.80 3.00 0.53 10.60 169.10 197.85 21.98 3.38 122.86 12.00 2.90 DBST
5+140 20 7.73 1.93 1.96 39.20 1.55 1.57 31.40 3.00 0.53 10.60 171.80 201.01 22.33 3.44 125.53 12.30 2.95 DBST
5+160 20 7.00 1.75 1.84 36.80 1.40 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
5+180 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
5+200 20 7.47 1.87 1.96 39.20 1.49 1.57 31.40 3.00 0.53 10.60 171.70 200.89 22.32 3.43 125.43 12.29 2.95 DBST
5+220 20 8.60 2.15 2.01 40.20 1.72 1.61 32.20 3.00 0.53 10.60 175.70 205.57 22.84 3.51 129.39 12.73 3.04 DBST
5+240 20 8.20 2.05 2.10 42.00 1.64 1.68 33.60 3.00 0.53 10.60 183.00 214.11 23.79 3.66 136.62 13.53 3.20 DBST
5+260 20 7.62 1.91 1.98 39.60 1.52 1.58 31.60 3.00 0.53 10.60 173.20 202.64 22.52 3.46 126.92 12.45 2.99 DBST
5+280 20 7.90 1.98 1.95 39.00 1.58 1.55 31.00 3.00 0.53 10.60 170.20 199.13 22.13 3.40 123.95 12.12 2.92 DBST
5+300 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
5+320 20 8.30 2.08 1.92 38.40 1.66 1.53 30.60 3.00 0.53 10.60 168.00 196.56 21.84 3.36 121.77 11.88 2.87 DBST
5+340 20 8.02 2.01 2.05 41.00 1.60 1.63 32.60 3.00 0.53 10.60 178.20 208.49 23.17 3.56 131.87 13.00 3.10 DBST
5+360 20 7.04 1.76 1.89 37.80 1.41 1.51 30.20 3.00 0.53 10.60 165.60 193.75 21.53 3.31 119.39 11.62 2.82 DBST
5+380 20 7.75 1.94 1.85 37.00 1.55 1.48 29.60 3.00 0.53 10.60 162.90 190.59 21.18 3.26 116.72 11.32 2.76 DBST
5+400 20 7.65 1.91 1.93 38.60 1.53 1.54 30.80 3.00 0.53 10.60 169.00 197.73 21.97 3.38 122.76 11.99 2.89 DBST
5+420 20 8.20 2.05 1.98 39.60 1.64 1.59 31.80 3.00 0.53 10.60 173.50 203.00 22.56 3.47 127.22 12.49 2.99 DBST
5+440 20 7.58 1.90 1.98 39.60 1.52 1.58 31.60 3.00 0.53 10.60 172.80 202.18 22.46 3.46 126.52 12.41 2.98 DBST
5+460 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 160.80 188.14 20.90 3.22 114.64 11.09 2.71 DBST
5+480 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
5+500 20 7.70 1.93 2.04 40.80 1.54 1.63 32.60 3.00 0.53 10.60 178.00 208.26 23.14 3.56 131.67 12.98 3.09 DBST
5+520 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 162.00 189.54 21.06 3.24 115.83 11.22 2.74 DBST
5+540 20 7.94 1.99 1.87 37.40 1.59 1.50 30.00 3.00 0.53 10.60 164.40 192.35 21.37 3.29 118.21 11.48 2.79 DBST
5+560 20 7.71 1.93 1.96 39.20 1.54 1.57 31.40 3.00 0.53 10.60 171.50 200.66 22.30 3.43 125.24 12.27 2.95 DBST
5+580 20 7.84 1.96 1.95 39.00 1.57 1.56 31.20 3.00 0.53 10.60 170.50 199.49 22.17 3.41 124.25 12.16 2.93 DBST
5+600 20 7.97 1.99 1.98 39.60 1.59 1.58 31.60 3.00 0.53 10.60 173.10 202.53 22.50 3.46 126.82 12.44 2.98 DBST
5+620 20 8.60 2.15 2.07 41.40 1.72 1.66 33.20 3.00 0.53 10.60 180.70 211.42 23.49 3.61 134.34 13.28 3.15 DBST
5+640 20 7.00 1.75 1.95 39.00 1.40 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
5+660 20 7.19 1.80 1.78 35.60 1.44 1.42 28.40 3.00 0.53 10.60 156.90 183.57 20.40 3.14 110.78 10.66 2.63 DBST
5+680 20 7.24 1.81 1.81 36.20 1.45 1.45 29.00 3.00 0.53 10.60 159.30 186.38 20.71 3.19 113.16 10.92 2.68 DBST
5+700 20 7.00 1.75 1.78 35.60 1.40 1.43 28.60 3.00 0.53 10.60 157.40 184.16 20.46 3.15 111.28 10.71 2.64 DBST
5+720 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
5+740 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
234 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
5+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+780 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
5+800 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
5+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+840 20 7.49 1.87 1.81 36.20 1.50 1.45 29.00 3.00 0.53 10.60 159.90 187.08 20.79 3.20 113.75 10.99 2.69 DBST
5+860 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.90 187.08 20.79 3.20 113.75 10.99 2.69 DBST
5+880 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
5+900 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
5+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
5+940 20 8.15 2.04 1.90 38.00 1.63 1.52 30.40 3.00 0.53 10.60 166.50 194.81 21.65 3.33 120.29 11.72 2.84 DBST
5+960 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 166.50 194.81 21.65 3.33 120.29 11.72 2.84 DBST
5+980 20 7.74 1.94 1.85 37.00 1.55 1.48 29.60 3.00 0.53 10.60 162.40 190.01 21.11 3.25 116.23 11.26 2.75 DBST
6+000 20 8.60 2.15 2.05 41.00 1.72 1.64 32.80 3.00 0.53 10.60 178.40 208.73 23.19 3.57 132.07 13.02 3.10 DBST
6+020 20 7.72 1.93 2.04 40.80 1.54 1.63 32.60 3.00 0.53 10.60 178.20 208.49 23.17 3.56 131.87 13.00 3.10 DBST
6+040 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
6+060 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
6+080 20 8.03 2.01 2.03 40.60 1.61 1.63 32.60 3.00 0.53 10.60 177.30 207.44 23.05 3.55 130.98 12.90 3.08 DBST
6+100 20 8.20 2.05 2.03 40.60 1.64 1.63 32.60 3.00 0.53 10.60 177.30 207.44 23.05 3.55 130.98 12.90 3.08 DBST
6+120 20 7.60 1.90 1.98 39.60 1.52 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
6+140 20 7.47 1.87 1.89 37.80 1.49 1.51 30.20 3.00 0.53 10.60 165.70 193.87 21.54 3.31 119.49 11.63 2.82 DBST
6+160 20 7.90 1.98 1.93 38.60 1.58 1.54 30.80 3.00 0.53 10.60 168.70 197.38 21.93 3.37 122.46 11.96 2.89 DBST
6+180 20 7.42 1.86 1.92 38.40 1.48 1.53 30.60 3.00 0.53 10.60 168.20 196.79 21.87 3.36 121.97 11.90 2.88 DBST
6+200 20 8.20 2.05 1.96 39.20 1.64 1.56 31.20 3.00 0.53 10.60 171.20 200.30 22.26 3.42 124.94 12.23 2.94 DBST
6+220 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
6+240 20 7.21 1.80 1.93 38.60 1.44 1.54 30.80 3.00 0.53 10.60 169.10 197.85 21.98 3.38 122.86 12.00 2.90 DBST
6+260 20 7.36 1.84 1.82 36.40 1.47 1.46 29.20 3.00 0.53 10.60 160.70 188.02 20.89 3.21 114.54 11.08 2.71 DBST
6+280 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
6+300 20 7.36 1.84 1.80 36.00 1.47 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
6+320 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
6+340 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
6+360 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
6+380 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
6+400 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
6+420 20 7.56 1.89 1.97 39.40 1.51 1.58 31.60 3.00 0.53 10.60 172.60 201.94 22.44 3.45 126.32 12.39 2.97 DBST
6+440 20 7.82 1.96 1.93 38.60 1.56 1.54 30.80 3.00 0.53 10.60 168.80 197.50 21.94 3.38 122.56 11.97 2.89 DBST
6+460 20 8.90 2.23 2.10 42.00 1.78 1.67 33.40 3.00 0.53 10.60 182.20 213.17 23.69 3.64 135.83 13.44 3.18 DBST
6+480 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
6+500 20 7.73 1.93 2.08 41.60 1.55 1.67 33.40 3.00 0.53 10.60 181.30 212.12 23.57 3.63 134.94 13.34 3.16 DBST
6+520 20 7.00 1.75 1.84 36.80 1.40 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
6+540 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
6+560 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
6+580 20 7.48 1.87 1.81 36.20 1.50 1.45 29.00 3.00 0.53 10.60 159.80 186.97 20.77 3.20 113.65 10.98 2.69 DBST
235 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
6+600 20 8.20 2.05 1.96 39.20 1.64 1.57 31.40 3.00 0.53 10.60 171.80 201.01 22.33 3.44 125.53 12.30 2.95 DBST
6+620 20 7.25 1.81 1.93 38.60 1.45 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
6+640 20 8.20 2.05 1.93 38.60 1.64 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
6+660 20 8.39 2.10 2.08 41.60 1.68 1.66 33.20 3.00 0.53 10.60 180.90 211.65 23.52 3.62 134.54 13.30 3.15 DBST
6+680 20 8.60 2.15 2.13 42.60 1.72 1.70 34.00 3.00 0.53 10.60 184.90 216.33 24.04 3.70 138.50 13.74 3.24 DBST
6+700 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
6+720 20 8.01 2.00 2.08 41.60 1.60 1.66 33.20 3.00 0.53 10.60 181.10 211.89 23.54 3.62 134.74 13.32 3.16 DBST
6+740 20 7.80 1.95 1.98 39.60 1.56 1.58 31.60 3.00 0.53 10.60 173.10 202.53 22.50 3.46 126.82 12.44 2.98 DBST
6+760 20 7.73 1.93 1.94 38.80 1.55 1.56 31.20 3.00 0.53 10.60 170.30 199.25 22.14 3.41 124.05 12.13 2.92 DBST
6+780 20 7.00 1.75 1.84 36.80 1.40 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
6+800 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
6+820 20 7.34 1.84 1.91 38.20 1.47 1.53 30.60 3.00 0.53 10.60 167.40 195.86 21.76 3.35 121.18 11.81 2.86 DBST
6+840 20 7.57 1.89 1.87 37.40 1.51 1.49 29.80 3.00 0.53 10.60 164.10 192.00 21.33 3.28 117.91 11.45 2.79 DBST
6+860 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.70 188.02 20.89 3.21 114.54 11.08 2.71 DBST
6+880 20 7.29 1.82 1.79 35.80 1.46 1.43 28.60 3.00 0.53 10.60 157.90 184.74 20.53 3.16 111.77 10.77 2.65 DBST
6+900 20 7.00 1.75 1.79 35.80 1.40 1.43 28.60 3.00 0.53 10.60 157.90 184.74 20.53 3.16 111.77 10.77 2.65 DBST
6+920 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
6+940 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
6+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
6+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+000 20 7.17 1.79 1.77 35.40 1.43 1.42 28.40 3.00 0.53 10.60 156.70 183.34 20.37 3.13 110.58 10.64 2.62 DBST
7+020 20 8.90 2.23 2.01 40.20 1.78 1.61 32.20 3.00 0.53 10.60 175.70 205.57 22.84 3.51 129.39 12.73 3.04 DBST
7+040 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
7+060 20 7.54 1.89 2.06 41.20 1.51 1.65 33.00 3.00 0.53 10.60 179.40 209.90 23.32 3.59 133.06 13.13 3.12 DBST
7+080 20 7.04 1.76 1.83 36.60 1.41 1.46 29.20 3.00 0.53 10.60 160.80 188.14 20.90 3.22 114.64 11.09 2.71 DBST
7+100 20 7.02 1.76 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.60 182.05 20.23 3.11 109.49 10.52 2.60 DBST
7+120 20 7.00 1.75 1.76 35.20 1.40 1.40 28.00 3.00 0.53 10.60 155.20 181.58 20.18 3.10 109.10 10.47 2.59 DBST
7+140 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
7+160 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
7+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+200 20 7.63 1.91 1.83 36.60 1.53 1.47 29.40 3.00 0.53 10.60 161.30 188.72 20.97 3.23 115.14 11.14 2.72 DBST
7+220 20 8.20 2.05 1.98 39.60 1.64 1.59 31.80 3.00 0.53 10.60 173.30 202.76 22.53 3.47 127.02 12.46 2.99 DBST
7+240 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
7+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+300 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+360 20 7.33 1.83 1.79 35.80 1.47 1.44 28.80 3.00 0.53 10.60 158.30 185.21 20.58 3.17 112.17 10.81 2.66 DBST
7+380 20 7.00 1.75 1.79 35.80 1.40 1.44 28.80 3.00 0.53 10.60 158.30 185.21 20.58 3.17 112.17 10.81 2.66 DBST
7+400 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
7+420 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
236 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
7+440 20 7.85 1.96 2.06 41.20 1.57 1.65 33.00 3.00 0.53 10.60 179.50 210.02 23.34 3.59 133.16 13.15 3.12 DBST
7+460 20 7.00 1.75 1.86 37.20 1.40 1.49 29.80 3.00 0.53 10.60 163.50 191.30 21.26 3.27 117.32 11.39 2.77 DBST
7+480 20 7.86 1.97 1.86 37.20 1.57 1.49 29.80 3.00 0.53 10.60 163.60 191.41 21.27 3.27 117.41 11.40 2.77 DBST
7+500 20 8.60 2.15 2.06 41.20 1.72 1.65 33.00 3.00 0.53 10.60 179.60 210.13 23.35 3.59 133.25 13.16 3.13 DBST
7+520 20 7.98 2.00 2.08 41.60 1.60 1.66 33.20 3.00 0.53 10.60 180.80 211.54 23.50 3.62 134.44 13.29 3.15 DBST
7+540 20 7.00 1.75 1.88 37.60 1.40 1.50 30.00 3.00 0.53 10.60 164.80 192.82 21.42 3.30 118.60 11.53 2.80 DBST
7+560 20 8.17 2.04 1.90 38.00 1.63 1.52 30.40 3.00 0.53 10.60 166.70 195.04 21.67 3.33 120.48 11.74 2.84 DBST
7+580 20 7.86 1.97 2.01 40.20 1.57 1.60 32.00 3.00 0.53 10.60 175.30 205.10 22.79 3.51 129.00 12.68 3.03 DBST
7+600 20 8.20 2.05 2.01 40.20 1.64 1.61 32.20 3.00 0.53 10.60 175.60 205.45 22.83 3.51 129.29 12.72 3.04 DBST
7+620 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
7+640 20 7.64 1.91 1.83 36.60 1.53 1.47 29.40 3.00 0.53 10.60 161.40 188.84 20.98 3.23 115.24 11.15 2.73 DBST
7+660 20 7.81 1.95 1.93 38.60 1.56 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
7+680 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.10 190.83 21.20 3.26 116.92 11.34 2.76 DBST
7+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+720 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+740 20 8.90 2.23 1.99 39.80 1.78 1.59 31.80 3.00 0.53 10.60 174.00 203.58 22.62 3.48 127.71 12.54 3.00 DBST
7+760 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
7+780 20 8.28 2.07 2.15 43.00 1.66 1.72 34.40 3.00 0.53 10.60 186.80 218.56 24.28 3.74 140.38 13.95 3.28 DBST
7+800 20 7.00 1.75 1.91 38.20 1.40 1.53 30.60 3.00 0.53 10.60 167.80 196.33 21.81 3.36 121.57 11.86 2.87 DBST
7+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+840 20 7.50 1.88 1.82 36.40 1.50 1.45 29.00 3.00 0.53 10.60 160.00 187.20 20.80 3.20 113.85 11.00 2.70 DBST
7+860 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
7+880 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
7+900 20 7.28 1.82 1.85 37.00 1.46 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
7+920 20 8.15 2.04 1.93 38.60 1.63 1.55 31.00 3.00 0.53 10.60 169.30 198.08 22.01 3.39 123.06 12.02 2.90 DBST
7+940 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 166.50 194.81 21.65 3.33 120.29 11.72 2.84 DBST
7+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
7+980 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
8+000 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
8+020 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
8+040 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
8+060 20 7.37 1.84 1.80 36.00 1.47 1.44 28.80 3.00 0.53 10.60 158.70 185.68 20.63 3.17 112.56 10.86 2.67 DBST
8+080 20 8.60 2.15 2.00 40.00 1.72 1.60 32.00 3.00 0.53 10.60 174.70 204.40 22.71 3.49 128.40 12.62 3.02 DBST
8+100 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
8+120 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
8+140 20 7.71 1.93 2.04 40.80 1.54 1.63 32.60 3.00 0.53 10.60 178.10 208.38 23.15 3.56 131.77 12.99 3.09 DBST
8+160 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 162.10 189.66 21.07 3.24 115.93 11.23 2.74 DBST
8+180 20 7.78 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
8+200 20 8.60 2.15 2.05 41.00 1.72 1.64 32.80 3.00 0.53 10.60 178.80 209.20 23.24 3.58 132.46 13.07 3.11 DBST
8+220 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
8+240 20 7.36 1.84 2.00 40.00 1.47 1.60 32.00 3.00 0.53 10.60 174.60 204.28 22.70 3.49 128.30 12.61 3.02 DBST
8+260 20 7.63 1.91 1.88 37.60 1.53 1.50 30.00 3.00 0.53 10.60 164.90 192.93 21.44 3.30 118.70 11.54 2.80 DBST
237 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
8+280 20 7.00 1.75 1.83 36.60 1.40 1.47 29.40 3.00 0.53 10.60 161.30 188.72 20.97 3.23 115.14 11.14 2.72 DBST
8+300 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
8+320 20 7.38 1.85 1.92 38.40 1.48 1.53 30.60 3.00 0.53 10.60 167.80 196.33 21.81 3.36 121.57 11.86 2.87 DBST
8+340 20 8.20 2.05 1.95 39.00 1.64 1.56 31.20 3.00 0.53 10.60 170.80 199.84 22.20 3.42 124.54 12.19 2.93 DBST
8+360 20 8.15 2.04 2.05 41.00 1.63 1.64 32.80 3.00 0.53 10.60 178.50 208.85 23.21 3.57 132.17 13.04 3.10 DBST
8+380 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 166.50 194.81 21.65 3.33 120.29 11.72 2.84 DBST
8+400 20 7.83 1.96 1.86 37.20 1.57 1.49 29.80 3.00 0.53 10.60 163.30 191.06 21.23 3.27 117.12 11.36 2.77 DBST
8+420 20 7.00 1.75 1.86 37.20 1.40 1.49 29.80 3.00 0.53 10.60 163.30 191.06 21.23 3.27 117.12 11.36 2.77 DBST
8+440 20 8.46 2.12 1.94 38.80 1.69 1.55 31.00 3.00 0.53 10.60 169.60 198.43 22.05 3.39 123.35 12.06 2.91 DBST
8+460 20 8.90 2.23 2.18 43.60 1.78 1.74 34.80 3.00 0.53 10.60 188.60 220.66 24.52 3.77 142.16 14.15 3.32 DBST
8+480 20 8.80 2.20 2.22 44.40 1.76 1.77 35.40 3.00 0.53 10.60 192.00 224.64 24.96 3.84 145.53 14.52 3.40 DBST
8+500 20 7.00 1.75 1.98 39.60 1.40 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
8+520 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
8+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
8+560 20 7.66 1.92 1.84 36.80 1.53 1.47 29.40 3.00 0.53 10.60 161.60 189.07 21.01 3.23 115.43 11.18 2.73 DBST
8+580 20 8.20 2.05 1.99 39.80 1.64 1.59 31.80 3.00 0.53 10.60 173.60 203.11 22.57 3.47 127.31 12.50 2.99 DBST
8+600 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
8+620 20 8.04 2.01 2.03 40.60 1.61 1.63 32.60 3.00 0.53 10.60 177.40 207.56 23.06 3.55 131.08 12.91 3.08 DBST
8+640 20 7.00 1.75 1.88 37.60 1.40 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
8+660 20 7.06 1.77 1.76 35.20 1.41 1.41 28.20 3.00 0.53 10.60 155.60 182.05 20.23 3.11 109.49 10.52 2.60 DBST
8+680 20 7.88 1.97 1.87 37.40 1.58 1.50 30.00 3.00 0.53 10.60 164.40 192.35 21.37 3.29 118.21 11.48 2.79 DBST
8+700 20 7.00 1.75 1.86 37.20 1.40 1.49 29.80 3.00 0.53 10.60 163.80 191.65 21.29 3.28 117.61 11.42 2.78 DBST
8+720 20 8.13 2.03 1.89 37.80 1.63 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
8+740 20 7.00 1.75 1.89 37.80 1.40 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
8+760 20 8.25 2.06 1.91 38.20 1.65 1.53 30.60 3.00 0.53 10.60 167.50 195.98 21.78 3.35 121.28 11.83 2.86 DBST
8+780 20 8.90 2.23 2.15 43.00 1.78 1.72 34.40 3.00 0.53 10.60 186.50 218.21 24.25 3.73 140.09 13.92 3.28 DBST
8+800 20 8.77 2.19 2.21 44.20 1.75 1.77 35.40 3.00 0.53 10.60 191.70 224.29 24.92 3.83 145.23 14.49 3.39 DBST
8+820 20 7.00 1.75 1.97 39.40 1.40 1.58 31.60 3.00 0.53 10.60 172.70 202.06 22.45 3.45 126.42 12.40 2.97 DBST
8+840 20 7.16 1.79 1.77 35.40 1.43 1.42 28.40 3.00 0.53 10.60 156.60 183.22 20.36 3.13 110.48 10.63 2.62 DBST
8+860 20 8.20 2.05 1.92 38.40 1.64 1.54 30.80 3.00 0.53 10.60 168.60 197.26 21.92 3.37 122.36 11.95 2.88 DBST
8+880 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
8+900 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
8+920 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
8+940 20 8.41 2.10 1.93 38.60 1.68 1.54 30.80 3.00 0.53 10.60 169.10 197.85 21.98 3.38 122.86 12.00 2.90 DBST
8+960 20 7.27 1.82 1.96 39.20 1.45 1.57 31.40 3.00 0.53 10.60 171.80 201.01 22.33 3.44 125.53 12.30 2.95 DBST
8+980 20 7.00 1.75 1.79 35.80 1.40 1.43 28.60 3.00 0.53 10.60 157.70 184.51 20.50 3.15 111.57 10.75 2.64 DBST
9+000 20 7.22 1.81 1.78 35.60 1.44 1.42 28.40 3.00 0.53 10.60 157.20 183.92 20.44 3.14 111.08 10.69 2.63 DBST
9+020 20 8.60 2.15 1.98 39.60 1.72 1.58 31.60 3.00 0.53 10.60 173.20 202.64 22.52 3.46 126.92 12.45 2.99 DBST
9+040 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
9+060 20 7.88 1.97 2.06 41.20 1.58 1.65 33.00 3.00 0.53 10.60 179.80 210.37 23.37 3.60 133.45 13.18 3.13 DBST
9+080 20 7.00 1.75 1.86 37.20 1.40 1.49 29.80 3.00 0.53 10.60 163.80 191.65 21.29 3.28 117.61 11.42 2.78 DBST
9+100 20 7.16 1.79 1.77 35.40 1.43 1.42 28.40 3.00 0.53 10.60 156.60 183.22 20.36 3.13 110.48 10.63 2.62 DBST
238 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
9+120 20 8.90 2.23 2.01 40.20 1.78 1.61 32.20 3.00 0.53 10.60 175.60 205.45 22.83 3.51 129.29 12.72 3.04 DBST
9+140 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
9+160 20 8.36 2.09 2.16 43.20 1.67 1.73 34.60 3.00 0.53 10.60 187.60 219.49 24.39 3.75 141.17 14.04 3.30 DBST
9+180 20 7.00 1.75 1.92 38.40 1.40 1.54 30.80 3.00 0.53 10.60 168.60 197.26 21.92 3.37 122.36 11.95 2.88 DBST
9+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+220 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
9+240 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
9+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+280 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
9+300 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
9+320 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
9+340 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
9+360 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
9+380 20 7.03 1.76 1.76 35.20 1.41 1.41 28.20 3.00 0.53 10.60 155.30 181.70 20.19 3.11 109.20 10.48 2.59 DBST
9+400 20 8.08 2.02 1.89 37.80 1.62 1.52 30.40 3.00 0.53 10.60 166.10 194.34 21.59 3.32 119.89 11.67 2.83 DBST
9+420 20 8.60 2.15 2.09 41.80 1.72 1.67 33.40 3.00 0.53 10.60 181.80 212.71 23.63 3.64 135.43 13.40 3.17 DBST
9+440 20 8.20 2.05 2.10 42.00 1.64 1.68 33.60 3.00 0.53 10.60 183.00 214.11 23.79 3.66 136.62 13.53 3.20 DBST
9+460 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
9+480 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
9+500 20 8.11 2.03 1.99 39.80 1.62 1.59 31.80 3.00 0.53 10.60 174.10 203.70 22.63 3.48 127.81 12.55 3.01 DBST
9+520 20 7.00 1.75 1.89 37.80 1.40 1.51 30.20 3.00 0.53 10.60 166.10 194.34 21.59 3.32 119.89 11.67 2.83 DBST
9+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+560 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+580 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+600 20 8.07 2.02 1.89 37.80 1.61 1.51 30.20 3.00 0.53 10.60 165.70 193.87 21.54 3.31 119.49 11.63 2.82 DBST
9+620 20 8.60 2.15 2.09 41.80 1.72 1.67 33.40 3.00 0.53 10.60 181.70 212.59 23.62 3.63 135.33 13.39 3.17 DBST
9+640 20 7.80 1.95 2.05 41.00 1.56 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
9+660 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
9+680 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
9+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+720 20 7.38 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 158.80 185.80 20.64 3.18 112.66 10.87 2.67 DBST
9+740 20 7.56 1.89 1.87 37.40 1.51 1.50 30.00 3.00 0.53 10.60 164.40 192.35 21.37 3.29 118.21 11.48 2.79 DBST
9+760 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
9+780 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
9+800 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
9+820 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
9+840 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
9+860 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
9+880 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
9+900 20 7.87 1.97 1.86 37.20 1.57 1.49 29.80 3.00 0.53 10.60 163.70 191.53 21.28 3.27 117.51 11.41 2.78 DBST
9+920 20 7.08 1.77 1.87 37.40 1.42 1.50 30.00 3.00 0.53 10.60 164.50 192.47 21.39 3.29 118.31 11.50 2.79 DBST
9+940 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.80 182.29 20.25 3.12 109.69 10.54 2.60 DBST
239 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
9+960 20 7.12 1.78 1.77 35.40 1.42 1.41 28.20 3.00 0.53 10.60 156.20 182.75 20.31 3.12 110.09 10.58 2.61 DBST
9+980 20 7.90 1.98 1.88 37.60 1.58 1.50 30.00 3.00 0.53 10.60 165.20 193.28 21.48 3.30 119.00 11.57 2.81 DBST
10+000 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
10+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+040 20 7.50 1.88 1.82 36.40 1.50 1.45 29.00 3.00 0.53 10.60 160.00 187.20 20.80 3.20 113.85 11.00 2.70 DBST
10+060 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
10+080 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
10+100 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
10+120 20 7.00 1.75 1.82 36.40 1.40 1.45 29.00 3.00 0.53 10.60 160.00 187.20 20.80 3.20 113.85 11.00 2.70 DBST
10+140 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+160 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+300 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+340 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
10+360 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
10+380 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
10+400 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+440 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
10+460 20 7.23 1.81 1.90 38.00 1.45 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
10+480 20 7.90 1.98 1.90 38.00 1.58 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
10+500 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
10+520 20 7.12 1.78 1.88 37.60 1.42 1.50 30.00 3.00 0.53 10.60 165.20 193.28 21.48 3.30 119.00 11.57 2.81 DBST
10+540 20 7.21 1.80 1.79 35.80 1.44 1.43 28.60 3.00 0.53 10.60 158.30 185.21 20.58 3.17 112.17 10.81 2.66 DBST
10+560 20 8.03 2.01 1.91 38.20 1.61 1.53 30.60 3.00 0.53 10.60 167.40 195.86 21.76 3.35 121.18 11.81 2.86 DBST
10+580 20 7.00 1.75 1.88 37.60 1.40 1.51 30.20 3.00 0.53 10.60 165.30 193.40 21.49 3.31 119.10 11.58 2.81 DBST
10+600 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+660 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
10+700 20 7.72 1.93 1.84 36.80 1.54 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
10+720 20 8.33 2.08 2.01 40.20 1.67 1.61 32.20 3.00 0.53 10.60 175.50 205.34 22.82 3.51 129.20 12.71 3.04 DBST
10+740 20 7.60 1.90 1.99 39.80 1.52 1.60 32.00 3.00 0.53 10.60 174.30 203.93 22.66 3.49 128.01 12.57 3.01 DBST
10+760 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
10+780 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
240 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
10+800 20 7.52 1.88 1.89 37.80 1.50 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
10+820 20 7.55 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 165.70 193.87 21.54 3.31 119.49 11.63 2.82 DBST
10+840 20 7.90 1.98 1.94 38.80 1.58 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
10+860 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
10+880 20 7.45 1.86 1.92 38.40 1.49 1.54 30.80 3.00 0.53 10.60 168.50 197.15 21.91 3.37 122.27 11.94 2.88 DBST
10+900 20 7.37 1.84 1.85 37.00 1.47 1.48 29.60 3.00 0.53 10.60 163.20 190.94 21.22 3.26 117.02 11.35 2.77 DBST
10+920 20 8.20 2.05 1.95 39.00 1.64 1.56 31.20 3.00 0.53 10.60 170.70 199.72 22.19 3.41 124.44 12.18 2.93 DBST
10+940 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
10+960 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
10+980 20 7.76 1.94 1.96 39.20 1.55 1.57 31.40 3.00 0.53 10.60 171.60 200.77 22.31 3.43 125.33 12.28 2.95 DBST
11+000 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 162.60 190.24 21.14 3.25 116.42 11.29 2.75 DBST
11+020 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+040 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+060 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+080 20 7.73 1.93 1.84 36.80 1.55 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
11+100 20 7.80 1.95 1.94 38.80 1.56 1.56 31.20 3.00 0.53 10.60 170.30 199.25 22.14 3.41 124.05 12.13 2.92 DBST
11+120 20 8.16 2.04 2.00 40.00 1.63 1.60 32.00 3.00 0.53 10.60 174.60 204.28 22.70 3.49 128.30 12.61 3.02 DBST
11+140 20 8.60 2.15 2.10 42.00 1.72 1.68 33.60 3.00 0.53 10.60 182.60 213.64 23.74 3.65 136.22 13.49 3.19 DBST
11+160 20 7.59 1.90 2.03 40.60 1.52 1.62 32.40 3.00 0.53 10.60 176.90 206.97 23.00 3.54 130.58 12.86 3.07 DBST
11+180 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 160.90 188.25 20.92 3.22 114.74 11.10 2.71 DBST
11+200 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
11+220 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
11+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+280 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
11+300 20 8.09 2.02 2.00 40.00 1.62 1.60 32.00 3.00 0.53 10.60 174.90 204.63 22.74 3.50 128.60 12.64 3.02 DBST
11+320 20 8.54 2.14 2.08 41.60 1.71 1.67 33.40 3.00 0.53 10.60 181.30 212.12 23.57 3.63 134.94 13.34 3.16 DBST
11+340 20 7.00 1.75 1.95 39.00 1.40 1.56 31.20 3.00 0.53 10.60 170.40 199.37 22.15 3.41 124.15 12.14 2.92 DBST
11+360 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+380 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+400 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+420 20 7.10 1.78 1.87 37.40 1.42 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
11+440 20 8.14 2.04 1.91 38.20 1.63 1.53 30.60 3.00 0.53 10.60 167.40 195.86 21.76 3.35 121.18 11.81 2.86 DBST
11+460 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 178.40 208.73 23.19 3.57 132.07 13.02 3.10 DBST
11+480 20 7.89 1.97 2.01 40.20 1.58 1.61 32.20 3.00 0.53 10.60 175.90 205.80 22.87 3.52 129.59 12.75 3.04 DBST
11+500 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 172.90 202.29 22.48 3.46 126.62 12.42 2.98 DBST
11+520 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
11+540 20 7.70 1.93 1.84 36.80 1.54 1.47 29.40 3.00 0.53 10.60 162.00 189.54 21.06 3.24 115.83 11.22 2.74 DBST
11+560 20 8.20 2.05 1.99 39.80 1.64 1.59 31.80 3.00 0.53 10.60 174.00 203.58 22.62 3.48 127.71 12.54 3.00 DBST
11+580 20 7.90 1.98 2.02 40.40 1.58 1.61 32.20 3.00 0.53 10.60 176.00 205.92 22.88 3.52 129.69 12.76 3.05 DBST
11+600 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
11+620 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
241 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
11+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+660 20 7.09 1.77 1.76 35.20 1.42 1.41 28.20 3.00 0.53 10.60 155.90 182.40 20.27 3.12 109.79 10.55 2.60 DBST
11+680 20 8.20 2.05 1.91 38.20 1.64 1.53 30.60 3.00 0.53 10.60 167.90 196.44 21.83 3.36 121.67 11.87 2.87 DBST
11+700 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
11+720 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
11+740 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+760 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+780 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+800 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
11+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+840 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
11+860 20 7.17 1.79 1.77 35.40 1.43 1.42 28.40 3.00 0.53 10.60 156.70 183.34 20.37 3.13 110.58 10.64 2.62 DBST
11+880 20 8.20 2.05 1.92 38.40 1.64 1.54 30.80 3.00 0.53 10.60 168.70 197.38 21.93 3.37 122.46 11.96 2.89 DBST
11+900 20 7.74 1.94 2.00 40.00 1.55 1.60 32.00 3.00 0.53 10.60 174.40 204.05 22.67 3.49 128.11 12.58 3.01 DBST
11+920 20 8.20 2.05 2.00 40.00 1.64 1.60 32.00 3.00 0.53 10.60 174.40 204.05 22.67 3.49 128.11 12.58 3.01 DBST
11+940 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
11+960 20 7.11 1.78 1.92 38.40 1.42 1.53 30.60 3.00 0.53 10.60 168.10 196.68 21.85 3.36 121.87 11.89 2.87 DBST
11+980 20 8.60 2.15 1.97 39.40 1.72 1.57 31.40 3.00 0.53 10.60 172.10 201.36 22.37 3.44 125.83 12.33 2.96 DBST
12+000 20 7.27 1.82 1.99 39.80 1.45 1.59 31.80 3.00 0.53 10.60 173.70 203.23 22.58 3.47 127.41 12.51 3.00 DBST
12+020 20 7.06 1.77 1.80 36.00 1.41 1.43 28.60 3.00 0.53 10.60 158.30 185.21 20.58 3.17 112.17 10.81 2.66 DBST
12+040 20 7.37 1.84 1.81 36.20 1.47 1.44 28.80 3.00 0.53 10.60 159.30 186.38 20.71 3.19 113.16 10.92 2.68 DBST
12+060 20 8.60 2.15 2.00 40.00 1.72 1.60 32.00 3.00 0.53 10.60 174.70 204.40 22.71 3.49 128.40 12.62 3.02 DBST
12+080 20 8.67 2.17 2.16 43.20 1.73 1.73 34.60 3.00 0.53 10.60 187.70 219.61 24.40 3.75 141.27 14.05 3.30 DBST
12+100 20 7.76 1.94 2.06 41.20 1.55 1.64 32.80 3.00 0.53 10.60 179.30 209.78 23.31 3.59 132.96 13.12 3.12 DBST
12+120 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 162.60 190.24 21.14 3.25 116.42 11.29 2.75 DBST
12+140 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
12+160 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
12+180 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
12+200 20 7.33 1.83 1.91 38.20 1.47 1.53 30.60 3.00 0.53 10.60 167.30 195.74 21.75 3.35 121.08 11.80 2.86 DBST
12+220 20 7.00 1.75 1.79 35.80 1.40 1.44 28.80 3.00 0.53 10.60 158.30 185.21 20.58 3.17 112.17 10.81 2.66 DBST
12+240 20 7.34 1.84 1.80 36.00 1.47 1.44 28.80 3.00 0.53 10.60 158.40 185.33 20.59 3.17 112.27 10.82 2.66 DBST
12+260 20 7.80 1.95 1.90 38.00 1.56 1.52 30.40 3.00 0.53 10.60 166.40 194.69 21.63 3.33 120.19 11.70 2.84 DBST
12+280 20 7.45 1.86 1.91 38.20 1.49 1.53 30.60 3.00 0.53 10.60 167.50 195.98 21.78 3.35 121.28 11.83 2.86 DBST
12+300 20 7.66 1.92 1.89 37.80 1.53 1.51 30.20 3.00 0.53 10.60 166.10 194.34 21.59 3.32 119.89 11.67 2.83 DBST
12+320 20 7.90 1.98 1.95 39.00 1.58 1.56 31.20 3.00 0.53 10.60 170.60 199.60 22.18 3.41 124.34 12.17 2.93 DBST
12+340 20 7.88 1.97 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 172.80 202.18 22.46 3.46 126.52 12.41 2.98 DBST
12+360 20 7.00 1.75 1.86 37.20 1.40 1.49 29.80 3.00 0.53 10.60 163.80 191.65 21.29 3.28 117.61 11.42 2.78 DBST
12+380 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
12+400 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
12+420 20 7.03 1.76 1.91 38.20 1.41 1.53 30.60 3.00 0.53 10.60 167.30 195.74 21.75 3.35 121.08 11.80 2.86 DBST
12+440 20 7.60 1.90 1.83 36.60 1.52 1.47 29.40 3.00 0.53 10.60 161.30 188.72 20.97 3.23 115.14 11.14 2.72 DBST
12+460 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
242 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
12+480 20 7.90 1.98 1.94 38.80 1.58 1.55 31.00 3.00 0.53 10.60 170.00 198.90 22.10 3.40 123.75 12.10 2.92 DBST
12+500 20 7.64 1.91 1.95 39.00 1.53 1.56 31.20 3.00 0.53 10.60 170.40 199.37 22.15 3.41 124.15 12.14 2.92 DBST
12+520 20 7.55 1.89 1.90 38.00 1.51 1.52 30.40 3.00 0.53 10.60 166.90 195.27 21.70 3.34 120.68 11.76 2.85 DBST
12+540 20 7.90 1.98 1.94 38.80 1.58 1.55 31.00 3.00 0.53 10.60 169.50 198.32 22.04 3.39 123.26 12.05 2.90 DBST
12+560 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
12+580 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
12+600 20 7.59 1.90 1.94 38.80 1.52 1.55 31.00 3.00 0.53 10.60 169.90 198.78 22.09 3.40 123.65 12.09 2.91 DBST
12+620 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 160.90 188.25 20.92 3.22 114.74 11.10 2.71 DBST
12+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
12+660 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
12+680 20 7.90 1.98 1.94 38.80 1.58 1.55 31.00 3.00 0.53 10.60 169.60 198.43 22.05 3.39 123.35 12.06 2.91 DBST
12+700 20 7.01 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.10 192.00 21.33 3.28 117.91 11.45 2.79 DBST
12+720 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.10 192.00 21.33 3.28 117.91 11.45 2.79 DBST
12+740 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
12+760 20 7.86 1.97 1.98 39.60 1.57 1.58 31.60 3.00 0.53 10.60 172.60 201.94 22.44 3.45 126.32 12.39 2.97 DBST
12+780 20 7.56 1.89 1.93 38.60 1.51 1.54 30.80 3.00 0.53 10.60 169.20 197.96 22.00 3.38 122.96 12.01 2.90 DBST
12+800 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
12+820 20 7.08 1.77 1.83 36.60 1.42 1.47 29.40 3.00 0.53 10.60 161.40 188.84 20.98 3.23 115.24 11.15 2.73 DBST
12+840 20 7.87 1.97 1.87 37.40 1.57 1.50 30.00 3.00 0.53 10.60 164.50 192.47 21.39 3.29 118.31 11.50 2.79 DBST
12+860 20 8.60 2.15 2.06 41.20 1.72 1.65 33.00 3.00 0.53 10.60 179.70 210.25 23.36 3.59 133.35 13.17 3.13 DBST
12+880 20 7.94 1.99 2.07 41.40 1.59 1.66 33.20 3.00 0.53 10.60 180.40 211.07 23.45 3.61 134.05 13.24 3.14 DBST
12+900 20 7.90 1.98 1.99 39.80 1.58 1.59 31.80 3.00 0.53 10.60 173.40 202.88 22.54 3.47 127.12 12.47 2.99 DBST
12+920 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
12+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
12+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
12+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+000 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
13+020 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
13+040 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
13+060 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+080 20 7.47 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.70 186.85 20.76 3.19 113.55 10.97 2.69 DBST
13+100 20 7.80 1.95 1.91 38.20 1.56 1.53 30.60 3.00 0.53 10.60 167.70 196.21 21.80 3.35 121.47 11.85 2.86 DBST
13+120 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
13+140 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
13+160 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+260 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
13+280 20 7.20 1.80 1.89 37.80 1.44 1.51 30.20 3.00 0.53 10.60 166.00 194.22 21.58 3.32 119.79 11.66 2.83 DBST
13+300 20 7.00 1.75 1.78 35.60 1.40 1.42 28.40 3.00 0.53 10.60 157.00 183.69 20.41 3.14 110.88 10.67 2.63 DBST
243 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
13+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+360 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+380 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
13+400 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
13+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+440 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
13+460 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
13+480 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
13+500 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
13+520 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
13+540 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
13+560 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
13+580 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
13+600 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
13+620 20 7.40 1.85 1.88 37.60 1.48 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
13+640 20 7.01 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.10 186.15 20.68 3.18 112.96 10.90 2.68 DBST
13+660 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.10 195.51 21.72 3.34 120.88 11.78 2.85 DBST
13+680 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
13+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+720 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+740 20 7.72 1.93 1.84 36.80 1.54 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
13+760 20 8.20 2.05 1.99 39.80 1.64 1.59 31.80 3.00 0.53 10.60 174.20 203.81 22.65 3.48 127.91 12.56 3.01 DBST
13+780 20 7.90 1.98 2.02 40.40 1.58 1.61 32.20 3.00 0.53 10.60 176.00 205.92 22.88 3.52 129.69 12.76 3.05 DBST
13+800 20 7.40 1.85 1.92 38.40 1.48 1.53 30.60 3.00 0.53 10.60 168.00 196.56 21.84 3.36 121.77 11.88 2.87 DBST
13+820 20 8.20 2.05 1.95 39.00 1.64 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
13+840 20 8.19 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 178.90 209.31 23.26 3.58 132.56 13.08 3.11 DBST
13+860 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 166.90 195.27 21.70 3.34 120.68 11.76 2.85 DBST
13+880 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
13+900 20 7.50 1.88 1.82 36.40 1.50 1.45 29.00 3.00 0.53 10.60 160.00 187.20 20.80 3.20 113.85 11.00 2.70 DBST
13+920 20 7.90 1.98 1.93 38.60 1.58 1.54 30.80 3.00 0.53 10.60 169.00 197.73 21.97 3.38 122.76 11.99 2.89 DBST
13+940 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
13+960 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
13+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+000 20 7.74 1.94 1.85 37.00 1.55 1.48 29.60 3.00 0.53 10.60 162.40 190.01 21.11 3.25 116.23 11.26 2.75 DBST
14+020 20 7.03 1.76 1.85 37.00 1.41 1.48 29.60 3.00 0.53 10.60 162.70 190.36 21.15 3.25 116.52 11.30 2.75 DBST
14+040 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.30 181.70 20.19 3.11 109.20 10.48 2.59 DBST
14+060 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
14+080 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
14+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+120 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+140 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
244 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
14+160 20 7.40 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
14+180 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
14+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+280 20 7.58 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 160.80 188.14 20.90 3.22 114.64 11.09 2.71 DBST
14+300 20 7.84 1.96 1.93 38.60 1.57 1.55 31.00 3.00 0.53 10.60 169.20 197.96 22.00 3.38 122.96 12.01 2.90 DBST
14+320 20 7.90 1.98 1.97 39.40 1.58 1.58 31.60 3.00 0.53 10.60 172.40 201.71 22.41 3.45 126.13 12.36 2.97 DBST
14+340 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
14+360 20 7.42 1.86 1.92 38.40 1.48 1.53 30.60 3.00 0.53 10.60 168.20 196.79 21.87 3.36 121.97 11.90 2.88 DBST
14+380 20 7.80 1.95 1.91 38.20 1.56 1.52 30.40 3.00 0.53 10.60 167.20 195.62 21.74 3.34 120.98 11.79 2.85 DBST
14+400 20 7.90 1.98 1.97 39.40 1.58 1.57 31.40 3.00 0.53 10.60 172.00 201.24 22.36 3.44 125.73 12.32 2.96 DBST
14+420 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
14+440 20 7.53 1.88 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.30 187.55 20.84 3.21 114.15 11.03 2.70 DBST
14+460 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 165.90 194.10 21.57 3.32 119.69 11.65 2.82 DBST
14+480 20 8.13 2.03 1.96 39.20 1.63 1.57 31.40 3.00 0.53 10.60 171.90 201.12 22.35 3.44 125.63 12.31 2.96 DBST
14+500 20 7.00 1.75 1.89 37.80 1.40 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
14+520 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+560 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
14+580 20 7.87 1.97 1.98 39.60 1.57 1.58 31.60 3.00 0.53 10.60 172.70 202.06 22.45 3.45 126.42 12.40 2.97 DBST
14+600 20 7.21 1.80 1.89 37.80 1.44 1.51 30.20 3.00 0.53 10.60 165.80 193.99 21.55 3.32 119.59 11.64 2.82 DBST
14+620 20 8.60 2.15 1.98 39.60 1.72 1.58 31.60 3.00 0.53 10.60 173.10 202.53 22.50 3.46 126.82 12.44 2.98 DBST
14+640 20 8.02 2.01 2.08 41.60 1.60 1.66 33.20 3.00 0.53 10.60 181.20 212.00 23.56 3.62 134.84 13.33 3.16 DBST
14+660 20 7.00 1.75 1.88 37.60 1.40 1.50 30.00 3.00 0.53 10.60 165.20 193.28 21.48 3.30 119.00 11.57 2.81 DBST
14+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+720 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+740 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+760 20 7.68 1.92 1.84 36.80 1.54 1.47 29.40 3.00 0.53 10.60 161.80 189.31 21.03 3.24 115.63 11.20 2.73 DBST
14+780 20 8.20 2.05 1.99 39.80 1.64 1.59 31.80 3.00 0.53 10.60 173.80 203.35 22.59 3.48 127.51 12.52 3.00 DBST
14+800 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
14+820 20 8.11 2.03 2.04 40.80 1.62 1.63 32.60 3.00 0.53 10.60 178.10 208.38 23.15 3.56 131.77 12.99 3.09 DBST
14+840 20 7.00 1.75 1.89 37.80 1.40 1.51 30.20 3.00 0.53 10.60 166.10 194.34 21.59 3.32 119.89 11.67 2.83 DBST
14+860 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
14+880 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
14+900 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
14+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
14+980 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
245 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
15+000 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
15+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
15+040 20 7.43 1.86 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.30 186.38 20.71 3.19 113.16 10.92 2.68 DBST
15+060 20 8.60 2.15 2.01 40.20 1.72 1.61 32.20 3.00 0.53 10.60 175.30 205.10 22.79 3.51 129.00 12.68 3.03 DBST
15+080 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
15+100 20 7.01 1.75 1.95 39.00 1.40 1.56 31.20 3.00 0.53 10.60 171.10 200.19 22.24 3.42 124.84 12.22 2.94 DBST
15+120 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.10 195.51 21.72 3.34 120.88 11.78 2.85 DBST
15+140 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
15+160 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
15+180 20 8.35 2.09 1.92 38.40 1.67 1.54 30.80 3.00 0.53 10.60 168.50 197.15 21.91 3.37 122.27 11.94 2.88 DBST
15+200 20 8.60 2.15 2.12 42.40 1.72 1.70 34.00 3.00 0.53 10.60 184.50 215.87 23.99 3.69 138.11 13.70 3.23 DBST
15+220 20 8.14 2.04 2.10 42.00 1.63 1.68 33.60 3.00 0.53 10.60 182.40 213.41 23.71 3.65 136.03 13.46 3.19 DBST
15+240 20 7.94 1.99 2.02 40.40 1.59 1.61 32.20 3.00 0.53 10.60 175.80 205.69 22.85 3.52 129.49 12.74 3.04 DBST
15+260 20 8.60 2.15 2.07 41.40 1.72 1.66 33.20 3.00 0.53 10.60 180.40 211.07 23.45 3.61 134.05 13.24 3.14 DBST
15+280 20 8.38 2.10 2.13 42.60 1.68 1.70 34.00 3.00 0.53 10.60 184.80 216.22 24.02 3.70 138.40 13.73 3.24 DBST
15+300 20 8.20 2.05 2.08 41.60 1.64 1.66 33.20 3.00 0.53 10.60 180.80 211.54 23.50 3.62 134.44 13.29 3.15 DBST
15+320 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
15+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
15+360 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
15+380 20 8.28 2.07 1.91 38.20 1.66 1.53 30.60 3.00 0.53 10.60 167.80 196.33 21.81 3.36 121.57 11.86 2.87 DBST
15+400 20 8.60 2.15 2.11 42.20 1.72 1.69 33.80 3.00 0.53 10.60 183.80 215.05 23.89 3.68 137.41 13.62 3.22 DBST
15+420 20 8.24 2.06 2.11 42.20 1.65 1.69 33.80 3.00 0.53 10.60 183.40 214.58 23.84 3.67 137.02 13.57 3.21 DBST
15+440 20 8.20 2.05 2.06 41.20 1.64 1.65 33.00 3.00 0.53 10.60 179.40 209.90 23.32 3.59 133.06 13.13 3.12 DBST
15+460 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
15+480 20 8.02 2.01 2.03 40.60 1.60 1.62 32.40 3.00 0.53 10.60 177.20 207.32 23.04 3.54 130.88 12.89 3.07 DBST
15+500 20 7.90 1.98 2.00 40.00 1.58 1.59 31.80 3.00 0.53 10.60 174.20 203.81 22.65 3.48 127.91 12.56 3.01 DBST
15+520 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
15+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
15+560 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
15+580 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
15+600 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
15+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
15+640 20 7.65 1.91 1.83 36.60 1.53 1.47 29.40 3.00 0.53 10.60 161.50 188.96 21.00 3.23 115.34 11.17 2.73 DBST
15+660 20 7.00 1.75 1.83 36.60 1.40 1.47 29.40 3.00 0.53 10.60 161.50 188.96 21.00 3.23 115.34 11.17 2.73 DBST
15+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
15+700 20 7.13 1.78 1.77 35.40 1.43 1.42 28.40 3.00 0.53 10.60 156.30 182.87 20.32 3.13 110.19 10.59 2.61 DBST
15+720 20 7.80 1.95 1.87 37.40 1.56 1.50 30.00 3.00 0.53 10.60 164.30 192.23 21.36 3.29 118.11 11.47 2.79 DBST
15+740 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
15+760 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
15+780 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
15+800 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
15+820 20 8.01 2.00 1.99 39.80 1.60 1.59 31.80 3.00 0.53 10.60 174.10 203.70 22.63 3.48 127.81 12.55 3.01 DBST
246 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
15+840 20 7.84 1.96 1.98 39.60 1.57 1.59 31.80 3.00 0.53 10.60 173.50 203.00 22.56 3.47 127.22 12.49 2.99 DBST
15+860 20 7.66 1.92 1.94 38.80 1.53 1.55 31.00 3.00 0.53 10.60 170.00 198.90 22.10 3.40 123.75 12.10 2.92 DBST
15+880 20 7.48 1.87 1.90 38.00 1.50 1.52 30.40 3.00 0.53 10.60 166.40 194.69 21.63 3.33 120.19 11.70 2.84 DBST
15+900 20 7.31 1.83 1.85 37.00 1.46 1.48 29.60 3.00 0.53 10.60 162.90 190.59 21.18 3.26 116.72 11.32 2.76 DBST
15+920 20 7.90 1.98 1.91 38.20 1.58 1.52 30.40 3.00 0.53 10.60 167.10 195.51 21.72 3.34 120.88 11.78 2.85 DBST
15+940 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
15+960 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
15+980 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
16+000 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
16+020 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
16+040 20 7.66 1.92 1.99 39.80 1.53 1.59 31.80 3.00 0.53 10.60 173.60 203.11 22.57 3.47 127.31 12.50 2.99 DBST
16+060 20 7.56 1.89 1.91 38.20 1.51 1.52 30.40 3.00 0.53 10.60 167.20 195.62 21.74 3.34 120.98 11.79 2.85 DBST
16+080 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
16+100 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
16+120 20 7.10 1.78 1.77 35.40 1.42 1.41 28.20 3.00 0.53 10.60 156.00 182.52 20.28 3.12 109.89 10.56 2.61 DBST
16+140 20 7.50 1.88 1.83 36.60 1.50 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
16+160 20 7.28 1.82 1.85 37.00 1.46 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
16+180 20 8.90 2.23 2.03 40.60 1.78 1.62 32.40 3.00 0.53 10.60 176.80 206.86 22.98 3.54 130.48 12.85 3.06 DBST
16+200 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
16+220 20 8.02 2.01 2.12 42.40 1.60 1.69 33.80 3.00 0.53 10.60 184.20 215.51 23.95 3.68 137.81 13.66 3.23 DBST
16+240 20 7.00 1.75 1.88 37.60 1.40 1.50 30.00 3.00 0.53 10.60 165.20 193.28 21.48 3.30 119.00 11.57 2.81 DBST
16+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+300 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+360 20 7.04 1.76 1.76 35.20 1.41 1.41 28.20 3.00 0.53 10.60 155.40 181.82 20.20 3.11 109.30 10.49 2.59 DBST
16+380 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.40 181.82 20.20 3.11 109.30 10.49 2.59 DBST
16+400 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+420 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
16+440 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
16+460 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
16+480 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+500 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+520 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
16+540 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
16+560 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
16+580 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
16+600 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
16+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+640 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
16+660 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
247 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
16+680 20 8.60 2.15 2.07 41.40 1.72 1.65 33.00 3.00 0.53 10.60 180.00 210.60 23.40 3.60 133.65 13.20 3.14 DBST
16+700 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
16+720 20 8.38 2.10 2.13 42.60 1.68 1.70 34.00 3.00 0.53 10.60 184.80 216.22 24.02 3.70 138.40 13.73 3.24 DBST
16+740 20 7.46 1.87 1.99 39.80 1.49 1.59 31.80 3.00 0.53 10.60 173.40 202.88 22.54 3.47 127.12 12.47 2.99 DBST
16+760 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
16+780 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
16+800 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
16+820 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
16+840 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+860 20 7.40 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
16+880 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
16+900 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
16+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
16+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+000 20 7.92 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
17+020 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
17+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+060 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+080 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+100 20 7.78 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
17+120 20 8.06 2.02 1.99 39.80 1.61 1.59 31.80 3.00 0.53 10.60 173.40 202.88 22.54 3.47 127.12 12.47 2.99 DBST
17+140 20 8.20 2.05 2.04 40.80 1.64 1.63 32.60 3.00 0.53 10.60 177.60 207.79 23.09 3.55 131.27 12.94 3.08 DBST
17+160 20 7.66 1.92 1.99 39.80 1.53 1.59 31.80 3.00 0.53 10.60 173.60 203.11 22.57 3.47 127.31 12.50 2.99 DBST
17+180 20 7.90 1.98 1.95 39.00 1.58 1.56 31.20 3.00 0.53 10.60 170.60 199.60 22.18 3.41 124.34 12.17 2.93 DBST
17+200 20 7.22 1.81 1.90 38.00 1.44 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
17+220 20 7.81 1.95 1.88 37.60 1.56 1.50 30.00 3.00 0.53 10.60 165.30 193.40 21.49 3.31 119.10 11.58 2.81 DBST
17+240 20 7.90 1.98 1.97 39.40 1.58 1.57 31.40 3.00 0.53 10.60 172.10 201.36 22.37 3.44 125.83 12.33 2.96 DBST
17+260 20 7.21 1.80 1.89 37.80 1.44 1.51 30.20 3.00 0.53 10.60 166.10 194.34 21.59 3.32 119.89 11.67 2.83 DBST
17+280 20 8.20 2.05 1.93 38.60 1.64 1.54 30.80 3.00 0.53 10.60 169.10 197.85 21.98 3.38 122.86 12.00 2.90 DBST
17+300 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
17+320 20 8.40 2.10 2.08 41.60 1.68 1.66 33.20 3.00 0.53 10.60 181.00 211.77 23.53 3.62 134.64 13.31 3.16 DBST
17+340 20 7.90 1.98 2.04 40.80 1.58 1.63 32.60 3.00 0.53 10.60 178.00 208.26 23.14 3.56 131.67 12.98 3.09 DBST
17+360 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
17+380 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
17+400 20 7.59 1.90 1.94 38.80 1.52 1.55 31.00 3.00 0.53 10.60 169.90 198.78 22.09 3.40 123.65 12.09 2.91 DBST
17+420 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 160.90 188.25 20.92 3.22 114.74 11.10 2.71 DBST
17+440 20 7.74 1.94 1.85 37.00 1.55 1.48 29.60 3.00 0.53 10.60 162.40 190.01 21.11 3.25 116.23 11.26 2.75 DBST
17+460 20 7.90 1.98 1.96 39.20 1.58 1.57 31.40 3.00 0.53 10.60 171.40 200.54 22.28 3.43 125.14 12.25 2.95 DBST
17+480 20 7.08 1.77 1.88 37.60 1.42 1.50 30.00 3.00 0.53 10.60 164.80 192.82 21.42 3.30 118.60 11.53 2.80 DBST
17+500 20 7.90 1.98 1.88 37.60 1.58 1.50 30.00 3.00 0.53 10.60 164.80 192.82 21.42 3.30 118.60 11.53 2.80 DBST
248 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
17+520 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
17+540 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
17+560 20 7.17 1.79 1.85 37.00 1.43 1.48 29.60 3.00 0.53 10.60 162.70 190.36 21.15 3.25 116.52 11.30 2.75 DBST
17+580 20 7.00 1.75 1.77 35.40 1.40 1.42 28.40 3.00 0.53 10.60 156.70 183.34 20.37 3.13 110.58 10.64 2.62 DBST
17+600 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+640 20 7.63 1.91 1.83 36.60 1.53 1.47 29.40 3.00 0.53 10.60 161.30 188.72 20.97 3.23 115.14 11.14 2.72 DBST
17+660 20 8.20 2.05 1.98 39.60 1.64 1.59 31.80 3.00 0.53 10.60 173.30 202.76 22.53 3.47 127.02 12.46 2.99 DBST
17+680 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
17+700 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
17+720 20 7.68 1.92 1.99 39.80 1.54 1.59 31.80 3.00 0.53 10.60 173.80 203.35 22.59 3.48 127.51 12.52 3.00 DBST
17+740 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 161.80 189.31 21.03 3.24 115.63 11.20 2.73 DBST
17+760 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
17+780 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
17+800 20 8.03 2.01 2.00 40.00 1.61 1.60 32.00 3.00 0.53 10.60 174.30 203.93 22.66 3.49 128.01 12.57 3.01 DBST
17+820 20 8.20 2.05 2.03 40.60 1.64 1.63 32.60 3.00 0.53 10.60 177.30 207.44 23.05 3.55 130.98 12.90 3.08 DBST
17+840 20 7.84 1.96 2.01 40.20 1.57 1.61 32.20 3.00 0.53 10.60 175.40 205.22 22.80 3.51 129.10 12.69 3.03 DBST
17+860 20 8.17 2.04 2.00 40.00 1.63 1.60 32.00 3.00 0.53 10.60 175.10 204.87 22.76 3.50 128.80 12.66 3.03 DBST
17+880 20 8.60 2.15 2.10 42.00 1.72 1.68 33.60 3.00 0.53 10.60 182.70 213.76 23.75 3.65 136.32 13.50 3.19 DBST
17+900 20 7.00 1.75 1.95 39.00 1.40 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
17+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
17+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+000 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+020 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
18+040 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
18+060 20 7.36 1.84 1.90 38.00 1.47 1.52 30.40 3.00 0.53 10.60 166.60 194.92 21.66 3.33 120.38 11.73 2.84 DBST
18+080 20 7.06 1.77 1.81 36.20 1.41 1.44 28.80 3.00 0.53 10.60 159.20 186.26 20.70 3.18 113.06 10.91 2.68 DBST
18+100 20 7.00 1.75 1.76 35.20 1.40 1.41 28.20 3.00 0.53 10.60 155.60 182.05 20.23 3.11 109.49 10.52 2.60 DBST
18+120 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
18+140 20 7.66 1.92 1.94 38.80 1.53 1.55 31.00 3.00 0.53 10.60 169.60 198.43 22.05 3.39 123.35 12.06 2.91 DBST
18+160 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 161.60 189.07 21.01 3.23 115.43 11.18 2.73 DBST
18+180 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
18+200 20 7.60 1.90 1.94 38.80 1.52 1.55 31.00 3.00 0.53 10.60 170.00 198.90 22.10 3.40 123.75 12.10 2.92 DBST
18+220 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
18+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+300 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+340 20 7.11 1.78 1.77 35.40 1.42 1.41 28.20 3.00 0.53 10.60 156.10 182.64 20.29 3.12 109.99 10.57 2.61 DBST
249 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
18+360 20 7.90 1.98 1.88 37.60 1.58 1.50 30.00 3.00 0.53 10.60 165.10 193.17 21.46 3.30 118.90 11.56 2.81 DBST
18+380 20 7.52 1.88 1.93 38.60 1.50 1.54 30.80 3.00 0.53 10.60 169.20 197.96 22.00 3.38 122.96 12.01 2.90 DBST
18+400 20 7.80 1.95 1.92 38.40 1.56 1.53 30.60 3.00 0.53 10.60 168.20 196.79 21.87 3.36 121.97 11.90 2.88 DBST
18+420 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
18+440 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
18+460 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
18+480 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
18+500 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+520 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
18+540 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
18+560 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
18+580 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
18+600 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
18+620 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
18+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+660 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
18+680 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
18+700 20 7.66 1.92 1.95 39.00 1.53 1.56 31.20 3.00 0.53 10.60 170.60 199.60 22.18 3.41 124.34 12.17 2.93 DBST
18+720 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 161.60 189.07 21.01 3.23 115.43 11.18 2.73 DBST
18+740 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
18+760 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
18+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+800 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+820 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
18+840 20 8.09 2.02 2.04 40.80 1.62 1.63 32.60 3.00 0.53 10.60 177.90 208.14 23.13 3.56 131.57 12.97 3.09 DBST
18+860 20 7.90 1.98 2.00 40.00 1.58 1.60 32.00 3.00 0.53 10.60 174.90 204.63 22.74 3.50 128.60 12.64 3.02 DBST
18+880 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
18+900 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
18+920 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
18+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
18+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+000 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
19+020 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
19+040 20 7.20 1.80 1.93 38.60 1.44 1.54 30.80 3.00 0.53 10.60 169.00 197.73 21.97 3.38 122.76 11.99 2.89 DBST
19+060 20 7.36 1.84 1.82 36.40 1.47 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
19+080 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
19+100 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
19+120 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
19+140 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
19+160 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
19+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
250 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
19+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+260 20 7.38 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 158.80 185.80 20.64 3.18 112.66 10.87 2.67 DBST
19+280 20 7.46 1.87 1.86 37.20 1.49 1.49 29.80 3.00 0.53 10.60 163.40 191.18 21.24 3.27 117.22 11.37 2.77 DBST
19+300 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
19+320 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
19+340 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
19+360 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
19+380 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
19+400 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+440 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+460 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
19+480 20 7.78 1.95 1.97 39.40 1.56 1.57 31.40 3.00 0.53 10.60 171.80 201.01 22.33 3.44 125.53 12.30 2.95 DBST
19+500 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
19+520 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
19+540 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
19+560 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
19+580 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+600 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+660 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+700 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
19+720 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
19+740 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
19+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+800 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
19+820 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
19+840 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+860 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+880 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+900 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
19+920 20 8.20 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
19+940 20 7.13 1.78 1.92 38.40 1.43 1.54 30.80 3.00 0.53 10.60 168.30 196.91 21.88 3.37 122.07 11.91 2.88 DBST
19+960 20 7.80 1.95 1.87 37.40 1.56 1.50 30.00 3.00 0.53 10.60 164.30 192.23 21.36 3.29 118.11 11.47 2.79 DBST
19+980 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
20+000 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
20+020 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
251 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
20+040 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
20+060 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
20+080 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
20+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+120 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+140 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
20+160 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
20+180 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
20+200 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
20+220 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
20+240 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
20+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+300 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
20+320 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
20+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+360 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+380 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+400 20 7.20 1.80 1.78 35.60 1.44 1.42 28.40 3.00 0.53 10.60 157.00 183.69 20.41 3.14 110.88 10.67 2.63 DBST
20+420 20 7.00 1.75 1.78 35.60 1.40 1.42 28.40 3.00 0.53 10.60 157.00 183.69 20.41 3.14 110.88 10.67 2.63 DBST
20+440 20 7.38 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 158.80 185.80 20.64 3.18 112.66 10.87 2.67 DBST
20+460 20 7.21 1.80 1.83 36.60 1.44 1.46 29.20 3.00 0.53 10.60 160.90 188.25 20.92 3.22 114.74 11.10 2.71 DBST
20+480 20 7.00 1.75 1.78 35.60 1.40 1.42 28.40 3.00 0.53 10.60 157.10 183.81 20.42 3.14 110.98 10.68 2.63 DBST
20+500 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+520 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+540 20 8.04 2.01 1.88 37.60 1.61 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
20+560 20 8.20 2.05 2.03 40.60 1.64 1.63 32.60 3.00 0.53 10.60 177.40 207.56 23.06 3.55 131.08 12.91 3.08 DBST
20+580 20 8.20 2.05 2.05 41.00 1.64 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
20+600 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
20+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+640 20 7.48 1.87 1.81 36.20 1.50 1.45 29.00 3.00 0.53 10.60 159.80 186.97 20.77 3.20 113.65 10.98 2.69 DBST
20+660 20 7.70 1.93 1.90 38.00 1.54 1.52 30.40 3.00 0.53 10.60 166.80 195.16 21.68 3.34 120.58 11.75 2.84 DBST
20+680 20 7.00 1.75 1.84 36.80 1.40 1.47 29.40 3.00 0.53 10.60 162.00 189.54 21.06 3.24 115.83 11.22 2.74 DBST
20+700 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
20+720 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
20+740 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
20+760 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
20+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+800 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
20+840 20 7.26 1.82 1.79 35.80 1.45 1.43 28.60 3.00 0.53 10.60 157.60 184.39 20.49 3.15 111.47 10.74 2.64 DBST
20+860 20 7.71 1.93 1.88 37.60 1.54 1.50 30.00 3.00 0.53 10.60 164.70 192.70 21.41 3.29 118.50 11.52 2.80 DBST
252 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
20+880 20 8.60 2.15 2.04 40.80 1.72 1.63 32.60 3.00 0.53 10.60 178.10 208.38 23.15 3.56 131.77 12.99 3.09 DBST
20+900 20 8.47 2.12 2.14 42.80 1.69 1.71 34.20 3.00 0.53 10.60 185.70 217.27 24.14 3.71 139.29 13.83 3.26 DBST
20+920 20 7.39 1.85 1.99 39.80 1.48 1.59 31.80 3.00 0.53 10.60 173.60 203.11 22.57 3.47 127.31 12.50 2.99 DBST
20+940 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.90 185.91 20.66 3.18 112.76 10.88 2.67 DBST
20+960 20 7.40 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
20+980 20 7.46 1.87 1.86 37.20 1.49 1.49 29.80 3.00 0.53 10.60 163.60 191.41 21.27 3.27 117.41 11.40 2.77 DBST
21+000 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
21+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+060 20 7.47 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.70 186.85 20.76 3.19 113.55 10.97 2.69 DBST
21+080 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.70 186.85 20.76 3.19 113.55 10.97 2.69 DBST
21+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+120 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+140 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
21+160 20 7.58 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 166.80 195.16 21.68 3.34 120.58 11.75 2.84 DBST
21+180 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 160.80 188.14 20.90 3.22 114.64 11.09 2.71 DBST
21+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+260 20 8.01 2.00 1.88 37.60 1.60 1.50 30.00 3.00 0.53 10.60 165.10 193.17 21.46 3.30 118.90 11.56 2.81 DBST
21+280 20 8.90 2.23 2.12 42.40 1.78 1.69 33.80 3.00 0.53 10.60 184.10 215.40 23.93 3.68 137.71 13.65 3.23 DBST
21+300 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
21+320 20 7.40 1.85 2.04 40.80 1.48 1.63 32.60 3.00 0.53 10.60 178.00 208.26 23.14 3.56 131.67 12.98 3.09 DBST
21+340 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
21+360 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+380 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+400 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+440 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+460 20 7.36 1.84 1.80 36.00 1.47 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
21+480 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
21+500 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+520 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+560 20 7.67 1.92 1.84 36.80 1.53 1.47 29.40 3.00 0.53 10.60 161.70 189.19 21.02 3.23 115.53 11.19 2.73 DBST
21+580 20 8.60 2.15 2.04 40.80 1.72 1.63 32.60 3.00 0.53 10.60 177.70 207.91 23.10 3.55 131.37 12.95 3.08 DBST
21+600 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
21+620 20 7.19 1.80 1.98 39.60 1.44 1.58 31.60 3.00 0.53 10.60 172.90 202.29 22.48 3.46 126.62 12.42 2.98 DBST
21+640 20 7.00 1.75 1.78 35.60 1.40 1.42 28.40 3.00 0.53 10.60 156.90 183.57 20.40 3.14 110.78 10.66 2.63 DBST
21+660 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
253 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
21+720 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
21+740 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
21+760 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
21+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+800 20 7.88 1.97 1.86 37.20 1.58 1.49 29.80 3.00 0.53 10.60 163.80 191.65 21.29 3.28 117.61 11.42 2.78 DBST
21+820 20 7.25 1.81 1.89 37.80 1.45 1.52 30.40 3.00 0.53 10.60 166.30 194.57 21.62 3.33 120.09 11.69 2.83 DBST
21+840 20 7.00 1.75 1.78 35.60 1.40 1.43 28.60 3.00 0.53 10.60 157.50 184.28 20.48 3.15 111.38 10.73 2.64 DBST
21+860 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
21+880 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
21+900 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
21+960 20 8.83 2.21 1.98 39.60 1.77 1.59 31.80 3.00 0.53 10.60 173.30 202.76 22.53 3.47 127.02 12.46 2.99 DBST
21+980 20 8.90 2.23 2.22 44.40 1.78 1.78 35.60 3.00 0.53 10.60 192.30 224.99 25.00 3.85 145.83 14.55 3.41 DBST
22+000 20 8.50 2.13 2.18 43.60 1.70 1.74 34.80 3.00 0.53 10.60 189.00 221.13 24.57 3.78 142.56 14.19 3.33 DBST
22+020 20 7.00 1.75 1.94 38.80 1.40 1.55 31.00 3.00 0.53 10.60 170.00 198.90 22.10 3.40 123.75 12.10 2.92 DBST
22+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+060 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+080 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
22+100 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
22+120 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
22+140 20 7.42 1.86 1.81 36.20 1.48 1.44 28.80 3.00 0.53 10.60 159.20 186.26 20.70 3.18 113.06 10.91 2.68 DBST
22+160 20 8.60 2.15 2.01 40.20 1.72 1.60 32.00 3.00 0.53 10.60 175.20 204.98 22.78 3.50 128.90 12.67 3.03 DBST
22+180 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
22+200 20 7.43 1.86 2.01 40.20 1.49 1.61 32.20 3.00 0.53 10.60 175.30 205.10 22.79 3.51 129.00 12.68 3.03 DBST
22+220 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.30 186.38 20.71 3.19 113.16 10.92 2.68 DBST
22+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+260 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
22+280 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
22+300 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
22+320 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+340 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+360 20 8.19 2.05 1.90 38.00 1.64 1.52 30.40 3.00 0.53 10.60 166.90 195.27 21.70 3.34 120.68 11.76 2.85 DBST
22+380 20 8.90 2.23 2.14 42.80 1.78 1.71 34.20 3.00 0.53 10.60 185.90 217.50 24.17 3.72 139.49 13.85 3.26 DBST
22+400 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
22+420 20 7.00 1.75 1.99 39.80 1.40 1.59 31.80 3.00 0.53 10.60 174.00 203.58 22.62 3.48 127.71 12.54 3.00 DBST
22+440 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+460 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+480 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+500 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
22+520 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
22+540 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
254 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
22+560 20 7.63 1.91 1.90 38.00 1.53 1.52 30.40 3.00 0.53 10.60 166.90 195.27 21.70 3.34 120.68 11.76 2.85 DBST
22+580 20 8.60 2.15 2.03 40.60 1.72 1.63 32.60 3.00 0.53 10.60 177.30 207.44 23.05 3.55 130.98 12.90 3.08 DBST
22+600 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
22+620 20 7.28 1.82 1.99 39.80 1.46 1.59 31.80 3.00 0.53 10.60 173.80 203.35 22.59 3.48 127.51 12.52 3.00 DBST
22+640 20 7.48 1.87 1.85 37.00 1.50 1.48 29.60 3.00 0.53 10.60 162.60 190.24 21.14 3.25 116.42 11.29 2.75 DBST
22+660 20 7.56 1.89 1.88 37.60 1.51 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
22+680 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
22+700 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
22+720 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+740 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+760 20 7.36 1.84 1.80 36.00 1.47 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
22+780 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
22+800 20 8.07 2.02 1.89 37.80 1.61 1.51 30.20 3.00 0.53 10.60 165.70 193.87 21.54 3.31 119.49 11.63 2.82 DBST
22+820 20 8.90 2.23 2.13 42.60 1.78 1.70 34.00 3.00 0.53 10.60 184.70 216.10 24.01 3.69 138.30 13.72 3.24 DBST
22+840 20 8.90 2.23 2.23 44.60 1.78 1.78 35.60 3.00 0.53 10.60 193.00 225.81 25.09 3.86 146.52 14.63 3.42 DBST
22+860 20 7.16 1.79 2.01 40.20 1.43 1.61 32.20 3.00 0.53 10.60 175.60 205.45 22.83 3.51 129.29 12.72 3.04 DBST
22+880 20 7.00 1.75 1.77 35.40 1.40 1.42 28.40 3.00 0.53 10.60 156.60 183.22 20.36 3.13 110.48 10.63 2.62 DBST
22+900 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
22+980 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
23+000 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
23+020 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
23+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+060 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+080 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+120 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+140 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
23+160 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
23+180 20 7.26 1.82 1.89 37.80 1.45 1.51 30.20 3.00 0.53 10.60 165.60 193.75 21.53 3.31 119.39 11.62 2.82 DBST
23+200 20 7.00 1.75 1.79 35.80 1.40 1.43 28.60 3.00 0.53 10.60 157.60 184.39 20.49 3.15 111.47 10.74 2.64 DBST
23+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+240 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
23+260 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
23+280 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
23+300 20 7.40 1.85 1.86 37.20 1.48 1.49 29.80 3.00 0.53 10.60 163.60 191.41 21.27 3.27 117.41 11.40 2.77 DBST
23+320 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
23+340 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
23+360 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
23+380 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
255 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
23+400 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+440 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+460 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+480 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+500 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+520 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
23+540 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
23+560 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+580 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+600 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+620 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+640 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+660 20 7.60 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
23+680 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
23+700 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
23+720 20 0.00 - 0.95 19.00 - 0.76 15.20 3.00 0.53 10.60 91.00 106.47 11.83 1.82 45.54 3.41 1.18 DBST
23+740 20 7.36 1.84 0.92 18.40 1.47 0.74 14.80 3.00 0.53 10.60 88.60 103.66 11.52 1.77 43.16 3.15 1.12 DBST
23+760 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
23+780 20 7.36 1.84 1.84 36.80 1.47 1.47 29.40 3.00 0.53 10.60 162.20 189.77 21.09 3.24 116.03 11.24 2.74 DBST
23+800 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 158.60 185.56 20.62 3.17 112.46 10.85 2.66 DBST
23+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+840 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+860 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+880 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+900 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+920 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+940 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
23+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+000 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
24+020 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
24+040 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
24+060 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
24+080 20 7.80 1.95 2.05 41.00 1.56 1.64 32.80 3.00 0.53 10.60 179.00 209.43 23.27 3.58 132.66 13.09 3.11 DBST
24+100 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
24+120 20 7.20 1.80 1.88 37.60 1.44 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
24+140 20 7.00 1.75 1.78 35.60 1.40 1.42 28.40 3.00 0.53 10.60 157.00 183.69 20.41 3.14 110.88 10.67 2.63 DBST
24+160 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+180 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
24+200 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
24+220 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
256 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
24+240 20 8.26 2.07 2.11 42.20 1.65 1.69 33.80 3.00 0.53 10.60 183.60 214.81 23.87 3.67 137.21 13.60 3.21 DBST
24+260 20 7.00 1.75 1.91 38.20 1.40 1.53 30.60 3.00 0.53 10.60 167.60 196.09 21.79 3.35 121.37 11.84 2.86 DBST
24+280 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+300 20 8.12 2.03 1.89 37.80 1.62 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
24+320 20 8.20 2.05 2.04 40.80 1.64 1.63 32.60 3.00 0.53 10.60 178.20 208.49 23.17 3.56 131.87 13.00 3.10 DBST
24+340 20 7.50 1.88 1.97 39.40 1.50 1.57 31.40 3.00 0.53 10.60 172.00 201.24 22.36 3.44 125.73 12.32 2.96 DBST
24+360 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
24+380 20 7.50 1.88 1.88 37.60 1.50 1.50 30.00 3.00 0.53 10.60 165.00 193.05 21.45 3.30 118.80 11.55 2.81 DBST
24+400 20 7.00 1.75 1.82 36.40 1.40 1.45 29.00 3.00 0.53 10.60 160.00 187.20 20.80 3.20 113.85 11.00 2.70 DBST
24+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+440 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+460 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+480 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
24+500 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
24+520 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
24+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+560 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
24+580 20 7.80 1.95 1.97 39.40 1.56 1.57 31.40 3.00 0.53 10.60 172.00 201.24 22.36 3.44 125.73 12.32 2.96 DBST
24+600 20 8.20 2.05 2.00 40.00 1.64 1.60 32.00 3.00 0.53 10.60 175.00 204.75 22.75 3.50 128.70 12.65 3.03 DBST
24+620 20 7.90 1.98 2.02 40.40 1.58 1.61 32.20 3.00 0.53 10.60 176.00 205.92 22.88 3.52 129.69 12.76 3.05 DBST
24+640 20 7.78 1.95 1.97 39.40 1.56 1.57 31.40 3.00 0.53 10.60 171.80 201.01 22.33 3.44 125.53 12.30 2.95 DBST
24+660 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 162.80 190.48 21.16 3.26 116.62 11.31 2.76 DBST
24+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+700 20 7.48 1.87 1.81 36.20 1.50 1.45 29.00 3.00 0.53 10.60 159.80 186.97 20.77 3.20 113.65 10.98 2.69 DBST
24+720 20 7.25 1.81 1.84 36.80 1.45 1.48 29.60 3.00 0.53 10.60 162.30 189.89 21.10 3.25 116.13 11.25 2.75 DBST
24+740 20 7.57 1.89 1.85 37.00 1.51 1.48 29.60 3.00 0.53 10.60 163.20 190.94 21.22 3.26 117.02 11.35 2.77 DBST
24+760 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 166.70 195.04 21.67 3.33 120.48 11.74 2.84 DBST
24+780 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
24+800 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
24+820 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
24+840 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
24+860 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
24+880 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
24+900 20 7.18 1.80 1.89 37.80 1.44 1.51 30.20 3.00 0.53 10.60 165.80 193.99 21.55 3.32 119.59 11.64 2.82 DBST
24+920 20 8.20 2.05 1.93 38.60 1.64 1.54 30.80 3.00 0.53 10.60 168.80 197.50 21.94 3.38 122.56 11.97 2.89 DBST
24+940 20 7.68 1.92 1.99 39.80 1.54 1.59 31.80 3.00 0.53 10.60 173.80 203.35 22.59 3.48 127.51 12.52 3.00 DBST
24+960 20 7.90 1.98 1.95 39.00 1.58 1.56 31.20 3.00 0.53 10.60 170.80 199.84 22.20 3.42 124.54 12.19 2.93 DBST
24+980 20 7.14 1.79 1.89 37.80 1.43 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
25+000 20 7.11 1.78 1.79 35.80 1.42 1.43 28.60 3.00 0.53 10.60 157.50 184.28 20.48 3.15 111.38 10.73 2.64 DBST
25+020 20 7.80 1.95 1.87 37.40 1.56 1.49 29.80 3.00 0.53 10.60 164.10 192.00 21.33 3.28 117.91 11.45 2.79 DBST
25+040 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
25+060 20 7.30 1.83 1.79 35.80 1.46 1.43 28.60 3.00 0.53 10.60 158.00 184.86 20.54 3.16 111.87 10.78 2.65 DBST
257 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
25+080 20 7.40 1.85 1.84 36.80 1.48 1.47 29.40 3.00 0.53 10.60 162.00 189.54 21.06 3.24 115.83 11.22 2.74 DBST
25+100 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
25+120 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
25+140 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
25+160 20 7.22 1.81 1.83 36.60 1.44 1.46 29.20 3.00 0.53 10.60 161.20 188.60 20.96 3.22 115.04 11.13 2.72 DBST
25+180 20 8.20 2.05 1.93 38.60 1.64 1.54 30.80 3.00 0.53 10.60 169.20 197.96 22.00 3.38 122.96 12.01 2.90 DBST
25+200 20 8.14 2.04 2.05 41.00 1.63 1.64 32.80 3.00 0.53 10.60 178.40 208.73 23.19 3.57 132.07 13.02 3.10 DBST
25+220 20 7.08 1.77 1.91 38.20 1.42 1.53 30.60 3.00 0.53 10.60 167.20 195.62 21.74 3.34 120.98 11.79 2.85 DBST
25+240 20 7.46 1.87 1.82 36.40 1.49 1.46 29.20 3.00 0.53 10.60 160.40 187.67 20.85 3.21 114.25 11.04 2.70 DBST
25+260 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+280 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
25+300 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+320 20 7.80 1.95 1.85 37.00 1.56 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
25+340 20 7.80 1.95 1.95 39.00 1.56 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
25+360 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
25+380 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+400 20 7.02 1.76 1.76 35.20 1.40 1.40 28.00 3.00 0.53 10.60 155.20 181.58 20.18 3.10 109.10 10.47 2.59 DBST
25+420 20 7.46 1.87 1.82 36.40 1.49 1.45 29.00 3.00 0.53 10.60 159.80 186.97 20.77 3.20 113.65 10.98 2.69 DBST
25+440 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+460 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+480 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+500 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
25+520 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+540 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+560 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+580 20 7.46 1.87 1.81 36.20 1.49 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
25+600 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+620 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+640 20 7.46 1.87 1.87 37.40 1.49 1.49 29.80 3.00 0.53 10.60 164.20 192.11 21.35 3.28 118.01 11.46 2.79 DBST
25+660 20 7.00 1.75 1.81 36.20 1.40 1.45 29.00 3.00 0.53 10.60 159.60 186.73 20.75 3.19 113.45 10.96 2.69 DBST
25+680 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+720 20 7.20 1.80 1.78 35.60 1.44 1.42 28.40 3.00 0.53 10.60 157.00 183.69 20.41 3.14 110.88 10.67 2.63 DBST
25+740 20 7.90 1.98 1.89 37.80 1.58 1.51 30.20 3.00 0.53 10.60 166.00 194.22 21.58 3.32 119.79 11.66 2.83 DBST
25+760 20 7.44 1.86 1.92 38.40 1.49 1.54 30.80 3.00 0.53 10.60 168.40 197.03 21.89 3.37 122.17 11.92 2.88 DBST
25+780 20 7.42 1.86 1.86 37.20 1.48 1.49 29.80 3.00 0.53 10.60 163.60 191.41 21.27 3.27 117.41 11.40 2.77 DBST
25+800 20 7.90 1.98 1.92 38.40 1.58 1.53 30.60 3.00 0.53 10.60 168.20 196.79 21.87 3.36 121.97 11.90 2.88 DBST
25+820 20 7.81 1.95 1.97 39.40 1.56 1.57 31.40 3.00 0.53 10.60 172.10 201.36 22.37 3.44 125.83 12.33 2.96 DBST
25+840 20 7.00 1.75 1.85 37.00 1.40 1.48 29.60 3.00 0.53 10.60 163.10 190.83 21.20 3.26 116.92 11.34 2.76 DBST
25+860 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
25+880 20 7.30 1.83 1.79 35.80 1.46 1.43 28.60 3.00 0.53 10.60 158.00 184.86 20.54 3.16 111.87 10.78 2.65 DBST
25+900 20 8.60 2.15 1.99 39.80 1.72 1.59 31.80 3.00 0.53 10.60 174.00 203.58 22.62 3.48 127.71 12.54 3.00 DBST
258 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
25+920 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
25+940 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
25+960 20 7.00 1.75 1.95 39.00 1.40 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
25+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+000 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+020 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+040 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+060 20 7.26 1.82 1.79 35.80 1.45 1.43 28.60 3.00 0.53 10.60 157.60 184.39 20.49 3.15 111.47 10.74 2.64 DBST
26+080 20 7.00 1.75 1.79 35.80 1.40 1.43 28.60 3.00 0.53 10.60 157.60 184.39 20.49 3.15 111.47 10.74 2.64 DBST
26+100 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+120 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+140 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+160 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+240 20 7.58 1.90 1.83 36.60 1.52 1.46 29.20 3.00 0.53 10.60 160.80 188.14 20.90 3.22 114.64 11.09 2.71 DBST
26+260 20 7.80 1.95 1.93 38.60 1.56 1.54 30.80 3.00 0.53 10.60 168.80 197.50 21.94 3.38 122.56 11.97 2.89 DBST
26+280 20 7.41 1.85 1.90 38.00 1.48 1.52 30.40 3.00 0.53 10.60 167.10 195.51 21.72 3.34 120.88 11.78 2.85 DBST
26+300 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.10 186.15 20.68 3.18 112.96 10.90 2.68 DBST
26+320 20 7.20 1.80 1.78 35.60 1.44 1.42 28.40 3.00 0.53 10.60 157.00 183.69 20.41 3.14 110.88 10.67 2.63 DBST
26+340 20 7.40 1.85 1.83 36.60 1.48 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
26+360 20 8.20 2.05 1.95 39.00 1.64 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
26+380 20 7.60 1.90 1.98 39.60 1.52 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
26+400 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
26+420 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+440 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+460 20 7.40 1.85 1.80 36.00 1.48 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
26+480 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
26+500 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
26+520 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
26+540 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
26+560 20 7.40 1.85 1.85 37.00 1.48 1.48 29.60 3.00 0.53 10.60 163.00 190.71 21.19 3.26 116.82 11.33 2.76 DBST
26+580 20 7.00 1.75 1.80 36.00 1.40 1.44 28.80 3.00 0.53 10.60 159.00 186.03 20.67 3.18 112.86 10.89 2.67 DBST
26+600 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+620 20 7.56 1.89 1.82 36.40 1.51 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
26+640 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
26+660 20 7.56 1.89 1.89 37.80 1.51 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
26+680 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
26+700 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+720 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+740 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
259 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
26+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+800 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+820 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+840 20 8.60 2.15 1.95 39.00 1.72 1.56 31.20 3.00 0.53 10.60 171.00 200.07 22.23 3.42 124.74 12.21 2.94 DBST
26+860 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
26+880 20 8.60 2.15 2.15 43.00 1.72 1.72 34.40 3.00 0.53 10.60 187.00 218.79 24.31 3.74 140.58 13.97 3.29 DBST
26+900 20 7.11 1.78 1.97 39.40 1.42 1.57 31.40 3.00 0.53 10.60 172.10 201.36 22.37 3.44 125.83 12.33 2.96 DBST
26+920 20 7.90 1.98 1.88 37.60 1.58 1.50 30.00 3.00 0.53 10.60 165.10 193.17 21.46 3.30 118.90 11.56 2.81 DBST
26+940 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
26+960 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
26+980 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+000 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+020 20 7.48 1.87 1.81 36.20 1.50 1.45 29.00 3.00 0.53 10.60 159.80 186.97 20.77 3.20 113.65 10.98 2.69 DBST
27+040 20 7.56 1.89 1.88 37.60 1.51 1.51 30.20 3.00 0.53 10.60 165.40 193.52 21.50 3.31 119.20 11.59 2.81 DBST
27+060 20 7.00 1.75 1.82 36.40 1.40 1.46 29.20 3.00 0.53 10.60 160.60 187.90 20.88 3.21 114.44 11.07 2.71 DBST
27+080 20 7.48 1.87 1.81 36.20 1.50 1.45 29.00 3.00 0.53 10.60 159.80 186.97 20.77 3.20 113.65 10.98 2.69 DBST
27+100 20 8.20 2.05 1.96 39.20 1.64 1.57 31.40 3.00 0.53 10.60 171.80 201.01 22.33 3.44 125.53 12.30 2.95 DBST
27+120 20 7.60 1.90 1.98 39.60 1.52 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
27+140 20 7.60 1.90 1.90 38.00 1.52 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
27+160 20 7.00 1.75 1.83 36.60 1.40 1.46 29.20 3.00 0.53 10.60 161.00 188.37 20.93 3.22 114.84 11.11 2.72 DBST
27+180 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+200 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+220 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+240 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+260 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+280 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
27+300 20 7.49 1.87 1.93 38.60 1.50 1.54 30.80 3.00 0.53 10.60 168.90 197.61 21.96 3.38 122.66 11.98 2.89 DBST
27+320 20 7.17 1.79 1.83 36.60 1.43 1.47 29.40 3.00 0.53 10.60 161.60 189.07 21.01 3.23 115.43 11.18 2.73 DBST
27+340 20 8.60 2.15 1.97 39.40 1.72 1.58 31.60 3.00 0.53 10.60 172.70 202.06 22.45 3.45 126.42 12.40 2.97 DBST
27+360 20 7.38 1.85 2.00 40.00 1.48 1.60 32.00 3.00 0.53 10.60 174.80 204.52 22.72 3.50 128.50 12.63 3.02 DBST
27+380 20 7.90 1.98 1.92 38.40 1.58 1.53 30.60 3.00 0.53 10.60 167.80 196.33 21.81 3.36 121.57 11.86 2.87 DBST
27+400 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
27+420 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
27+440 20 7.00 1.75 1.87 37.40 1.40 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
27+460 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+480 20 8.44 2.11 1.93 38.60 1.69 1.55 31.00 3.00 0.53 10.60 169.40 198.20 22.02 3.39 123.16 12.03 2.90 DBST
27+500 20 8.60 2.15 2.13 42.60 1.72 1.71 34.20 3.00 0.53 10.60 185.40 216.92 24.10 3.71 139.00 13.79 3.25 DBST
27+520 20 7.52 1.88 2.02 40.40 1.50 1.61 32.20 3.00 0.53 10.60 176.20 206.15 22.91 3.52 129.89 12.78 3.05 DBST
27+540 20 7.00 1.75 1.82 36.40 1.40 1.45 29.00 3.00 0.53 10.60 160.20 187.43 20.83 3.20 114.05 11.02 2.70 DBST
27+560 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+580 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
260 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
27+600 20 7.90 1.98 1.87 37.40 1.58 1.49 29.80 3.00 0.53 10.60 164.00 191.88 21.32 3.28 117.81 11.44 2.78 DBST
27+620 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
27+640 20 7.90 1.98 1.98 39.60 1.58 1.58 31.60 3.00 0.53 10.60 173.00 202.41 22.49 3.46 126.72 12.43 2.98 DBST
27+660 20 7.22 1.81 1.90 38.00 1.44 1.51 30.20 3.00 0.53 10.60 166.20 194.45 21.61 3.32 119.99 11.68 2.83 DBST
27+680 20 7.07 1.77 1.79 35.80 1.41 1.43 28.60 3.00 0.53 10.60 157.90 184.74 20.53 3.16 111.77 10.77 2.65 DBST
27+700 20 8.20 2.05 1.91 38.20 1.64 1.53 30.60 3.00 0.53 10.60 167.70 196.21 21.80 3.35 121.47 11.85 2.86 DBST
27+720 20 7.00 1.75 1.90 38.00 1.40 1.52 30.40 3.00 0.53 10.60 167.00 195.39 21.71 3.34 120.78 11.77 2.85 DBST
261 of 323
QUANTITY CALCULATIONS FOR PAVEMENT
Name of the road:…………………………….
Chainage:0+000 to ….
Remarks
Mean Mean Prime coat
Chainage Area Volume Area Volume Volume Area Volume (Application rate 1 1.3 ltr/Sqm(90% bitumen(1.17ltr/Sqm) and 1.1 ltr/Sqm(90% bitumin(0.99ltr/Sqm) and
Area Area ltr/sqm) 10%kerosene(0.13ltr/Sqm)) 10%kerosene(0.11ltr/Sqm))
27+740 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+760 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+780 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
27+800 20 7.00 1.75 1.75 35.00 1.40 1.40 28.00 3.00 0.53 10.60 155.00 181.35 20.15 3.10 108.90 10.45 2.59 DBST
Length Nos. Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty
Quantity to be added
Average pavement width For branch roads (m) 6
Branch Road 15.00 50 900.00 900.00 112.50 450.00 4500.00 5265.00 585.00 94.50 4455.00 495.00 49.50
Final Total 27794.00 52934.42 42507.22 4281.60 15180.40 233256.60 272910.14 30323.87 4669.33 168999.47 16484.72 3937.13
262 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
Err:509
Items Application Rate Rate SBSD Area Total Qnty. Unit Remarks
Items Application Rate Rate SBSD Area Total Qnty. Unit Remarks
Summary
Items Total Qnty. Unit
Bitumen 80/100 0.00 Lit.
Kerosene as cutter 0.00 Lit.
20 mm Nominal chips 0.00 Ton
10 mm Nominal chips 0.00 Ton
263 of 323
Government of ………..
Ministry of Physical Infrastructure and Transport
Department of Road
0
Err:509
#REF!
Item Total
Description of works No. Length Breadth Height Quantity Unit
No. Quantity
(m) (m) (m)
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Road Design and planning Branch
Planning Monitoring and Evaluation unit
Final sum rates
Specification Rate (
S.N. Norms No BOQ Description Language Unit
Clause No. NRs.)
1 2.02 201 Clearing of grass, removing roots breaking sods, levelling the surface and disposal all complete [201 ] m2 13.08
Providing, jointing and laying HDP pipes (110 mm/125mm outer diameter) with or without collar etc.
2 7.01.a 701
complete in place as per specification. [701 ]
m 351.10
Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff mixture
3 7.02.iii 701
of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ). [701 ]
m 14,956.50
4 9.01.a 905 Road way excavation in soft soil including disposal all complete. [905 ] m3 426.42
Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift upto 1.5
5 9.01.b 905
m etc. all complete as per specification. [905 ]
m3 568.56
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per
6 9.01.c 905
specification. [905 ]
m3 1,563.54
Earthwork excavation in soft soil for drain and trenches including shoring, struting, bracing, sheeting and
7 9.02.a 905
disposal all complete. [905 ]
m3 511.70
Earthwork excavation in Hard soil/Gravels/Boulder mixed soil for drain and trenches including shoring,
8 9.02.b 905 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification m3 852.84
[905 ]
Earthwork excavation in soft rock for drain and trenches including shoring, struting, bracing, sheeting and
9 9.02.c 905
disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification [905 ]
m3 1,705.68
Backfilling in layers in foundation pits,trenches etc with approved filler material including compaction and
10 9.10.a 908
watering etc completefor depth of foundation upto 1.5m . [908 ]
m3 1,889.25
Backfilling in layers in foundation pits,trenches with common excavated material etc including compaction
11 9.10.a 908
and watering etc complete for depth of foundation upto 1.5m . [908 ]
m3 648.15
Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in
12 10.05.a 1003
common soil. [1003 ]
m2 30.05
Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as
13 12.01 1201
per table 12.1 of standard specification. [1201 ]
m3 1,647.00
Supplying and erecting traffic sign in place including 50mm dia. 2 steel tube, 2mm. thick steel plate, cement
14 15.01.b 1501 concrete, painting, writing and supporting steel angle nut and bolt etc. complete for size 1.2m.x 0.75m with no 9,652.04
back support. [1501 ]
Providing , Preparing and Installing form work including necessary supports and removing after completion
15 18.01 1804, 1805
for foundation and footings . [1804, 1805 ]
m2 525.84
Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc. including
16 20.01.a.02 2000
compaction, curing, testing etc. all complete as per specification and drawing. [2000 ]
m3 9,990.50
Providing and placing machine mixed M20/40 cement concrete for the foundation and footing etc. including
17 20.01.a.03 2000
compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing. [2000 ]
m3 11,239.76
Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc. including
18 20.01.a.04 2000
compaction, curing, testing etc. all complete as per specification and drawing. [2000 ]
m3 11,451.41
Providing and placing machine mixed M25/20 cement concrete for the foundation and footing etc. including
19 20.01.a.05 2000
compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing. [2000 ]
m3 13,199.30
Providing and laying Reinforcement ( diameter upto 8 mm) including cutting, bending, binding, fixing in
20 20.07.01 2000
position etc. all complete as per specification and drawing. [2000 ]
mt 127,436.46
Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting, bending,
21 20.07.02 2000
binding, fixing in position etc. all complete as per specification and drawing. [2000 ]
mt 122,872.27
Providing and laying Reinforcement ( diameter above 16 mm) including cutting, bending, binding, fixing in
22 20.07.03 2000
position etc. all complete as per specification and drawing. [2000 ]
mt 118,425.30
23 24.09 3110 Providing, laying, fixing in positions of Geo-textile (filter fabrics). [3110 ] m2 186.02
26.01, 6.05
24 old
2602, 2603 Providing, laying and levelling of dry stone soling works in the foundation all complete. [2602, 2603 ] m3 3,034.83
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including
25 26.04.b 2607 scaffolding, curing, preparation of mortar etc. complete, masoned height 0-5m, lead 30m (manual mixing), m3 10,138.33
mortar 35% [2607 ]
269 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
Assembling machine made Gabion boxes/mattresses, palcing in position including stretching, forming compartments; tying with bracing wires and tie wires; tying
9 2400 Spec. cl. No: Norms down the lid complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all transporation as per Cu.m 5,122.31
2041(1st specification.
ammendment 2050)
2400 Spec. cl. No: Norms Providing and filling stones into Gabion crates all complete as per specification along with reuse of stones/rubbles from existing ones.as per Engineers direction Cu.m 1,596.02
2041(1st (SS/SP-2400).
ammendment 2050)
10 24.09 2404, 3110 Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m Sq.m 186.02
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc. complete,
11 26.03.b 2602 2603 2607 Cu.m 9,717.35
masoned height 0-5m, lead 30m (machine mixing), mortar 35%
Providing and placing machine mixed M10/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all
12 20.01.a.1 2000 Cu.m 9,202.05
complete as per specification and drawing.
14 908 Backfilling in layers in foundation pits,trenches etc with approved filler material including compaction and watering etc complete,lead 10 m Cu.m 1,889.25
Backfilling in layers in foundation pits,trenches etc including compaction and watering etc complete,lead 10 m
15 9.10.a 908 Cu.m 648.15
a) Depth of foundation upto 1.5m
Norms 2041(1st
17 24.02.04 Providing, laying and levelling of dry stone soling works in the foundation all complete. Cu.m 3,034.83
ammendment 2050)
18 20.01.a.2 2000 Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all comple Cu.m 9,990.50
Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all
19 20.03.a.i 2000 Cu.m 11451.41
complete as per specification and drawing.
Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc. complete,
20 26.04.b 2607 Cu.m 9,717.35
masoned height 0-5m, lead 30m (manual mixing), mortar 35%
Providing and laying Reinforcement ( diameter upto 8 mm) including cutting, bending, binding, fixing in position etc. all complete as per specification and drawing.
20.07.01 2000 mt 127,436.46
[2000 ]
Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting, bending, binding, fixing in position etc. all complete as per
20.07.02 2000 mt 122,872.27
specification and drawing. [2000 ]
Providing and laying Reinforcement ( diameter above 16 mm) including cutting, bending, binding, fixing in position etc. all complete as per specification and
20.07.03 2000 mt 118,425.30
drawing. [2000 ]
21 2000 Providing and laying Reinforcement of all size including cutting, bending, binding, fixing in position etc. all complete as per specification and drawing. [2000 ] mt 122,911.34
22 18.01 1804, 1805 Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings . [1804, 1805 ] sqm 525.84
Proving and laying RCC pipes of diameter 600 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2
23 7.02.1 701 RM 9,457.15
fine sand ) , lead upto 100m.
Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2
24 7.02.03 701 RM 14,956.50
fine sand ) , lead upto 100m.
Backfilling in layers in foundation pits,trenches etc including compaction and watering etc complete,lead 10 m
25 Norms No. 908 Cu.m 648.15
a) Depth of foundation upto 1.5m
26 908 Backfilling in layers in foundation pits,trenches etc with approved filler material including compaction and watering etc complete,lead 10 m 1,889.25
Assembling machine made Gabion boxes/mattresses, palcing in position including stretching, forming compartments; tying with bracing wires and tie wires; tying
28 2400 Spec. cl. No: Norms down the lid complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all transporation as per Cu.m 5,122.31
2041(1st specification.
ammendment 2050)
D Pavement work rates
29 10.05.b 1003 Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in gravel & boulder mixed soil. Sq.m 30.05
30 12.01 1201 Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m. Cu.m 1,647.00
31 12.07 1202 Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base course with lead up to 10 m (1202) Cu.m 2,865.65
32 13.03 1301 1302 Providing and spraying bituminous prime coat MC30/MC70 including cleaning the road surface using wire, brushes, broom etc. before applying prime coat lit 187.39
Supply, Spread and compact 20mm (First coat) and 10mm(Second coat) nominal size chips for double bituminous surface dressing (DBSD) as per specified
33 13.05.05 1301 1303 ton 1,580.36
spreading rates for each layer of surface dressing to meet all the requirements of special specification all complete.(SS/SP 1300)
Laying of single/double/multiple bituminious coats for surface dressing using river gravels(grits), shingles or broken stone chips including compaction, Bitumen binder
34 13.05.01 1301 1303 lit 171.18
for surface dressing
Prepared By: Checked By: Approved By:
271 of 323
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
Provide and erecting "W" metal beam crashbarrier comprising of 3.43mm thick corrugated sheet metal beam rail, 70cm above road/ground level,fixed on ISMC
41 irc 7.08 serises channel vertical post, 150*75*5 mm spaced 2m c/c,1.8m high,1.1m below ground/road level,all steel paetsand fitment to be galvanized by hot dip process,all rm 8,701.48
fittings to confirm to IS 1367 and IS 1364,metal beam rail to be fixed on the vertical post with a spacer of chaneel section 150*75*5mm 330mm long, all complete
42 15.02 a 1502 Supplying and applying Thermoplastic Paint for Road marking including cleaning,watering,brooming etc. all complete sqm 1,317.74
43 15.04 1504 Supplying and fixing in place R.C.C. delineator and guard post including excavation, back filling, painting and erection etc. all complete as per drawing. no 1,112.17
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate, cement concrete, painting, writing and supporting steel angle nut
44 15.01.b 1501 and bolit etc. complete no 3,294.65
a)60 cm dia circular,60cm.equilateral triangle and 60cm x 45cm rectangular shaped sign(single post)
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate, cement concrete, painting, writing and supporting steel angle nut
45 15.01.b 1501 and bolit etc. complete no 9,652.04
b) 1.2m.x 0.75m. Size bigger traffic sign with back support and two or more post.
RATE ANALYSIS
Description of works: Clearing of grass, removing roots breaking sods, levelling the surface and disposal 10 m.
Unit : 1 m2
Spec. cl. No: 201
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
2.02 Unskilled md 0.0230 480.00 11.04 Tools and plants % 3.00 0.33
Description of works: Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and diposal of usable materials within 50 m lead for
(a) Plain cement concrete, 1:4:8 or leaner mix Unit : 1 m3
Spec. cl. No: 202
2.08.01 Skilled md 0.050 775.00 38.75 Tools and plants % 3.00 21.32
Description of works: Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and diposal of usable materials within 50 m lead for
(b) Plain cement concrete, 1:3:6 or richer mix Unit : 1 m3
Spec. cl. No: 202
2.08.02 Skilled md 0.050 775.00 38.75 Tools and plants % 3.00 34.28
Description of works: Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and diposal of usable materials within 50 m lead for
(c) Reinforced cement concrete work Unit : 1 m3
Spec. cl. No: 202
RATE ANALYSIS
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
2.08.03 Skilled md 0.050 775.00 38.75 Tools and plants % 3.00 47.96
Description of works: Dismantling Bridge, culvert and other structures including stockpiling the reusable materials and diposal of usable materials within 50 m lead for
(e) Random rubble masonry in cement mortar Unit : 1 m3
Spec. cl. No: 202
2.08.05 Skilled md 0.100 775.00 77.50 Tools and plants % 3.00 34.72
2.17.i Skilled md 0.01 775.00 7.75 Tools and plant 3.00% of L.C. 5.99
2.17.ii Skilled md 0.01 775.00 7.75 Tools and plant 3.00% of L.C. 11.75
RATE ANALYSIS
Description of works: Scarifying existing granular/bituminous road surface for carrying out the required operations necessary to complete the work (SS/SP-201).
Unit : 1 m2
Spec. cl. No: 201
Description of works: Dismantling gabion works including stockpiling the reusable materials and disposal of reusable materials within 50m lead.
Unit : 1 m3
Spec. cl. No: 202
2.18 Skilled md 0.10 775.00 77.50 Tools and plant 3.00% of L.C. 16.72
RATE ANALYSIS
Description of works: Providing HDP pipes (110 mm/125mm outer diameter) for weepholes complete in place as per specification.
Unit : 50 m
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.01 Skilled md 3.0 775.00 2325.00 HDP pipe m 50.00 230.00 11500.00 Generator (<2kva) hr. 8.00 150.00
Unskilled md 3.0 480.00 1440.00 Petrol lit 5.00 0.00 Screw Jack hr. 8.00 20.00
electric heating plate hr. 8.00 20.00
Rate (1 m ) 351.10
Description of works: Proving and laying RCC pipes of diameter 600 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of
1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m. Unit : 1 rm
Spec. cl. No: 701
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
7.02.1 Skilled md 0.281 775.00 217.77 RCC Pipe m 1.0 7100.83 7100.83 Ballies, crow, bars, chain , pulleys , block
3.00% of total cost 239.52
Unskilled md 1.094 525.12 Cement kg 6.813 111.25 and ropes etc.
480.00 16.33
Sand m3 0.009 802.58 7.22
Description of works: Proving and laying RCC pipes of diameter 900 mm (internal) with or without collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) ,
lead upto 100m.
Unit : 1 rm
Spec. cl. No: 701
7.02.03 Skilled md 0.344 775.00 266.60 RCC Pipe m 1.0 11414.58 11414.58 Ballies, crow, bars, chain , pulleys , block
3.00% of total cost 378.80
Unskilled md 1.562 749.76 Cement kg 9.062 147.98 and ropes etc.
480.00 16.33
Sand m3 0.013 802.58 10.43
RATE ANALYSIS
Description of works: Road way excavation in Hard soil / Gravel / Boulder mixed soil including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
9.01.b Unskilled md 1.000 480.00 480.00 Tools and plant 3.00% of L.C. 14.40
Description of works: Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
9.01.c Unskilled md 2.750 480.00 1320.00 Tools and plant 3.00% of L.C. 39.60
Description of works: Road way excavation in hard rock including disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
Unit : 1 m3
Spec. cl. No: 905
9.01.d Unskilled md 12.000 480.00 5760.00 Tools and plant 3.00% of L.C. 172.80
RATE ANALYSIS
Description of works: Earthwork excavation in hard soil by bulldozer
Unit : 1 m3
Spec. cl. No: 900
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
900.02. Unskilled md 0.010 480.00 4.80 Diesel Lit 0.132 89.38 11.79816 Bulldozer hr 0.00440 1800.00 7.92
900.03 Unskilled md 0.010 480.00 4.80 Diesel Lit 0.195 89.38 17.4291 Bulldozer hr 0.00660 1800.00 11.88
900.04 Unskilled md 0.010 480.00 4.80 Diesel Lit 0.258 89.38 23.06004 Bulldozer hr 0.00660 1800.00 11.88
Description of works: Earthwork excavation in B.M.S / Hard Soil (10% Manual and 90% Equipment)
Unit : 1 m3
RATE ANALYSIS
Description of works: Earthwork excavation in Soft Rock (10% Manual and 90% Equipment)
Unit : 1 m3
Sub total of A +B 166.66 Contractor's overhead expenses 15% = 25.00 Unit Rate = 191.66
Description of works: Earthwork excavation in hard Rock (10% Manual and 90% Equipment)
Unit : 1 m3
Sub total of A +B 629.05 Contractor's overhead expenses 15% = 94.36 Unit Rate = 723.41
Roadway excavation in all type of soils including Rock and safe disposal of materials all complete. (SS/SP - 900) (Weighted rate)
Unit : 1 m3
Description of works: Quantity Rate Weighted Rate
Earthwork excavation in hard Rock (10% Manual and 90% Equipment) 0.00 723.41
Earthwork excavation in Soft Rock (10% Manual and 90% Equipment) 291168.15 191.66 90.38
Earthwork excavation in B.M.S / Hard Soil (10% Manual and 90% Equipment) 5532194.85 85.05
Description of works: Formation of embankment including compaction in layers not exceeding 150 mm compacted depth, watering and haulage 10 m etc. all complete as per specification (ii)using
equipments.
Unit : 1 m3
Spec. cl. No: 909
RATE ANALYSIS
Description of works: Excavation for foundation through all types of soil including relevant lift and disposal upto 20m.
(a) Depth upto 1.5 m Unit : 1 m3
Spec. cl. No: 907
9.07.01.a Unskilled md 2.000 480.00 960.00 Tools and plant 3.00% of L.C. 28.80
Excavation for foundation in all type of soils including Rock and safe disposal of materials all complete usng Equipment (average rate) Unit : 1 m3
Description of works: Rate Average Rate
Earthwork Excavation in Hard soil 28.20
Description of works: Excavation for foundation in all type of soils including Rock and safe disposal of materials all complete (10% Manual and 90% Equipment)
Unit : 1 m3
Spec. cl. No: 907
Manual (A) Equipment (B)
Norms No.
% Rate Amount % Rate Amount
Description of works: Backfilling in layers in foundation pits,trenches etc with approved filler material including compaction and watering etc complete,lead 10 m
a) Depth of foundation upto 1.5m Unit : 1 m3
Spec. cl. No: 908
9.10.a Unskilled md 1.140 480.00 547.20 Filler Material m3 1.1 981.11 1079.22 Tools and plant 3.00% of L.C. 16.41
Sub total of A = 547.20 Sub total of B = 1079.22 Sub total of C = 16.41
Sub total of A +B + C = 1642.83 Contractor's overhead expenses 15% = 246.42 Unit Rate = 1889.25
RATE ANALYSIS
Description of works: Backfilling in layers in foundation pits,trenches etc including compaction and watering etc complete,lead 10 m
a) Depth of foundation upto 1.5m Unit : 1 m3
Spec. cl. No: 908
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.10.a Unskilled md 1.140 480.00 547.20 Tools and plant 3.00% of L.C. 16.41
Description of works: Excavation and disposal of slides including haulage distance upto 50m (by machine)
Unit : 1 m3
9.11.a Unskilled md 0.00315 480.00 1.51 Diesel Ltr 0.1512 89.38 13.514256 Wheel Loader hr. 0.0084 1000 0.01
Transportation Cost As per clause 8.04.03 1(a) as shown in transporatation rate chart for up to 1 km 290.75
Basic Haulage Rate included in slide removal is assumed to be half of the transportation rate 145.38
Description of works: Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in common soil.
Unit : 1 m2
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
10.05.a Unskilled md 0.10 480.00 48.00 Diesel lit 0.122 89.38 10.90 Grader (75 hp) hr 0.040 1600.00 64.00
skilled md 0.01 775.00 7.75 Roller 8-10t hr 0.017 500.00 8.50
RATE ANALYSIS
Description of works: Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in gravel & boulder mixed soil.
Unit : 1 m2
Spec. cl. No: 1003
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Description of works: Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m.
Unit : 1 m3
Spec. cl. No: 1201
Unskilled md 0.0400 480.00 19.20 Diesel lit 0.7920 89.38 70.78 Vibrator Rolller hr 0.0220 700.00 15.40
13.03 Skilled md 0.0030 775.00 2.32 Bitumen MC30/MC70 lit. 1.0500 98.29 103.20 Boiler hr 0.0025 180 0.45
Unskilled md 0.0460 480.00 22.08 kerosene lit 0.1000 89.38 8.93 Sprayer hr 0.0025 260.00 0.65
Diesel lit 0.2750 89.38 24.57 Air compresser hr 0.0030 250.00 0.75
RATE ANALYSIS
Description of works: Providing, laying, spreading, watering, levelling and compaction of crusher run materials for base course with lead up to 10 m (1202)
Spec. cl. No: 1202 Unit : 1 m3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
12.06
Skilled md 0.0050 775.00 3.87 Base agg. cu.m. 1.2000 1895.67 2274.80 Grader hr 0.0330 1600.00 52.80
Unskilled md 0.0200 480.00 9.60 Diesel lit 0.9900 89.38 88.48 Vibrator Rolller hr 0.0330 700.00 23.10
Description of works: Laying of single/double/multiple bituminious coats for surface dressing using river gravels(grits), shingles or broken stone chips including compaction, Bitumen binder for surface
dressing Unit : 1 ltr
Spec. cl. No: 1301
Unskilled md 0.0140 480.00 6.72 Kerosene lit 0.1000 89.38 8.93 Distributor hr 0.0025 1300.00 3.25
Diesel lit 0.2700 89.38 24.13 Air Compressor hr 0.0025 250.00 0.62
Description of works: Laying of single/double/multiple bituminious coats for surface dressing using river gravels(grits), shingles or broken stone chips including compaction, Cutter for bitumen grade
Spec. cl. No: 1301 80/100 Unit : 1 ltr
RATE ANALYSIS
Description of works: Laying of single/double/multiple bituminious coats for surface dressing using river gravels(grits), shingles or broken stone chips including compaction, Chipping for surface
Spec. cl. No: 1301 1303 dressing for 1st coat size, 20 mm dia Unit : 1 ton
Unskilled md 0.2100 480.00 100.80 Diesel lit 3.6000 89.38 Tyred Roller hr 0.2000 1200.00 240.00
680.90
321.76
Note: Unit weight of stone chips = 1.65 gm/cc, 1 ton chips = 1m3/1.65
Description of works:
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate, cement concrete, painting, writing and supporting steel angle nut and bolit etc.
complete Unit : 1 no.
Spec. cl. No: 1501 a)60 cm dia circular,60cm.equilateral triangle and 60cm x 45cm rectangular shaped sign(single post)
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.01.b Skilled md 0.033 775.00 25.57 Enamel paint lit 0.100 550.00 55.00
Formwork (F1) m 2
0.36 457.25 164.61
RATE ANALYSIS
Description of works:
Supplying and erecting traffic sign in place including 50mm dia. Steel tube, 2mm. thick steel plate, cement concrete, painting, writing and supporting steel angle nut and bolit etc.
complete Unit : 1 no.
Spec. cl. No: 1501 b) 1.2m.x 0.75m. Size bigger traffic sign with back support and two or more post.
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.01.b Skilled md 0.085 775.00 65.87 Enamel paint lit 0.400 550.00 220.00
Formwork (F1) m 2
1.00 457.25 457.25
15.03.a Skilled md 0.030 775.00 23.25 M15/40 RCC m3 0.060 8687.39 521.24
RATE ANALYSIS
Description of works: Supplying and placing R.C.C. kilometer post including excavation, back filling, painting and writing etc. all complete as per specification
b) Bigger kilometer post (placed at each 5 km.) Unit : 1 no.
Spec. cl. No: 1503
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.03.b Skilled md 0.080 775.00 62.00 M15/40 RCC m3 0.170 8687.39 1476.85
Description of works: Supplying and fixing in place R.C.C. delineator and guard post including excavation, back filling, painting and erection etc. all complete as per drawing.
Unit : 1 no.
Spec. cl. No: 1504
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
15.04 Skilled md 0.021 775.00 16.27 M20/20 PCC m3 0.030 9957.75 298.73
Description of works: Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings
(a) using timber ( soft wood) - Class F1 finish. Unit : 10 m2
Spec. cl. No: 1804,1805
Unskilled md 2.00 480.00 960.00 struts, ballies, etc. m3 0.18 2888.89 520.00
RATE ANALYSIS
Description of works: Providing and placing machine mixed M10/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.1 Skilled md 0.50 775.00 387.50 cement mt 0.220 16331.09 3592.83 mixer (0.28/ 0.20 m3 ) hr 0.60 470 282.00
Description of works: Providing and placing machine mixed M15/40 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per
specification and drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.2 Skilled md 0.50 775.00 387.50 cement mt 0.260 16331.09 4246.08 mixer (0.28/ 0.20 m )
3
hr 0.60 470 282.00
Unskilled md 3.50 480.00 1680.00 aggregate 20-40mm m3 0.530 1009.58 535.07 vibrator hr 0.25 100 25.00
aggregate 10-20mm m 3
0.240 1070.00 256.80
of Cost of
Mix Design and Quality Control 2.50% 211.88
aggregate 10mm & down m3 0.110 117.70 concrete
1070.00
coarse sand m3 0.460 802.58 369.18
RATE ANALYSIS
Description of works: Providing and placing machine mixed M20/20 cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.a.4 Skilled md 0.50 775.00 387.50 cement mt 0.330 16331.09 5389.25 mixer (0.28/ 0.20 m )
3
hr 0.60 470 282.00
Unskilled md 3.50 480.00 1680.00 aggregate 10-20mm m3 0.580 1070.00 620.60 vibrator hr 0.25 100 25.00
Description of works: Providing and laying Reinforcement ( diameter above 8 mm and upto 16 mm) including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per
specification and drawing. Unit : 1 mt.
Spec. cl. No: 2000
RATE ANALYSIS
Description of works: Providing and laying Reinforcement ( diameter above 16 mm) including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and
drawing. Unit : 1 mt.
Spec. cl. No: 2000
Sub total of A +B + C = 102978.52 Contractor's overhead expenses 15% = 15446.78 Unit Rate = 118425.30
Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.(2000)
Unit : 1 mt
Description of works: Quantity Rate Average Rate Average
diameter upto 8mm 127436.46
Unit : 1 box
Description of works: assembling Gabion
Assembling machineboxes
mademattresses, palcing in position
Gabion boxes/mattresses, including
palcing stretching,
in position forming
including compartments;
stretching, forming tying with bracing
compartments; wires
tying withand tie wires;
bracing wirestying
and down the lid
tie wires; complete;
tying down theandlid
providing and
complete; andfilling stoneand
providing / boulder in gabion
filling stone boxesin/ gabion
/ boulder mattresses
boxesetc. including dressing,
/ mattresses beding,
etc. including bondingbeding,
dressing, and allbonding
transporation
and allastransporation
per specification.
as per[specification.
3 x 1 x 1 : (16[ sq.
3 x m)]
1x1: Unit : 1 box
(16 sq. m)]
Spec. cl. No: 2401
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 1.04 480.00 499.20 Binding wire(12 SWG) Kg 1.81 101.93 184.49
RATE ANALYSIS
Description of works: Assembling machine made Gabion boxes/mattresses palcing in position including stretching, forming compartments; tying with bracing wires and tie wires; tying down the lid
complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all transporation as per specification. [ 2 x 1 x 1 :
(11sq. m)] Unit : 1 box
Unskilled md 0.75 480.00 360.00 Binding wire(12 SWG) Kg 1.30 91.93 119.50
Description of works: Assembling machine made Gabion boxes/mattresses, palcing in position including stretching, forming compartments; tying with bracing wires and tie wires; tying down the lid
complete; and providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all transporation as per specification. [ 1.5 x 1 x 1 :
(9 sq. m)] Unit : 1 box
Unskilled md 0.68 480.00 326.40 Binding wire(12 SWG) kg 1.25 91.93 114.91
RATE ANALYSIS
Assembling machine made Gabion boxes/mattresses, palcing in position including stretching, forming compartments; tying with bracing wires and tie wires; tying down the lid complete; and
Spec. cl. No: 2401 Unit : 1 m3
providing and filling stone / boulder in gabion boxes / mattresses etc. including dressing, beding, bonding and all transporation as per specification. [average]
Providing and filling stones into Gabion crates all complete as per specification along with reuse of stones/rubbles from existing ones.as per Engineers direction (SS/SP-2400).
Description of works:
Unit : 1 m2
Spec. cl. No: Norms 2041(1st
ammendment 2050)
Description of works: Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m
Unit : 1 m2
Spec. cl. No: 2404,3110
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
RATE ANALYSIS
Description of works: Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification Lead 30m, lift 1.5m , using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
24.14.01.a Skilled md 0.30 775.00 232.50 cement t 0.169 16331.09 2759.95 Concrete mixer ( 0.28 / 0.20 m3 ) hr. 0.50 470 235.00
Description of works: Providing and placing concrete with 60% M 15/40 concrete and 40% boulders/stones as per specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
RATE ANALYSIS
Description of works: Providing and placing plum-concrete with 70% M 15/40 concrete and 30% boulders/stones as per specification. Lead 30m, lift 1.5m using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
24.14.02.a Skilled md 0.30 775.00 232.50 cement t 0.195 16331.09 3184.56 Concrete mixer ( 0.28 / 0.20 m3 ) hr. 0.50 470 235.00
Aggregates 20-40(mm)
Unskilled md 3.00 480.00 1440.00 m3 0.398 1009.58 401.81 Concrete vibrator hr. 0.10 100 10.00
Aggregates 5-10(mm)
m3 0.082 1009.58 82.78
sand m3 0.345 802.58 276.89
petrol lit 0.100 100.88 10.08
diesel lit 3.000 89.38 268.14
Boulder/Stone m3 0.330 1895.67 625.57
Description of works: Providing and placing concrete with 70% M 15/40 concrete and 30% boulders/stones as per specification Lead 30m, lift 1.5m , without using concrete mixer and vibrator.
Unit : 1 m3
Spec.cl.No: 2406: 2, 4
RATE ANALYSIS
Description of works: Providing, laying and levelling of dry stone soling works in the foundation all complete.
Description of works: Providing and laying Random rubble stone masonry in cement mortar [ cement(1) : sand(4)] including scaffolding, curing, preparation of mortar etc. complete, masoned height 0-
5m, lead 30m (machine mixing), mortar 35% Unit : 1 m3
Spec. cl. No: 2602,2603,2607
26.03.b Skilled md 1.50 775.00 1162.50 Cement t 0.155 16331.09 2531.31 Concrete mixer (0.28/0.2 m3) hr. 0.15 470 70.50
Stone m 3
1.150 1895.67 2180.02
RATE ANALYSIS
Description of works: Providing and laying semi-grouting with compaction 50mm thickness.
Unit : 10 m2.
Spec. cl. No: 1301,1304
13.06.01 Skilled md 0.2100 775.00 162.75 Bitumen lit 35.0000 98.29 3440.15 Boiler hr 0.0700 180 12.60
Unskilled md 1.8000 480.00 864.00 Kerosene lit 0.1700 89.38 15.19 Roller hr 0.0700 500.00 35.00
Coarse agg. m3 0.6000 1070.00 642.00 Agg. Spreader hr 0.0700 300.00 21.00
Description of works: Provide and erecting "W" metal beam crashbarrier comprising of 3.43mm thick corrugated sheet metal beam rail, 70cm above road/ground level,fixed on ISMC serises channel
vertical post, 150*75*5 mm spaced 2m c/c,1.8m high,1.1m below ground/road level,all steel paetsand fitment to be galvanized by hot dip process,all fittings to confirm to IS 1367
and IS 1364,metal beam rail to be fixed on the vertical post with a spacer of chaneel section 150*75*5mm 330mm long, all complete Unit : 4.5m
IRC 7.08
RATE ANALYSIS
Unit Rate per meter= 8701.48
RATE ANALYSIS
Description of works:
Supplying and applying Thermoplastic Paint for Road marking including cleaning,watering,brooming etc. all complete Unit : 10 m2.
Spec. cl. No: 1502
15.02.a Skilled md 0.660 775.00 511.50 Thrmoplastic paint kg 50.000 170.00 8500.00 Compresser hr 2.33 250 582.5
Unskilled md 1.660 480.00 796.80 Glass beads kg 3 154.00 462.00 Sprayer hr 2.33 260 605.8
Resources
Norms Specification
Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
DoR 107 Unskilled md 1.000 480.00 480.00 tools 12 % of labour cost 0.00
Sub - total (A) 480.00 Sub - total (B) 0.00 Sub total (c) 0.00
NB: As per DoR Maintenace Norms Direct Cost (A+B+C) = NRs. 480.00
DoR 107 Unskilled md 1.000 480.00 480.00 tools 12 % of labour cost 0.00
Sub - total (A) 480.00 Sub - total (B) 0.00 Sub total (c) 0.00
NB: As per DoR Maintenace Norms Direct Cost (A+B+C) = NRs. 480.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 72.00
Total Item Rate = NRs. 552.00
Say NRs. per 2km/day X= 552.00
NRs. Per1km/Day Y=X/2= 276.00
Say NRs. per 1km/month Z=Y*30= 8280.00
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
Total 129.11
Total 88.91
a Gravel size:5-40mm up
m3 Diesel Ltr 0.7456 68.14 Bull Dozer 100-150 HP Hr 0.0115 1800.00 71.51
Total 117.38
Norms for collection of materials by machine
DOR Norms
Activity Spec Material Equipments Total
S.N. Description Unit
no No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Amount
a Gravel size:5-20mm up
m3 Diesel Ltr 1.1298 68.14 Bull Dozer 100-150 HP Hr 0.0174 1800.00 108.30
Total 177.80
a Gravel size:40-70mm up
m3 Diesel Ltr 2.2596 68.14 Bull Dozer 100-150 HP Hr 0.0348 1800.00 216.61
Total 361.17
a Gravel size:70-100mm up
m3 Diesel Ltr 5.0841 68.14 Bull Dozer 100-150 HP Hr 0.0783 1800.00 487.37
Total 812.63
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
1.a. Excavated earth work (Soil Material) Average Speed of the Vehicle in E/W Road = 10 km/hr In Black Top = 20 km/hr Unit :1 cu.m
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
First one km md 0.4 480.00 192 ltr 0.40 89.38 35.75 hr 0.14 450.00 63.00 290.75
First two km md 0.4 480.00 192 ltr 0.80 89.38 71.50 hr 0.17 450.00 76.50 340.00 49.25
First three km md 0.4 480.00 192 ltr 1.20 89.38 107.26 hr 0.20 450.00 90.00 389.26 49.26
First four km md 0.4 480.00 192 ltr 1.60 89.38 143.01 hr 0.23 450.00 103.50 438.51 49.25
First five km md 0.4 480.00 192 ltr 2.00 89.38 178.76 hr 0.26 450.00 117.00 487.76 49.25
RA No. : 31
Description of item : Haulage of excessive cut materials using Machinary beyond 1 km length
Sub - total (A) 0.00 Sub - total (B) 0.00 Sub total (c) 49.25
NB: Transportation Cost As per clause 8.04.03 1(a) as shown in transportation rate chart for additional km/cum Direct Cost (A+B+C) = NRs. 49.25
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 7.39
The rate has been calculated by deducting total transportation cost from origin up to two km and up to 1km respectively , to find out the haulage cost
beyond 1 km. Total Item Rate = NRs. 56.64
Say NRs. per cu.m. 57.00
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0.00
Labour Total
Earthen Km Gravel Km Blacktop Km Total Travel Fuel Fuel, Truck Load / Unload Truck,
Material Type Unit Transportation
(10 kmph) (20 Kmph) (40 kmph) Time (T) Coefficient Ltr. Coefficient Time Hr.
Unskilled Skilled Cost per unit
Earthwork Calculation
Total Length (Km): 38.4
Err:509
Err:509
Earthwork in Roadway including drain Structure E/W for Retaining wall / Gabion Road Way Cutting Soil type
e Excess filling Pro.
ks
Length
ag
Length
ar
Road way Cutting Filling Cutting Back filling BMS Soft Rock Hard Rock
in
(m)
em
ha
R
C
Total
15 of 323
Gabion Retaining Breast Structure Quantity Calculation
Err:509
Err:509
District: Dhadhing
Structure quantity
Chainage Gabion Retaining wall Gabion Retaining Wall Remarks
Total Volume Geotextile(m
Length (m) Left side Right side (m3) 2)
Height Area(m2) Volume (m3) Height Area(m2) Volume (m3)
- 6.00 17.00 - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- 1.00 1.00 - - -
- 1.00 1.00 - - -
- 1.00 1.00 - - -
- 2.00 3.00 - - -
- 2.00 3.00 - - -
- 2.00 3.00 - - -
- 1.00 1.00 - - -
- 1.00 1.00 - - -
- 1.00 1.00 - - -
- - - -
- - - -
- - - -
- - - -
- 1.00 1.00 - - -
- 5.00 12.50 - - -
- - - -
- 1.00 1.00 - - -
- - - -
- - - -
- - - -
- - - -
- 2.00 3.00 - - -
- - - -
- - - -
- 3.00 5.50 - - -
- 8.00 27.50 - - -
- 7.00 22.00 - - -
- 3.00 5.50 - - -
- - - -
- - - -
- 10.00 40.00 - - -
- 10.00 40.00 - - -
- 6.00 17.00 - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- 1.00 1.00 - - -
Err:509
District: Dhadhing
Structure quantity
Chainage Gabion Retaining wall Gabion Retaining Wall Remarks
Total Volume Geotextile(m
Length (m) Left side Right side (m3) 2)
Height Area(m2) Volume (m3) Height Area(m2) Volume (m3)
ok
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
0
Err:509
###
2 Stone Pitching
a Causeway portion 10.00 8.00 0.20 16.00
b Apron @ d/s 10.00 3.00 0.20 6.00
22.00
6 Masonry Wall
a wall @ u/s 10.00 0.60 1.00 6.00
b ret wall @ d/s 10.00 1.00 1.50 15.00
c ret wall to apron@ d/s 10.00 0.60 1.00 6.00
27.00
7 Formwork 36.00 0.30 10.80
Clearing of grass, removing roots breaking sods, levelling the surface and
3 2.02 201 disposal 10 m.
m2 13.08
Feeling and uprooting of bamboo, clearing the area, stacking of bamboo, and
4 2.03 201 disposing of wastes to 10 m. (Voulme of the excavated area should be m3 1591.97
measured)
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
5 2.04.a 201 serviceable materials to 10m distance and back filling the depression/pits. (a)
no 523.07
above 300 mm to 600 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
6 2.04.b 201 serviceable materials to 10m distance and back filling the depression/pits. (b)
no 1989.96
above 600 mm to 900 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
7 2.04.c 201 serviceable materials to 10m distance and back filling the depression/pits. (c)
No 5543.46
above 900 mm to 1800 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
8 2.04.d 201 serviceable materials to 10m distance and back filling the depression/pits. (d)
No 9096.96
above 1800 mm to 2400 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
9 2.04.e 201 serviceable materials to 10m distance and back filling the depression/pits. (e) No 22742.40
above 2400 mm to 3000 mm.
Feeling trees (the girth measured at a height of 1m above the ground level)
including cutting of trunks and branches, removing the roots, stacking
10 2.04.f 201 serviceable materials to 10m distance and back filling the depression/pits. (e)
No 44751.35
above 3000 mm.
Dressing and levelling of the construction surface including cutting and filling of
11 2.05 201,909 small undulation.
m2 5.68
Excavation of top soil (sub grade) and carrying away from construction site,
12 2.06 201,1003 lead 10m and thickness upto 100mm.
m2 90.97
13 2.07 201,2800 Spreading, shaping and light compacting of top soil on slopes. m2 28.43
Excavation of metalled road and removal of all materials including soling and
screening, sorting out reusable materials and disposing unusable materials
18 2.15.a 202 upto 20m lead
m3 515.19
(a) Water bound macadam materials including soling / sub-base.
Excavation of metalled road and removal of all materials including soling and
screening, sorting out reusable materials and disposing unusable materials
19 2.15.b 202 upto 20m lead
m3 1385.09
(b)Bitumenous Materials
Providing, jointing and laying HDP pipes (110 mm/125mm outer diameter) with
23 7.01.a 701 or without collar etc. complete in place as per specification.
m 351.10
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Proving and laying RCC pipes of diameter 600 mm (internal) with or without
24 7.02.i 701 collars jointed with stiff mixture of cement mortar in the proportion of m 9457.15
1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
Proving and laying RCC pipes of diameter 750 mm (internal) with or without
25 7.02.ii 701 collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 m 12202.68
cement : 2 fine sand ) , lead upto 100m.
Proving and laying RCC pipes of diameter 900 mm (internal) with or without
26 7.02.iii 701 collars jointed with stiff mixture of cement mortar in the proportion of 1 : 2 ( 1 m 14956.50
cement : 2 fine sand ) , lead upto 100m.
ACTIVITY GROUP 9 :
C
EARTHWORKS
Road way excavation in soft soil including disposal upto 10 m and lift upto 1.5
27 9.01.a 905 m etc. all complete as per specification.
m3 426.42
Road way excavation in Hard soil / Gravel / Boulder mixed soil including
28 9.01.b 905 disposal upto 10 m and lift upto 1.5 m etc. all complete as per specification.
m3 568.56
Road way excavation in Soft rock including disposal upto 10 m and lift upto 1.5
29 9.01.c 905 m etc. all complete as per specification.
m3 1563.54
Earthwork excavation in soft soil for drain and trenches including shoring,
30 9.02.a 905 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all m3 511.7
complete as per specification
Earthwork excavation in soft rock for drain and trenches including shoring,
32 9.02.c 905 struting, bracing, sheeting and disposal upto 10 m and lift upto 1.5 m etc. all m3 1705.68
complete as per specification
Excavation for foundation through all types of soil including relevant lift and
35 9.07.01.a 907 disposal upto 20m. m3 1137.12
(a) Depth upto 1.5 m
Excavation for foundation through all types of soil including relevant lift and
36 9.07.01.b 907 disposal upto 20m. m3 1705.68
(b) Depth 1.5 m upto 3 m
Excavation for foundation through all types of soil including relevant lift and
37 9.07.01.c 907 disposal upto 20m. m3 2274.24
(c) Depth upto 3m upto 4.5 m
Excavation for foundation through all types of soil including relevant lift and
38 9.07.01.d 907 disposal upto 20m. m3 2700.66
(d) Depth 4.5 m upto 6 m
Excavation and disposal of slides manually haulage distance upto 50m a)Soft
49 9.11.a 908 soil m3 341.14
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Excavation and disposal of slides manually haulage distance upto 50m
50 9.11.b 908 b) Hard soil
m3 454.85
ACTIVITY GROUP 13 :
C BITUMINOUS SURFACE
AND BASE COURSE
Laying of single / double / multiple bituminous coats for surface dressing using
75 13.05.01 1301, 1303 river gravels, shingles or broken stone chips including compaction Ltr 171.18
I) Bituminous binder for surface dressing( mass work).
Laying of single / double / multiple bituminous coats for surface dressing using
76 13.05.02 1301, 1303 river gravels, shingles or broken stone chips including compaction Ltr 179.38
I) Bituminous binder for surface dressing( Patch work).
Specification Rate
S.N. Norms No Description Unit
Clause No. ( NRs.)
Laying of single / double / multiple bituminous coats for surface dressing using
77 13.05.03 1301, 1303 river gravels, shingles or broken stone chips including compaction -- II) Cutter Ltr 104.26
for bitumen grade 80/100.
Laying of single / double / multiple bituminous coats for surface dressing using
78 13.05.04 1301, 1303 river gravels, shingles or broken stone chips including compaction -- III) Mt 2089.35
Chipping for surface dressing for 1st coat size or second coat size.
Laying of single / double / multiple bituminous coats for surface dressing using
79 13.05.05 1301, 1303 river gravels, shingles or broken stone chips including compaction -- IV) m3 0
Production of percorated chipping.
80 13.06.01 1301, 1304 Providing and laying semi-grouting with compaction 50mm thickness. m2 836.59
81 13.06.02 1301, 1304 Providing and laying semi-grouting with compaction 75mm thickness. m2 1095.47
82 13.06.03 1301, 1304 Providing and laying full grouting with compaction 50 mm thicknes. m2 1063.68
83 13.07 1301, 1305 Providing and laying sand seal. m2 115.09
84 13.08.01 1301, 1306 Providing, mixing and laying slurry seal with fine slurry mix. m2 181.06
85 13.08.02 1301, 1306 Providing, mixing and laying slurry seal with normal slurry mix. m2 202.34
86 13.08.03 1301, 1306 Providing, mixing and laying slurry seal with coarse slurry mix. m2 235.75
87 13.09 1307, 1308 Providing, mixing, laying and compaction of premix carpet. m3 15373.13
88 13.1 1307, 1308 Providing, mixing, and laying asphalt concrete with compaction. m3 18067.34
ACTIVITY GROUP 15 :
TRAFFIC SIGNS AND ROAD
MARKING
Supplying and erecting traffic sign in place including 50mm dia. Steel tube,
2mm. thick steel plate, cement concrete, painting, writing and supporting steel
89 15.01.a 1501 angle nut and bolit etc. complete a) 60cm. Dia. Circular, 60cm. equilateral
no 2384.33
traingle and 60cm.x 45cm. rectangular shaped sign (single post).
Supplying and erecting traffic sign in place including 50mm dia. Steel tube,
2mm. thick steel plate, cement concrete, painting, writing and supporting steel
90 15.01.b 1501 angle nut and bolit etc. complete b) 1.2m.x 0.75m. Size bigger traffic sign with
no 9652.04
back support and two or more post.
Supplying and applying paint for Road marking including cleaning, watering,
91 15.02.a 1502 brooming etc. all complete (10cm. wide strip) m 27.16
a) Two coats over old painted surface
Supplying and applying paint for Road marking including cleaning, watering,
92 15.02.b 1502 brooming etc. all complete (10cm. wide strip) m 47.13
b) More than two coats over new bitumin surface
Supplying and placing R.C.C. kilometer post including excavation, back filling,
93 15.03.a 1503 painting and writing etc. all complete as per specification no 2537.96
a) Standard KM post placed at each kilometer.
Supplying and placing R.C.C. kilometer post including excavation, back filling,
94 15.03.b 1503 painting and writing etc. all complete as per specification no 5768.93
b) Bigger kilometer post (placed at each 5 km.)
Supplying and fixing in place R.C.C. delineator and guard post including
95 15.04 1504 excavation, back filling, painting and erection etc. all complete as per drawing.
no 1112.17
ACTIVITY GROUP 18 :
FASLEWORK, FORMWORK
& SURFACE FINISH FOR
CONCRETE STRUCTURES
ACTIVITY GROUP 19 :
BEARINGS AND
EXPANSION JOINTS
(BRIDGES, SLABS ETC.)
Providing and fixing in positions, 100 mm diameter drainage spouts with
107 19.01 1901 necessary hardware.
nos 1425.00
Providing and installing Expansion Joints and tarfelt sheet including all
108 19.02 1901 necessaary axilliary and incidental works etc. complete as per drawing and rm 18089.5
specification.
ACTIVITY GROUP 20 :
CONCRETE FOR
STRUCTURES
Providing and placing machine mixed M10/40 cement concrete for the
110 20.01.a.01 2000 foundation and footing etc. including compaction, curing, testing and lead m3 9202.05
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M15/40 cement concrete for the
111 20.01.a.02 2000 foundation and footing etc. including compaction, curing, testing and lead m3 9990.5
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M20/40 cement concrete for the
112 20.01.a.03 2000 foundation and footing etc. including compaction, curing, testing and lead m3 11239.76
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for the
113 20.01.a.04 2000 foundation and footing etc. including compaction, curing, testing and lead m3 11451.41
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M25/20 cement concrete for the
114 20.01.a.05 2000 foundation and footing etc. including compaction, curing, testing and lead m3 13199.3
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M10/40 cement concrete for the
115 20.01.b.01 2000 foundation and footing etc. including compaction, curing, testing and lead m3 10643.03
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M15/40 cement concrete for the
116 20.01.b.02 2000 foundation and footing etc. including compaction, curing, testing and lead m3 11404.48
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M20/40 cement concrete for the
117 20.01.b.03 2000 foundation and footing etc. including compaction, curing, testing and lead m3 12793.44
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M20/20 cement concrete for the
118 20.01.b.04 2000 foundation and footing etc. including compaction, curing, testing and lead m3 13033.65
30m. etc. all complete as per specification and drawing.
Providing and placing manually mixed M25/20 cement concrete for the
119 20.01.b.05 2000 foundation and footing etc. including compaction, curing, testing and lead m3 14063.72
30m. etc. all complete as per specification and drawing.
Providing and placing machine mixed M15/40 cement concrete for abutment,
120 20.02.a.i 2000 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all m3 14316.93
complete as per specification and drawing.
Providing and placing machine mixed M20/40 cement concrete for abutment,
121 20.02.a.iii 2000 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all m3 15547.02
complete as per specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for abutment,
122 20.02.a.iii 2000 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all m3 15740.10
complete as per specification and drawing.
Providing and placing machine mixed M25/20 cement concrete for abutment,
123 20.02.a.iv 2000 pier, wall, etc. including compaction, curing, testing and lead 30m. etc. all m3 16697.67
complete as per specification and drawing.
Providing and placing machine mixed M20/20 cement concrete for the
124 20.03.a.ii 2000 superstructure, deckslab, girder etc. including compaction, curing, testing and m3 13139.97
lead 30m. etc. all complete as per specification and drawing.
ACTIVITY GROUP 24 :
MISCELLANEOUS
STRUCTURES
2403(5), Providing and laying grouted stone pitching in protection work with stone size
133 24.04 m3 8522.12
2406 -5(b) not less than 0.01 m3 and cement : sand motar (1:3) lead 30m, lift 1.5m
134 24.09 2404,3110 Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m m2 186.02
Providing and placing concrete with 60% M 15/40 concrete and 40%
135 24.14.01.a 2406; 2, 4 boulders/stones as per specification Lead 30m, lift 1.5m , using concrete mixer m3 8154.67
and vibrator.
Providing and placing concrete with 60% M 15/40 concrete and 40%
136 24.14.01.b 2406; 2, 4 boulders/stones as per specification Lead 30m, lift 1.5m , without using m3 7866.08
concrete mixer and vibrator.
Providing and placing plum-concrete with 70% M 15/40 concrete and 30%
137 24.14.02.a 2406; 2, 4 boulders/stones as per specification. Lead 30m, lift 1.5m using concrete mixer m3 7991.41
and vibrator.
Providing and placing concrete with 70% M 15/40 concrete and 30%
138 24.14.02.b 2406; 2, 4 boulders/stones as per specification Lead 30m, lift 1.5m , without using m3 8938.09
concrete mixer and vibrator.
ACTIVITY GROUP 25 :
BRICKWORKS FOR
STRUCTURES
Providing and laying brick masonry in manual mixed cement mortar including
139 25.02.b 2502,3,4,5,7 preparation of mortar as per specification, lead 30 m.
m3 15107.98
Providing and applying 20mm thick cement plaster including mortar mixing,
140 25.06.b 2502,2510 scaffolding, curing etc. complete as per specification lead 30 m (manual m2 406.30
mixing)
ACTIVITY GROUP 26 :
MASONRY WORK FOR
STRUCTURES
Providing, laying and levelling of dry stone masonry works in the foundation all
141 26.01, 6.05 old 2602, 2603 complete.
m3 3034.83
Providing and laying dry stone masonry (coursed rubble) including dressing
142 26.01 2602, 2603, 2068 etc. complete as per specification, lead 30m.
m3 4791.62
Providing, mixing, and Pointing cement mortar over rubble masonry works in
152 26.07.a 2602, 2603, 2610 cement mortar [ cement(1) : sand(1)] including scaffolding, curing, preparation m2 299.40
of mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing).
Providing, mixing, and Pointing cement mortar over rubble masonry works in
153 26.07.b 2602, 2603, 2610 cement mortar [ cement(1) : sand(2)] including scaffolding, curing, preparation m2 261.16
of mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing).
Providing, mixing, and Pointing cement mortar over rubble masonry works in
154 26.07.c 2602, 2603, 2610 cement mortar [ cement(1) : sand(3)] including scaffolding, curing, preparation m2 241.83
of mortar etc. complete, masoned height 0-5m, lead 30m (machine mixing).
ACTIVITY GROUP 27 :
REPAIR OF STRUCTURES
Removal of old paints by sand blasting, cleaning and repairing of metal
155 27.07 2713 surfaces for the application of new paints as per specification.
m2 1327.01
157 Single coat whitewash on old surface including supply of materials all complete m2 26.11
Single coat enamel paint/ readymade emulsion paint with primer including
158 supply of materials all complete.
m2 233.63
ACTIVITY GROUP 29 :
MAINTENANCE WORKS
Restoration of rain cuts in embankment slopes including watering and
159 29.01 2902 compaction etc. all complete lead 10 m.
m3 518.21