ID Task Task Name Duration Start Finish January February March April May June July August

Mode E B M E B M E B M E B M E B M E B M E B M E B M
0 Indoor Stadium Project with 180 days 01 Jan '19 30 Jun '19
1 General 180 days 01 Jan '19 30 Jun '19
2 Project Commencement 0 days 01 Jan '19 01 Jan '19 01-01
3 Sub-structure Completion 0 days 02 Mar '19 02 Mar '19 02-03
4 Project Completion 0 days 30 Jun '19 30 Jun '19 30-06
5 Preliminary 2 days 01 Jan '19 02 Jan '19
6 Site Cleaning Work 2 days 01 Jan '19 02 Jan '19 Site Cleaning Work
7 Sub-structure 59 days 03 Jan '19 02 Mar '19
8 Excavation Work 9 days 03 Jan '19 11 Jan '19 Excavation Work
9 Hardcore Work 7 days 05 Jan '19 11 Jan '19 Hardcore Work
10 Lean Concrete Work 2 days 11 Jan '19 12 Jan '19 Lean Concrete Work
11 Footing 7 days 13 Jan '19 19 Jan '19
12 FT_Rebar Work 4 days 13 Jan '19 16 Jan '19 FT_Rebar Work
13 FT_Formwork 5 days 14 Jan '19 18 Jan '19 FT_Formwork
14 FT_Concrete Casting 1 day 19 Jan '19 19 Jan '19 FT_Concrete Casting
15 Short Column (up to Plinth 13 days 13 Jan '19 25 Jan '19
16 level)
SCP_Rebar Work 5 days 13 Jan '19 17 Jan '19 SCP_Rebar Work
17 SCP_Formwork 5 days 20 Jan '19 24 Jan '19 SCP_Formwork
18 SCP_Concrete Casting 1 day 25 Jan '19 25 Jan '19 SCP_Concrete Casting
19 Retaining Wall (up to Plinth 6 days 26 Jan '19 31 Jan '19
20 level)
Brick Work 6 days 26 Jan '19 31 Jan '19 Brick Work
21 Earth Filling 26 days 01 Feb '19 26 Feb '19
22 Back Filling with Sand (Well 5 days 16 Feb '19 20 Feb '19 Back Filling with Sand (Well Watered)
23 Watered)
Ground Beam 15 days 01 Feb '19 15 Feb '19
24 GB_Rebar Work 7 days 01 Feb '19 07 Feb '19 GB_Rebar Work
25 GB_Formwork 7 days 08 Feb '19 14 Feb '19 GB_Formwork
26 GB_Concrete Casting 1 day 15 Feb '19 15 Feb '19 GB_Concrete Casting
27 0' 6" Thick Sand Filling 6 days 21 Feb '19 26 Feb '19 0' 6" Thick Sand Filling Including
28 Including
Ground Slab 4 days 27 Feb '19 02 Mar '19
29 41/2" Thick1:3:6 Cement 4 days 27 Feb '19 02 Mar '19 41/2" Thick1:3:6 Cement con; Floor
30 Supercon; Floor
- Structure 80 days 26 Jan '19 15 Apr '19
31 R.C Long Column 13 days 03 Mar '19 15 Mar '19
32 L.C _ Rebar Work 6 days 03 Mar '19 08 Mar '19 L.C _ Rebar Work
33 L.C _ Formwork 6 days 09 Mar '19 14 Mar '19 L.C _ Formwork
34 L.C _ Concrete Casting 1 day 15 Mar '19 15 Mar '19 L.C _ Concrete Casting
35 Public Stand & Stair 27 days 16 Mar '19 11 Apr '19
36 PS_Rebar Work installation 15 days 16 Mar '19 30 Mar '19 PS_Rebar Work installation
37 PS_Formwork installation 10 days 31 Mar '19 09 Apr '19 PS_Formwork installation
38 PS_Concrete Casting 2 days 10 Apr '19 11 Apr '19 PS_Concrete Casting
39 Steel Strucutre Framing 80 days 26 Jan '19 15 Apr '19
40 Work
Steel Structure Farbrication 21 days 26 Jan '19 15 Feb '19 Steel Structure Farbrication Work
41 WorkStructure Installation 15 days
Steel 16 Mar '19 30 Mar '19 Steel Structure Installation Work
Work
Task Project Summary Manual Task Start-only Deadline

Project: Indoor Stadium Project Split Inactive Task Duration-only Finish-only Progress

Date: 29 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish January February March April May June July August
Mode E B M E B M E B M E B M E B M E B M E B M E B M
42 Wind Bracing Work 2 days 31 Mar '19 01 Apr '19 Wind Bracing Work
43 Steel Structure Painting 5 days 02 Apr '19 06 Apr '19 Steel Structure Painting Work
44 Work Work
Roofing 7 days 02 Apr '19 08 Apr '19 Roofing Work
45 Ridging Work 2 days 09 Apr '19 10 Apr '19 Ridging Work
46 Eave Board 5 days 11 Apr '19 15 Apr '19 Eave Board
47 Scaffolding Work 7 days 31 Mar '19 06 Apr '19 Scaffolding Work
48 Archi 37 days 09 Apr '19 15 May '19
49 Brick Work 13 days 09 Apr '19 21 Apr '19
50 Chowket Work 6 days 09 Apr '19 14 Apr '19 Chowket Work
51 GF_Internal Brick Work 7 days 15 Apr '19 21 Apr '19 GF_Internal Brick Work (4.5" thk:)
52 (4.5" thk:)
Plastering Work 15 days 18 Apr '19 02 May '19 Plastering Work
53 Steel Strucutre Walling Work 7 days 03 May '19 09 May '19 Steel Strucutre Walling Work
54 Topping Work 6 days 10 May '19 15 May '19 Topping Work
55 Finishing 58 days 03 May '19 29 Jun '19
56 Teak Door & Window Work 15 days 03 May '19 17 May '19
57 Teak Panel Door 5 days 03 May '19 07 May '19 Teak Panel Door
58 Teak Window frame & 5 days 08 May '19 12 May '19 Teak Window frame & Glass
59 Glass
Fixed Glass Work 5 days 13 May '19 17 May '19 Fixed Glass Work
60 Aluminium Window Work 14 days 18 May '19 31 May '19
61 Aluminium Fixed Work 7 days 18 May '19 24 May '19 Aluminium Fixed Work
62 Alu; Louver Work 7 days 25 May '19 31 May '19 Alu; Louver Work
63 Steel Handrail Work 8 days 16 May '19 23 May '19 Steel Handrail Work
64 Floor Finishing 35 days 16 May '19 19 Jun '19
65 Timber Flooring Work 15 days 16 May '19 30 May '19 Timber Flooring Work
66 Plank (6"x1") Diagonal 10 days 31 May '19 09 Jun '19 Plank (6"x1") Diagonal Floor
67 Floor
1" Tongue & Grooved 10 days 10 Jun '19 19 Jun '19 1" Tongue & Grooved Plank Flooring
68 PlankBoard
Plaster Flooring
Ceiling 5 days 16 May '19 20 May '19 Plaster Board Ceiling
69 Painting Work 45 days 16 May '19 29 Jun '19
70 Putty Work 9 days 16 May '19 24 May '19 Putty Work
71 Emulsion Paint for External 3 days 25 May '19 27 May '19 Emulsion Paint for External
72 Emulsion Paint for Internal 7 days 28 May '19 03 Jun '19 Emulsion Paint for Internal
73 Enamel paint 5 days 04 Jun '19 08 Jun '19 Enamel paint
74 Polishing work 10 days 20 Jun '19 29 Jun '19 Polishing work
75 Mechanical Work 59 days 16 Apr '19 13 Jun '19
76 Plumbing System Installation 59 days 16 Apr '19 13 Jun '19
77 Internal Water Supply & 12 days 03 May '19 14 May '19 Internal Water Supply & Sanitation
78 Sanitation
1600 Gals Capacity Ground 14 days 16 May '19 29 May '19 1600 Gals Capacity Ground Tank
79 Tank
1200 Gals Capacity Septic 15 days 30 May '19 13 Jun '19 1200 Gals Capacity Septic Tank
80 Tank
400 Gals SteelTrestle 15 days 16 Apr '19 30 Apr '19 400 Gals SteelTrestle
81 2" Φ Tube Well 15 days 01 May '19 15 May '19 2" Φ Tube Well
82 Electircal Work 58 days 03 May '19 29 Jun '19
83 Installation of Lighting 30 days 03 May '19 01 Jun '19 Installation of Lighting

Task Project Summary Manual Task Start-only Deadline

Project: Indoor Stadium Project Split Inactive Task Duration-only Finish-only Progress

Date: 29 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish January February March April May June July August
Mode E B M E B M E B M E B M E B M E B M E B M E B M
84 Installation of Gang Switch 30 days 03 May '19 01 Jun '19 Installation of Gang Switch and Combine Sockets
85 and Combine
Installation ofSockets
Distribution 7 days 02 Jun '19 08 Jun '19 Installation of Distribution Box
86 Box
Installation of Wire 14 days 02 Jun '19 15 Jun '19 Installation of Wire Distribution
87 Distribution
P.V.C and Accespries 10 days 02 Jun '19 11 Jun '19 P.V.C and Accespries
88 Earthing System 7 days 09 Jun '19 15 Jun '19 Earthing System
89 Testing &Commission 14 days 16 Jun '19 29 Jun '19 Testing &Commission
90 Infrastructure Work 20 days 16 May '19 04 Jun '19
91 Apron & Drain Work 20 days 16 May '19 04 Jun '19 Apron & Drain Work

Task Project Summary Manual Task Start-only Deadline

Project: Indoor Stadium Project Split Inactive Task Duration-only Finish-only Progress

Date: 29 Nov '20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone