Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

How to Bring Existing Ammonia

Plants Up-to-Date
Many existing ammonia plants located in areas with high feedstock prices are facing difficulties in today’s
more and more competitive market. In order to survive the competition from new plants coming up in areas
with low gas cost, existing plant owners can revamp their plants to reduce the energy consumption and/or
increase the plant capacity. Capacity revamps often offer a lower cost option to meet increased demand.

This paper will highlight a preferred approach to a revamp project and list a number of revamp features
available for bringing existing ammonia plants up-to-date. Following this a number of revamp projects cur-
rently under implementation will be described. Finally, a novel revamp option, the proprietary and patented
Haldor Topsøe Exchange Reformer (HTER), and the benefits by installing the same will be presented. The
HTER can be applied in existing plants, or may be included in the design of new plants. It offers, when in-
stalled in parallel with an existing reforming unit, the potential for increasing the capacity by up to 25% or
more depending upon specific plant configuration.

Svend Erik Nielsen


Haldor Topsøe A/S, Lyngby, Denmark

Peter Vang Christensen


Haldor Topsøe A/S, Lyngby, Denmark

Introduction with a lower investment compared to erect-


ing new facilities. Furthermore, local infra-
The increasing demand for ammonia and fertil- structure is available and can be utilised.
isers is widely discussed and well documented. The
world population is constantly growing and the fertil- If the plant owner consider revamping an existing
iser consumption increases by 2-3% every year. plant it is our experience that the best way to structure a
The increasing demands can in principle be satis- revamp project is to divide the project into a study
fied by a number of actions such as: phase followed by an engineering and implementation
phase provided that the scheme identified in the study is
• Construct new production facilities at loca- attractive to the plant owner.
tions where natural gas is cheap, and trans- The target of the study phase is to establish the
port the products to the consumers. most attractive revamp scheme in accordance with the
• Revamp existing production facilities for objective of the project together with a cost estimate for
increased capacity as required in order to the implementation of the project. Thus, the main pur-
satisfy the increased demand locally. This pose of the study is to establish a solid basis for the
additional capacity can often be achieved

AMMONIA TECHNICAL MANUAL 168 2004


plant owner to evaluate the attractiveness of the revamp by installing new internals or by adding
project at a minimum cost. new converter(s)
Which specific revamp features to consider in the • Changing make-up gas addition point by
study phase of the revamp project will have to be using a make-up drying unit or alterna-
evaluated on a case to case basis depending on the ob- tively an ammonia washing unit
jective and the specific conditions prevailing. Below are • Introduction of purge gas recovery unit
listed a number of the current revamp features which • Modification/replacement of rotating ma-
can be considered when establishing the best possible chinery to add more capacity or to reduce
revamp scheme: energy consumption

• Upgrading of feed purification and desul- The most often used features are introduction of
phurization section prereformer, installation of additional ammonia con-
• Installation of feed gas saturator verter capacity, new reformer tubes and reduction of
• Upgrading of mixed feed preheater and in- S/C ratio. However, the choice beween the above op-
let header system to increase reformer inlet tions must of course be made during the study phase on
temperature the basis of a careful analysis of the specific situation,
• Reduction of the steam to carbon ratio in keeping in mind that an attractive revamp concept will
the reformer, taking advantage of new be characterised by:
high-activity reforming catalysts
• Change of reformer catalyst tubes with • Low investment cost per additional ton of
thinner wall tubes made from new, ammonia product
stronger alloys • Low operating costs
• Introduction of combustion air preheat • Short implementation time
• Installation of adiabatic prereformer • Minimum interference with the existing in-
• Installation of a “heated prereformer”, a stallation
heat exchange reformer heated by either
flue gas or by process gas The above approach to a revamp project has been
• Installation of an add-on convection re- applied in connection with a number of revamp projects
forming unit (e.g. the Topsøe HTCR de- currently under implementation for a plant owner in In-
sign) with associated waste heat recovery dia. In the following we will list the selected revamp
in parallel with the existing reformer options and describe one of the revamp features to be
• Installation of a primary reformer with as- implemented in more detail. Following this we will
sociated waste heat recovery in parallel demonstrate that the list of available revamp options is
with the existing reformer constantly being extended by the development of new
• Introduction of new high-activity shift technology features. In this respect a novel and attrac-
catalysts and re-configuration of shift sec- tive revamp feature which is of particular interest when
tion by e.g. introduction of a LT shift the reforming capacity of an existing plant is a bottle-
guard reactor neck will be presented.
• Modification of shift reactor outlet system
to reduce pressure drop
• Upgrade of CO2 removal unit to boost ca- Revamp Projects Currently under
pacity or reduce energy consumption by Implementation
introducing improved packing materials
and/or by adding additional flash stages In India, for a significant period of time, gas short-
• Modifications/additions of coils in the re- age has presented significant restrictions to the ammo-
former waste heat section nia producers. Many plants changed their feedstock
• Replacement/addition of heat exchangers from natural gas to naphtha and some plants have even
to handle revised operating conditions been designed for mixed feed operation. These days,
• Addition of more ammonia synthesis ca- LNG is becoming available in India. In view of this,
pacity by modifying the existing converter many plant owners consider revamping their plants to
be able to operate on LNG and at the same time to re-

2004 169 AMMONIA TECHNICAL MANUAL


duce the specific energy consumption to the lowest pos- • Introduction of LT shift guard
sible level, with reasonable investment cost. • New outlet systems from HT, LT shifts
One of the major fertiliser producers in India, and methanator in Kellogg designed plants
IFFCO (Indian Farmers and Fertilisers Cooperative) has • Revamp of the oldest CO2 removal units to
decided to revamp all their ammonia plants to be able to two stage Giammarco Vetrocoke/aMDEA
meet the future Indian fertiliser scenario and is cur- with two-stage flash
rently implementing energy saving revamp projects in • Introduction of make-up gas chilling
their 5 ammonia plants. The five plants are: • Retrofit of synthesis gas compressor train
• New make-up gas point along with ammo-
• Kalol, natural gas-based plant started up in nia wash unit in Kellogg designed plants
1975 designed by Kellogg • Introduction of radial flow S-50 converter
• Phulpur I, naphtha-based plant started up and new waste heat boiler
in 1980 designed by Kellogg
• Aonla I, natural gas-based plant started up The achievable energy savings by implementing the
in 1988 designed by Topsøe revamp schemes in the five ammonia plants vary be-
• Aonla II, mixed feed-based plant started up tween 0.3 – 0.9 Gcal/MT NH3 (1.3 – 3.9 MMBtu/ST
in 1996 designed by Topsøe NH3). Considering that the introduction of the S-50
• Phulpur II, naphtha-based plant started up converter is the revamp feature that accounts for the
in 1997 designed by Topsøe highest contribution to the overall energy savings, this
feature will be described in more detail in the follow-
The revamp schemes that will be implemented in ing.
each of the five ammonia plants was developed during
the study phase of the project where various alternative
features were considered before arriving at the most at- S-50 Converter – M.W. Kellogg Plants
tractive schemes. Considering that the plants are of dif-
ferent designs and of very different vintage the revamp In Kellogg plants, the ammonia synthesis loop con-
features that were evaluated during the study phase was tains an existing ammonia converter unit with
carefully considered in each specific case. built-in feed/effluent exchanger. From the existing
As part of the study work a cost estimate was de- converter, the exit gas is sent direct to the new S-50
veloped in order to provide the plant owner with a solid
converter at a temperature of approx. 325° (617°F).
basis for deciding if implementing the schemes would
be an attractive investment.
After the S-50 converter a new MP steam boiler is
A number of revamp features that will be imple- introduced. See Fig 1.
mented in the five ammonia plants are listed below (not As the inlet temperature to the S-50 converter
all features will be implemented in all of the plants): is lower than the required inlet temperature to the
catalyst bed, an S-50 converter with a lower heat
• Final desulphurisation section to handle exchanger is applied in the Kellogg plants.
the new feedstock
• New coils in cold end of reformer waste
heat section

AMMONIA TECHNICAL MANUAL 170 2004


Purge
Gas

BFW
Preheater

New MP CW NH (l) NH (l) NH (l)


Steam Boiler 3 3 3
Ammonia
Product

Figure 1: Lay-out of Synthesis Loop in M.W. Kellogg-designed Plant with S-50 Converter

The S-50 converter consists of a full closure pres- passed the shell side of the heat exchanger, and the
sure vessel and a converter basket. The converter basket mixed gas stream passes to the top of the converter
consists of a catalyst bed and a feed/effluent heat ex- through the transfer pipe located in the centre of the
changer (lower heat exchanger). See Fig 2 for details. catalyst bed. The amount of cold shot gas determines
The main part of the gas is introduced into the con- the inlet temperature to the catalyst bed.
verter through the main inlet in the top of the converter At the top of the converter the gas passes to the
(A) and passes downwards through the outer annulus inlet panels of the catalyst bed. It passes the catalyst
between the basket and the pressure shell, keeping the bed in radial inward direction and flows to the annulus
latter cooled. It passes to the shell side of the feed- between the bed and the central transfer pipe.
effluent exchanger, where it is heated to reaction tem- The effluent from the catalyst bed passes the tube
perature by heat exchange with the converter effluent side of the heat exchanger, thereby heating the feed gas
leaving the catalyst bed. to the reaction temperature, and flows to the converter
The remaining part of the gas, the cold shot gas, is outlet (C).
introduced through the inlet in the bottom of the con-
verter (B). It mixes with the main inlet gas having

2004 171 AMMONIA TECHNICAL MANUAL


fore the gas enters the S-50 converter at approx. 370°C
(698°F). See Fig 3 for details.

S-200 S-50
Converter Converter

Purge Gas
NH3 (l)

Preheater
BFW CW

Boiler NH3 (l) NH3 (l)


Product
Ammonia
Make-up Gas

Figure 3: Lay-out of Synthesis Loop in a Topsøe-


designed Plant with S-50 Converter

In the Topsøe designed plants, the S-50 converter is


designed as a hot wall radial flow converter (further de-
tails on the hot wall design are provided in [1]). The
converter lay-out is shown in Fig 4.
In this case, the S-50 converter has no lower heat
exchanger and the optimum inlet temperature to the
ammonia converter is achieved by cooling the effluent
from the first ammonia converter in the intermediate
HP steam boiler. The inlet temperature to the S-50 con-
verter is controlled by means of a by-pass around the
HP steam boiler.
The actual energy saving achieved by installing an
S-50 converter depends upon the lay-out of the synthe-
sis loop, but varies in the IFFCO cases between 0.15 –
0.30 Gcal/MT NH3 (0.65 – 1.30 MMBtu/ST). With the
high feedstock cost in India, this gives very attractive
payback times ranging from 1.5 – 3 years.
The revamp projects in IFFCO’s five ammonia
plants are implemented in a phased manner, and all the
revamp options will be installed from now and up to
3rd quarter 2005.
As stated previously the main objective in the re-
vamp projects for IFFCO has been to reduce the spe-
Figure 2: S-50 Converter with Lower Heat Ex- cific energy consumption, and the revamp options
changer evaluated in this connection has therefore been with the
target to meet this objective.
S-50 Converter – Topsøe Plants

The ammonia synthesis loop in the Topsøe-


designed plants contains an existing converter without a
built-in feed/effluent exchanger. From the existing con-
verter, the exit gas is sent to a new HP steam boiler be-

AMMONIA TECHNICAL MANUAL 172 2004


However, very often the plant owner has the main
objective to increase the capacity of the plant. In this
connection it will be relevant to evaluate how to in-
crease the capacity of the existing reforming section in
the most attractive way. In the following a new revamp
feature addressing this issue will be presented.

Revamp by Installation of HTER


When significant capacity increase is desired, the
traditional revamp options may be insufficient
because bottlenecks in existing equipment, espe-
cially in the reforming section, restrict a possible in-
crease in production capacity. In such cases the pre-
ferred solution was the introduction of a prereformer [2]
to reduce the load on the primary reformer. In other
cases it has been necessary to construct a new primary
reformer in parallel to the existing one. In addition to
these options, Topsøe offers a new revamp option – in-
stallation of a newly developed proprietary and pat-
ented Haldor Topsøe Exchange Reformer (HTER) in
parallel with the existing reformer. This revamp feature
caters for significant capacity increase, and may repre-
sent an attractive solution especially in cases where the
existing reformer or the steam generation system is a
bottleneck.

This new revamp option will be described in the


following. The basis will be a typical ammonia plant
with a lay-out as illustrated in Fig 5.

Figure 4: Hot Wall Radial Flow S-50 Converter

2004 173 AMMONIA TECHNICAL MANUAL


Desulphurization Reforming Shift

Natural Gas
Process Air

Flue Gas

Purge Gas

CO2- CO2
Removal
Ammonia Process
Product Condensate

Ammonia Synthesis Methanation

Figure 5: Typical Lay-out of an Ammonia Plant

The HTER is a newly developed proprietary heat HTER concept for revamps of hydrogen plants may be
exchange reformer design, which offers a compact and found in [3].
cost-effective increase of the reforming capacity when The installation of a HTER in parallel with the
installed in parallel with an existing steam reformer reforming section in a typical ammonia plant is illus-
(SMR). A description of the trated in Fig 6.

Secondary HTER
Reformer

Process
Steam

Desulp.
Natural
Gas

Process Air

Figure 6: Revamp of an Ammonia Plant by installation of HTER in Parallel with SMR

AMMONIA TECHNICAL MANUAL 174 2004


The HTER is installed in parallel with the SMR and change to the reforming reaction in the HTER, be-
fed independently with desulphurized feed mixed with fore it passes to waste heat recovery and further proc-
steam. This allows for individual adjustment of the essing.
feedstocks, e.g. the steam to carbon ratio, to obtain a The operating conditions before and after revamp
desired conversion. The outlet gas from the existing by installation of a HTER in an ammonia plant are
secondary reformer is transferred to the HTER and summarised in Table 1 and compared with the installa-
mixed internally with the product gas from the catalyst tion of a prereformer and a fired
bed installed in the HTER. The mixed gas is then sup- heater.
plying heat by heat ex

Before After After


Revamp Revamp Revamp
Prereformer HTER
NH3 Production, MTPD 1,500 1,650 1,650
(STPD) (1,654) (1,819) (1,819)
SMR Duty, Gcal/h 78.5 71.2 72.9
(MMBtu/h) (311.5) (282.5) (289.3)
NG Consumption for Feed and Fuel, 57,786 61,683 59,532
Nm3/h (MMSCFD) (2.15) (2.30) (2.21)
HP Steam Prod. (110 kg/cm2g, 510°C), MT/h 283 284 267
(ST/h) (312) (313) (294)
Steam Export (44 kg/cm2g, 390°C), MT/h 91 66 33
(ST/h) (100) (73) (36)
Outlet Temperature SMR, °C 820 816 801
(°F) (1,508) (1,501) (1,474)
Relative Flow through Reformer 1.00 1.10 0.99

Table 1: Operating Conditions Before and After Revamp by Installation of Prereformer or HTER

The operating conditions are unchanged for the normally used for steam production. Furthermore, due
SMR after the revamp with respect to steam to carbon to the parallel operation, the pressure drop across the
ratio. Since the duty of the reformer is slightly reduced, reforming unit is minimised.
the amount of waste heat available from the flue gas is In most cases, the steam production lost in the proc-
reduced. This in combination with the fact that the natu- ess unit after the revamp can be substituted by steam
ral gas preheat duty along with the process air preheat production in already existing installations, e.g. by util-
duty is increased more or less proportionally to the ca- ising idle capacity in auxiliary boilers. In other cases,
pacity increase, gives certain modified operating condi- especially in cases with very large capacity increase, it
tions in the existing flue gas waste heat section and the may be necessary to install additional steam generating
revised operating conditions have been taken into ac- capacity. In both situations, additional steam production
count. can often be made with cheaper fuel than the fuel nor-
Compared to a revamp including a prereformer, the mally used in the tubular reformer.
inclusion of a HTER offers certain benefits.
Using the HTER, which operates in parallel to the
existing primary reformer, both the load on the combus-
tion side as well as the process side of the primary re-
former are reduced. The overall effect is seen directly
on the steam production, since the HTER utilises part of
the waste heat available after the secondary reformer

2004 175 AMMONIA TECHNICAL MANUAL


A HTER has been in successful industrial operation References
in combination with an ATR in a synthesis gas generat-
ing plant at SASOL in South Africa for more than 16 1. Dybkjær, I., “Advances in Ammonia Con-
months. The operating conditions in this installation, verter Design and Catalyst Loading”, pre-
which has a capacity corresponding to more than sented at the NITROGEN ’97 Conference,
100,000 Nm3/h (3.7 MMSCFD) of hydrogen, are more Geneva, Switzerland, Feb. 9-11, 1997
severe than what would be expected in a revamp of an 2. Nielsen S.E., Dybkjær I., ”Use of Adia-
ammonia plant as described above. batic Prereforming in Ammonia Plants”,
It should be emphasized that the HTER installed in Ammonia Plant Safety & Related Facili-
SASOL was also as a revamp project in an existing ties, Vol. 37, AIChE, New York (1997)
plant, i.e. the tie-in of the HTER in an existing plant has 3. Winter Madsen, S., Dybkjær I., ”Novel
already been successfully demonstrated. Revamp Solutions for Increased Hydrogen
Regarding the economical attractiveness of install- Demand”, presented at the 8th Europeran
ing a HTER in an ammonia plant a cost comparison re- Technology Conference, London, U.K.,
veals that the expected investment cost for the HTER Nov. 17-19, 2003
concept in most cases will be a very attractive alterna-
tive compared to the cost related to the installation of a
prereformer with a fired heater for the same capacity
increase.

Conclusions
• In order to arrive at the most attractive re-
vamp scheme it is of paramount impor-
tance that the scheme is optimised based
on the objective and the specific conditions
prevailing.
• As demonstrated with the IFFCO revamps,
various attractive possibilities exist for re-
vamping ammonia plants to save energy or
to increase capacity.
• The novel revamp feature, the Haldor Top-
søe Exchange Reformer (HTER), is an at-
tractive alternative for increasing the ca-
pacity of the reforming section in an
ammonia plant.

AMMONIA TECHNICAL MANUAL 176 2004

You might also like