Professional Documents
Culture Documents
Overview of Pipeline Engineering PDF
Overview of Pipeline Engineering PDF
Overview of Pipeline Engineering PDF
subsea engineering
Overview of
pipeline
engineering
2
All information contained in this document has been prepared solely to illustrate
engineering principles for a training course, and is not suitable for use for engineering
purposes. Use for any purpose other than general engineering design training constitutes
infringement of copyright and is strictly forbidden. No liability can be accepted for any
loss or damage of whatever nature, for whatever reason, arising from use of this
information for purposes other than general engineering design training.
All rights reserved. No part of this publication may be reproduced or transmitted in any
form or by any means whether electronic, mechanical, photographic or otherwise, or
stored in any retrieval system of any nature without the written permission of the
copyright holder.
Jee Limited
Hildenbrook House
The Slade
Tonbridge
Kent
TN9 1HR
England
ROUTE SELECTION 43
Expectation 45
Survey Techniques 47
Soil Types 56
Routing of pipeline 63
PIPE SIZING 77
Expectation 79
Diameter Sizing 80
Wall Thickness for Bursting 88
Wall Thickness for Hydrostatic Collapse 95
Rigid steel pipe manufacture 101
Buckles 116
4 Overview of pipeline engineering
MATERIALS 127
Expectation 129
Selection for Strength 130
Selection for Corrosion Resistance 134
Clad and Lined pipes 139
Titanium and Composites 143
PROFILES 535
EXPECTATION
EXPECTATION
Different parts of the world take different approaches to offshore hydrocarbon recovery.
This is due to a number of factors, including custom and practice for the region and the
cost and confidence in carrying out a particular solution in that region.
We will introduce some of the common terms that are used in the industry.
It is uncommon to find just a single pipeline running from the field to the land terminal.
We examine the other types of additional lines found in an offshore field.
10 Overview of pipeline engineering
EXAMPLE LAYOUTS
LAYOUT
Refinery Facility
Crossing
fence
Landline
1st valve at pig trap
Pipework
Landfall /
shore approach
Process
Floating Crossing
platform SPM
hose & tails
Unmanned
Pig launcher platform with
FPSO surface trees
Riser SSIV
PLEM Trunk / export
for gas pipeline to shore
Catenary
riser (gas, condensate or oil)
Z spool
Wellheads may either be on an unmanned platform with surface trees, or with subsea
wellheads around a manifold cluster. This slide shows the recovery of hydrocarbons
from the wellheads through a FLOWLINE and RISER to the FPSO or platform, from
where it leaves through a TRUNK or EXPORT PIPELINE to the landfall. Normally,
the fluid from the wells (gas, oil, water and sand plus any injected chemicals) would be
separated into two commercial streams at the facility (two out of oil, gas and
condensate), which are delivered to shore down separate pipelines. Sometimes, the gas
condensate is injected into the oil export line.
In deep water, the processing facilities are on a FPSO (Floating Production, Storage and
Offloading) vessel, with the product being shuttled to a SPM (Single Point Mooring)
system and a pipeline to shore. In shallower water, it is possible to use a fixed process
platform on a jacket with a pair of permanent pipelines to shore. The trunklines
continue as LANDLINES to the refinery, where heavier wall PIPEWORK is used.
PIPEWORK is also used on the process facility.
This course provides an overview of the design, installation and operation of pipelines.
Field layouts 11
GULF OF THAILAND
Shallow water
Dry trees on
unmanned platforms
Process platforms
In many areas of the world, oil and gas is found in relatively shallow water depths of up
to 100 m (330ft).
Developments often take the form of unmanned platforms with ‘dry’ trees fitted on top.
These can be easily serviced – unlike the deeper water wet trees which are fitted to the
top of wells at seabed level. (We will examine dry and wet trees later: a dry tree is above
the sea surface and can be easily maintained whereas a wet tree is located at the seafloor.)
The flowlines link the unmanned platforms to the manned process platform. Export
lines send the gas, oil or condensate to shore or to a tanker from a buoy or floating
storage unit (FSU).
12 Overview of pipeline engineering
Two extremes of field layout show how different deeper water developments vary.
British Borneo’s Morpeth development is a small field and a neat layout, and was
completed in 1998. It is located in 520 m (1700ft) of water, in the Gulf of Mexico
Ewing Bank (EW) blocks 921, 964 and 965, off the shore of Louisiana.
The Morpeth deck is 34 m (110ft) square and the facilities are spread over two levels.
The process equipment has a design throughput of 6100 m³ (38 500bbl) per day and 1.2
million m³ (42 million scf) per day of gas. It was the first tension leg platform (TLP)
without surface completions.
There are three production wells and an adjacent water injection tree located some 460
m (1500ft) from the Atlantia Seastar TLP. The production flowlines can be pigged back
to the wells using loops at the wellheads. Well fluids and water injection lines are
brought into I tubes below the waves using six flexible lines. Strakes on the 219.1 mm
and 323.8 mm (8in and 12in) rigid export steel catenary risers (SCRs) are used to prevent
vortex-induced vibration (VIV). The pipeline system was designed to handle throughput
volumes of twice the Morpeth peak production rates.
The two export lines deliver the processed oil and gas to the Grand Isle 115 platform
lying in 112 m (366ft) of water near the continental shelf margin, some 35 km (19 miles)
from Morpeth. From Grand Isle 115, the oil continues through the main Amberjack
pipeline system to the Clovelly onshore terminal in Louisiana. The gas and gas liquids
go through Texaco’s Discovery pipeline system.
Field layouts 13
The Foinaven gas and oil development, shown above (based on as-built survey data), is a
very different story.
It is a far more complicated arrangement with further flowlines and risers having been
added since the original installation was completed in 1997. Water depth at the field is
around 500 m (1640ft) reducing to around 450 m (1500ft) at the floating production
storage offloading (FPSO) unit.
The pliant wave configuration for the risers was developed for this installation, making
use of their flexibility to connect to the flowlines. This is not quite as straightforward as
it sounds and was designed to avoid clashing of the risers and umbilicals.
The two drill centres to the left (orange) and foreground (cerise) north and west of the
FPSO are served by 219.1 mm to 355.6 mm (8in to 14in) rigid lines bringing the well
fluids to flowline termination assemblies (FTAs) which are connected to flexible risers
(green). Lines to both fields provide injection from the rear cluster. The grey lines show
submerged buoys supporting the anchor cables that maintain the FPSO on station. The
length of these can be adjusted at the vessel to move within a predefined envelope so
balancing out fatigue damage of the anchor cables.
Process facilities consist of two parallel oil separation and gas compression trains with a
combined liquid handling capacity of 23 000 m³ (145 000 bbls) per day and 3.2 million
m³ (114 million scf) per day of gas. Gas compression capacity is shared approximately
50:50 between export and providing artificial lift to oil production wells (gas-lift).
Currently around 15% of produced gas is used as fuel.
The gas is exported through the lines to the right (salmon pink) first through
Schiehallion and on to Sullom Voe before being sent offshore again to the Magnus EOR
project to increase recovery from that reservoir.
Where
■ EOR = enhanced oil recovery
14 Overview of pipeline engineering
The Foinaven FPSO has a central turret system permitting the vessel to ‘weathervane’
minimising environmental (wind, waves and current) loading.
Other such vessels may have a forward turret or a fixed orientation depending upon the
environmental forces they must withstand. In Arctic or tropical regions, some FPSOs
can release the attached riser flowlines and cables so that the vessels can steam out of
danger of icebergs or hurricanes/typhoons.
The Petrojarl Foinaven FPSO was one of the first vessels to be used in such extreme
conditions, being exposed to the hostile Atlantic weather and strong seabed currents. It
has an overall length of 240 m (787ft) and an oil storage capacity of around 47 700 m³
(300 000 bbls).
Crude offloading and fiscal metering facilities are installed at the stern of the FPSO and
shuttle tankers hook up and load approximately every two days at current oil production
rates. Two new 95 000 m³ (600 000 bbl) shuttle tankers were commissioned in early
2003 (Petronordic and Petroatlantic) and transport oil primarily to the Flotta oil terminal
in Orkney with a small number to Tranmere on Merseyside.
Field layouts 15
In deeper water, subsea trees from remote well clusters may connect either to a floating
unit or to a fixed platform. We will see later that tensioned floating facilities may be
fitted with ‘dry trees’ if they are stationed above the drilling centre.
Once treated, the product is sent to shore by separate streams. This may be through
pipelines or shuttle tankers. Some gas may be used as fuel aboard or re-injected to aid
recovery of oil.
16 Overview of pipeline engineering
IN-FIELD OR FLOWLINES
We will be referring to two main types of line – flowlines and trunklines. Some general
rules are shown above. However, diameters and lengths outwith the ranges specified
may be encountered. The type of pipe (rigid or flexible) and methods of installation may
also differ. Installation method is usually determined by cost and is affected by the water
depth, barge availability, diameter and coating type amongst other things.
Notwithstanding this, the rule holds that the flowline takes the mixed fluids to the
processing facility on the platform or FPSO where the oil, gas and condensate are
separated from the water, sand and any chemicals injected into the reservoir. Then, the
individual streams can be sent to shore normally in two export pipelines – for an oil
field, the lines will be for oil and gas, for a gas field, the lines will be for gas and
condensate. It may be that a shuttle tanker is used to transfer oil from a small field to an
SPM ashore – avoiding the need for a large diameter oil export line.
Subsea separation is a new technology that is being proposed for some Norwegian
developments. It will completely eliminate the need on small fields for a platform or
FPSO. The two streams of oil and gas can be sent ashore from an underwater
separation unit controlled and powered using umbilical cables.
Field layouts 17
EXPORT OR TRUNKLINES
Occasionally, the reservoir product and flow rate is such that unseparated gas is sent to
shore for processing from an unmanned platform (for example, Goldeneye in Scotland).
This decision was taken when the whole-life capital and operating costs (CAPEX and
OPEX) were assessed.
Other terms for pipelines that may be encountered are jumpers which are used to
connect the wellhead to the manifold and spool pieces which connect between the
pipeline and risers. There is some overlap between these terms. Jumpers tend to refer
to short lengths of flexible lines and rigid spools may be used to connect the wellhead to
the infield line or manifold.
18 Overview of pipeline engineering
Rigid spools and jumpers are often shaped to allow thermal expansion of the pipeline
itself. This may be of the order of 1 m to 2 m (3ft to 7ft) or even more. These L or Z
shaped connections allow bending to take place at the platform or wellhead, avoiding
loads being transmitted from the pipeline to these structures.
BUNDLES
In-field flowlines
Many small diameter lines in a carrier pipe
Carrier 813 mm to 1219 mm (32in to 48in)
Thin wall – less than 12.7 mm (½in)
Used to gather flow from separate wells
Improved thermal and impact protection
Towed out to field and annulus flooded
Lengths up to 7.5 km (5 miles)
Two lengths connected together using jumpers
Integrated manifolds
In cases where a cluster of wellheads remote from the platform, serves a small field,
instead of running separate flowlines a bundle may be used. This contains a number of
rigid flowlines in a large diameter (but thin-walled) carrier and the whole unit is towed
out to the field in lengths up to 8 km (5 miles) where it is lowered to the seabed by
flooding the annulus.
By gathering all the lines within a carrier, it is possible to provide better thermal
properties and improve on the impact protection.
The manifolds can be integrated within the bundle package to save on the numbers of
offshore spool pieces and installation operations that are required.
Field layouts 19
The commercially recoverable reserves in Fram Vest are estimated to total 16 million m³
(100 million bbl) of oil and 3.5 billion m³ (120 billion ft³) of gas, with a life of 15 years.
The field commenced production in the autumn of 2003.
It lies some 22 km (14 miles) north of the Troll C facility and is being developed by
Norsk Hydro, taking advantage of the existing infrastructure in the Troll area. This first
development may pave the way for the development of other low volume reservoirs in
the area that are not profitable at present, .
The oil is transported in two 90 km (56 mile) long pipelines from Troll C to Mongstad.
The gas is re-injected as pressure support.
Additional lines in the development include provision for a pigging loop, water injection,
gas injection and gas lift, along with associated umbilicals.
20 Overview of pipeline engineering
With a number of wells located at a remote site, it may be prudent to gather the product
(oil/gas mix) together in a single, co-mingled flowline to avoid loss of heat and improve
flow rates. However, it is common to provide a smaller diameter test line of to prove
individual down hole conditions.
Alternatively, this may also be configured as a pair of lines which combine the co-
mingled/test line operations with a pigging loop. The pig can be sent down from the
process facility to the wellhead manifold and returned to the platform, sweeping out wax
or hydrates ahead of it.
Some flows need injection from the platform to the well in order either to improve flow
or prevent corrosion. This uses a small diameter – 76 mm (3in) diameter line
piggybacked on the main flowline or it can be pumped through one of the hoses in an
umbilical.
Some fields require water to be injected to improve the recovery of gas from the
reservoir. This is injected through a separate well from the recovery well, driving the
product ahead.
Similarly, gas may be abstracted and re-injected into an oil reservoir to aid recovery. Or
gas may be needed just at the well or riser to help heavy oil flow up through the vertical
section of the flowline.
Control of the valves and manifolds at the field is usually accomplished with a separate
umbilical laid adjacent to flowlines. This may also contain chemical injection lines and
monitoring cables to determine the conditions at the wellhead.
Field layouts 21
Any questions?
Short in-field lines carry mixed product out of the well to the process facility. Separate
streams are then sent to shore through export lines.
The ends of these pipelines are connected to the riser at the platform and the manifold
or wellhead using short lengths of rigid or flexible jumpers or spoolpieces.
Some in-field lines are installed in bundles, possibly incorporating the many other lines
and cables needed for field development.
22 Overview of pipeline engineering
SUBSEA EQUIPMENT
WELLHEAD TREES
Once a well has been drilled into the formation, the blow-out preventer (BOP) stack is
replaced with a wellhead tree unit such as shown above. Because of the shape and
structure of early units, they were sometimes fancifully called Christmas trees.
Different configurations are used for various fields depending upon what future work is
envisaged. Operations to carry out repairs or increase flowrates are called well
‘workovers’.
The trees are attached onto the casing tube and control the production rate along the
flowline using valves and chokes.
The right hand picture shows the installation of such a unit through the moonpool for
the Petrobras Roncador project. The operators provide an indication of the equipment’s
size.
Where fishing interaction is likely, a trapezoidal protective structure (not shown) can be
fitted over the wellhead tree.
Field layouts 23
MANIFOLDS
Where a cluster of wells is remote from the platform, as shown on the right, they are
often served by a manifold and are connected using flexible or rigid jumpers .
Added functionality can be provided to control of the wells through an umbilical cable
to the platform, or a pigging loop to flush wax or hydrates on a regular basis (daily or
weekly).
The Troika oil field development is in 823 m (2700ft) deep water and is located 241 km
(150 miles) offshore Louisiana in Green Canyon 244 unit.
Troika was developed using a compact eight-slot subsea manifold, tied back to Shell’s
Bullwinkle platform 22.5 km (14 miles) away in 410 m (1350ft) of water. This required
the longest multi-phase subsea tie-back system in the Gulf of Mexico.
The Troika field was initially developed using five wells, positioned 15.2 m to 33.5 m
(50ft to 110ft) from the central manifold. The conventional subsea trees are rated at 69
MPa (10ksi), and are dual-bore 102 mm x 51 mm (4in x 2in) configurations, installed
using guidelines.
Thermally-insulated jumpers are used to connect the individual trees to the subsea
manifold. Each jumper is rigid, although normal bends accommodate thermal
expansion. Electrical connections from the manifold to the tree were made with the aid
of an ROV.
The Troika template/manifold system measures 13.7 m long by 9.4 m wide (45ft by
31ft) and reaches a maximum height of 7.9 m (26ft) above the seafloor. This small size
permitted its installation, using just a supply boat and the drilling rig (shown in
photograph top right). The template weighs approximately 43 tonne (95kip) and
provides support to the manifold and the jumpers, flowlines and trees.
Two 273.1 mm (10in) diameter carbon steel production flowlines connect the Troika
subsea manifold to the Bullwinkle platform. These flowlines are insulated to minimise
paraffin deposition and to provide reaction time for hydrate prevention, following an
unplanned shut-in. Corrosion inhibition is provide by means of chemical injection into
the subsea manifold. The flowlines were constructed in bundled cross-sections in four
11.3 km (7 mile) lengths, and are encased in an open-cell foam, in 609.6 mm (24in)
carrier pipes. The design heat-transfer coefficient for the assembly is 1 W/m²/K (0.176
BTU/hr/ft²/°F).
Field layouts 25
LARGE MANIFOLD
An appreciation of the size of some manifolds can be gained from this photograph.
In areas of the world with deepwater, soft seabeds and no fishing interaction, it is
common to use a vertical connection between the end of the pipeline and spool. PLETs
are lowered to the seabed attached to the end of the pipeline with a vertical bend. A
hinged attachment point as shown on the top left photograph provides tension to
prevent buckling of the pipeline. The central photograph shows the testing of a
spoolpiece connection to the Mardi Gras PLET. The right hand photograph shows
similar pre-installation testing for a flexible jumper.
26 Overview of pipeline engineering
PLEMs include some valve work and can be larger. They are sometimes connected after
the pipeline has been installed and pigged.
The lower left photograph shows a 610 mm (24in) pipeline with two 323.8 mm (12in)
marine loading lines These were pulled from the beach attached to a PLEM/loading
system manifold and installation sled at Isle de Bioko, Equatorial Guinea, West Africa.
A simple PLEM on a skid on the lower right is installed following the pipeline
installation.
The buoy is of diameter 11.0 m x 4.0 m x 4.8 m high (36ft x 13ft x 16ft). It is held by
just four 120 mm (5in) diameter chains attaches to seabed anchors or piles.
It is sized for a maximum moored vessel of 280 000 DWT. The maximum loading rate
is 12 000 m³/hr (75 500 bbl/hr) for 24 hour turnaround.
The vessel is connected to the buoy and can weathervane on the rotating top section.
The hoses connect to the swan neck seen at sea surface level. SPMs are often used in
shallow water for discharge to shore but can also be found at deepwater fields associated
with FPSOs.
A SALM is a mooring system utilizing a single anchor base and single riser, designed to
operate as an unmanned marine terminal in shallow water.
One is used in the Sakhalin fields, Russia, north of Japan. The unit can be lowered into
the glory hole during winter months to avoid the ice floes.
Field layouts 27
PIPELINE CROSSINGS
Crossings
Blocks
Mattresses
Rock dump
Because the spans may be subject to vibration in currents and could snag trawler nets, it
is usual that the whole length is protected with rock dump or mattresses.
The photographs show the stern deck of the Oceaneering’s DP-2 MSV Ocean
Intervention during pipeline crossing mattress installation work. It successfully installed
100 concrete mattresses, weighing 4.5 tonnes (10 000lb) each, as insulation and thermal
protection for a flowline at depths greater than 1800 m (6000ft) in the Gulf of Mexico.
An Oceaneering ROV manoeuvred the 12.2 m (40ft) handling frame at the seabed to
position the mattresses end to end.
28 Overview of pipeline engineering
Wellhead trees
Manifolds
PLETs and PLEMs
SPMs and SALMs
Pipeline crossings
Any questions?
This has shown a selection of typical equipment and features associated with field
development, as well as introducing some of the common acronyms used.
Field layouts 29
FIXED PLATFORMS
In the shallowest water, we can make use of fixed platforms. These can be constructed
from a lattice of tubular steel or reinforced concrete.
The former are normally used from the shallowest seas up to a depth of about 300 m
(1000ft). However, some examples are found in deep enclosed seas in up to 500 m
(1600ft). Such structures are generally installed by launching horizontally from a carrier
barge and then tilting to the vertical by flooding various compartments. The legs are
then piled into the seabed.
Concrete gravity based (CGB) platforms are generally floated out upright using
evacuated storage cells in the base to provide buoyancy and ballast. A minimum water
depth is needed en route to the final destination to accommodate the CGB’s draught.
At the field, the cells can be flooded in a controlled sequence to progressively sink the
CGB until it is in position on the seabed. They have the advantage that spare cells can
be used for product storage. They are often used in arctic regions where they need to
resist sea ice or bergs. Examples of this are the Hibernia platform shown and the
Russian Sakhalin platforms, north of Japan.
30 Overview of pipeline engineering
Risers for these steel platforms can be rigid steel pipework attached to the legs or jacket
face. On a CGB, the risers can be run either up the outside of the structure or more
commonly, internally within the legs. These are then connected up to the pipeline using
rigid spool pieces on the seabed. Alternatively, I tubes or J tubes may be attached in the
construction yard. Flexible pipelines are then pulled into these after installation. Small
diameter rigid pipe can also be pulled into J tubes (yielding the pipe steel) if the radii are
gentle enough. Rigid steel catenary risers have also been used with fixed platforms.
Compliant towers,
compliant piled towers
and guyed towers
250 m to 1750 m
(800ft to 5750ft) Compliant
piled tower
Risers as for shallow
water platforms
GB260
compliant
tower
GB260 floatout
As water depths increase, compliant towers, compliant piled towers or guyed towers are
used. Instead of splayed legs, these tend to have parallel sides.
Guyed platforms have diagonal cables (in a similar manner to broadcasting masts) to
provide lateral stability against currents.
Since these structures are essentially fixed to the seabed, they use riser designs similar to
other fixed platforms.
FPSOs
FPSOs are used in all water depths. They are vessel shaped as shown above.
In shallower water, they are used for early production or shallower fields. In deeper
water, they provide an alternative to fixed platforms.
There was a limitation on their use within USA waters until early 2006, when double-
hulled FPSOs gained approval.
They usually rely on four or five groups of anchor cables to hold their station. In order
to minimise wind and current forces, they may ‘weather vane’. This means that all the
anchor cables and risers are connected to a turret, which can rotate. This may be located
either centrally or at the bow as shown.
In areas where winds from a single direction predominate, the vessels are kept at a fixed
alignment and designed to resist all environmental forces. They can be anchored at the
bow and stern with the risers attached to the side of the vessel.
Risers for FPSOs can be flexible pipelines between approximately 250 m and 1500 m
(800ft to 5000ft). Different arrangements such as simple catenary, steep S, lazy S, steep
wave or lazy wave can be used, depending on the water depth, current and vessel
movement.
Hybrid risers consist of a buoyant stalk (or tower) from the seabed up to about 100 m
beneath the surface. From the top of the stalk to the vessel a flexible pipe is used.
Some vessels use a rigid steel pipeline in a simple catenary. This can be subjected to
vortex-induced vibration (VIV).
32 Overview of pipeline engineering
Tension leg platforms rely on vertical anchoring to the seabed. The semi-submersible
pontoons provide buoyancy.
Spars, deep draught floaters, deep draught caisson vessels (DDCV) and single column
floaters (SCF) all rely on a large cylindrical tube combined with catenary anchor cables,
to provide improved lateral stability.
Risers for both of these systems can be vertical rigid steel pipes. These are often
attached to the platform on an independently-tensioned floor. SCRs are also used.
Not shown above are semi-floating production systems (SFPS). These have a surface
structure similar to that for a TLP. However, they are anchored in a similar manner to
FPSOs using catenary cables. Their risers are similar to those for the fixed alignment
FPSO: flexibles, hybrids or SCR.
Field layouts 33
RISER USES
The riser is normally defined as a section of pipeline from seabed to topside. This
would normally include the multiflow lines from the wells or manifold to the processing
facility and the export trunk oil and gas lines to shore.
However, for a FPSO, the term ‘riser’ might mean the export lines to the SPM, which
need not necessarily return to the seafloor. And, as the picture shows, the drilling mud
riser is also slung between the platform and the vessel without touching the seabed.
So, there are many variants on this theme and we can categorise risers in terms of their
functions, where they are used, and their physical configurations.
First of all, let us look at the functions that the risers perform. Risers are used for
drilling, production, export, workover and umbilicals. For the pipeline engineer, the
main focus of attention is on the production risers. However, similar technology applies
to all of them.
The picture shows a traditional fixed platform. It contains a rack of production risers in
the centre of the jacket (from the platform wells) and also a rack of production risers on
one outside face, serving the flowlines and export pipelines. The platform derrick may
either be used to workover existing new wells or drill new ones, in which event there will
be a workover or drilling riser in the main rack beneath it. In this particular case, the
drilling fluids are provided from a floater adjacent to the platform via temporary flexible
risers hung in a catenary.
34 Overview of pipeline engineering
DRILLING RISER
Conductor
Riser
system
Insulation/
buoyancy
BOP
stack
system
The above picture shows a drilling riser with a blow out preventer (BOP) stack beneath
it. This provides four methods of preventing blow-out, ultimately by crimping the riser.
This fatally damages the riser, so its operation is controlled by the drillers and only used
in an emergency.
As you can see from the cross-section, the purpose of this riser is to contain the rotating
drill bit. Mud is forced down the centre, and mud plus cuttings up the annulus.
FPSO SPM
FPSO W riser
Clump weight
Touchdown
Subsea manifold clamp and tether
The picture shows flexible flowline risers running from the seabed in a lazy S
configuration up to a floating production vessel. The export risers are configured in a
lazy wave with the distributed buoyancy rather than the midwater arch tethered to the
clump on the seabed.
An alternative used on the Girassol project for a pipeline linking to the SPM buoy is a W
riser. This uses distributed buoyancy to lift the central section (avoiding high hydrostatic
head), yet keeping the area adjacent to the buoy deeper than the shuttle tanker’s draught.
Although the lefthand view above shows flexible risers, rigid steel risers are also used in
deeper water.
The W riser shown is rigid pipe although flexibles can be used. They are designed to
provide enough draught for vessels passing over them but remain shallow enough to
avoid excessive collapse pressures due to the density differential between seawater and
product oil.
36 Overview of pipeline engineering
RISER CODES
The picture shows a semi-sub workover rig with a workover riser connected to a subsea
well. The FPSO is already on station and connected to the shuttle or storage tanker.
The well may be some distance from the FPSO.
The purpose of the workover riser is to connect the production tubing and annulus back
to the rig in order that maintenance tasks can be done downhole or the production
tubing can be pulled and replaced.
A comparison is given of the relevant sections of the ISO and API codes for different
aspects of the work.
Buoyant
Compliant sleeves
Vertical
Axis Riser Steel
Catenary
Bare pipe
Riser
The Compliant Vertical Axis Riser (CVAR) and the Lazy Wave Steel Catenary Risers
(LWSCR) are alternatives to the simple Steel Catenary Riser (SCR). They accommodate
greater vessel movement by flexing. The Top Tensioned Riser (TTR) accommodates
vessel movement by applying a tension at the vessel and allowing the riser to ride up and
down in a shaft.
Both the CVAR and LWSCR make use of sections of buoyant sleeved pipe to modify
the simple catenary shape. Buoyancy on the W riser ensures that the hydrostatic
pressure is not excessive.
In the case of the CVAR, the lower section of pipe (perhaps half of the water depth)
ensures a near-horizontal portion of pipe (at mid-water depth), allowing vertical
movement at the vessel to be taken out of the system and preventing it from
significantly modifying the axial stress. The horizontal offset is typically a quarter of the
water depth. The CVAR can be used with well development and workover vessels (not
shown above).
For export risers with severe vessel movement, the LWSCR may be used. This requires
a significantly greater horizontal offset than either the CVAR or the SCR, approximately
the same as the water depth. The total suspended length approaches twice the water
depth. It has a buoyant length of about one third of the water depth set a similar
distance along the pipe from the touchdown position.
It is possible to use TTRs and CVARs configurations for drilling or well development.
38 Overview of pipeline engineering
Welded
connections
Touchdown
point
It lifts off the seabed at the touchdown point and rises in a catenary to attach to the
vessel. Normally there will be a flex joint at the connection to the vessel. Sometimes,
titanium is used for the critically stressed section at the touchdown point.
These types of riser are commonly used at depths up to 1500 m (5000ft) but on the
Mardi Gras Thunder Horse project in the Gulf of Mexico, two SCRs have just been
installed in 1840 m (6035ft) of water. The diameters of these are 508 mm and 610 mm
(20in and 24in).
SCRs are rarely used at depths shallower than around 450 m (1500ft), because fatigue
becomes a major issue and other types of riser are more cost effective.
Field layouts 39
Tensioned risers are primarily used in conjunction with ‘floating’ facilities such as the
tension leg platform illustrated, semi-submersible drill rigs and production platforms (eg
Buchan) and drill ships. The riser response to wave and currents loads and to vortex-
induced vibration (VIV) is controlled by the application of tension.
With top tensioned risers, it is possible to locate the tree in the dry rather than at the
seabed.
VIV fatigue
CVAR LWSCR
Use of catenary vertical axis riser (CVAR) or lazy wave steel catenary riser (LWSCR) will
accommodate more vessel excursion and movement. The CVAR configuration can be
used for all stages from drilling to export of the product.
These require similar end fixity considerations at the seabed as those of the TTR and
SCR.
Checks are also needed with regard to VIV fatigue in steady high currents just below the
surface wave layer.
HYBRID RISERS
Self buoyant
Minimise transfer
of load to FPSO Export lines
from
Flexible
Linking flexibles risers
FPSO to SPM
Fixed vessel
orientation Rigid
riser
Benign conditions tower
Girassol field
with hybrid risers
and flowline bundles
Hybrid risers involve a combination of tensioned rigid and flexible pipe. The example
above shows the rigid pipe used for the (long) vertical portion and the flexibles attaching
from the top of that vertical portion in a catenary to a floating production vessel.
Hybrids are seen as a potential deep water solution, where the use of flexibles is limited
by the weight of the flexible being held at the top. The rigid part of the system is limited
to the lower depths where the hydrodynamic loadings are low.
They have been used with fixed orientated FPSOs (rather than turrets) in the benign
waters of West Africa.
Field layouts 41
Any questions?
The different types of production facilities have been shown along with their limitations
in water depth.
Ideally, the tree used to control flow from the well is located on the lower deck of the
platform or host floater. This means that it can be operated and maintained easily.
However, this is only possible when the riser is vertical and the vessel is immediately
above the template.
Where the well cluster is remote from the host, or rigid catenary and flexible risers are
used then subsea trees are essential.
42 Overview of pipeline engineering
Any questions?
The main examples have been given – both subsea and above water – introducing their
names and acronyms.
This course will concentrate on the pipelines (flowlines and export lines) but it important
to be aware of associated equipment used.
Route selection
Route selection 45
EXPECTATION
EXPECTATION
We will introduce the main survey techniques for designing and constructing rigid subsea
pipelines. Some equipment can also be used during the operational and maintenance
phase. Metocean data collected at field exploration stage is needed during design.
The soil at the seabed has an important bearing on a pipeline’s ability to withstand
environmental forces. We also need such data prior to trenching operations in order to
select appropriate equipment.
The main considerations that influence the routing of a pipeline are presented. We will
show some example areas of the seabed which need to be avoided.
The selected route naturally determines the length of the pipeline and leads to the next
stage of design.
46 Overview of pipeline engineering
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
TYPICAL PROJECT
Seismic exploration
Exploration drilling
Deep seismic Feasibility
and metocean Conceptual design
Front end engineering design
First of all, when during the life of a pipeline do we carry out surveys?
Here we have a typical schedule for a project, from seismic exploration through to the
start of production operations. Surveys of various types feature strongly throughout.
At the reservoir discovery and evaluation stage (shown above as deep seismic
exploration), it is likely that metocean data will also be collected. Desktop studies are
likely to be used prior to offshore surveys for pipeline design.
With regard to pipelines, we are concerned with three main phases of survey:
■ DESIGN: The proposed pipeline route is surveyed to identify seabed features and
soil properties along the pipeline route. These are necessary for the pipeline design
and the installation engineering.
■ CONSTRUCTION: At various stages during construction, the pipeline is surveyed
to ensure that the as-installed pipeline is in accordance with the design.
■ OPERATION: During operation, the pipeline is surveyed to ensure that it remains
in the design condition. Operational surveys are addressed later in the Integrity
Management Inspection module.
Route selection 47
SURVEY TECHNIQUES
SONAR DEVICES
Towed fish
sidescan
Sidescan
transducer
Pinger
Hydrophone
Combined Sub bottom profiler
transducer (boomer)
Picture courtesy Sonar Research Development Ltd
Geophysical surveys are carried out using a variety of sonar devices as illustrated above.
All send sound signals from a device to the seabed and listen for the echo return from
the bed itself or from soil layers just beneath. The equipment then interprets the
strength, time and direction of the echoes.
GEOPHYSICAL SURVEY
Seabed bathymetry
Contours – false colour
Sub-bottom profile
Soil layers
and rockhead
A geophysical survey plots the shape of the seabed (its contours) and those of the soil
layers underneath. In the case of oil exploration, the geophysical surveyors are looking
for deep layers containing oil and gas structures. In the case of a pipeline route survey,
we are really only interested in the very top layer, or down to about 4 m (13ft) if we are
trenching or dredging.
Horizon lines are correlated using known geophysical data (i.e. vibrocores) and these are
used to determine the actual make up of the layers seen in the geophysical survey.
ROTV
Deploying BRUTIV
Use of ROTVs is now the main source of pipeline route survey information.
50 Overview of pipeline engineering
By flying the equipment at a controlled height above the seabed, it is possible to rapidly
obtain topological and pipeline span data. The operator on the vessel is able to change
the pitch of the fins through the data umbilical cable.
ROV SURVEYS
ROV surveys are conducted both prior to construction for small areas of concern, and at
stages during construction particularly the touchdown point or crossings. However, they
are classically used during the life of the pipeline to determine spanning sections and
depth of soil cover.
In addition to providing a visual video record of the pipeline condition, a range of other
activities can be performed as listed above. These include wall thickness measurement,
where Ultrasonic Testing (UT) equipment is mounted on the ROV. Also the ROV can
be used to determine if structural tubular members have become flooded. This is
particularly useful for the analysis of jacket legs, when it is necessary to determine if
structural members have cracked and become flooded.
The photograph is of a small ROV used for minor survey work – perhaps the
touchdown location during installation in shallow waters or the inspection of a riser or
short lengths of spanning or rock dump. Much more powerful ROVs rigged with
multiple cameras, lights and CP test equipment would be required for the inspection of
the whole length of a pipeline in strong currents.
Route selection 51
AUV
AUVs are un-tethered ROVs that are programmed with the survey route, launched from
the support vessel and then recovered at the end of the survey. For pipelines that are
reasonably close to land, the AUV does not even require a support vessel as it can be
launched and recovered from land.
The survey information can be downloaded from the AUV either after retrieval or in real
time as it is gathered during the survey itself. The benefit is the speed of the survey is
greater than a normal ROV and the support vessel does not have to be close to the
vehicle.
52 Overview of pipeline engineering
AUV RATIONALE
Heavy R&D
All types of seabed
survey
Not mature for
pipeline inspection
No turning circle
ROTV and fish
AUV
‘Salvage’ issue
There is heavy investment in AUV research and development at present by the major
survey companies. However, they are best used for seabed and route surveys. Their use
for pipeline inspection is as yet not a mature technology.
Removing the umbilical from the inspection tool has particular benefits in deep water.
Surveys can be completed more quickly and the handling is improved. An AUV is better
able to follow curves, arcs and changing depths than a tethered vehicle.
The AUV can be programmed to maintain a constant height above the seabed, typically
about 40 m (130ft), and it will maintain this more easily than a tethered ROV as it is not
affected by the heaving, pitching and rolling of the surface vessel.
An AUV sortie mission may be 48 hours at 2 m/s (4 knots) with a final positional
accuracy of around 3½ m (10 ft). AUVs have been used throughout the world including
the North Sea, Gulf of Mexico, West Africa and Brazil. Many tens of kilometres of
survey lines have been successfully run.
One advantage of AUVs over towed equipment such as fish is that they do not require a
turning circle when carrying out the transverse runs (see upper portion of track). To
avoid tangling of tow lines it is necessary to make a wide sweep at each end of the track.
AUVs can reduce data gathering time by half (see lower portion of track).
Although potentially, AUVs could be launched from a slipway and recovered a number
of days later having gathered all the data, at present they still require a vessel as a guard
ship. A trawler skipper catching one with his haul of fish can claim compensation for
net damage and claim the unmanned vehicle as salvage.
Reports of recent AUV work in the Mediterranean suggests that they could not recover
inshore data in depths less than 100 m (330ft) and the cost was more than that for other
more conventional equipment. Typical rates are $90 000 per day compared with an
ROV at $30 000 per day. However, in deep water, the rule of thumb is that they cost
three times that of the alternatives for five times the benefit.
Route selection 53
GEOTECHNICAL SURVEYS
Geotechnical surveys establish the nature of the soil along the pipeline route.
They typically use a cone penetrometer tester (CPT), as shown in the picture above left.
This is a small device dropped onto the seabed with a coiled probe which is forced into
the seabed. On its way in, it measures the cone resistance, sleeve friction on its side,
friction ratio and pore pressure at its tip.
All of these are recorded as they vary with depth of penetration. By cross-referring to
calibration data, these features can be used to determine whether the soil is sand or clay
and what strength or friction angle it has.
The picture is of a Fugro Seascout CPT. It weighs 1 tonne (2200lb), is 2 m (6.6ft) square
by 2.4 m (7ft) high, has a 100 mm² (0.155in2) probe cross sectional area and a maximum
penetration of 6 m (20ft).
The picture on the right is the head of a vibrocorer. This recovers a sample tube of the
actual seabed for correlation. It is often used with a tripod stand to ensure accurate
entry.
54 Overview of pipeline engineering
METOCEAN SURVEY
The third element of survey is the metocean survey, telling us the environmental
conditions. This data is needed at the design stage and is normally assessed from
existing measurements and interpolation techniques.
The slide lists the instruments used to measure currents and waves and shows a picture
of an acoustic doppler current meter, a relatively recent development, which can
determine the currents at various locations throughout the water column.
Radar monitoring from satellites is also now used to provide wave heights worldwide.
There are two types of survey that are performed prior to preparing the route for
pipeline installation, these being geotechnical and geophysical surveys. Metocean data
has usually been already collected during the field evaluation phase. Where it is likely
that an anchored laybarge will be used, the width of side-scan survey should be extended
to the width of the anchor pattern – perhaps as much as 3 km (2 miles) to either side of
the pipeline route.
The surveys assess if the route is suitable for installation of the pipeline and identify any
obstructions to construction. Survey ships can cover an area of the seabed more quickly
than an ROV. However, more detailed work is best done close to the seabed by ROV-
mounted units. AUVs are still being developed but they have the potential for rapid
collection of data.
SOIL TYPES
WHAT IS SOIL?
Engineers
Soils are weathered or decomposed bedrock
May have been eroded
Transported by wind, water or ice
Re-deposited in homogenous or mixed layers
May contain organic (plant) material
Geologists
Classify the above as ‘weak rock’
Farmers and gardeners
Interested in
Top 0.2 m (8in) of organic topsoil for growing
Drainage of subsoil under-layer
Although engineers are interested in soils from the point of view of their foundation
strength, groups such as geologists and agriculturalists have other different interests and
ways of looking at soil.
We tend to define soil as weathered bedrock which may have been eroded, sorted and
transported by natural processes before being re-deposited some distance from its origin.
It may have organic material mixed with it, which tends to reduce its strength. It may be
partly reformed into weak sandstone or mudstones.
We differentiate between soils and rock. Geologists tend to view all rock and soils as a
continuum (no classification division between them). They are more concerned with the
origin and mineralization than the engineering strength.
Whereas engineers usually have to understand the behaviour of Quaternary deposits (last
2 million years); from a geologist’s point of view, this is regarded as very young drift
material that has yet to fully form.
Route selection 57
Agriculture is more interested in the upper layers which need to contain plenty of
organic material although drainage is also of concern. Organic material is definitely
undesirable from the point of view of sound foundation strength.
All these groups – and many others – have their own ideas about the optimum method
of classifying soils. There is no universal approach or codes so caution should be
maintained when reviewing soils reports.
Silt Clay
Real soil is a matrix with a range of sizes
Sands and gravels can be identified in the field by visual inspection. Sands are particles
smaller than 2 mm (79thou) in diameter but larger than 60 μm (2.4thou).
Finer soils such as silts and clays can be discriminated by touch and simple tests in water.
Silts are slightly granular – testing between the teeth is common. Clays are smoother
with no discernable grains. Silts will disintegrate when dropped into water whereas clays
will remain as a clump. Silts will dry quickly in the hand. With silt, dry lumps can be
powdered easily by hand whereas dry lumps of clays can be broken but not powdered
between fingers.
Silts exhibit little plasticity and marked dilatancy. Clays exhibits plasticity but no
dilatancy. Dilatancy (or bulking) is the inelastic volume increase caused by soil particles
moving relative to each other under shearing forces.
It should be noted that pure soils are rare as real soil is a mixture of particle sizes.
The exact division between each term depends upon the soils investigation code being
used. Examples of particle size distributions for real soils are given later on.
58 Overview of pipeline engineering
Fine
Coarse
Fine
Coarse
Fine
Coarse
Cobbles
Boulders
Medium
Medium
Medium
Basic soil CLAYS
type
SILTS SANDS GRAVELS
VERY COARSE
FINE SOILS COARSE SOILS
SOILS
Drainage Practically
Low permeability poor High permeability generally k>10-5 m/s (fine sands).
impervious
properties k<10-8 m/s
drainage 10-6 >k>10-9 m/s Maximum can approach 1 m/s
100%
Well graded
Gap-graded Uniform
Percentage
sandy,
passing
0%
The slide shows three typical soil descriptions and the particle size distribution arranged
in accordance to BS 5930 : 1999 Code of practice for site investigations; and BS 1377-2 :
1996 Methods of test for soils for civil engineering purposes – Classification tests.
In general, very coarse soils such as cobbles and boulders cannot be recovered from
samples because they are larger than the core diameters.
Descriptors such as ‘gravelly’ and ‘slightly sandy’ or ‘very silty’ are set at up to 5%,
between 5% and 20% and more than 20% levels, respectively. Terms such as
GRAVEL/SAND means approximately equal proportions of each. Gap-graded means
that there are missing particle sizes.
Some codes have been designed for agriculture – others for geology – rather than
engineering. Descriptions and the number of divisions vary greatly between codes used
around the world: soil types may be shifted across, resulting in a “coarse sand” being
defined as a “fine gravel” etc. The rule is to look at the actual gradings rather than the
descriptors.
Note that some codes show the larger particles on the left; others (as above) show them
on the right. But shapes of profiles may be similar (top left to bottom right) because
percentage retained is changed to percentage passing. Again, look carefully at the sizes.
In the US, there are a number of different systems for various purposes:
■ Unified Soil Classification
■ Highway Research Board (AASHO) Classification
■ ASTM (Pedological Soils Classification) – but used for engineering design
■ Federal Aviation Agency (FAA) or Civil Aeronautical Administration (CAA)
Classification
■ Geological Classification (Wentworth)
■ Textural Classification for Agriculture
Route selection 59
σn
c
φ
σ3
θ
σ1
σn σn
c = 0 or φ soil φ = 0 or c soil c - φ soil
The three graphs show the shear strength against normal stress for the different
classification of soil using the traditional approach.
Where:
■ c = cohesion
■ τ = shear stress
■ σn = normal stress
■ σ1 = major principal stress
■ σ3 = minor principal stress
■ φ = internal angle of friction
Pure sands have no cohesion and can be represented by the equation τ = σn· tan(φ),
indicating that the frictional resistance varies with the value of normal stress.
With ductile materials such as steel, we often use von Mises equivalent stress (maximum
distortion energy theory) or Tresca (maximum shear stress theory).
Soils are better modelled using the Coulomb-Mohr Theory. The Mohr’s circle diagrams
are shown above can be visualised as the principle stresses acting on a wedge of soil of
angle θ to the horizontal. The normal stress, σ1 with shear down the slope σ3.
The principal stresses (σ1 and σ3) are drawn on the lower axis. The vertical line from
the axis to where the Mohr’s circle is tangential, indicates the failure shear stress.
It is possible to make a vertical cut in a clay and for this to remain standing without
support for some time. This cannot be done with dry sand which tends to slump until a
slope with an angle approximately equal to the angle of internal friction (the friction
between the grains) is formed. Pure clays do not increase in strength with increasing
normal stress. For this reason, the equation τ = c is applicable, showing cohesion as a
constant value with increasing overburden. That is to say, a cohesive soil has a shear
strength even when the normal stress is zero (at the soil surface).
60 Overview of pipeline engineering
However, many real soils exhibit some features of both cohesion and internal friction, so
the equation τ = c + σn· tan(φ) is used. The figure shows two Mohr’s circles used to
describe such as soil, calculated at different depths (overburdens).
Sands and gravels are non-plastic and non-cohesive. Silts and loess (wind-formed
deposits) are even finer grained particles and are usually also cohesionless.
However, clays are both plastic and cohesive. They tend to have other properties such
as being expansive or compressible when loaded.
Most soil investigation work was originally undertaken on silicate soils. However, some
30% of the sea floor has carbonate soils. The assumption generally made is that these
are predominately calcium carbonate (CaCO3). They may be of any particle size (from
very fine to cobble size) and tend to reform by cementation, forming layers of harder
material.
Route selection 61
Because soil is a naturally occurring deposit, its properties vary both vertically and
horizontally. Commonly, there is more variation in the vertical direction because soils
tend to be laid in lenses. Even within a homogenous soil horizon, natural soils have
different properties due to variation in mineral composition, environmental conditions
during deposition, stress history and moisture content. It is common to average the
results of a number of samples and look at the best estimate, upper and lower bounds.
A large factor of safety should also be used. We may not have identified the fabric of
the soil which may have thin deposits of sand just a few grains thick within a body of
clay helping with drainage.
We often have to limit the number of tests along the pipe route. This can be because of
costs or restriction in access due to adjacent seabed equipment. Existing operators have
been known to prevent sampling within 500 m (1640ft) of their pipeline – even for a
crossing design. For critical designs of wellheads or clump anchors, it is common to
return to undertake additional soil testing at the exact location of the item.
However, it must be recognised that testing samples of soil does not necessarily provide
us with exact values for design. The equipment has some inherent error (tolerance or
accuracy) by its very nature. If we recover soil to the surface for laboratory testing, it
will have been disturbed, giving slightly different values from that on the seabed. Our
sample is generally of a limited size – typically 100 mm (4in) in diameter so any bedding
or joints (cracks) in a sample of clay or chalk may not be well represented, leading to
inaccurate estimation of strength or permeability of rubbly or blocky material. Finally,
the values that we measure are generally not those used for design. We make use of
empirical relationships to derive the engineering information, leading to either randomly
or systematically based inaccuracies.
The new Eurocode 3 (ENV 1997 parts 1 to 3) gives good guidance on soil design using
limit state methods. However, there is no comprehensive international standard for soil
identification and testing yet. National standards such as BS 8004 and the US Unified
Classification can be used but are primarily designed for land-based work. The Norsok
standard G-001 Rev 2 Oct 2004 - Marine Soil Investigations - is specifically designed for
offshore use.
62 Overview of pipeline engineering
The figure shows how variability in soil properties tends to be greater vertically than
horizontally, even in a homogenous horizon of a single soil type. The colours simulate
perhaps weak to strong soil or fine to coarse grain size. The CPT on the left has
encountered average to low values. The pipe trench will be cut through average to high
values. In this instance the scale of fluctuation is large, but changes may occur at a much
finer scale.
Any questions?
There are no international standards as yet. However, we normally describe soils on the
basis of their grain size.
Granular soils are described by their angle of friction (φ). Clays are defined by a value of
cohesion.
Most soil is mixed and require both φ and cohesion to describe their strength. Muds are
such an example and may contain significant amounts of organic material.
A further class of soil are the carbonates found throughout the warmer seas of the
world. The soil particles here may be of any size but tend to bind together in a weak
rock.
It must be noted that our results of surveys are bound to provide variation due not only
to the changes in soil type along the route but to the method of recovering survey data.
Route selection 63
ROUTING OF PIPELINE
Straight line
The starting point for the best route is a straight line from where you found the reserves
to where you want them delivered.
However, very few pipelines go in a straight line and there are numerous factors which
lead us away from the straight route.
DESK STUDY
Sources are:
■ Admiralty Charts
■ Geological Survey maps of surficial sediments and underlying geology
■ Government block licence information
■ Wellhead and pipeline positions from Notices to Mariners
■ Oil company surveys conducted during seismic and drilling operations
■ Oil company surveys of adjacent subsea facilities
SEABED OBSTRUCTIONS
Platforms
Wells
Wrecks
Cables
No deviation
Protection
Safety zone
500 m (1640ft) or
201 m (660ft)
Seabed obstructions cause deviations in the pipeline route around them. In the North
Sea, platforms, wells and wrecks are normally avoided by 500 m (1640ft). In the US, the
distance is somewhat less at 201 m (660ft) - one furlong, though this was originally
defined when fields were in shallower waters.
We also need to consider anchoring areas around subsea works for work-over vessels.
The oil industry shares the seabed with the telecommunications industry (amongst
others). With the advent of subsea fibre optics for international phone calls and internet
traffic, there are many cables currently being installed. Whilst crossing an existing cable
would probably not require a pipeline route deviation, it would be important to know
where the crossing would occur and to take measures to protect the cable against
damage.
66 Overview of pipeline engineering
PIPELINE CROSSINGS
Existing line
30° min
Protection
1 km (3300 ft) straight
1 km to 2 km
(3300ft to 6600ft) radius
Existing pipelines are preferably crossed perpendicularly, with the minimum angle being
30°. The reason for this is that any shallower angle of the approach would lead to a long
and extensive crossing with a greater amount of protection needed over the area. With
anchored laybarges, the anchoring procedure also becomes more difficult at angles less
than 30°.
Looking in plan at the pipeline route, there is a minimum radius for the curves that the
laybarge can achieve. Typically this is 1 km (3300ft) radius for a small (6in, 152 mm)
pipeline and up to 2 km (6600ft) for a large (40in, 1.016 m) pipeline. The reason for this
is that we are relying on seabed friction to pull against in order to form the bend.
Other countries
Exclusion zones NORTH SEA
Bacton
Dredging areas
UNITED UK
Shipping lanes KINGDOM Sector
Dutch
Sector
Other companies’
acreage Dredging
Restricted
areas
Area
Belgian
Sector
Zeebrugge
BELGIUM
Interconnector Pipeline
Route selection 67
Many other users have a claim on the seabed and can influence the seabed route, as can
be seen from the route chosen for the interconnector pipeline between Bacton and
Zeebrugge.
Fishing grounds
Spawning and
nursery areas
SAC – special areas
of conservation
Corals and sponges
Landfalls – SSSI
Environmental impact assessment (EIA)
There may be environmental pressure to avoid fishing grounds, sites of special scientific
interest and special areas of conservation.
The approach is to evaluate the sensitive areas and select the route of minimum
environmental impact in consultation with interested parties.
The main photograph shows a twin-rigged beam trawler used for flatfish, shrimp and
prawn fishing. The insets show a soft coral, a blue sponge and an anemone found in
cold North Atlantic waters at depths of 300 m to 600 m (1000ft to 2000ft) near the
Foinaven development, West of Shetland. The cold water corals were unexpected finds
during the initial surveys for this development.
68 Overview of pipeline engineering
SEABED FEATURES
Sandwaves
Rocks
Pock marks
Iceberg scour
Mud slides
Mud volcanoes
Coral
As a fallback, the pipeline may be routed through the valleys of sandwaves if they have a
suitable orientation. As a last resort, and if it is necessary to cross mobile sandwaves, the
sandwave may be dredged down to the level of the valleys.
Rock outcrops are avoided to permit trenching or limited self embedment, which
improves pipeline stability. Damage can occur to pipelines laid directly on rock so where
ridges of rock must be crossed, a layer of gravel is laid between as a bedding.
Mudslides sometimes occur on steep slopes, particularly near river estuaries and on the
continental slope. If these slopes cannot be avoided, then the route should run directly
down the slope rather than across it.
SANDWAVES
Avoid or pre-sweep
Reforms quickly
These two pictures show an aerial view of sandwaves in a shallow sea and (right) a false-
colour side scan along a pipe route.
They can be encountered wherever strong currents combine with sandy seabeds in
shallow water.
The region is either avoided or the waves are removed just before the pipeline is laid.
They reform within a few tides.
This view of a pockmark field in the Beaufort Sea (with an ice scour through the middle)
shows how uneven the seabed can be.
Such fields of pockmarks are found throughout the world adjacent to hydrocarbon
reservoirs. They are thought to be caused by release of small shallow gas deposits, which
remove the finer particles from the seabed sediments, leaving a depression.
If the route cannot be avoided, then these holes will need to be filled in during seabed
modifications prior to pipelay operations.
MUD VOLCANOES
Near hydrocarbons
Gas leak from formations
Careful routing of lines
Cold mud mounds
5 m to 500 m high on land
Currents sweep away soft deposits
Mud volcanoes are also known as sedimentary volcanoes or gas-oil volcanoes. The
above photographs show small examples on land at Cape Alyat near the Caspian Sea.
Because they are cool, they are considered a tourist attraction, and the mud is deemed to
have curative properties being mainly composed of silica with trace elements.
They also occur subsea and can erupt powerfully, similarly to magmatic volcanoes,
hurling flames to great heights. However, they tend to spew water, hydrocarbon gases
and tons of mud. They have periods of quiescence and then burst into activity again.
If possible, the area should be avoided. However, they often are found close to
hydrocarbon regions and are caused by leakage of gas from great depths. The methane
gas is formed in younger strata overlying the oil fields.
On land, they can reach heights of up to 500 m (1600ft) but subsea, due to the soft
nature of the mud, deposits tend to be rapidly moved by currents. The resulting soft
seabed is not ideal for pipelaying.
Route selection 71
The BP Shah Deniz gas condensate platform is located adjacent to an extinct subsea
mud volcano.
The oil field lies between Mobil's Oquz, Chevron's Asheron and Exxon's Nakhchiuan
fields. Its name can be translated as 'King's Sea'. The prospect is situated in the South
Caspian Sea, off the Azerbaijan shore, approximately 70 km (44 miles) south-east of
Baku. It lies in water depths ranging from 50 m (160ft) in the north-west, to 600 m
(2000ft) in the south-east. The contract area covers approximately 860 km² (330 sq
miles). Reserve estimates have been calculated at between 250 to 500 million tonnes (1.5
to 3 billion barrels) of oil and 50 to 100 billion m³ (2 to 4 trillion ft³) of gas.
Detailed bathymetry provided information on the faults associated with mud diapir†
collapse, shallow gas, debris flows 1 km (3300ft) below the seabed and modern-day
features such as mud volcanoes and seabed channels. In total, twelve separate mud
volcanoes have been identified. The largest of these, north of the reservoir, produces a
major debris flow over 5 km (3 miles) wide.
The grid lines on the lower sonar plot of the field are at 2.5 km (1.5 mile) spacing.
†Diapirsare low density rocks such as salt, shale or magma that force their way upward
in domes or mushroom shapes.
72 Overview of pipeline engineering
CORAL
Types
Coral reefs
Deep cold water coral
Field character
100 m diameter, 5 m high
1000 m deep
Mound and tail
Sand volcanoes
Impact
Environmentally sensitive
Damaged by trawling
Damaging to coating
Flexible pipelines
Although coral reefs have been known about for millennia, it is only very recently that
coral mounds have been found in deep and cold waters.
The Darwin mounds in the Rockall trough off the north-east coast of Scotland are
shown above. These were discovered in 1998, and hundred of these mounds cover an
area of around 100 km². Similar fields have been located in deep waters off the coast of
Brazil having caused damage to flexibles. Mounds in that region are even closer together
having the appearance of a cheese grater.
The individual mounds are around 100 m (330ft) in diameter and some 5 m (16ft) high.
However much larger mounds exist southwest of Ireland in Porcupine Seabight, some
800 m (2600ft) deep. Here, they reach over 1000 m (0.6 mile) across and are 200 m
(660ft) high.
The carbonate rock of the Darwin mounds is built on what appear to be sand volcanoes
– the result of fluidised sand dewatering possibly as a result of slumping. The tops of
the mounds (shown orange) are home to live colonies of deep-water coral species and
the biological communities they support. The green areas on the chart show the much
larger tails (invisible on sidescan images), but which are characterised by high density
populations of giant protozoans, up to 0.2 m (8in) in diameter.
These corals are extremely slow growing and are easily damaged. Trawl damage has
been seen (even at such depths), which is unlikely to be repaired for centuries. For
pipelines laid in such regions, we may expect damage to coatings, especially to flexibles.
Route selection 73
PLATFORM APPROACH
Pipelay
vessel H
Platform
H
Axial movement
of pipe due to
thermal
expansion Flanged connections
(could also be welded
or mechanical connectors)
Where a pipeline is laid to any existing platform, the laybarge must pass to one side of
the platform. The pipeline end is laid down to be later connected with a dogleg or the L
shaped spoolpiece shown above. (The line cannot lay straight up to the platform
without the barge running into the platform.)
However, the spoolpiece must also be liftable and alignable. This means it will have a
limited length, so it is necessary to find a compromise between the requirements of the
laybarge and the spoolpiece.
SHORE APPROACH
Wave refraction
Direct route
74 Overview of pipeline engineering
However, first generation work barges operating in sheltered waters around the Gulf of
Mexico (GoM) were able to come into shallower depths down to 4 m (13ft). The larger
fourth-generation DP barges may need a water depth of 16 m (52ft) for their thrusters to
operate without churning up the seabed.
A second reason for pipelines approaching perpendicular to the shoreline, is for stability.
The waves refract as they come into shallow water, which means that they approach the
shore in a direction close to a right angle, no matter which way they had been travelling
further out. The high water particle velocities associated with breaking waves are in the
same direction as the waves, so routing the pipeline perpendicular to the shore
minimises the destabilising cross-velocities. Even so, it is normal to bury the pipeline on
its final approach and across the beach in the surf zone.
For areas of the world where there are already a number of developed fields, a lot of
information can be obtained using low-cost desk studies. We would supplement this
information with topographic and soils surveys.
Subsea pipelines are generally unable to follow the direct straight line route for many
reasons.
It is common to examine a number of possible routes and minimise the clashes. The
finally chosen route is a cost-driven compromise.
Route selection 75
Survey methods
Used for all stages throughout a pipeline life
Vessels, ROTVs, ROVs
Soil types
Sands or clays
Variability and uncertainty
Routing issues
Desk studies, topographic and soils surveys
Length of line now fixed
Any questions?
The three different types of offshore survey have been shown along with the main
techniques and equipment.
Soils and their variability are an important issue in trenching and stability.
Initially, desk top surveys can help with route planning. This is followed by geotechnical
and topographic surveys at sea. Metocean data will normally have been obtained from
desk top or have been undertaken at the original reservoir determination/evaluation
stage.
The main considerations that influence the routing of a pipeline have been presented.
This provides us with the length of line.
76 Overview of pipeline engineering
Pipe sizing
Pipe sizing 79
EXPECTATION
EXPECTATION
This section outlines the process of determining the diameter and wall thickness of a
pipeline.
There are three methods of making linepipe for the hydrocarbon industry. Videos of
these show the processes.
The causes and effects of buckling are described along with methods of avoidance.
80 Overview of pipeline engineering
DIAMETER SIZING
Having selected the pipeline route, the next problem to be addressed is to determine its
diameter.
The pipeline diameter is sized for peak flow and ensures that flow conditions and
pressure drop are within acceptable ranges. However, one must also check for low flow
condition in case this leads to laminar flow and corrosion at the bottom of the pipe.
In this section, we will examine the three types of flow and how to size the diameter for
each.
Hydrocarbon pipelines are specified by outside diameter, D. This remains constant such
that as the wall thickness, t increases, the bore reduces. This contrasts with pipe used in
the lower pressure water industry which keeps the internal diameter (bore) constant,
varying the outside diameter with changing wall thickness.
TYPES OF FLOW
Multiphase
Riser
Flowline Oil/condensate
Wellhead
Multiphase Gas
Well
Cap-rock
Gas
Oil
Reservoir
Water
Pipelines are designed for one of three types of flow: either liquid, gas or multiphase.
The diagram above shows a schematic of a subsea development. Following the oil from
the reservoir where it is single-phase, it passes up to the wellhead. As the pressure
reduces on the way up, gas comes out of solution and gives multiphase flow. This
passes through the wellhead (which is essentially a valve) and into the horizontal
flowline. It passes through here in multi-phase flow back towards the production facility
where it travels up the riser and into the separator. The prime function of the
production facility is to separate the oil and gas into single phases, and put these into
separate export pipelines where they can be pumped to shore or to a tanker.
The following pages show how pipeline diameter is determined for the different flow
regimes.
82 Overview of pipeline engineering
f ⋅ ρ ⋅v 2 ⋅ L
ΔP =
2⋅D
1
ΔP ∝ 5
D
The pressure drop, ΔP in a liquid flow line is defined by the above formula, where:
■ f = friction factor
■ ρ = liquid density
■ v = liquid velocity
■ L = pipeline length
■ D = internal diameter (pipe bore)
The friction factor is found from the Moody diagram (see next slide) and is generally
constant across a wide range of velocities. The density and length are similarly known.
The design is carried out by trying a range of standard diameters, finding the minimum
size at which the available pressure drop is sufficient to deliver the peak volumetric flow.
The equation reduces to pressure drop being inversely proportional to the fifth power of
the diameter. This is an extreme sensitivity to the bore: since the pipelines we normally
specify are manufactured in steps of 51 mm (2in), experienced engineers can quickly size
the outside pipe diameter. An example may be given that using inch sizes, the ratio
(10/8)5 = 3 – or pressure drop would be a three times more going from a 10in to 8in
bore – and (16/14)5 = 2.
Obviously, here we have ignored the wall thickness, but the principle is demonstrated:
stepping up to the next standard diameter can significantly reduce the pressure drop in a
line.
MOODY DIAGRAM
D ⋅ν ⋅ρ
R e =
μs
hL
f =
L ν2
⋅
D 2 ⋅g
Friction factor, f
The Moody diagram above is a plot of friction factor on the vertical axis against
Reynolds number (proportional to velocity) on the horizontal axis. The curves show
values of friction factor for different roughness of the inside of the riser. The curves for
a given roughness are fairly flat in the turbulent region to the right hand side of the
diagram. This means that for a given roughness, the friction factor varies little with
velocity if the flow is in the turbulent region.
A note of caution on Moody diagrams and friction factors: there are two different
systems in use. The above is the US system which is used throughout the oil and gas
industry. The other system has a friction factor f ' or λ (lambda) = 0.25 f, and is shown
in some UK water industry textbooks.
For common pipeline sizes and materials, the ranges of values are:
■ Reynolds numbers between 105 and 107
■ Line pipe roughness < 0.5 mm (20mil), giving
■ Relative Roughness between 0.0005 and 0.002
These ranges result in most pipelines having friction factors between 0.01 and 0.015.
The graph shows use of the chart: by following the curve from the relative roughness of
0.0001 to where it crosses the Reynolds N° of 6 x 105, we can read off the friction factor
on the left axis of 0.014.
Where
■ D = inside diameter of pipe
■ f = friction factor
■ g = gravitational acceleration
■ hL = head lost in friction
■ L = length of pipeline
■ Re = Reynolds’ number
■ μ = kinematic viscosity
■ ν = dynamic viscosity
■ ρ = density of fluid
84 Overview of pipeline engineering
As the slide indicates, sizing the diameter for a gas pipeline requires a similar approach to
liquid lines but is slightly more complex. The complexity is introduced by the
compressibility of the gas, which means that, as the pressure drops along the pipeline,
the gas expands. Its velocity increases and the drag increases in proportion to the square
of the velocity. The overall result of this is that the pressure drops along the initial
sections of the gas pipeline are small, compared with those at the far end.
Although this sounds complex, the relationship can be described with empirically
derived formulae allowing a straightforward assessment of pressure-drop for a given line
size.
Bubble Froth
Liquid flowrate
Slug
Plug
Annular mist
Smooth Wavy
stratified stratified
Gas flowrate
Oil Gas
Pipe sizing 85
From a well, you typically find a mixture of oil, water, gas and sand. Any combination
of gas and liquid flowing together down a pipeline is known as multi-phase flow.
Depending on the proportion of gas and liquid and the overall speed of the flow, the
phases may adopt different patterns. These are known as flow regimes.
The flow regime will also be influenced by the geometry of the pipeline (whether it is
going up or down hill or on the level). The importance of determining the flow regime
is that different flow regimes cause different pressure drops per unit length of pipeline.
The slide above shows seven flow regimes for a horizontal line, depending upon the
proportion of oil and gas, and the driving pressure in the line:
■ Where the oil and gas flow rates are low, the flow is smooth stratified. The liquid
separates to the bottom of the line and the gas flows at higher speed at the top of it.
■ As the gas flowrate increases, the differential flow causes the surface to become
wavy.
■ At higher rates still, we get annular mist flow. This is typical of gas condensate
lines where the gas velocity is very high and there is only a small proportion of
liquid, which is forced out to the edges and runs along the pipe wall in tears.
■ If the proportion of oil is increased from an annular mist flow, whilst keeping the
pressures high, the flow can form froth. Both phases are dispersed and travel at the
same speed.
■ At the highest flow rates but when the oil is the greater fraction, the regime moves
to bubble flow where bubbles of gas are entrained in a matrix of liquid and all flows
at the same speed.
■ If the flow rate decreases slightly, then the bubbles tend to coalesce and separate out
at the top of the pipeline. They form plugs of gas.
■ Slug flow is common in oil and gas production flowlines where the flow rates are
fairly high. Liquid travels in slugs, with pockets of gas in between. The slugs
generally initially form at low points on the line or at the foot of risers.
Plug and slug flow can cause problems at pumps and fittings due to the surges as the
density of the flow changes.
The transitions between the different flow regimes depend upon a number of factors
such as topography of the pipeline and additives to the fluid. Researchers adopt
different terms (such as pseudo-slug, intermittent slug or bubbly slug) to further
subdivide the phases.
86 Overview of pipeline engineering
Explicit software
Olga 2000
Profes Transient
The technique for sizing for multi-phase flow is essentially the same as liquid and gas
single-phase lines, in that one initially finds the size required to accommodate the
maximum flow, and then checks that there are no problems induced by the minimum
flow condition.
Also, life is rarely so simple as to have a single well and a single tie-back flowline. As the
diagram indicates, subsea developments often have many wells, manifolded together
with multiple flowlines back to the separator. In order to design for these conditions, it
is necessary to use computer simulation to determine the flow regimes and therefore the
pressure drop. Computer simulations can either rely on correlations or can solve the
physics of the flow explicitly.
Examples of explicit codes are Olga 2000 and Profes Transient. These use equations
rooted in the basic fluid properties; they can, for example, model the shape of the front
and rear of a slug in order to determine the forces as it passes through a bend.
Pipe sizing 87
Diameter sizing
Peak flow
Low flow
Extreme sensitivity to bore
Limited number of standard diameters available
Liquid flow sizing
Gas flow sizing
Multi-phase flow
Any questions?
To summarise diameter sizing, one finds a diameter suitable for conveying the peak flow
at the available pressure drop and then checks that this does not cause problems at the
minimum flow.
The bore has a strong effect on pressure drop. The standard diameters are normally
available in 51 mm (2in) steps. It is therefore a relatively quick process selecting the
diameter required to suit both peak and low flow rates.
For single-phase liquid and gas flows this process can be done analytically.
The principle for sizing for wall thickness is to make the pipe wall thick enough to
contain the maximum allowable operating pressure.
There are many other factors to take into account which may lead to the selection of a
thicker wall. These are detailed in the following section.
Pipe sizing 89
The slide above lists the factors to be taken into account in determining wall thickness:
■ In cases where the pipeline runs close to people, such as on risers and spoolpieces,
the wall thickness is increased to give an additional safety margin (lower stress).
■ Internal pressure has already been mentioned.
■ The wall thickness design must allow for corrosion and for manufacturing tolerances
on the thickness of the steel (or the centrality of the hole within the pipe).
■ The pipe must resist hydrostatic collapse due to the external pressure of sea water -
more on this later.
■ The pipeline must resist bending due to self-weight or environmental loading.
■ It must resist running buckles. This is an effect where a single imperfection (e.g.
some ovality) can allow hydrostatic collapse to start and to run both ways along the
pipeline until it is all flattened, or runs into shallow water. The material needs to be
strong enough to resist this, or must have thick buckle arrestors at intervals along
the pipeline.
■ If the pipe is to be reeled, it needs to be fairly thick to avoid local wrinkling on the
reel.
■ In some circumstances the pipeline may need a thicker wall to increase its self
weight to ensure that it remains stable on the seabed - more on this later.
■ Fatigue can occur due to wave and current motion on risers and pipeline spans.
■ In manufactured bends, allowance needs to be made for thinning of the wall during
the bending process.
■ As shown in the figure, where a pipe is attached to a stiffer fitting, this can induce a
stress concentration which may require local thickening of the wall to give a proper
transition.
90 Overview of pipeline engineering
( pi − pe ) ⋅ D
tmin = + C A + t tol
2 ⋅ A ⋅σ y
Corrosion Manufacturing
Resist bursting
allowance
Where tolerance
The wall thickness needed for pressure containment is found using the above equation.
Where:
■ t min = minimum wall thickness
■ pi and pe = internal and external pressures (Normally, p is defined as the difference
between the maximum internal pressure and the minimum external pressure)
■ D = outside diameter
■ A = design factor (traditionally 0.72 for pipelines and 0.6 for risers, which sets the
peak hoop stress to 72% and 60% of yield respectively)
■ σy = specified minimum yield stress for the material (see next section)
■ τtol = negative manufacturing tolerance on wall thickness (typically 1 mm or 1.5 mm
(40thou to 60thou) for welded and 12.5% of nominal thickness for seamless for ISO
3183)
■ CA = corrosion allowance, typically 3 to 6 mm (1/8in to ¼in)
Having found the minimum thickness, the nominal thickness is found as the next
standard pipe thickness above this (taken from API 5L or ISO 3183).
However, when purchasing long lengths of pipe (hundreds of kilometers or miles), it can
be more economical to manufacture specials using the minimum thickness.
Pipe sizing 91
COMBINED LOADS
Equivalent stress
σ eq = (σ 2
h + σ l2 − σ h ⋅ σ l + 3 ⋅ τ 2 )
Lay tension, pressure
Internal pressure
and thermal forces Self weight or current causes differential causes
cause axial stresses bending (axial) stresses hoop stresses
The above equation calculates the equivalent stress using Von Mises method.
Where:
■ σeq = equivalent stress
■ σh = hoop stress
■ σl = longitudinal (axial) stress
■ τ = shear or torsional stress
Where we have loads in different orientations we need to use a yield method, such as
Von Mises to combine stresses to determine an equivalent stress.
The diagram above shows an example of a pipeline spanning across a gap, causing
bending.
The hoop stress induced by the internal over-pressure is orientated in the circumferential
direction around the pipe.
The residual lay tension or axial forces produce tension or compression in the pipe wall.
This must be added to the bending stress, which is also orientated axially along the pipe -
producing a tensile or compressive stress at top or bottom at different positions along
the pipe (hog or sag condition).
We can normally ignore the shear stresses in pipeline analysis since these do not occur at
the same point around the circumference as the peak axial forces. It is uncommon to
have torsional stresses in rigid pipelines.
92 Overview of pipeline engineering
As already mentioned, close to the platform or at the landfall, the hoop stress levels are
typically reduced from 72% to 60% of SMYS.
Some codes also require a stronger section of pipeline within a certain distance of
personnel. The distance varies with the code – the Norwegian DNV is further than that
for API. The British PD code has no specified requirement. In very deep waters of
1000 m (3300ft) or more, perhaps even the DNV requirement should be increased:
bubbles from a gas leak may be carried some distance by sea currents towards the
platform.
This is in order to give an added margin of strength and therefore an increased factor of
safety due to the proximity of people.
Pipe sizing 93
SURGE
Valve closure
Fluid stops against valve whilst fluid behind
still moving
Fluid compresses
Pressure wave backs up pipeline as
moving fluid meets stationary fluid
When valves are closed, a pressure wave is set up in the pipeline. The effect is
sometimes seen in the domestic setting with copper pipes and is known as ‘water
hammer’.
The celerity (transmission velocity) of the pressure wave is the speed of sound in the
product.
SURGE PRESSURES
Joukousky equation ΔP = ρ ⋅ α ⋅ V
Where:
ΔP = change in velocity
ρ = density of oil
α = speed of sound in oil = 1300 m/s (=4265 ft/s)
V = velocity of oil prior to shut-in
Slow closure of the valve
Closure time longer than wave travelling to pipeline
end and back
Allow 10% internal design pressure
Maximum surge value is given by the Joukousky equation. ‘Velocity of oil’ can be
replaced by ‘change in velocity’ for cases of partial valve closure. It is apparent that
lower fluid velocities give lower surge pressures.
94 Overview of pipeline engineering
The pressure wave resulting from a valve closure travels back up the pipeline. It is
reflected at the pipeline end and travels back down the line to the valve.
The surge pressure can be greatly reduced by slow closure of the valve. If the valve is
closed slowly, particularly if the closure time is greater than the time required for the
surge wave to travel to the pipeline end and back, the total overpressure is reduced.
To avoid increasing the strength of the pipe excessively, it is common to allow 10%
extra design pressure and slow the rate of valve closure. Closure time may be 2 minutes
or more.
Various influences
Thick enough for pressure
Bending during installation and at spans
Risers and landfalls
Surge pressures
Any questions?
The wall thickness design of a pipe starts off by picking a minimum thickness for
pressure containment and then checking for other loading – particularly bending –
during installation or if spanning is expected.
In some countries, the wall thickness design of pipelines is prescribed in their national
legislation.
Pipe sizing 95
HYDROSTATIC COLLAPSE
Deep water pipelines can often have periods when the external hydrostatic water
pressure exceeds the internal pressure. The governing criterion for wall thickness and
material grade can be resistance to collapse (due to external loads) rather than resistance
to bursting (due to internal loads).
96 Overview of pipeline engineering
COLLAPSE CRITERIA
Where:
■ D = diameter of pipeline
■ fo = pipe ovality = (Dmax - Dmin)/D
■ pc = characteristic resistance pressure to collapse of pipeline
■ pel = elastic collapse pressure for a perfect tube
■ pp = plastic collapse pressure for a perfect tube
■ t = wall thickness
External collapse of thin walled pipes is primarily driven by the elastic properties of the
steel. Ovalisation of the pipe results in the hydrostatic forces on the flat sides being
much larger than the hydrostatic forces on the ends. This creates moments within the
pipe wall that tend to increase the ovalisation. When elastic and plastic resistance to this
ovalisation is overcome, a runaway flattening of the pipe occurs.
The above criterion is taken from DNV OS-F101 Submarine Pipeline Systems 2000
(commonly called DNV 2000). The characteristic resistance is given by solving the
above equation (which is equation 5.18 in the DNV code) for external overpressure of
an oval pipe.
This is essentially the same approach as PD 8010, although the inherent safety factor is
different, the ovality (fo) is defined differently and the code has a less conservative lower
limit.
Pipe sizing 97
Where:
■ Md = design bending moment
■ Mp = bending moment capacity
■ Sd = design axial compressive force
■ Sp = axial force plastic capacity
■ pc = characteristic collapse pressure
■ pe = external overpressure
■ αc = flow stress parameter
■ γm = partial factor for material resistance
■ γSC = partial factor for safety class
This is equation 5.24 given by DNV OS-F101 for pipes subjected to bending moment,
effective axial force and external overpressure.
98 Overview of pipeline engineering
DIFFERENT FORMULAE
14000
12000
6000
4000
2000
Comparison of
existing collapse
prediction methods
Because it is only recently that pipelines have been laid at extreme depths, some codes
do not define the method for calculating collapse pressure.
There are various formulae available for predicting the collapse of pipe.
As illustrated in the figure above, although there is good correlation between the
equations in the shallower depths, there is significant variation in the predictions in the
deep water, low D/t region.
Even the use of the latest API 1111 and DNV OS-F101 codes results in the selection of
different wall thicknesses.
Assessment of the additional bending during installation needs to be included along with
the response behaviour of the particular laybarge chosen.
Pipe sizing 99
BLUESTREAM SOLUTION
16000
14000
Water depth m (ft)
12000
8000
6000 Bluestream
design case
4000
2000
The selected solution indicates that the more conservative predictions may be more
appropriate in deep water. An allowance must always be made for the installation
stresses (bending, spanning and axial) in addition to the pure collapse pressures for the
line once installed at depth.
100 Overview of pipeline engineering
HYDROSTATIC COLLAPSE -
SUMMARY
Any questions?
We have looked at the causes of hydrostatic collapse which are principally the external
overpressure of the pipeline during laying when there is no counterbalancing internal
fluid pressure. However, the ovality of a laid pipeline has a major influence on the
pressure needed to initiate collapse.
The collapse is resisted by increasing either the wall thickness or the yield strength of the
steel.
Since such buckles are most likely to occur during laying, some additional considerations
must be allowed for. There are stresses induced in bending (such as at touchdown for S,
J-lay or Reel lay methods) and axial compressive forces again due to hydrostatic
pressures.
We have shown that different formulae give different solutions in terms of D/t
especially at depth. The Bluestream Project used a conservative formula backed up by
testing of the pipelines.
The consequence of the initial collapse results in a local buckle. However, this can turn
into a running buckle which zips along pipeline until it reaches shallow water or a stiffer
section of pipeline. The common way to provide this extra stiffness is to fit buckle
arrestors at regular intervals.
Pipe sizing 101
LINEPIPE OPTIONS
There are three methods of manufacturing rigid steel pipe for the oil and gas industry.
These are seamless, HFI and SAW.
Seamless pipe is commonly used for smaller diameter lines subsea, especially for the reel
lay method where a thick wall is advantageous. It is also often used for manufacturing
process pipework in refineries where the pipe needs to span between supports.
A second method uses continuous steel strip to form pipes. High frequency induction
(HFI) welding effectively limits the thickness of pipe wall and so it cannot be used to
make the thicker pipes. The width of the steel strip also limits the maximum
circumference of the pipe. In USA, the term electric resistance welding (ERW) is used
instead of HFI. Strictly speaking, this is a similar process using copper anodes to deliver
the current. It is still in use for the manufacture of small structural hollow sections –
both square and circular up to 6in (150 mm) – but which is prohibited for use on
hydrocarbon pipelines.
There are three different types of submerged arc welding (SAW) processes used to make
line pipe. The UOE method is when a plate of steel is first formed into a U shape, then
102 Overview of pipeline engineering
rounded into an O and welded, and then finally expanded (E) to form the finished pipe
shape.
Maximum plate dimensions and the forming mills limit the diameter of pipe that can be
made using UOE. When the diameter needs to be bigger than that commonly used in
oil and gas (but often required by the water industry), a similar SAW process can be
used. The plates are curved into the pipe shape using three-roller-bending and then the
short pup sections are welded together to form the 12 m (40ft) long linepipe.
An alternative SAW method forms the strip into a spiral (just like a cardboard tube) and
can make any diameter of pipeline. However, it is not often used for offshore
hydrocarbon lines because of perceived problems with tolerances and subsequent
forming of the field butt welds close to the diagonal seams. Additionally, there is much
more weld required than for any other method and inevitably some must be at the
bottom of the pipe when laid. Intelligent pig inspections may not identify all down-
stream weld defects because the sensor may skip over the frequent beads.
SOURCE OF MATERIALS
Iron ore
Smelter
Pig iron
The above diagram shows the routes for the materials from smelting iron ore, to making
steel, to forming the steel ingot into plate and strip, to the formation of pipes.
Modern mills use vacuum degassing method to remove gas from the steel whilst molten.
The alternative is to repeatedly roll an ingot or to cast the steel directly as a plate. These
methods are still undertaken at older facilities.
Note that only the seamless method is classed as hot-forming. The other two processes
use steel strip or plate which has been pre-rolled to the correct thickness. This improves
the pipe wall tolerances though it means that a seam weld is needed.
Pipe sizing 103
MANUFACTURING METHODS
1. Seamless
2. High frequency induction (HFI) welded
3. UOE or submerged arc welded (SAW)
35
Wall thickness in mm (inch)
1¼
30
25 1
20 1 3 ¾
15
½
10 2
5 ¼
The choice of pipe manufacturing method is primarily dependent on pipe size and wall
thickness. The above graph shows approximate areas of diameter and wall thickness
available from each method.
All three methods can produce the high standards of pipe necessary for offshore
pipelines. In areas of capability overlap, cost is usually the prime driver in selecting the
manufacturing method, and the usual ranking is HFI as lowest cost, then SAW, then
seamless.
Some mills extend the range of diameters and wall thicknesses which can be achieved by
each of these methods. The graph is a guide only on typical sizes supplied worldwide.
Some plants can produce thicker walls – for example, Corus SAW mill can handle up to
50 mm (2in) and HFI pipe trials have been made at the Welding Institute up to 25 mm
(1in).
104 Overview of pipeline engineering
COMPARISONS
Seamless
Clean - lamination-free
Eccentricity
Thick
HFI
Successor to ERW (electric resistance welding)
Better control of thickness in strip
SAW
Thicker wall than HFI
Good control of plate thickness
Seamless has the advantage of no weld and tends to be a “clean” steel (without
laminations), suitable for use on sour duty where hydrogen-induced cracking might
otherwise be a problem. Due to the manufacturing process, the hole can be eccentric,
leading to a requirement for greater wall thickness tolerances (API 5L permits 12.5%
rather than 5% for HFI or SAW pipe). Whilst it can be made very thick, this can lead to
less than 12 m (40ft) joint lengths in the larger sizes simply due to the mass of steel
within the ingot.
This is the only method to form the pipe from hot steel. The other two methods have
laminations embedded during the rolling process within either the steel strip or plate.
They form the pipe from essentially cold steel and have an axial weld.
HFI (High Frequency Induction) is the most recent process, and produces low cost, high
quality tube from strip.
With HFI and SAW, control of the thickness of strip or plate is better, but the seam
needs careful checking since the highest stresses are normally in the hoop direction.
Pipe sizing 105
The seamless pipe manufacturing process is generally used for small to medium diameter
pipe.
3-ROLL PIERCER
106 Overview of pipeline engineering
By angling the three rollers on the diagonal, the hot billet can be rotated to form a
cylinder at the same time as it is being forced onto the piercer.
The rapid speed of pipe manufacture is determined by the rate of cooling of the billet.
The Vallourec & Mannesman plug rolling mill produces seamless pipes in sizes between
177 mm and 355 mm (7in and 14in) diameter with wall thicknesses of between 6 mm
and 30 mm (¼in and 1¼in).
The video shows the manufacture of up to six strands of tube-making rounds using
continuous casting methods from the liquid steel. These are 175 mm, 225 mm or 270
mm (6.9in, 8.8in or 10.6in) in diameter. These are cut to length and delivered to the pipe
mill.
‘Centred’ billets (for handling) up to 4.7 m (15½ft) long and 2.1 tonnes in weight are first
preheated to about 700°C (1290°F) before placing in the rotating hearth furnace. Here,
they are further heated to around 1280°C (2340°F) and soaked to ensure optimal heat
distribution through the cross section.
Hot billets are removed at 30 s cycles and sent to the rolling mill, where they are pierced
using a die and helical rollers. This process forms the hollow tube and elongates the
bloom by five-fold. From here, the plug rolling mill reduces the wall thickness and the
reeler smoothes the inside and outside faces using helical rollers.
A further reheating process to 900°C (1650°F) and descaling is required before the
bloom is sent to the 10 stand sizing mill, where the correct diameter is formed. The pipe
is then cooled and straightened. Heat treatment may be used to attain the finished
hardness of steel. NDT testing, inspection and marking the now-cut pipe ensures the
quality of the finished product.
Other treatment such as coating with polyethylene, threading or upsetting of one end
(not shown) may be required prior to delivery to the client.
Pipe sizing 107
Whilst not shown on the above diagram, there are storage devices prior to the forming
mill that allows the plate preparation to continue independently of the welding, so that
stopping one does not immediately stop the whole line.
108 Overview of pipeline engineering
FINISHED FORMING
Smaller diameter pipe is processed slightly to its finished diameter, wall thickness and
length in the standardising or stretch reducing mill.
This same process is used to manufacture circular and rectangular hollow steel sections
for buildings.
The video follows the manufacture of line pipe in the 20in mill in Hartlepool through
the following stages:
■ Joining of steel coils to form a continuous strip
■ Forming before welding
■ Welding and NDT (non-destructive testing)
■ Heat treatment of the HAZ (heat affected zone)
■ Cutting into lengths
■ Quality of the line pipe is recorded by an individual number on each section,
ensuring traceability
The photograph above shows the continuous length of pipe being cut into standard 12
m (40ft) lengths.
Submerged arc welding (SAW) permits thicker plate to be joined than HFI.
Generally used for large diameter pipes, the first half of the UOE process consists of the
following:
■ Plate edge preparation and pre-forming
■ Rolling (or die form, e.g. UOE) to form cylinder as per the picture below
■ Edge closure and tack weld seam
110 Overview of pipeline engineering
U PRESS
Tags have been attached for the subsequent welding and the plate width is trimmed to
the correct circumference. The edges are crimped to help with further processes.
It is then bent in the U press using massive rams first to push down, and then rams
either side of the side rollers are brought together to complete the first forming
operation.
A second press (not shown) finalises the forming of the pipe into the O shape, at which
stage the joint is tack-welded.
SAW WELDING
Pipe sizing 111
The pipe is welded using granular flux piled around the two edges of the pipe.
With thicker plate, it is common for two passes of SAW. The first is undertaken on the
inside of the pipe. The second (as shown above) is with the units on the outside of the
pipe. (A double V shape weld preparation is needed for this at the earlier edge trimming
stage.)
The picture shows the pile of white granular flux piled onto the joint. Surplus flux is
being vacuumed off to the right and the still hot, welded seam is revealed.
The following are pictures of the ultrasonic inspection and the mechanical expander.
112 Overview of pipeline engineering
ULTRASONIC INSPECTION
MECHANICAL EXPANSION
Mechanical expansion brings the diameter to tolerance and also improves the physical
properties of the steel.
The photograph above shows the etched micrograph of the submerged arc weld with
the internal and external passes (the pipe must be rotated so both can be executed from
above). The heat affected zone (HAZ) is also clearly seen in the plate metal to either
side of the welds.
114 Overview of pipeline engineering
OTHER MANUFACTURING
METHODS
Three-roller bending
Large diameter / thick wall
Short drum lengths
SAW seam and butt welds
Spiral pipe
Continuous process
Internal and external SAW
Low pressure in water industry
There are other methods of manufacture but these are not commonly used for oil and
gas pipelines offshore.
When the pipe diameter becomes large – 1066.8 mm (42in) and above in some plants –
or the wall thickness is excessive, it is necessary to roll plate longitudinally using three
roller bending techniques. These can then be connected using multiple SAW welds and
the short drum lengths connected with butt welds.
Spiral pipe is commonly found in the low pressure water industry and to a limited extent,
for land-lines, where repairs can more easily be undertaken. Like HFI, it is a continuous
process but larger diameters can be manufactured. The angle of the machine is adjusted
to suit the width of coil steel and pipe size.
Pipe sizing 115
Any questions?
Line pipe for subsea usage can be rigid or flexibles. We will look at flexibles in a later
module.
Here we examined the three common manufacturing methods for rigid steel pipe. They
each require a different form of steel as input.
Each has a different range of diameter and wall thickness. The tolerances achieved by
each method are also different.
We mentioned two other methods for the manufacture of larger diameter, low pressure
lines used by the water industry.
116 Overview of pipeline engineering
BUCKLES
Just about everything the pipeline engineer fears may go wrong with his pipeline tends to
be called a buckle, so there is plenty of scope for confusion.
Combination of
External overpressure Local pipeline buckle
Bending
Axial compression
Geometric imperfection
Pipe wall collapses
Blocking pipe bore
May cause a leak
Wet buckle
The main fear in all cases is blockage or rupture of pipes. In the case of the strut buckle,
the global bending is not so much of a problem as the fact that it induces high levels of
local bending at the mid-point of the buckle, which could induce a local buckle.
The above picture shows a side scan sonar image of a lateral buckle, where a small
diameter flowline has snaked as a result of a modest 50°C (122°F) temperature rise.
118 Overview of pipeline engineering
However, it is rare that an S-laybarge can achieve the frequency of snaking needed to
achieve this (due to the high lay tension).
Allowing the pipeline on the seabed to snake due to pressure and temperature loads can
realistically be accommodated during design, and had probably been occurring for many
years before survey techniques were able to detect and measure it.
The key here is to avoid all the expansion being taken out at a single location. Instead, it
is preferable to induce large numbers of small lateral buckles along the length of pipe.
These would then dissipate the strain harmlessly.
Pipe sizing 119
UPHEAVAL BUCKLING
Pipeline buckle
Uplift
Axial movement ‘fed-in’
by thermal expansion
Initial out-of-straightness
In previous slides, we noted that lateral buckling takes advantage of the lack of
constraint in an unburied pipeline. In the case of a buried pipeline, it does not have the
ability to snake laterally. Instead the pressure and temperature loads are locked in and
the pipeline acts as a coiled spring.
The diagram above shows an upheaval buckle where the pipe initially has a slight upward
imperfection which becomes amplified by the compressive load. It reaches the point
where the forces moving the buckle upwards exceed the overburden offered by the soil.
The result is the pipe erupting through the soil and forming a loop. These are typically 5
to 10 m (16 to 33ft) high above the seabed and have a 40 m (130ft) wavelength.
The bend at the apex may be so severe as to induce a local buckle and/or rupture. Even
if the pipe survives the initial upheaval buckle, the next fishing vessel to cross the
location will probably tangle with the pipeline and may break it.
When the buckle has been identified and fishermen advised (but prior to rectification), if
hooking still occurs, then the fault may lie with the trawlermen. However, it would not
be in the oil company’s best interest to sue!
120 Overview of pipeline engineering
BUCKLE PROPAGATION
Propagation pressure
Less than collapse hydrostatic pressure
Hence once started, buckle ‘zips’ along
pipeline
fy ⋅ α fab ⎛ t ⎞ 2.5
p pr = 35 ⋅ ⋅⎜ ⎟
γ m ⋅ γ SC ⎝ D ⎠
Propagation
Where:
■ D = nominal outside diameter
■ fy = yield strength
■ ppr = plastic collapse pressure
■ t = nominal wall thickness (uncorroded)
■ αfab = fabrication factor
■ γm = partial factor for material resistance
■ γSC = partial factor for safety class
The external pressure required to cause a buckle to propagate is lower than is required to
collapse the pipe. Hence if the pipe is not designed to resist buckle propagation, any
local buckle accidentally introduced will propagate. This is not normally a problem for
pipelines installed in shallow water, where wall thickness is governed by internal pressure
containment. As water depths increase, buckle propagation design begins to dominate.
It is possible to design pipelines to exceed the buckle propagation pressure and design
instead to the external collapse pressure with adequate mitigation measures. These
include the use of buckle arrestors to limit the damage caused if a buckle is initiated.
Since buckles are normally caused during installation, and the worst conditions for
buckle propagation also occur during installation when the pipeline is empty, this forms
the principal design case.
It is normal to design allowing 100% of any corrosion allowance as part of the wall in
the analysis because we have a new pipe during installation. During its operational life,
the thinner wall (due to corrosion) is not subject to the high installation bending forces.
122 Overview of pipeline engineering
7010
Collapse Pressure
60
Propagation Pressure
8
50 1. Increased thickness ratio
40 6
prevents buckle propagation
This graph compares the collapse and propagation pressures for an API X60 pipe with
an ovality of 1% over a range of D/t ratios.
For a particular D/t ratio, there will be a maximum water depth that the pipe can
withstand.
However, if the pipe does start to buckle, we can derive two results from the graph:
■ By tracing from the blue line horizontally to the left, we obtain the increased ratio
and thus the wall thickness needed to prevent buckle propagation.
■ By tracing vertically down to the red line below, we obtain the overpressure and thus
the water depth to which the buckle will propagate.
Pipe sizing 123
BUCKLE ARRESTORS
Grout
The onset of a local buckle is most likely to occur under combined load conditions, i.e.
when the hydrostatic pressure is combined with bending and axial load. Pipelay is a
critical condition when high bending is combined with the hydrostatic pressure. If a
local buckle does occur, it will initiate at the location of highest combined load.
Once initiated, the buckle can propagate beyond the region of combined loading because
the pipe’s resistance to hydrostatic collapse is reduced either side of the buckle by the
flattening and increased ovalisation in those locations. Buckle arrestors are commonly
used at intervals along the pipeline to limit the propagation of the buckle.
A typical pipe wall 19 mm (0.75in) thick may need around 50 mm (2in) thickness to
arrest a buckle. These would be located at perhaps 100 m to 500 m (330ft to 1640 ft)
centres along the pipeline.
The spacing is determined by the method proposed to rectify the buckle - it may be the
size of the tensioners on the barge (which are needed to pull the damaged section back
on deck). Larger tensioners can recover more flattened (and non-buoyant) pipe, so
spacing can be increased.
Buckle arrestors will stop running buckles after a local buckle has formed at any time.
However, they are most useful during installation when the effects of bending are
greatest: the laybarge can stop and recover the flattened section. During operation,
however, a major operation is required to mobilise equipment to cut out and replace part
of the pipeline.
124 Overview of pipeline engineering
The solution for design against hydrostatic collapse must take account of the ovality of
the line pipe supplied and installed, along with the predicted stresses due to bending and
tension during pipelay.
In deep water, the wall thickness is generally greater than that needed just for the
operating and test pressure of the contents.
Where buckles may propagate, then buckle arrestors need to be added at regular
intervals.
The spacing is dependant on the risk assessment and the procedure proposed to recover
from a buckle.
Pipe sizing 125
BUCKLES - SUMMARY
Any questions?
There are three types of buckling that can occur in a pipeline. Local buckles are
generated by either a localised hydrostatic collapse or by significant bending stresses.
Running buckles result from the propagation of a local hydrostatic induced buckle.
Global buckles occur over long sections of the pipeline. Lateral and upheaval buckles
can both be categorised as global buckles and result from the expansions associated with
the thermal and pressure loads applied to the pipeline during operation.
Lateral buckles occur in the horizontal plane with pipelines resting on the seabed
surface. They are less severe than upheaval buckles as longer sections of the pipeline are
able to deflect laterally. Upheaval buckles occur when there is insufficient soil on top of
a buried pipeline to restrain the out-of-plane buckling deflections resulting from
expansion. The pipeline buckles over a relatively short length and so the strains are
concentrated into a smaller section of the pipeline than in lateral buckling.
Local buckles, running buckles and upheaval buckles are considered as failure modes and
should be avoided by design. Lateral buckles may be acceptable provided that they are
are not too severe.
126 Overview of pipeline engineering
Diameter sizing
Wall thickness determination
Bursting and hydrostatic collapse
Methods of rigid steel pipe manufacture
Seamless, HFI/ERW, UOE/SAW
Buckles
Combined bending, external overpressure,
compression and geometric imperfections
Local, strut and running
Any questions?
We have introduced the principal concepts for subsea pipeline design for diameter and
wall thickness.
The main manufacturing methods for rigid steel pipelines have been described.
The causes and means of prevention of different types of pipeline buckle have been
explained.
Materials
Materials 129
EXPECTATION
EXPECTATION
Material selection
Strength
Corrosion resistance
Normally bare steel inside
Corrosion allowance
Corrosion inhibitors and chemical additives
Corrosion resistant alloys (CRAs)
Clad and lined pipes
Linepipe supply and welding
Titanium and composites – not for linepipe
Risers, topsides, gratings and protection covers
We examine what limitations there are in using carbon steel for pipe walls.
Clad and lined pipe construction may prove cheaper to purchase but welding can
be more difficult.
Although not used for linepipe, the use of titanium may be used for certain
sections of risers. Similarly, composite materials are used for liners and topsides
pipework as well as walkway gratings and wellhead protection covers. Use of
such materials may be more commonplace as their properties become better
known to designers and installers.
130 Overview of pipeline engineering
Question coming
2 slides ahead …
please look up
from notes
In selecting a pipe material, there are two major factors we are looking for: these
are its yield strength and its corrosion resistance.
The technique is to start with common carbon steel and escalate to more
expensive solutions in order to meet the yield strength and corrosion resistance
requirements.
By ‘common carbon steel’ we mean one containing between 0.2% and 0.3%
carbon. This is slightly more than mild steel, which has less than 0.15% carbon.
Weldability is better with lower carbon content. Steels with a carbon equivalent
more than 0.4% normally require heat treatment.
Materials 131
YIELD STRENGTH
0
0 0.2 0.5 15 to 20
Strain, ε (%)
What do we mean by yield strength? This is illustrated in the graph above for
grade X60 steel pipe. The vertical axis shows stress and the horizontal axis
shows strain.
If you imagine cutting a cuboid sample out of the wall of the pipeline and
stretching it, its behaviour would reflect the above graph. As you first applied
the load, it would stretch (imperceptibly) and if the load were released, the
sample would return elastically to its original size, following the line of Young’s
modulus, E. If the stress remains below the elastic limit then the material returns
to its original state when the load is released, and there is no permanent
deformation. However, if you applied a load past the elastic limit, the material
would stretch plastically. Releasing the loads within this zone would leave the
sample stretched and permanently deformed. Applying further load would cause
the sample to ‘neck’ and finally to break.
In design, we generally seek to keep the pipeline steel in the region below SMYS.
If it goes past this, we are into strain-based design.
In the example above, the yield stress of the material is 413 MPa (megapascals).
This corresponds to 60 ksi (thousand pounds per square inch) in imperial units
and is termed grade X60, as defined in API standard 5L. In ISO 3183 (the
international linepipe code), the equivalent steel grade is L415.
132 Overview of pipeline engineering
CHOICE OF GRADE
Given that steel costs about the same per tonne regardless of grade, why should
we stick with X65 and not go for twice the strength?
The answer to this lies in terms of the ductility, toughness and weldability of the
steel.
■ Ductility is the ability of the material to deform plastically before failure.
■ Weldability means that the pipe can be welded together aboard the laybarge without
the need for heat treatment.
■ Fracture toughness is the ability of the material to accept defects (such as weld
inclusions) without these leading to brittle fracture.
As a result of these requirements, most pipeline steels come in the X52 to X65
range, although higher grades (X70 to X100) and lower grades (X42 or even
grade B) are available.
Materials 133
Most pipeline design maintains the steel within the linear elastic region up to
0.5% strain. Notable exceptions are during construction when the wall is
deliberately pushed well into the plastic region during reel-lay and J-tube
installation.
The main constraints limiting the use of very strong pipe have been described.
We usually select grades X52 to X65 that are relatively easy to weld successfully.
134 Overview of pipeline engineering
Sour corrosion causes cracking in the pipe wall leading to deep pits which may
cause leakage.
Oxygen corrosion (rust) can come from water injection duty on the inside of the
pipe or seawater on the outside. Having said that, it is very rare to experience
oxygen corrosion on the outside of a subsea pipeline because it is protected by a
cathodic protection system (see ahead).
Note that ISO 3183 Class C linepipe is specifically for sour service lines. API 5L
does not have an equivalent.
Materials 135
COMBATTING INTERNAL
CORROSION
Corrosion allowance
3 to 6 mm (0.118in to 0.236in)
Use an inhibitor
Coats pipe wall
Use a CRA
316 stainless
Duplex
Nickel alloy
Use a liner/cladding
Methanol or glycol
‘Mops up’ water
Methanol and glycol (for gas pipelines) are added to pipelines to absorb water,
binding to it at a molecular level. They mop up free water, preventing it forming
acids with any H2S or CO2 present. They are also added for process reasons (to
prevent hydrates or wax formation) rather than to prevent corrosion, but if they
are present they will enhance the effectiveness of corrosion inhibitors. These
additives need to be separated at the terminal and returned to the field. One way
of doing this is via a piggyback line, as shown in the above picture.
136 Overview of pipeline engineering
CORROSION INHIBITORS
Inhibitor vaporises
Migrates to recessed
areas and cavities
Condenses on surface
Ions dissolve in
moisture film
Ions form protective
film Pipeline section showing active VCI
protection in all three phases :
liquid, inter-phase and vapour phase
Corrosion Inhibitor
The slide details the process by which corrosion inhibitors work. However, at
the interface of the oil and brine, preferential corrosion can occur to produce
‘tramlines’ along the length of the pipe.
CORROSION-RESISTANT ALLOYS
CRA properties
More expensive to purchase than carbon steel
Long lead times – limited worldwide supply
Strength and other properties
Strength, density, thermal expansion and conductivity
Product composition for selection
Shorter lengths and slower to weld
Common types
316 stainless, duplex, nickel alloy
Cheapest to dearest – but improved resistance
13% chrome difficult to weld
Corrosion-resistant alloys are far more expensive to purchase per tonne than
carbon steel with the common duplex grade about five times the cost.
With a limited number of manufacturers, there are long lead times. A single
pipeline project may use a significant percentage of the worldwide supply.
Their properties differ with some being notably different from that of carbon
steel.
Thick wall seamless CRA pipes may only be available in short lengths of 9 m or 6
m (30ft or 20ft) and butt welding operations may take twice as long for duplex as
that for carbon steel.
Common grades are listed above in increasing cost. However, the most
expensive grades are the most resistant to corrosion. For example, grade 316 is
only resistant to sweet corrosion, duplex is resistant to sweet and low levels of
H2S, whilst nickel alloys resist sweet and high levels of H2S.
Any questions?
The product composition provides an indication of the content of the line. With
carbon dioxide, hydrogen sulphide or water in the line, it is likely that different
forms of corrosion may occur.
For low levels of attack, the initial approach of providing additional wall
thickness may be sufficient.
Savings may be made by using the CRA as a cladding inside oil or gas lines.
Water injection lines installed using the reel-lay or bundle methods may demand
the use of PE liners.
Materials 139
CRA-CLAD FLOWLINES
By using a thin layer of CRA on the inside of a pipeline, it is possible to use a strong
carbon steel pipe for highly corrosive product. The purchase cost is less than a thick-
walled wholly CRA linepipe and because we can take advantage of the stronger grades of
steel, it may result in a thinner wall overall.
These pipes are usually limited to flowlines because it is more cost-effective to take out
corrosive product at the facility than to clad a whole length of export line.Commonly,
the cladding is 2 mm to 3 mm thick on pipelines less than 328.3 mm (12in) and up to 5
mm on larger diameters.
Post-manufacture heat treatment is needed to restore the properties of the cladding and
the carbon steel pipe.
Because of the thinness of the cladding, it is important that care be taken with alignment
at the ends for the butt welds. In some cases, it is possible to weld the liner and the pipe
itself with the same high grade alloy. In this instance, buttering of the weld bevel is
required.
With other combinations, it is necessary to weld the inner section separately from the
outer using different welding wire and techniques. TIG is often used for the cladding
and first pass of the outer pipe, and NDT of this is required before continuing with the
remainder of the weld. Cladding therefore slows the field weld process considerably,
with far higher rates of rejects: it may take three times longer to butt weld clad pipe
compared with simple carbon steel.
PLASTIC-LINED PIPE
The process of lining the steel pipe with the MDPE liner is known as
Swagelining, this process is illustrated above. It requires that the MDPE liner has
an outer diameter slightly larger than the inner diameter of the steel pipe. The
liner is then pulled through the die and steel pipe under tension. The tension
through the die reduces the diameter of the liner enough for it to pass through
the steel pipe. Once pulled through, the tension is released and the liner attempts
to return to its original diameter. This then creates a tight fit between the liner
and the steel pipe.
To connect two sections of lined pipe together then the connection is made as
illustrated above. Two short sections of pipe made from a corrosion resistant
alloy (CRA) are welded to the end of each steel pipe joint. A larger diameter cap
Materials 141
is then placed and welded over the whole joint. The two sections of MDPE are
then positioned to ensure the water contents will only contact the CRA pipe
sections.
The make-up of the joints for plastic lined pipe is a time consuming process,
which makes the process uneconomical if using the S-lay or J-lay methods.
Reeling has the advantage that the pipe strings are fabricated onshore in 500 m
(1640 ft) lengths. It is then possible to swage line these long pipe strings in a
single activity onshore, prior to reeling the string onto the spool. This then
means only one joint is required for each 500m pipe string. It then becomes
viable to use plastic lined pipe for reeling operations.
This type of lined pipe has been used on the Foinaven field for the water
injection flowlines. The field is west of the Shetland Isles at a depth of between
396 m (1300 ft) and 607 m (2000 ft). The depth meant that the water injection
flowlines would have to survive their required 25 year service life without
maintenance. Development of the field began in 1996 and 15 km (50000 ft) of
254 mm (10 in) pipe and 2.8 km (9300 ft) of 203 mm (8 in) PE lined pipe were
installed by reeling from the Norlift vessel.
The main problem with PE-lined pipe relates to the field joints. It is not possible
to continuously coat the whole length of the line and field joints. It is necessary
to use a CRA field joint system which is too costly to undertake at every 12 m
(40ft) pipe joint.
This limits its use to land-based assembly methods such as reel lay and bundles
when lengths up to 500 m can be threaded before PE recovery takes place.
Nevertheless, it is the only system permitted by leading clients for water injection
lines. The alternative is to coat the inside of these lines with either FBE or epoxy
142 Overview of pipeline engineering
paint. However, severe corrosion of such lines has often occurred and has been
linked to erosion from particles in the water or poor field joint repairs.
Clad pipe
Corrosive hydrocarbon products
Sweet and sour service
Thin bonded layer of CRA
Cheaper than wholly CRA
Difficulties with welding
PE-lined pipe
Used for water-injection lines
Specified by leading clients
Limited to reel-lay and bundles
because of expensive connections
Any questions?
Cladding is cheaper than providing linepipe out of CRA but does present
difficulties with the butt welds.
TITANIUM PROPERTIES
In its pure form, titanium has a comparatively low strength and few applications.
However, when combined with other elements to form alloys, the material
properties can be greatly enhanced.
Titanium has a relatively low elastic stiffness (Young’s Modulus) compared to its
strength. It also has a greater spring back in forming and machining operations
than steel.
One of the main benefits of titanium alloy is very high strength to weight ratios.
Components that would otherwise be made in steel can be made using titanium,
giving comparable performance at a much lower weight.
1200
160
Ti-6AI-4V annealed
1000
140
Nominal Stress MPa (ksi)
120
800
100
X65 pipe steel
600
80
400 60
40
200
20
0 0
0 2 4 6 8 10 12 14 16
Strain (%)
The graph shows how carbon steel has a lower yield than titanium but has
approximately twice the Young’s modulus, E.
That is to say it is stiffer, and will elongate approximately half that of titanium
providing the stress remains below yield.
Materials 145
TITANIUM
High cost
Information on:
Touchdown point stress joints
Taper stress joints
Available from:
www.titaniuminfogroup.co.uk
To cope with the demands of the touchdown point, titanium joints may be used.
The strength, flexibility, fatigue properties and temperature range are very
beneficial compared to steel.
The yield stress given above relates to Ti-6Al-4V ELI (ASTM grade 23, UNS N°
R56407) used for deep water drilling risers, choke/kill lines, dynamic
production/export risers, taper stress joints and fasteners. The standard grade
Ti-6Al-4V (ASTM grade 5, UNS N° R56400) yields at 827 MPa (120 ksi) and is
used for drill pipe.
However, the cost per tonne is 20 to 40 times that of steel – though considerable
savings can be made because of the reduction in both the wall thickness and the
density of pipe.
The Heidrun drilling platform is a tension leg platform (TLP) which operates in a
northern area of the Norwegian Sea in 345 m (1132ft) of water. It is the most
northerly TLP installed to date. The platform was developed and run by Conoco
and Statoil, and has been operating since 1992.
The titanium alloy used is Ti-6Al-4V ELI (ASTM grade 23) – ELI has extra low
interstitial O, N and H for improved toughness. The joints are 552.3 mm (22in)
bore with 22.23 mm (0.75in) wall and 14.685 m (48.2ft) long. These are TIG
welded to compact flanges. The joints have a 3 mm (⅛in) internal hydrogenated
nitrile liner for wear resistance and external protective layer. Care was needed
with welding to limit the size of pore defects which limit the fatigue life.
The high strength to weight ratio of titanium means that the drilling riser weighs
55% that of the steel equivalent. At present, the titanium drilling riser has
produced 20 new wells and the inspection of the riser after each retrieval has
found no detrimental defects of the titanium material.
DNV has issued RP-F201 (2002), Design of titanium risers with fatigue guidance
(SN curves).
Note that successful testing of composite drilling risers (CDRs) has also been
carried out at Heidrun between July 2001 and January 2002 during
inspection/maintenance of the titanium risers.
Materials 147
The most important thing to remember about composites is that the final
properties are dependent on the manufacturing process and are only achieved
after the component has been manufactured.
COMPOSITE MATERIALS -
BENEFITS
Material
Lightweight
Corrosion resistance
Fatigue performance
Installation
Ease of handling
Use of hand tools Composite laminate sheet
Picture courtesy of EDO Speciality Plastics
May eliminate hot work
Others
Thermal insulation, fire, failure mode etc
148 Overview of pipeline engineering
The principle benefits that can be derived from the use of composites are listed
above.
Composites are very cost effective where high metallurgy CRA (corrosion
resistant alloy) alternatives would be required.
The installation advantages are often not appreciated at the start of a project and
become more apparent as the labour force progress through the learning curve.
SUBSEA PROTECTIVE
STRUCTURES
Wellhead
protection
Shell Cocoon
wellhead protection
Valve cover
(fisher-friendly)
Composite materials can be used for many protective subsea structures including
wellhead and valve protection.
The main value to be gained from the use of composites is weight saving, which
can enable substantial savings in installation cost by enabling the use of lower-
cost lift vessels, or to enable the protective structure to be attached to the
flowline during pipe installation.
The fabrication cost is competitive with that of conventional steel and concrete
technology.
The lower material modulus of GRP may impose limitations for some structural
applications, for example templates.
The purchase cost for GRP is slightly more expensive than that for steel.
However, the fabrication and installation costs are much less, making composites
very attractive financially.
Materials 149
Titanium
High strength to weight ratio
Good fatigue performance and corrosion resistance
Used successfully for Heidrun drilling riser joints
Composites
High strength to weight ratio if correctly designed
Good fatigue performance and corrosion resistance
Good thermal insulation properties for fire resistance
Used successfully in subsea protection structures
Reduced weight eases installation
Any questions?
Titanium and composites are advanced materials that can have significant
benefits when compared to steel.
Titanium, although expensive can become a feasible pipe material due to its
higher strength:weight ratios, better fatigue performance and corrosion resistance
in comparison with steel. Titanium drilling riser joints have been successfully
used on the Heidrun riser and to present date have showed no detrimental
effects.
Any questions?
In summary, material selection aims to satisfy the requirements for strength and
corrosion resistance. The technique is to start with common carbon steel and to
escalate until you find the solution.
Ensure that the effects of internal corrosion are minimised first using corrosion
allowance and chemical additives before moving on to costly exotic materials and
welding techniques.
EXPECTATION
EXPECTATION
External coatings
Corrosion protection
Concrete for on-bottom stability
Thermal
Why they are needed
What coatings are available
Pipe-in-pipe systems
Field joints
Active heating systems
The previous module defined the size and material for the pipeline.
Most pipelines have an exterior coating for prevention of corrosion. We explain why
this and other external coatings of concrete or thermal materials are sometimes applied,
and the types of coatings that are available.
Field joints need to be made quickly - generally a matter of minutes - and coatings which
are acceptable for the main linepipe may not be suitable for covering the welds.
Where insulation is not enough by itself, some lines use active heating systems to
maintain the product above the minimum allowable temperature.
154 Overview of pipeline engineering
The primary attack on the external surfaces of the pipe is oxygen corrosion. There are
two levels of defence - the first is the anticorrosion coating on the pipe. The second is
the cathodic protection system.
The anticorrosion coatings take the form of fusion-bonded epoxy (FBE) similar to the
enamel on cooker hobs, polypropylene coating or bitumen/coal tar epoxy (CTE). CTE
is a 6 mm layer of tar with a bonded-in layer of glass fibre. It is now used less frequently
in the UK and USA – although it may still found on operational pipelines installed a
decade or more ago.
In all cases the pipeline is first cleaned and shot-blasted to conform with the Swedish
standard Sa2½, according to ISO 8501-1. Sometimes, FBE is then used alone, but it is
usually used as a first layer in combination with polyurethane PU, polypropylene PP or
polyethylene PE for impact protection.
At the field joints, it is common to apply sheets of shrink wrap which bond to the pipe
and provide an overlap of 50 mm (2in) or so with the factory-applied coating. A cutback
at the pipe-ends of 100 mm to 200 mm (4in to 8in) is needed because the heat from the
External coatings 155
welding operations would damage the coating. This section needs to be protected using
a rapidly applied system.
With FBE-coated pipe, it is possible to simply shot-blast and spray on a rapid cure epoxy
layer at the field joint.
CORROSION COATINGS
The corrosion coating system is normally used to provide external protection, but some
pipelines also require internal protection (for example, water injection and tanker loading
lines).
The external protection system is often combined with other materials to provide
impact, thermal or other benefits.
156 Overview of pipeline engineering
COATING MATERIALS
Fusion-bonded epoxy (FBE) is by far the commonest coating for offshore pipelines.
This is typically 0.5 mm (0.040in) thick and is a very smooth hard coating. It is applied
by heating the pipe and spraying on a powder. However, FBE does tend to chip when
hit and it is often used as the base layer of a multi-layer coating systems. Occasionally, it
is used as a single or double application (with no further coatings) in the deep waters of
the Gulf of Mexico – careful handling is required to prevent mechanical damage.
Nevertheless, it should not be so used at temperatures over 70°C (158°F) when in
contact with seawater.
Tape wrap has often been used for pipe joints and for the whole length of some
landlines. It is quick to apply at butt welds, but other jointing systems with fewer
disadvantages (such as shrink wrap coating) have replaced it.
External coatings 157
COATING MATERIALS
Bituminous coatings were once the standard form of protection but they are now rarely
used offshore due to environmental concerns. Thin layers of glass reinforcement tape
are embedded into the thickness of bitumen whilst it is still liquid.
PE, PU and PP’s temperature and shear resistance disadvantages limit them to being
applied as part of a ‘coating system’ often in combination with FBE.
The particular cleaning chemical used to degrease the pipe and the grade of FBE may
prove to be a problem at temperatures over 110°C (230°F) due to disbondment issues.
158 Overview of pipeline engineering
SPLASH ZONE
Since this is a high light level region, some systems add antifouling to the coating to
prevent build-up of marine growth.
The method of applying the rubber is to clean and shot blast the length of pipe and then
helically wind on thin strips of rubber sheet from rolls. The pipes are then heated to
vulcanise the rubber into a single mass and bond it to the pipeline riser section. Because
the furnaces are of limited size, this necessarily limits the lengths of pipe to be coated.
External coatings 159
EXTERNAL PROTECTION -
SUMMARY
Any questions?
A number of different coating materials are used to prevent corrosion of the outside of
the pipeline in seawater.
Most pipelines are now coated using three-layer protection. The CTE process may still
be found in some areas of the world and on older pipelines.
In the highly corrosive environment of the splash zone of risers, it is often necessary to
use thick rubber coatings.
160 Overview of pipeline engineering
CATHODIC PROTECTION
CATHODIC PROTECTION
Galvanic system
Sacrificial method - gradual deterioration of anode
Potential difference between anode and steel
Uses zinc, magnesium or aluminium as anode
There are two main methods of providing protection against external corrosion: the
galvanic method or impressed current.
Offshore, the former predominates, and we attach anodes at intervals along the pipe.
External coatings 161
Anodes
8 to 12 pipelengths
Reel lay at much
greater centres
Bracelet or
half-shells
Ablate away
Protect exposed
areas of pipe with
coating damage
More important
at end of life
If the coating becomes scratched or damaged at any time during the life of the pipeline,
the second line of defence is the cathodic protection system, where aluminium or zinc
anodes are attached at intervals to the pipeline, as shown in the picture above.
Typical anode spacings would be 100 m (328 ft). However, this distance is increased by
perhaps five times on pipelines installed by the reel-lay method, which relies on a rapid
lay rate. Such anodes are less efficient and need to be larger than those using the S-lay or
J-lay methods.
If an area of pipe steel becomes exposed, the anode sets up an electric circuit whereby
aluminium or zinc goes into solution in the seawater, in preference to the iron from the
steel.
Although installed with the pipeline, they become more important towards the end of its
life as damage increases. In some cases, it may be necessary to replace spent anodes
during the life of the pipeline.
162 Overview of pipeline engineering
CATHODIC PROTECTION OR
COATING?
CP
Coating
Coating & CP
Cost
Optimum level
(typically 98%)
0 100
% Pipe of protected by coating
Hence, generally, a combination of the two methods is used, with the CP system
protecting the regions of the pipeline where defects or degradation of the coating over
time leave the pipeline exposed, allowing water and oxygen to reach the surface.
CATHODIC PROTECTION -
SUMMARY
Anodes
Used for subsea pipelines and manifolds
Impressed current
Used for land pipelines and platforms
Overall protection
Combination of coating and CP
Minimum cost solution
Any questions?
Anodes are attached to subsea pipelines to protect areas of coating that are damaged
during their life. That is an economic combination of coating and cathodic protection.
External coatings 163
An alternative is the impressed current which requires ground beds to produce the
potential.
164 Overview of pipeline engineering
ON-BOTTOM STABILITY
ON-BOTTOM STABILITY
It is necessary to ensure that once placed on the seabed, the pipeline does not move
under storm conditions.
This requirement often conflicts with the need for insulation, where applying thick layers
of foam makes the pipe much more buoyant and less stable.
We choose 1 year and 100 year return periods respectively, because they are each
approximately three times the design life of the pipeline in that condition.
External coatings 165
HYDRODYNAMIC FORCES
Hydrodynamic lift
Inertia
Lateral friction
Bottom reaction
Stability means ensuring that the pipe has sufficient submerged weight not to move
under storm conditions. Looking at the diagram above, this means that the (available)
lateral friction must exceed the drag due to the current and waves.
Looking at the vertical forces, when the pipeline is placed on the seabed it has its
submerged weight (ie self-weight less buoyancy) countered by the bottom reaction from
the seabed. If we now introduce a fluid flow over the top of the pipe, this results in lift
and drag.
You are perhaps familiar with the lift generated by aircraft wings where the air flows
faster over the top than it does underneath. In this case, we have water flow over the
top of the pipe but no flow underneath. This generates lift. In addition, there is a drag
force caused by a high-pressure build up on one side of the pipe and a low-pressure
wake behind it.
The effect of the lift is to reduce the bottom reaction. The lateral friction is proportional
to the bottom reaction. So, as the fluid speed increases, the lateral friction will reduce
and the drag will increase until the limit of stability is reached when the drag matches the
lateral friction.
In wave flow, there is an additional factor due to the acceleration of the wave, which
induces inertial forces on the pipeline as well as lift and drag. The drag, lift and inertial
forces all vary over a complete wave cycle..
166 Overview of pipeline engineering
STABILITY ANALYSIS
If the pipeline is not stable, the primary means of stabilising it is to add a concrete
weight coat. The picture shows a typical 50 to 100 mm (2in to 4in) of concrete being
added to the pipe joints.
■ Concrete is not generally applied over the top of foam coatings, but it is not
unknown with more rigid insulation systems such as the syntactic materials
■ Higher density concrete (specific gravity of 3.050 instead of 2.400) can be used to
reduce the required thickness
■ Almost every line over 16 inch diameter needs to be concrete-coated to counteract
the increased buoyancy of large diameter lines
■ Concrete also acts to protect the pipeline against impact
Typically, steel costs twelve times more than concrete per tonne. However, the
submerged weight of steel is five times that of normal concrete so the savings are
reduced.
Trenching alone
Reduces current
effects (shielding)
Steep side slope keeps pipeline in place
Slope angle is soil-type dependant
Helps reduce trawling impacts
Trenching with burial
Eliminates hydrodynamic forces on pipeline
Provides thermal insulation
Cover to top of pipeline varies
Landfall 2 m to 3 m (6ft to 10ft) – offshore 0.3 m (1ft)
An alternative to concrete-coating is to trench the pipeline. This has two main effects in
terms of stability. Firstly, it shields the pipeline from hydrodynamic loads. Secondly, it
provides an upward slope on either side of it which effectively increases the lateral
friction. However, the shape of the trench depends on soil type. Fine sands, soft muds
and silts do not usually result in a steep enough trench.
Additionally, some trawl interaction protection is given by lowering the pipeline below
the surrounding seabed.
If burial is undertaken as well, then a further insulating benefit is given by the soil.
The depth to the top of the pipe varies depending upon the risk of scour removing the
cover. At the landfall, 2 m or even 3 m may be needed. In deeper water where there are
low currents and a non-mobile seabed, this can be substantially less.
168 Overview of pipeline engineering
Any questions?
The principle of stability is to ensure that the pipeline has sufficient weight such that it
does not move under storm conditions. The main techniques are concrete-coating and
trenching.
External coatings 169
THERMAL INSULATION
Production temperatures
60°C to 160°C (140°F to 320°F)
Ambient
5°C (41°F)
This section addresses the issue of why we need to insulate pipelines and the techniques
available to do so.
170 Overview of pipeline engineering
Wax
Oil lines
Hydrates
Gas lines - water at high pressures
Viscosity
Increased friction - head loss
Separation
Emulsions
The main reason for insulating a pipeline is that process problems can occur if the oil or
gas is allowed to cool to ambient temperatures.
SELECTION OF COATINGS
Insulate
Thermal inertia
Withstand maximum temperature
Withstand maximum collapse pressure
Handling and reeling without damage
Not cause pipeline to destabilise (increased
uplift or flotation)
It must provide the insulation required to keep the product warm throughout the length
of the pipeline.
If the flow is stopped for some reason, then insulation will prevent the product from
cooling too much prior to restarting operations. This may be for 24 hours or more. On
restarting, the pumps must be able to cope with the increased viscosity.
Some insulation materials can withstand higher temperatures and pressures than others.
Typical product temperatures for flowlines are up to 110°C (230°F), though this can be
exceeded especially with deep water fields.
It is often the case that a protective outer coating is used to improve the handleability of
the coating, preventing damage to the insulation layer. Flowlines are often installed
using reelbarges. Softer foams cannot be reeled successfully without crushing damage.
If the insulation layer is too thick or not dense enough, then the pipeline may be too
light in weight for stability. In extreme cases, the pipeline may float during installation
when is empty.
172 Overview of pipeline engineering
INSULATION TECHNIQUES
Solid PU
PUF
FBE
Pipe-in-pipe Pipe
0.8 to 2.5 W/(m² K) (0.1 to 0.4 BTU/hr/ft²/°F)
Where:
■ PU = PolyUrethane
■ PUF = PolyUrethane Foam
■ FBE = Fusion-Bonded Epoxy
Typical range for PU foam coating is a U value between 1.5 and 5 W/m²/K (0.265 and
0.884 BTU/hr/ft²/°F).
The equivalent for P-I-P is 0.8 to 2.5 W/m²/K (0.141 and 0.442 BTU/hr/ft²/°F).
External coatings 173
The video shows the pipe being rotated and the foam being poured from nozzles which
move axially along the pipe.
Another method of applying the coating (but which is not shown) is to extrude the foam
over the outer surface of the pipeline.
174 Overview of pipeline engineering
COATING DEGRADATION
MECHANISMS
Creep
Water absorption
Cracking Through Life Overall Coating Strain
12
Hydrolysis
10
Combined
Strain (%)
6
effects 4
0
0 2 4 6 8 10 12 14 16
Time (years)
For foams, creep can be an important factor affecting their insulation properties. Over
time, the coating will become thinner due to the pressure of the surrounding water. Not
only do we have less thickness of insulation, but the thermal properties of the denser
coating are poorer. The graph shows typical strain over the life of a coating.
Water can diffuse through polymer coatings. The water conducts heat more readily than
the polymer, and so the thermal conductivity of the coating increases over time.
Where the pipe has been subjected to damage during installation bending or subsequent
impact, cracking can occur. It can even be caused by age degradation. This can cause
water penetration to the steel or even spalling of the coating.
Finally, all plastics are subject to hydrolysis or degradation when subjected to heat and
water. The water binds to and splits the bonds of the molecules. Some materials are
able to resist this better than others.
When assessing reduction in insulation capability over time, some of these mechanisms
combine - for example, if the coating cracks, water can reach deeper more quickly and
become absorbed into the material. Hydrolysis can then degrade the insulation
exacerbating creep.
The following slides look at the coating types and define the operational limits.
External coatings 175
INSULATION COATINGS
A range of coating systems are available or being developed for deep water applications.
The main coating types are shown above and the first three will be described further in
the following slides.
Mini-spheres act in a similar way to glass syntactic foams but are the size of a pea up to
golf-ball or more. The space between the mini-spheres is filled with GSPU. They are
commonly used for ROV and other buoyancy units.
Syntactic polyurethane
Glass or plastic microspheres in PU matrix
Maximum depth - 3000 m (9850 ft) for GSPU
Maximum temperature - 140°C (284°F)
Typical U-value range - 2 - 5 W/m²/K
(0.4 - 0.9 BTU/ft2/hr/°F)
Reelable
Widely used West Africa, South America,
Gulf of Mexico
176 Overview of pipeline engineering
Microscopic hollow glass or plastic spheres are used to provide insulation. These are
mixed into liquid polyurethane which then sets hard.
Plastic spheres cannot withstand the pressures that glass spheres can.
PPF
Polypropylene foam
Maximum depth - typically 600 m (1967 ft)
Maximum temperature - 150°C (302°F)
Typical U-value range - 2.5 - 5 W/m²/K
(0.44 - 0.9 BTU/ft2/hr/°F)
Reelable
Examples of advanced PPF
Nile - 1000 m - 90°C (3280 ft - 194°F)
Crosby - 1200 m - 90°C (3937 ft - 194°F)
Madison - 1400 m - 65°C (4593 ft - 149°F)
However, advanced PPF materials have been developed and applied at depths of around
3000 m (9840ft), though at the expense of their resistance to the highest of temperatures.
External coatings 177
PUF
Polyurethane foam
Low density option
Maximum water depth 100 m (328 ft)
Typical U: 0.3 to 2 W/m²/K (0.053 to 0.352 BTU/ft2/hr/°F)
High density option
Maximum water depth < 1000 m (3280 ft)
Typical U-values: 2 to 5 W/m²/K (0.4 to 0.9 BTU/ft2/hr/°F)
Crushing limitations at depth
Max temperature 150°C (302°F)
Depth range too limited for ‘deepwater’
applications
The simplest (and amongst the cheapest) insulation is a foamed polyurethane. It uses
gas bubbles to provide the required U value.
We need to carefully assess the crushing over the life of the pipeline and restrict the
maximum temperature.
The video shows manufacture of Løgstør Rør’s ‘single pipe’ insulation system which
features a pair of water stops either side of every field weld.
The pipes are precoated externally with FBE which is then preheated to ensure a good
bond with the sprayed on isocyanate foam coating. The foam can withstand 110°C
(230°F) and is typically applied as a 10 mm to 30 mm (0.4in to 1.2in) layer in densities of
150 kg/m³ to 375 kg/m³ (9.4 lb/ft³ to 23.4 lb/ft³).
An outer polyethylene shell is hot applied to provide full hydrostatic pressure resistance
down to 200 m (656ft). The ends are tapered for welding and bonded to the FBE pipe
coating.
A steel cage is spun around each pipe and a dense heavyweight concrete (containing iron
ore) is slip-formed around the pipe in a vertical system. This contrasts with other
methods which use sprayed, shotcreted or gunited concrete applied to a horizontal
rotating pipe. The vertical system results in a denser, less porous casting. Half shell
anodes are fitted to the ends of some of the pipes. Their outer diameter matches the
concrete coating.
Once the pipe is welded on the laybarge, the field coat is made up using a heat shrink
sleeve over the joint. Two insulated half shells are banded on and the gap is injected
with syntactic polyurethane foam. The slope of the firing line helps ensure no voids are
left as the foam sets. The properties of the foam are not as efficient as the pipe
insulation at 0.145 W/m³ (0.014 BTU/ft³/hr) at a density of 810 kg/m³ (51 lb/ft³).
Total water absorption is less than 2.5% and it can resist a pressure of 15 MPa at 23°C
(2176 psi at 73°F).
The total field joint process takes 7 minutes for each pair of the double jointed pipes.
External coatings 179
FIELD JOINTS
Once two sections of line pipe have been welded together, the corrosion protection and
insulation layers need to be made good.
Field joints need to be matched for compatibility with the main factory applied coatings.
In general they overlap these and make a seal of 50 mm (2in) or so.
If there is concrete applied for weight coat, the field joint is generally filled out to the
same diameter. This is necessary when the pipe is laid over a stinger from an S-lay barge.
It is important to fit the field joint makeup into the production plan. Speed is often of
the essence to reduce pipelay costs. For this reason, different materials may be used
than in the factory, but which can be applied and cured more quickly. This is
sometimes subject to detailed health and safety scrutiny.
180 Overview of pipeline engineering
DEEPWATER FLOWLINE
REQUIREMENTS
The major design conditions issues for a deepwater coating system often take the form
of a required U-value and a specified cool-down period. That is, we need to consider
both normal operations and shutdown conditions, when there may be a requirement to
maintain heat as long as possible or even warm the product up again from cold ambient
temperatures.
Any questions?
Wax builds in oil lines, hydrates form in gas lines, and viscosity increases at cooler
temperatures. All tend to increase friction (and hence production costs) or reduce the
flow. If a multi-phase product gets too cold, there may be separation problems at the
facility due to it forming an emulsion.
In this section, we have looked at typical insulation coatings. There are differences in
the materials used at field joints.
We have examined the particular problems which may arise in deep water flowlines due
to the high pressures and temperatures at the well head and the long lengths of lines
used.
182 Overview of pipeline engineering
PIPE-IN-PIPE SYSTEMS
PIPE-IN-PIPE CONSTRUCTION
Steel carrier
with FBE coating
Microspheres
Pipe
with FBE coating
Here is an example of a pipe-in-pipe system where the annulus between the steel carrier
and the pipe is filled with alumina silicate microspheres. The microspheres are tiny
hollow spheres and look like cement dust. The technique is to assemble the pipes
together, rotate them vertically, fill with the microspheres, and put rubber water stops at
both ends.
External coatings 183
HYDROTHERM - VIDEO
Courtesy
of CORUS
The process is carefully controlled by weighing to ensure that the correct packing of the
spheres permits some of the hydrostatic head to transfer from the outer to the inner
pipe.
PIPE-IN-PIPE SYSTEMS
Conventional thermal insulation coatings, such as low density foams, have low strength
and would crush in deep water applications. But they are very efficient as insulators.
184 Overview of pipeline engineering
Pipe-in-pipe systems offer a means of achieving high thermal efficiency in deep water
applications. The insulation product is placed in the annulus between the inner product
pipe and the outer carrier pipe, in pre-assembled lengths. The outer steel pipe has
sufficient strength to withstand the hydrostatic load, and the insulation product does not
require any intrinsic strength.
Pipe-in-pipe systems are made up on the laybarge, although the requirement to join both
an inner pipe and outer pipe significantly reduces the rate of lay. Various connection
systems have been developed to increase the speed at which the outer carrier pipe
connection can be made.
Thermal implications
The outer pipe wall thickness can be reduced by internally pressurising the annulus with
nitrogen gas.
THERMAL IMPLICATIONS
Foam insulant
Must be open-celled to avoid crushing
Open cells less efficient than closed cell foam
Increased convection
High pressure gives increased gas density
Increased convection within foam cells
Increased convection across annulus
When pressurising the annulus with gas, consideration has to be given to the effect of
the pressure on the insulant material. If a foam is being used, this must be open-celled
to allow pressure equalisation through the foam and to avoid crushing of the foam.
Open cells are less efficient insulators than closed cell foams.
A further implication of pressurising the gas is that, with the resultant increased density,
convective heat transfer increases.
The Troika pipe-in-pipe system in the Gulf of Mexico failed to meet its thermal targets
because these effects were not correctly accounted for.
PIPE-IN-PIPE DEEPWATER
CHALLENGES
The principal deepwater challenges for pipe-in-pipe systems are listed above.
■ Significant material costs can be incurred as a result of the thick outer pipe being
required to resist the full hydrostatic collapse pressure. Since the annulus is at 1
atmosphere, no beneficial effect can be taken from the internal product pressure.
■ Rapid assembly is required to control installation costs. The need for both inner and
outer pipe connections greatly reduces the layrate. This is especially true of J-lay
barges which use single welding stations.
■ Outer pipe connection details must be rigorously designed. Pipeline failure has
already occurred as a result of inappropriate design of the outer pipe connection
details.
With the J-lay method, there is a single weld and coating station. The pipe-in-pipe lay
rate is consequently much slower if conventional steel half-shells are used for the joint.
A number of systems have been proposed and used to speed this up.
Metal jacket
Steel
Half-shell
half-shell
Flow line
Weld
It is the outer jacket which is put in tension, so at least some of the jacket weld (both
girth and seam welds) must be completed before the first tensioner. Normally at least the
root weld and first pass are completed before the tensioner.
This requirement puts a limit on the use of tensioners (effectively the first pair are made
redundant as they are before the first jacket weld stations). This means that double
pipeline systems are laid approximately 1/2 to 1/3 times slower than conventional
‘single’ pipelines.
1
2 1. Inner pipes welded together
2. Sleeve slid across
3. Sleeve butt welded to bell-end
3 4 of outer carrier
4. Sleeve fillet welded to the
other pipeline
The purpose of the sliding sleeve is to reduce the welding time for the outer pipe. A
welded sliding sleeve will require at least one of the welds to be a fillet weld rather than a
butt weld. This has significant implications with respect to fatigue performance, which
must be duly accounted for in both design and fabrication. The Erskine pipeline failed
because of this type of connection.
BONGA SOLUTION
Pipe-in-pipe
Insulation
For the Bonga field, pre-formed ends were welded onto the outer pipe in order to speed
up the assembly of the pipe-in-pipe system. The axial stress in the outer pipe is then
transferred to the inner pipeline through a single structural weld.
External coatings 189
Preformed blocks of insulation are then fitted around the weld prior to a sleeve section
with the primary vacuum insulation being slid on.
Pipe-in-pipe systems can be reeled. The major issue is the control of bending and
straightening of the inner pipe.
The bending of the outer pipe is displacement-controlled by the reel and straightener.
The inner pipe is displacement-controlled at intermittent points only (the spacer
locations). The discontinuous contact with the inner pipe means it is not possible to
straighten the pipe fully during the reeling process.
Other issues include the design of intermediate bulkheads and water seals which also
have to be reelable. It is important that no additional strain is concentrated at these
points.
190 Overview of pipeline engineering
Technip have installed the Nile pipe-in-pipe flowline in 1100 m (3608ft) water depth in
the Gulf of Mexico (GoM), and are currently working on a project for 2100 m (6888ft)
water depth.
Spilled LNG (liquefied natural gas) in a large scale leak can produce very cold vapour
which in general will remain heavier than air until it absorbs sufficient heat from
surrounding surfaces and air. If the cold vapour forms a flammable heavier-than-air
fuel-air cloud, it may find an ignition source near the ground and cause an unconfined
vapour cloud explosion (UVCE) during the dispersion process. This could be a simple
spark from even a mobile phone or hobnail boots.
External coatings 191
Because cold LNG is reduced to some 1/628 of its original volume and the transporter
ships are so large - the largest Q Max vessels currently being built holds 265 000 m³
(9.4x106ft³) of liquid - there are serious concerns regarding leaks. Explosive release of
such a large amount of energy at once would be an absolutely calamitous disaster.
There are currently a number of concerns requiring the location of LNG moorings and
loading/unloading facilities to sites remote from habitation. If a cloud were to form
from an accidental leak or terrorist attack on the ship, it can spread a very long distance
from the source.
U.S. Coast Guard requested that Sandia National Laboratories review the ‘Independent
Risk Assessment of the Proposed Cabrillo Port LNG Deepwater Port Project’ off the
coast of Malibu, California. The conclusion states that a flammable liquefied natural gas
(LNG) vapour cloud could extend 12 kilometres (7.3 miles). (Reference Sandia Report
Sand2005-7339 January 2006.)
LNG PIPE-IN-PIPE-IN-PIPE
The alternative is to construct insulated pipelines and contraction loops on long jetties
out to the dolphin or sea-island where the LNG tankers moor. However costly this is,
the danger of catastrophic loss of a subsea LNG pipeline means that at present, such
proposals remain as cost-benefit and risk-assessment studies.
192 Overview of pipeline engineering
LNG needs to be kept very cold to maintain it as a liquid, but the required pressure is
low – only enough to pump the short distance to shore.
Invar or similar material has a zero (or even negative) coefficient of thermal expansion.
This provides designers with a means of matching the linear contraction of the
innermost sleeve (when in contact with LNG during discharge) with the behaviour of
that for the outer pipeline, in contact with seawater at perhaps 5°C (41°F). The wall
thickness of the inner pipe is very thin – only needing to resist low pressure. The
corrosion resistance of invar is excellent and there is no need for a corrosion allowance.
However, costs for Invar are very high.
The two outer pipes are of normal carbon steel grade X65 or similar. These need to
resist external water pressure. However, if they come into contact with the cold LNG,
they are liable brittle failure.
The annuli between the pipes contain either vacuum or aerogel to provide insulation and
a means of testing for leaks. Spacers holding the lines coaxially must be designed
carefully to avoid heat bridging between the pipe layers.
PIPE-IN-PIPE - SUMMARY
Any questions?
It is better able to resist high external pressure without creep or crushing. But this
comes at the cost of speed of installation. Additional care is needed at joints.
All the installation methods can make use of pipe-in-pipe. Special considerations for J-
lay and reel-lay have been explained.
The recent development for LNG terminals is limited to relatively short pipeline strings
as a replacement for existing insulated lines on jetties.
External coatings 193
HEATING
Approaches:
Use electrical cables
In bundles, use heating pipes - Gulfaks
Hot water in pipe-in-pipe annulus - Britannia
Insulation systems are widely used to reduce the heat loss from the pipeline system.
There are cases where we may have a requirement to add heat to the pipeline system,
particularly in shut-down and start-up conditions.
ELECTRICAL HEATING
3 main categories:
Induction
Wire induces eddy
currents
Pipe wall heats up
Direct impedance
Current passed down
pipe wall eg Asgard
Trace heating
Electric wire heats up
P-I-P systems
Consider costs
Shutdown/startup
Combipipe Induction system
However, there are considerable operating costs involved in continuous electrical heating
of lines. It may be best reserved for shutdown/startup operations.
External coatings 195
HEATING PIPES
Gullfaks bundle
1. Control lines
3 2. Gas injection
2 3. Methanol injection
4. Insulation
1 1
5. Production lines
6. Hot water return
7. Hot water supply
4
8. Insulation
6
5 5
8
7 7
Thermal Analysis
Hot water heating pipes have been used in bundles. This figure illustrates an
arrangement as used in the Gulfaks satellite bundles. The production flowlines and
heating pipes are within an insulated nitrogen filled carrier pipe, which is itself within an
outer water filled carrier pipe.
Heat input is required to sustain a long cool-down period following shut-down. Heat
transfer from the heating pipes to the production flowlines is by convection in the
nitrogen and radiation.
The Britannia bundles used an alternative hot water heating system, where the hot water
flowed within the carrier pipe itself.
Because part of the carrier annulus remains nitrogen filled, extra weight must be found
in the bundle to counteract buoyancy.
196 Overview of pipeline engineering
On the Britannia project, waste heat at the platform was utilised to keep warm water
circulating through a dedicated 324 mm (12in) pipe adjacent to the 356 mm (14in)
production flowline.
At the well manifold the slightly cooler water returns to the platform though the
annulus.
One difficulty with this system is that there may be hidden corrosion on the internal side
of the carrier pipe.
The system was designed to heat up to operating temperature from cold within 24 hours.
External coatings 197
Any questions?
We have listed the four main problems when heat is not provided (wax, hydrates,
viscosity and product separation).
The three methods of active heating using electrical power to provide heat have been
examined, along with the two bundle approaches to heating flowlines.
Corrosion protection
Cathodic protection
On-bottom stability
Thermal insulation
Pipe-in-pipe systems
Active heating of lines
Any questions?
They are needed to assist in avoiding external corrosion and keeping the pipe in place on
the seabed. The first is achieved with a combined approach of coating and CP. An
alternative to concrete coating is to trench the pipeline.
Thermal coatings can be applied directly or through the use of pipe-in-pipe systems.
EXPECTATION
EXPECTATION
We will look at modern limit state design theory and how this may be applied. We
introduce the Norwegian standard commonly known as DNV OS-F101, which is the
leading limit state design code used for pipelines.
The modern design approach can lead to cost savings when assessing pipe buckles. We
also consider how the use of HIPPS systems can lead to thinner walled flowlines.
We examine whether we need to design all pipelines for fishing interaction or if we can
safely make cost savings by eliminating trenching.
Fatigue damage to pipelines can be caused by rapid vibration caused by currents flowing
over them. We will look at means of assessing for VIV.
202 Overview of pipeline engineering
There are four limit state classifications that are usually considered in modern design.
There may be more than one limiting state in each class.
When assessing a pipeline, we need to ensure the design complies with the codes and the
client’s needs. We don’t necessarily need to worry too much about the detailed lead up
to the failure condition.
The adage above implies that we should strive to design as economically as possible.
Let us see how the four limit state classifications are applied to the failure of bridges.
Remember, we normally only need to determine the limiting mechanism conditions, not
what caused them.
However, in the next two slides, we are also describing how they came about. This is to
help us understand the differences between the four limit state conditions.
Design methods 203
Ultimate
Loads exceed strength
London bridge - heavier buildings
Foundations were exposed by scour
Fell down - unusable
Service Medieval London bridge
Usable but does not achieve client’s needs
Thin plank over stream
Feet get wet
Rope bridge
Feels wobbly
Rope
Millennium footbridge bridge Millennium bridge
The ultimate limit state indicates that the loads applied to the structure exceed its
strength. In other words, it fails or collapses.
In the nursery rhyme, ‘London Bridge is falling down’, the bridge had so many houses
and storerooms built on and over it that people may have thought that they were
walking through a tunnel with shop fronts on either side rather than crossing a bridge.
The piers to the bridge were so wide that they constricted the flow of the river. At
certain times of the tide, the differential water levels either side of the bridge were up to
1.5 m (5ft) and a weir effect prevented passage of boats. Severe scour of the soil
beneath the piers caused loss of support. This lead to the installation of protective
starlings (timber sheet piles) which further restricted flows.
Eventually, the weight of the buildings exceeded what the foundations could support.
In service limit state, the structure may be quite safe. However, people either cannot use
the structure in its intended manner (it does not achieve the requirements set out in the
Basis of Design), or they feel unsafe in using it. (Perhaps the boatmen beneath the old
London bridge would have perceived it as a service failure as they shot the weir.)
As children, we have all used too thin a plank to cross a gap. If we made a bridge to
cross a stream, perhaps we were able to cross without it dipping into the water.
However, if two were to cross together, they might get wet feet.
The rope bridge across a gorge in an Indiana Jones film invariably has someone too
scared to cross because it is moving too much.
The classic modern service failure was London’s millennium footbridge. When it
opened, the crowds crossing caused it to sway from side to side at a fundamental
frequency. This made others walk in step and the bridge began to oscillate even more.
The bridge was quickly closed and dampers fitted. Again, this is a service limit state
because of excessive deflections - though this time laterally rather than vertically.
204 Overview of pipeline engineering
Fatigue
Subject to repeated bending stress
Tacoma Narrows
Strength of material deteriorates
Avoid locations of stress concentration
S-N curve - assess-and-monitor or overdesign? S
Accidental
Unexpected incident N
Vehicle hits suspenders or ship hits pier
Provide Armco barrier and fendering
Kobe viaduct
Designed for lesser earthquakes
Not a design condition for the structure
Fatigue caused by repeated bending results in loss of strength of the material itself.
The classic example was the failure of the Tacoma Narrows suspension bridge (upper
photograph above), which is shown to most engineers at college. The bridge was
designed to resist predicted winds but the deck fluttered violently at speeds
approximately half these, 19 m/s (42 mph),. It originally was thought of as a service
failure (similar to the Millennium bridge), and it gained a reputation as ‘Galloping Gertie’
in such winds - with people ‘thrill-seekers’ using it from July through November of 1940.
However, the repeated flexing caused loss of strength due to fractures at points of stress
concentration and it eventually collapsed violently but with no loss of life (apart from a
dog).
It is possible to design members using the low stresses determined from horizontal
section of S-N curves. However, this is not necessarily the most economic option. It is
better to assess the number of cycles and use appropriate stress levels on the inclined
section of the graphs. By eliminating stress concentration points, design can be carried
out economically. Where fatigue damage is suspected, then monitoring the structure
can provide prior warning of damage.
Accidental limit states are not normally a design condition for the structure itself. They
are caused by unexpected incidents that would cause the structure itself to be totally
uneconomic.
As an example, we might consider a lorry that hits the suspension wires of a bridge or a
wayward ship hitting the support piers. We do not design the bridge to resist this: we
add Armco barriers or marine fendering to deflect such impacts back into the main flow
and thus protect the bridge with secondary structures.
Another example might be the Kobe elevated roadway (shown above), a 3 km section of
which fell over during the 1995 earthquake. Japan is a seismic region and the viaduct
was designed to resist what was thought a safe level acceleration. However, the shallow
event that hit the city occurred within 20 km (12 miles) of the centre, and at Richter 7.2
was well beyond what had been assessed as reasonable.
Design methods 205
Ultimate
Service
Fatigue
Accidental
Try to concentrate on the end condition, rather than what leads up to it.
Accidental limit states are normally not a design case for the pipeline itself. However,
we need to assess the likelihood of the incident, and to provide protection if required to
reduce the consequences to an acceptable level. For this reason, the cause does become
important.
Ultimate
Pipe bursting or collapsing (thin wall or corrosion)
Service
Insufficient throughput rate (bore too small)
Too low a delivery temperature (poor insulation)
Inability to pig line (bends too tight)
Fatigue
Loss of material strength (flexing at a dent, span VIV
or installation wave motion)
Accidental
Blockage of pig (trawlboard, vessel or
Reduced operating pressure } anchor impact dent)
Although not essential, we have included some of the possible causes to help understand
the issues.
206 Overview of pipeline engineering
Widely used pipeline engineering design codes such as ASME B31.4, B31.8 and BS PD
8010 specify generalised safety factors that were appropriate to technology and standards
of control in the 1950s.
Design was normally undertaken using slide-rules rather than calculators, so simplified
procedures were specified of necessity. It was common to consider only a limited
number of ultimate and service cases. Some codes do not even include the installation
case as one of these.
This design methodology is often termed allowable stress design. These techniques were
based on not taking the material beyond yield, although adaptations were subsequently
made to these codes to include strain-based design, such as required for reel-lay.
We can now rapidly undertake analysis of many cases using spreadsheets or more
advanced analysis methods. We can include the separate uncertainties associated with
the material and the loads, which may differ for each case under consideration.
This means that today, the allowable stress design (ASD) codes are now considered as
excessively conservative in some areas.
Design methods 207
Arbitrary
Not written in stone !
Has resulted in a few failures
The derivation of the 0.72 usage factor for pipe wall hoop stress is shown above.
The inherent level of safety which was chosen is quite arbitrary. However, it resulted in
few failures.
Manufacture Offshore
Better steel Better welding and
compositions and NDT
control Better pressure
Better thickness and measurement and
ovality tolerances control
Better factory welds Better corrosion
Better defect detection control
Better inspection and
repair
Probability
Burst
Operating Pressure
Pressure
Today
Today
1950
1950
Pressure
Bigger safety margin
All aspects of pipeline operations and manufacture will have tolerances. Over the years,
careful measurement of the various aspects have provided us with a better knowledge of
numerical values for these individual tolerances.
By better control of the operational loads and the strength of the pipe (shown in yellow
dashes), the two curves have been pulled apart from each other, so the effective safety
margin has increased.
This gives scope for new design methods to safely reduce the strength of the pipe or
increase the load.
Design methods 209
The new design techniques move away from the potentially arbitrary design criteria of
previous codes.
They are based on the actual failure conditions of the pipeline combined with an
assessment of the consequences of failure.
Separate partial safety factors are set down in the codes (both for materials and loads,
and for each failure condition) in order to achieve these margins.
PRIZE
The need for new design techniques has come from a number of drivers, as indicated
above.
These are principally the need to meet demands of lower cost and tougher technical
requirements, whilst maintaining an adequate (and fully assessed) level of safety.
Examples where new design techniques are being used are shown in the rest of this
module.
We have examined how the pipeline codes were developed in the 1950s. They were
based on not permitting the pipe steel to yield and having a single factor of safety.
Typically, for most codes worldwide, the permitted safe level of stress was 0.72 SMYS.
This new approach to design permits cost savings, or alternatively more throughput
down existing lines. We can now consider higher temperatures or pressures and deeper
water lines.
Design methods 211
Modern codes (such as the suite of structural Eurocodes for steel, concrete, aluminium,
masonry, timber, soils and seismic or the AISC LRFD code) are all written using limit
state principles.
The limit state codes use partial safety factors on loads and materials, rather than the
generalised safety factors used by the traditional design equations.
These are derived by the code writers using the method of risk and reliability. This is
also known as structural reliability analysis in the US.
Each possible failure mode is defined and an assessment is made of the risk of each
occurring.
The partial safety factors appropriate for each class are determined by the writers of the
codes using reliability methods, which define the distributions on the load and strength.
The safety factors are therefore applied rationally to give a specific level of safety.
The following slides give an overview of the risk and reliability methodology.
212 Overview of pipeline engineering
WHAT IS RISK?
Consequence of failure
risk
Medium
risk
Lowest
risk
Low
Low Probability of failure High
Risk is normally defined as the product of probability of an event occurring and the
consequences of that event. A simple Boston square is illustrated, which gives a means
of presenting and comparing levels of risk.
The consequence of failure is often determined in money terms with a price being put
on each life lost.
The probability of an event happening is usually determined by the use of event fault
trees, reliability block diagram or Markov methods, where reliability values and Boolean
logic calculate the likelihood of failure.
A failure that has a high probability of occurring and a high consequence would be
considered high risk.
For most systems, risks in the red and yellow squares must be removed by design. Even
those in the green squares should be removed if the costs of doing so are low.
More detailed systems now exist with more boxes and bands, numerically quantifying the
likelihood levels for each axis. Perhaps these would have six bands – the lowest being
something likely to occur at least once per year, and the highest being an event occurring
less frequently than every 10 000 years.
Knowing the consequence of failure, we can determine the appropriate or target level for
the probability of failure.
Design methods 213
TARGET RELIABILITY
Pipelines are assessed in DNV OS-F101 into one of three safety classes, depending upon
the consequence of failure and period of risk. The associated frequencies or probability
of failure normally considered acceptable to society are derived in order to give uniform
risk.
Note that probability of failure is stated in terms of a number of failures per year for
each pipeline. That should mean longer pipelines need better factors than short ones.
However, this is not reflected in the present codes.
Whereas we have been emphasising up to now just how accurate the code writers are in
the derivation of the load and strength probability distributions, this table seems
somewhat arbitrary. However, it reflects common practice for safety engineers in only
using the numbers 1, 2 or 5 multiplied by a power of ten for their answer.
For pipeline designers, there are only these three safety classes. Other industries (such as
nuclear) use more.
214 Overview of pipeline engineering
The basic reliability assessment method is shown in this flow diagram. Each step of the
process is described in the following slides.
The partial safety factors and their values are adjusted to ensure that the consequence of
failure is less than a target level deemed acceptable to society.
The first activity is to identify all of the things that could go wrong and lead to a failure.
This listing of failure modes on a particular contract is also known as a risk register.
Design methods 215
Examples of some of the possible ultimate failure modes and how they might occur are
itemised above.
MONTE-CARLO PREDICTION
Probability
Probability
Pipe diameter Wall thickness Material strength
Plus others such as ovality, eccentricity and weight
Derive probability for
Characteristic
pipe burst strength
Probability
5%ile
Pressure in pipe derived
in a similar manner Burst strength
By deriving the actual probability distributions for the measured tolerances in pipe
manufacture, it is possible to find the distribution of pipe strength in bursting when
subjected to an internal overpressure.
Typically, a random number generator produces a figure between 0 and 1.000. Using the
total length of ordinate bars on a histogram, the value of the random number can be
read along as a proportion of this, so determining a value for each parameter.
Nowadays, use of computer programmes can determine exact values, independent of the
width of the histogram bars.
Depending on the shape of the individual curves, generated numbers can be applied to
each of the variable distributions, deriving values for the diameter, wall thickness and
material strength for a particular pipe. (Pipe parameter combinations outwith those
given in API 5L or ISO 3183 are rejected.) However, for pipe within tolerances, an
individual burst strength can then be calculated.
A similar process can be applied to derive the distribution of pressure in the pipe along
with the characteristic load.
216 Overview of pipeline engineering
LOAD DISTRIBUTION
For each failure mode we need to consider the load that could lead to that failure. For
that load we need to first identify the load equation and those parameters that contribute
to the load. For example, if the failure mode is burst through over-pressure, the load is
pressure differential across the pipe wall and the parameters that contribute are the
internal contents pressure and the external hydrostatic pressure.
For each load parameter we then quantify the potential variations and distributions for
that parameter.
We then apply a probabilistic technique, such as Monte Carlo simulation, to the load
equation to determine the distribution of load.
Monte Carlo simulation uses random number generators and the probability
distributions of the particular loading condition. After many thousands of runs, the
combined probability graph can be derived for the loads.
Not that the code developers have chosen partial safety factors for the variations and
distribution in loads. The designer only has to assess the loads and combinations, and
apply the factor to them.
Design methods 217
STRENGTH DISTRIBUTION
We take the same approach to determine the distribution of strength. The following
slide shows the combination of the load and strength distributions on a probability
density graph.
Note that the code authors have undertaken this work for us, assessing all the tolerances
and defining the appropriate partial safety factors.
PROBABILITY OF FAILURE
Risk is probability
x consequence
Derive safety factors
R,S
From the Monte Carlo simulations, the code writers calculate the characteristic values
for the strengths and loads.
218 Overview of pipeline engineering
The probability of failure is then the overlap between the two curves.
The risk is then simply the product of the probability and the consequence.
From this, it is possible to derive a set of suitable safety factors to maintain risk at a
suitable level.
COMPARISON OF APPROACHES
True load-
FoS multiplier derives factored load
factor method
Euronorms &
current BSI
limit-state γload γmaterial
Probability
Risk of
Charac- failure Charac-
teristic teristic
5%
load, Gk 95% strength, fk
Stress
We may represent the increasing stress levels first due to the loads and then the yield and
the ultimate strength of the material on a linear graph.
The load factor method simply multiplies the load and checks whether it is less than the
elastic limit of the material. This is generally used when the method of calculating the
load is not rigorous.
In API and older BS codes, a slightly different approach reduced the yield stress by a
factor to obtain a permissible working stress for the material. This was then compared
with the calculated (un-factored) working stress due to load. Failures occur using the
load factor and allowable stress methods, but it is difficult to identify whether the
problem lies with the loads or the strength due to the single combined FoS.
With the modern DNV, BS and Euronorms, the limit state method is used. It is
recognised that the stress due to the load varies over time and may be represented by a
probability curve. Similarly, the strength of the material will vary, though over a
narrower band. By applying one partial safety factor to the characteristic loads, and one
to the characteristic material strength, these probability curves are brought together. The
partial factors on the loads cover a number of combinations. Note the shape of the
probability curves are different for each. The material factor (which is deemed here to
incorporate tolerances on the shape of beam) can be defined as a much sharper curve
than that of the loads. This is due to extensive testing and tighter quality control during
manufacture. Improved testing can result in smaller partial factors, and ultimately a
more economic design.
Design methods 219
The small area of overlap represents where the system would fail. It is normally quoted
in terms of powers of ten per year: e.g. 10-3, 10-4 or 10-5 yr-1. More sensitive or critical
designs attract higher confidence levels, thus necessitating either higher strength material
or thicker wall.
In designing using the limit state method, there is no need to worry about the shape of
the probability curves. The modern codes take care of these by adjusting the factors that
are applied to the characteristic loads (which are defined at the 95% confidence level).
Boston square
Cost and likelihood of failure determine risk
Acceptable target probabilities for pipelines
Risk and reliability
Assessment of probability of failure
Failure at overlap of load and strength distributions
Used to derive partial safety factors
Comparison of approaches
Load factor, allowable stress and limit state
Any questions?
We have introduced the concept of risk being dependent upon the costs and likelihood
of a failure occurring. This can be represented on a Boston square.
The acceptable targets for pipeline failure given in DNV OS-F101 are categorised into
three safety classes.
The procedures for risk and reliability assessment result in probability distributions for
loads on the pipeline and its strength. The area where these overlap is used to assess
likelihood of failure.
Such graphs are used by the code writers to derive appropriate partial safety factors.
Finally, we underlined the three main approaches used by designers showing how older
codes used the yield strength but the limit state codes also use the ultimate strength.
220 Overview of pipeline engineering
DNV OS-F101 embodies the limit state design methods and, in conjunction with
associated supporting documents, covers all aspects of pipeline design. It is generally
more comprehensive than API 1111 but at the cost of a slight increase in calculation
effort.
As previously stated, there are many limit states for a pipeline with several categories of
limit state. We have already covered the categories commonly used.
As an example, we will give a flavour of the document in how it designs for buckling.
Design methods 221
Guideline X
Reeling - Fracture assessment Guideline X upheaval buckling Upheaval
Reeling Laying buckling
JIP Criteria JIP
SUPERB
This diagram illustrates the general structure of the code. The code is supported by a
number of guidelines and recommended practices, many of which are recently developed
or still in the process of development.
DNV OS-F101 makes extensive use of limit state design. The areas are shown above.
As an example of limit state design, we consider one of the local buckle limit state
functions defined by DNV OS-F101.
For this, the criteria uses load-controlled conditions with internal overpressure. That is
the load conditions representative of an operating pipeline on the seabed.
This limit state function considers local buckling due to combined loads. It therefore
combines a number of individual limit state conditions and defines how they interact.
BUCKLE CRITERION
⎛ Sd ⎞
2 ⎛ 2⎞ 2
⎜ Md ⎛ Δp d ⎞ ⎟ ⎛ Δp d ⎞
γ SC ⋅ γ m ⎜ ⎟ + γ SC ⋅ γ m ⎜ ⎜
⋅ 1− ⎜ ⎟ ⎜ ⎟
⎟ ⎟+⎜ ⎟ ≤1
⎝ α c ⋅ pb (t 2 ) ⎠ ⎟ ⎝ α c ⋅ pb (t 2 ) ⎠
⎜ α c ⋅ Sp ⎟ ⎜ α c ⋅ Mp
⎝ ⎠ ⎝ ⎠
The criterion given by equation 5.23 of DNV OS-F101 is based on several ratios and
factors.
The first ratio is the applied axial force to the plastic compression force. The total axial
force is the resultant of the applied tension, submerged pipe weight and end pressure
load.
The second ratio is the total applied moment to the plastic moment. This gives us the
tendency of the moment due to the buckling bend to cause a plastic hinge in the pipe
wall.
The third ratio is the internal over-pressure to the collapse pressure. This gives us the
tendency of the pipeline to maintain its shape whilst pressurised.
There are several partial safety factors included in DNV OS-F101. These are included in
the equation to help improve the accuracy of the buckling prediction for ‘real life’
conditions.
Where:
■ Md = Design bending moment
■ Mp = Plastic moment resistance
■ pb = Burst pressure
■ Sd = Design effective axial force
■ Sp = Characteristic plastic axial force resistance
■ t2 = Nominal wall thickness less the corrosion allowance
■ αc = Flow stress parameter accounting for strain hardening
■ γSC = Safety class resistance factor
■ γm = Material resistance factor
■ Δpd = Design differential overpressure
The authors of the particular code have previously determined the particular safety
factors to be considered as variables to the input. Risk and reliability are used to provide
a logical derivation of the values.
The DNV approach has a number of documents that are fully compatible with limit
state design methods making it a more comprehensive approach than the API 1111 –
although the latter is slightly simpler to use.
Local buckles such as lateral or upheaval buckling are deemed to be load controlled
combined with the bending moment, the axial force and overpressure.
Design methods 225
As oil is found at ever increasing depths below the sea bed, then the technology required
to extract the oil must meet the specific design that this entails.
Although the definition for an HP/HT reservoir is one with pressures over 690 bar and
temperatures over 150°C, the term is more loosely applied when one of the parameters
lies just outside this range.
Deep reservoirs are naturally more highly pressured as a result of the greater depth.
Reservoir pressure is typically relative to the water column above it. Reservoir
temperatures are relative to the earth’s temperature, which is also a function of depth
below the surface.
Flowline design pressure is usually based on the shut-in wellhead pressure, which is
usually significantly greater than the operating (flowing) pressure.
226 Overview of pipeline engineering
HIPPS
Because shut-in wellhead pressures can be much higher than normal operating pressures,
there is wasted pipeline capacity other than in upset conditions. High integrity pressure
protection systems (HIPPS) have been developed to allow pipelines to be designed for
the flowing pressures rather than the shut-in pressures and to provide a high degree of
confidence that the maximum allowable operating pressure (MAOP) of a pipeline will
not be exceeded.
This has the potential to offer significant cost savings to production flowlines from
satellite developments, where there would be a possibility that the pipeline would see
shut-in wellhead pressures (SIWP). For example, if an SSIV (subsea isolation valve) or
ESV (emergency shut-down valve) were activated.
In a HP/HT development project, the cost of the pipeline can be 75% of total budget.
By providing a thinner wall pipeline, cost savings of a third may be made. Any pipeline
over 20 km (12 miles) with pressure rating of bar 350 bar (5ksi) or more may benefit.
The limit on pressure also applies to other equipment at the platform.
The HIPPS system is not 100% reliable and therefore other precautions are typically also
taken, for example:
The Kingfisher project went on line in late 1997, and the system operated with no
problems until a series of transmitter faults were reported by the HIPPS system. These
were successfully resolved by a modified maintenance regime using methanol to clear the
orifices of the input lines to the detectors.
Despite attracting much attention – as the savings in flow-line costs were several million
dollars and the whole project was brought on stream early and under budget – the
solution was not repeated for five years. Once proven, however, many repeat systems
followed in the North Sea, with over 20 systems installed up to the end of 2005.
Design methods 227
HIPPS LAYOUT
Maintenance/test valve
V1 V2
From wells To platform
Initiators P1 P2 P3
Logic solver
HIPPS
Control system
with redundancy
HIPPS STANDARD
Functional safety standard IEC 61508 ‘Safety Standard for Safety Instrumented Systems’
is a performance-based, non-prescriptive method of verifying safety of potentially
hazardous installations.
228 Overview of pipeline engineering
IEC61508 and its companion IEC61511 are the new standards for the life-cycle
management of instrumented protection systems, and will become common-place in
major contracts across all process industries in the near future. The need to specify
quantitative safety targets for overall systems, and for their separate protection sub-
systems, has grown rapidly over the last ten years. This feature has become known as
Functional Safety and numerous standards and guidelines have emerged, most of which
incorporate the idea of safety-integrity levels (SILs).
For the low demand mode of operation, the standard has associated average
probabilities of failure to perform its design function on demand as follows:
An individual valve may only reach SIL3. However, it is possible to achieve a SIL 4 for
the complete HIPPS system by using redundant components. Experience and
confidence with similar emergency shutdown valve systems has been gained on land-
lines, where they have been in use for over 30 years.
HIPPS REQUIREMENTS
HIPPS are designed to operate totally independently of other control systems operating
the pipeline or installation.
The overpressure in the main line is quickly detected and isolated at the source.
Design methods 229
This is done using three or more initiators with a very high accuracy of set-point. This is
typically 1% or better.
The voting logic determines if a situation is safe or unsafe based on the output of the
initiators. The valves automatically operated by the logic system with no input from
operators.
Because long flowlines will not be subjected to the full pressure immediately, it is
possible to use robust but slower actuators and valves to shut off the flow. Such units
are cheaper than fast closure equipment.
The actuators are normally spring-driven and are oversized to ensure closure. Typical
stroking times usually less than 5 s, although this is dependent upon the diameter and
length of the line.
Any questions?
As oil is extracted at ever greater depths, the pressures and temperatures of the well
fluids increase. This then requires the development of pipeline systems that can
accommodate higher pressures and temperatures.
The increases in temperatures can mean significant increases in wall thickness of the
pipelines to ensure pressure containment. HIPPS systems have been developed to limit
the maximum operating pressures within the pipelines at greater depths.
The objective is to enable thinner walled pipe to be installed and so save on the cost of
the pipeline materials.
The main features of the HIPPS initiators and valves have been listed. These need to be
supplied to IEC 61508 in order to ensure that the system functions on demand at the
appropriate SIL level.
230 Overview of pipeline engineering
FISHING INTERACTION
NON-TRENCHED PIPELINES
Trenching for stability reasons is seldom needed except in shallow waters. The main
reason for trenching in the past has been for protection of the pipeline from trawl gear.
Traditionally in the North Sea, all pipelines of less than 406 mm (16in) diameter have
been trenched. Whilst there has never been a legal requirement for this, the UK
Department of Energy issued guidelines in 1984 (based on work carried out by Shell)
which spawned the 16in rule of thumb for trenching of small diameter pipelines.
More recently, limit state design has been applied to the interaction of trawl gear on
pipelines leading to a number of developments not trenching small diameter lines.
Reference: OTH 561 - HSE Offshore Technology Report - Guidelines for the
Trenching Design of Submarine Pipelines, prepared for HSE by Jee, 1999.
Design methods 231
In the US, regulations differ: larger diameter lines and those in shallow water close to
shore must be buried. States have different distances from shore or depths to determine
what pipelines are classified as ‘inshore’.
In the softer sediments of the Gulf of Mexico smaller diameter pipelines will self bury
and there are no large trawlers cutting through the seafloor. However, a risk has been
identified of the small, local shrimp-boat trawls snagging on larger pipelines: an incident
has occurred in shallow water caused by a vessel hitting and rupturing a large diameter
gas-line, resulting in the total loss of boat and crew in the resulting fireball.
TYPES OF TRAWLING
Pelagic trawls
Warp
Large vessels fishing Otterboard
midwater (herring and
Net
mackerel) Bridle
Weights can touch seabed
Weight
Demersal beam trawls
Large steel beams hold net open
Tickler chains force Warp
A number of different types of trawling are used. Some of these can impact with
pipelines or subsea structures.
Pelagic (mid-water) trawling is not normally a problem for the oil and gas industry.
Although these powerful boats are extremely large, operating out of port for many
months at a time, the trawl nets are held open with doors (or otterboards) that are
designed to stay above the height of pipelines and well head manifolds. By adjusting the
speed of the vessel, the net height can be lifted or lowered to intercept shoals of fish.
However, the risk is from the weights used to keep the net down. These inevitably
touch the bottom from time to time and are typically 1.1 tonnes up to as much as 5
tonnes. The vessels operate at 1.9 m/s (3.75 knots) to 2.8 m/s (5.5 knots) for the faster-
swimming mackerel.
Beam trawls are used for whitefish and flatfish (sole plaice or megrim). Two nets are
trawled from warps attached from either side of the vessel. The beams used to hold the
net open can be 9 m to 12 m long and weigh up to 10 tonnes. Towing speeds are
between 2.1 m/s and 3.6 m/s (4 and 7 knots). The fishing grounds may be as deep as
200 m (650ft). Allowance needs to be made for added mass of the water in and around
the beams, the chains and other gear.
Scallops are also dredged using drag rigs, sometimes with a number of small toothed
nets trailing behind a bar. However, the size and weight of these bars is somewhat less
than for beam trawlers.
232 Overview of pipeline engineering
TYPES OF TRAWLING
The commonest method of trawling uses bottom or demersal otterboards. These are of
a slightly different shape to those used for pelagic trawling.
The fish are demersal (bottom dwellers) or benthic (live in the mud), such as cod, flatfish
and nephrops (scampi). They are of higher value at market than pelagic fish, which tend
to come ashore already sold, fully prepared for the supermarket shelves.
Otterboards are used to hold the nets open. The floats on the headline lift the top of
the net and the groundgear (kept somewhat behind the headline and consisting of chain
and circular rubber disks called rockhoppers) ensures that the mouth of the net is kept in
close contact with the seabed. The fish are guided into the net by plumes of mud
disturbed by the heavy otterboards (trawl doors). Smaller fish can escape through square
mesh panels in the net but larger ones collect in the cod-end.
The otterboards are between 5.3 m² and 8 m² (57ft² and 86ft²) and weigh between 1.4
tonnes and 3 tonnes. Again allowance should be made for added mass. The central
clump weights are roller or drag chain type and can be as heavy as 2 tonnes. Towing
speed is between 1.3 m/s and 1.8 m/s (2.5 and 3.5 knots).
It is common for these trawlermen to closely follow pipelines. These are fish attractive
devices (FAD) because of the warmth and protection from currents. Trawl scars can
even be found in the seabed above buried pipelines.
There are other types of fishing used throughout the world (such as purse seine, gill
netting, baited lines, creels and lobster pots) but these have little effect on oil field
developments.
Design methods 233
DESIGN APPROACHES
Overtrawlable
Structure cannot snag trawl equipment
Otterboard, ground equipment and nets ride over
Cannot be damaged by warp wires
Smooth surface - truncated pyramid
No obstructions or gaps
Not too high
Fisher-friendly
Location noted on charts
Structure catches trawl gear but does not hold fast
Trawler reverses and easily recovers gear
Preferred by some fishing associations
There are two approaches made by the offshore oil and gas industry when designing
structures for the seabed.
Pipelines and many well heads, manifolds and valves are normally designed to permit
trawling over them.
A common approach is to make the protection structures from tubular members with
infill panels in a truncated pyramid shape. The side slopes are typically 50° or less and
the height less than about 5 m (16ft). The panels are often hinged or removable to allow
access in the future.
Trawl boards can jam in any gaps left beneath or within the framework. Warps can hold
fast, or be guided by protruding bolt heads or other features and act as a cheese wire,
cutting into the structure. With high structures and steep sides, it is possible for the
rockhopper disks to tighten around the corner diagonals.
A lot of such protection structures, although still being installed as overtrawlable, are
not.
It is perhaps a surprise that some enlightened fishing associations (such as the SFF)
actually prefer structures not to be classified as overtrawlable but ‘fisher-friendly’. This
means that they are labelled as such on charts and fishermen avoid them. However,
should a trawl approach such a structure, the gear will not pass over it. The trawler can
reverse and recover the nets easily. This means that the structure should have no
overhanging snags or hooks that might cause the warps or bridles to be caught fast,
preventing recovery.
234 Overview of pipeline engineering
Jee has carried out research on the interaction of trawl gear and pipelines. The video clip
shows the various types of trawl gear, their motion across the top of the pipeline and the
resultant loadings on it. These are discussed further in the next slide.
Note that the term ‘warp’ refers to the wire leading from trawler down to the trawl door
(or otterboard). For pipeline interaction, we are concerned with sea floor (demersal)
fishing for cod, flatfish and shrimp rather than the mid-depth (pelagic) species.
The picture shows two typical V-type, steel otterboards as used in the North Sea.
There are three main interaction effects due to trawl gear passing over pipelines.
The first is the impact when the gear first comes into contact with the pipeline. This is
similar to a dropped object impact and can result in a dent. The main protective
measure against it is to apply a coating to the pipe.
The second effect is the pullover force as the gear is pulled over the top of the pipeline.
This can drag the pipeline and bend it, in extreme cases resulting in a local buckle. The
remedy for this would be to trench the pipeline to get it out of the way of the trawl gear.
The third effect is hooking of fishing gear on the pipeline. In other words, the gear
passes under the pipeline and becomes entangled to the point where it comes fast. For
small diameter lines, when the fishing vessel pulls hard it will lift the line and release the
gear, so there is no permanent entrapment of the gear. The implication is that the design
of the flowline needs to accommodate accidental lifting of the line by a height sufficient
to release the trawl gear.
For larger diameter lines, 324 mm to 406 mm (12in to 16in) and above the vessel may
not be able to lift the pipeline sufficiently before the warps break and this tends to be
more of a problem for the fishermen than the pipeline.
We have covered the types of trawling that may impact with subsea oil and gas pipelines
and seabed structures.
The two approaches for protection are to make them fully overtrawlable or to ensure
that fishermen will be able to recover gear if they clash.
Previous pipeline design philosophy was to assume that trawl gear interaction could
impart significant impact and bending loads to small diameter pipelines.
In the North Sea, it was usually specified that small diameter pipelines were trenched to
protect them from trawl gear. However, modern limit state design codes applied to
236 Overview of pipeline engineering
recent pipeline designs has meant that some small diameter lines are no longer required
to be trenched to protect them from trawl gear interaction.
Design methods 237
VORTEX-INDUCED VIBRATION
Hydrodynamic loadings
Give rise to bending
Oscillatory loads
Waves and currents
Vortex shedding
Give rise to fatigue
The riser experiences hydrodynamic loadings from the seawater flowing past. The riser
is therefore subjected to bending. Fluctuating loads due to waves and VIV will induce
fatigue damage.
238 Overview of pipeline engineering
As a fluid flows past any bluff body, such as a riser, it will not be able to stay attached to
the body. The flow separates from the body and vortices form behind it. These vortices
are unstable and are shed and drift downstream. This is illustrated above. The coloured
contours show the vorticity in the flow (i.e. areas where fluid is swirling).
Vortices are being shed alternately from either side of the riser. The shedding frequency
for a rigid riser depends only on the riser diameter and the fluid velocity. As the velocity
increases, so does the shedding frequency.
VORTEX-INDUCED VIBRATIONS
(VIV)
Vortex shedding frequency
Locked-in
Cross-flow
2 x Nat.freq.
Non-flexing
riser response
Locked-in
In-line
Nat.freq.
Flexing riser
response
Flow velocity
Design methods 239
The changing flow patterns cause fluctuating drag and lift forces on the riser. These
fluctuating loads cause the riser to oscillate. When the frequency of these forces is close
to the natural frequency of the riser span, the riser resonates and large-amplitude
vibrations occur. This effect is vortex-induced vibration.
The figure above shows how the riser response changes with current velocity. Initially
the vortex shedding frequency increases linearly with the flow velocity. As the frequency
of vortex shedding approaches the natural frequency of the riser span, the amplitude of
oscillations increases. The riser oscillations then start to control the vortex shedding and
the riser oscillations and the vortex shedding lock-in at the natural frequency of the riser
span. At first this will be in the form of in-line vibrations.
As the current velocity increases further, the in-line vibrations die out and are then
replaced by larger-amplitude cross-flow motions at twice the natural frequency of the
riser.
The video shows the results of a test of a pipeline span in a tow tank. The short section
of pipe is sprung at the ends in order to permit movement.
We first see the in-line vibrations from the top of the pipe, then as the velocity increases,
the camera angle moves to the rear and the more violent cross-flow oscillations occur.
240 Overview of pipeline engineering
1.2
0.8
Amplitude a/D
0.6
0.4
In-line Cross-flow
0.2
0.15
0
0 1 2 3 4 5 6 7 8 9 10 11 12
An overview of the response of vibrations is illustrated above. The axes are non-
dimensional amplitude and velocity.
As flow velocity increases, in-line vortex induced vibrations are initiated. The first mode
of in-line oscillations is caused by symmetrical vortices being shed. The second mode is
caused by asymmetrical shedding.
At higher flow velocities, the fluctuating loads due to the asymmetric shedding induce
vibrations in the cross-flow direction. These are of much larger amplitude.
Strake mouldings
banding strapped
to pipeline
Strakes fitted to
CRP installing chimney for wind
strakes on stinger VIV suppression
Design methods 241
The oscillation of the pipe will give rise to fatigue damage. If the analysis of VIV
predicts that fatigue life will be too short, then the solutions are to support the riser
more frequently or to add VIV suppression devices (such as helical strakes) to the span.
Strakes are a familiar sight on the tops of tall factory chimneys. They disrupt the
vortices to give a confused but steady wake, thus removing the excitation force. They do
increase the drag (about double), so the hydrodynamic loadings need to be checked
again. Strakes are also used to suppress vibrations on long risers (where adding a guide
is obviously not an option).
Since we are looking at technology issues in this course, here is a brief word about the
use of CFD (computational fluid dynamics), which in the broadest of terms is like finite
element analysis for fluids.
The above diagram shows a CFD model of flow around a straked riser. This analysis
was done by Jee in order to understand the behaviour of fluid flows around strakes with
different configurations.
This study was the first step towards improving and optimising the strake profile to give
maximum suppression for minimum drag.
242 Overview of pipeline engineering
More supports
Reduce effective span length
Shrouds
Fixed
Fairings
Fixed or rotating Perforated shroud with barnacles
For rigid risers fixed to jacket legs using sleeves, one option is to reduce the effective
length between the supports. Guides will reduce the span length, increase the natural
frequency, lower the reduced velocity (perhaps moving the riser out of the cross-flow
regime) and reduce the bending stresses.
Shrouds or splitters can be used. A range of designs is shown above. They work in
slightly different ways.
Shrouds have the advantage in that they are omni-directional. They are effective from
whichever way the current comes. They disrupt the flow around the riser and break up
the vortices.
Where there is a dominant direction of current flow, fixed vanes or fairings can be used.
If the current direction is not constant, then these units need to be allowed to swivel
around the pipe. Streamlined fairings work by allowing the flow to remain attached so
that vortices are not formed in the first place. They have the advantage in that the forces
acting on the pipe can be greatly reduced. Splitter plates do not stop vortices forming,
but they separate the flow passing on each side of the riser and prevent the vortices from
interacting. This stabilises the flow and stops the vortices from being shed.
The photograph shows a square perforated shroud on a riser. However, it also shows
that the grill openings are ideal niches for marine growth, which may block and nullify
the protection.
Design methods 243
VORTEX-INDUCED VIBRATION -
SUMMARY
Loads on risers
Hydrodynamic forces
Oscillatory loads
VIV and fatigue
Strakes and shrouds
Any questions?
The main design aspects included bending forces due to structural considerations but
also wave and current loads.
Any questions?
Proper evaluation of fishing effort and activity enables unburied pipelines to operate at
appropriate levels of risk.
Reduction in VIV means extending the fatigue life of risers and spanning pipelines.
Common work
Common work 247
EXPECTATION
EXPECTATION
Construction survey
Route preparation
Welding
Non-destructive testing (NDT)
We are required to survey the pipeline route before and after pipelaying. This module
provides the common types and equipment used for surveys. The preconstruction
survey ensures that the route is clear. Here, we examine the particulars for this route
survey.
Where the seabed is not suitable, some activity may be necessary to clear or improve the
route.
At present most pipelines are welded. The main methods of welding are covered along
with the non-destructive testing needed at each and every weld.
248 Overview of pipeline engineering
CONSTRUCTION SURVEY
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
TYPICAL PROJECT
Seismic exploration
Exploration drilling
Deep seismic Feasibility
and metocean Conceptual design
Front end engineering design
As we saw earlier, a number of surveys are carried out during the construction period.
Here, we will particularly look at the pre-lay, touchdown during lay, post-lay, post-
trench, post-burial and as-built surveys.
Common work 249
PRE-CONSTRUCTION SURVEY
OPERATIONS
It is often the case that minor additions to the survey route will be required.
Occasionally, discrepancies in the original work need to be resurveyed to prove the route
remains clear of shipwrecks and debris. This work is usually undertaken using towed
fish, vessel-mounted sonar or remotely operated towed vehicles (ROTVs). Sometimes,
additional survey work is needed to cover the full width between the anchors: the final
anchor pattern is determined by the particular vessel and the client may not have
covered sufficient distance from the pipeline centreline. Autonomous underwater
vehicles (AUVs) can be used to undertake longitudinal and transverse lines efficiently.
Where there are mobile sandwaves, the area needs to be resurveyed to estimate the
volume to remove. Other areas that require improvement are often resurveyed in more
detail by the rock-dump or blasting sub-contractors. In addition to the towed fish,
remotely operated vehicles (ROVs) are ideal for detailed surveys of smaller areas. Where
improvements have been made immediately before laying, the new condition of the
seabed is resurveyed to confirm its condition.
It is useful to resurvey the tie-ins in more detail. This may be to confirm the orientation
of the wellhead and double check the length of the spools to be used. For these tasks,
we can use ROVs, or even divers in shallower waters.
At present, we do not re-test the soils along the pipe route – whereas for cable
installation, this is now becoming standard practice.
250 Overview of pipeline engineering
It is important that the line be maintained within the construction corridor. This is
generally set at 10 m (30ft) wide although at the ends of the pipeline and critical points
such as crossings and horizontal bends it may be less.
Following laying, surveys determine where spans need rectification. If the pipeline is to
be trenched, then the depth and shape of trench is measured. Where burial or rock-
dump is required, then the cover is checked to prevent upheaval buckling. Normally, a
combination of ROV and ROTV surveys provide assurance to the client that the
pipeline has been installed in accordance with specification.
Common work 251
CONSTRUCTION SURVEYS -
SUMMARY
Pre-construction
Route resurvey and preparatory work
Touchdown position
Avoid buckling of pipeline
Post-construction
Assure client that pipeline installed to specification
Any questions?
Pre-construction surveys are undertaken to assure the contractor that the design survey
has identified all obstructions and where preliminary work is needed.
Surveys are carried out at all stages of construction to provide assurance both to the
contractor and the client that the pipeline is being installed according to the
specification. That is, it has not been overstressed and it is within the corridor permitted
with no unexpected spans, and for trenched pipelines it is at the correct depth.
252 Overview of pipeline engineering
ROUTE PREPARATION
START-UP ANCHORS
A target box for the end of the pipeline will have been defined in the coordinate system.
The coordinates are often defined as Eastings and Northings with reference to the
universal transverse Mercator (UTM) for a particular geoid such as ED50 – the
European datum defined in 1950.
The fixed point is often a long distance from the target box. For high tension
installation methods, such as S lay, it can be 5 to 8 times the water depth beyond the end
of the startup point. Often, such anchor legs are referred to as having a ‘scope’ of 5 to 8.
The holding power of a number of standard anchors can be utilised. Each is individually
positioned and tensioned against the vessel’s own anchors or a temporary anchor laid
specifically for the purpose at the bow. The groundleg chains are joined with rings and
brought together to connect to the abandonment and recovery wire of the lay vessel.
Though four anchors are shown here, with very high tensions 8, 12 or 16 high holding
capacity anchors may be required.
The clump anchor is the simplest method but it limited to shallow water and low
tensions. A dead weight of concrete and steel is placed on the seabed – it relies on
simple friction so the submerged weight needs to be three or four times the holdback
tension. It is most suited to sandy bottoms with higher friction coefficients than mud or
clay soils.
The wire is attached to the installation head on the end of the pipeline. Its length is
carefully adjusted to ensure the pipeline touches down within the box.
It is rare that a pipeline can be initiated using the existing structure of the platform. This
is because of the distance required and alignment. Also, the forces mean that the jacket
structure would need to have been designed with this use in mind.
ROUTE PREPARATION
Debris removal involves shifting objects which may have been dropped or dragged onto
the route since the route survey. These will normally only be moved if they present an
obstruction (or in the case of unexploded munitions, a danger) to pipelay and cannot
easily be avoided. If the pipeline is to be trenched, disused cables, anchor chains and
wires will be cleared or cut so as to avoid tangles with the trenching equipment.
On the approaches to the Norwegian coast, there have been instances where large piles
of rockdump have been placed to support a pipeline across submerged valleys which
would otherwise have led to unacceptably long spans.
Startup and laydown locations sometimes need a layer of concrete mattresses to keep the
pipeline ends clear of soft soil, with the flooding valves accessible to ROV or divers.
Also, there are cases where a separate anchor or pile may be installed for the laybarge to
pull against, though this operation is usually done by the laybarge itself.
The sketch at the bottom of the picture shows a typical crossing construction, where
concrete mattresses have been placed either side of an existing pipeline. This allows the
new pipeline to be laid across, and then rock-dumped for stability and making the system
overtrawlable.
254 Overview of pipeline engineering
PRE-SWEEP SANDWAVES
Pre-sweeping to clear (or reduce) sandwaves is normally carried out by trailing suction
hopper dredgers, such as that shown schematically above and in the picture below. A
pipe with a suitable head is trailed at the required depth and the spoil sucked up into the
hold of the ship. Excess water is skimmed off.
The pre-sweeping is undertaken only a few days prior to the pipe-laying operation to
reduce the risk of the area being naturally backfilled prematurely.
The maximum operating depth for such a vessel is in the region of 120 m (400ft).
However, sandwaves typically occur where the water depth is less than this, and there is
a mobile sandy seabed with high currents.
Common work 255
Typically the sand and water mix is sucked up and discharged into the hold. The water
and fines drain off and discharge directly to sea through the overflow. A plume of fines
is inevitably discharged into the sea.
It may take 2 hours to fill the hold before the vessel sails to the discharge site.
So it can be seen that most of the loss of fines in a plume is during the loading operation
rather than the discharge.
256 Overview of pipeline engineering
SAKHALIN - VIDEO
Glory Hole
SALM Buoy
Rock Pad
Pipeline
The Russian Sakhalin development – just north of Japan – has to contend with frozen
seas in winter. The SALM buoy is stored in a glory hole during these months.
The film shows the excavation and levelling of the glory hole using a trailing suction
dredger. Additional seabed preparation was carried out for the pipeline and to provide
scour protection for the platform.
Because the pipeline was only two kilometres (a mile and a quarter) long and the site is in
a new area of development, a crane barge was adapted with the addition of a stinger to
become the laybarge.
Any questions?
Common work 257
This means that any debris between the outer laybarge anchors may have to be removed.
Hollows or soft material along the route may need to be filled to provide a sound
foundation for the pipe itself.
At startup and laydown, there may be clearance requirements or deadman anchors may
need to be installed.
Where the route crosses existing pipelines, protection must be given to prevent damage.
If the route cannot avoid sandwaves then these are removed just days before the laying.
This avoids the waves reforming due to current movement.
258 Overview of pipeline engineering
WELDING
WELDING
There are three welding techniques that are commonly used on laybarges to join the
individual pipes together on the firing line.
We are not including in these the SAW method that we saw used for pipe manufacture
and which is sometimes used to join two 12 m (40ft) sections into a ‘double header’ or
‘double joint’. This necessitates rotating the pipes in a separate bay.
For all three techniques, we are going to examine the preparation of the pipe ends, the
shape of which is determined by the welding method and whether it is manual or
automated. The former produces V shaped welds, the latter produces the more efficient
(narrower) U shape. The standard bevel end to a pipe is for V slots: the alternative J
preparation is for U slots.
We will touch on the need to prepare full welding specifications and look at the methods
and types of defects which need rectification.
Common work 259
WHAT IS WELDING?
Field-welding is the most expensive factor in construction and is the most common
method of joining pipe sections for oil and gas pipeline construction.
The weld deposits should have a tensile strength at least equal to the parent metal, and
with a compatible chemical composition.
Most welding methods used for pipelines use a filler material (electrode) and an electric
arc between the electrode and the pipe to melt the metal.
Test coupons are used to prove the other properties of the proposed welding method.
These relate to the brittleness and toughness of the surrounding pipe steel as well as the
weld.
Air needs to be excluded from the weld deposit. This is done by the use of a gas as a
shield. Some methods also use a flux, which forms a layer of slag over the solidified
weld material.
260 Overview of pipeline engineering
WELDING
A number of techniques are used for field jointing of pipelines, the most common being
shielded metal arc, gas-tungsten arc and gas-metal arc welding. Their common names
are stick, TIG and MIG respectively.
The latter two of these lend themselves to semi-automatic and fully automatic processes.
The shielded metal arc is solely a manual method, during which the welder fully controls
the position of the electrode and the speed of the formation of the weld. This ‘stick’
technique is very common where there is a skilled workforce readily available. This
includes the USA. Repairs of defects in automated welding are often undertaken by
trained welders using SMAW.
By semi-automatic, we mean that there is some input from the welder. He needs to
adjust the lateral position of the ‘bug’ to ensure that the weld follows the correct track.
This is a very common method in Europe.
Fully automatic welding employs a laser device so that the bug can be guided
automatically. The welder is only required to fit the track and start the operation. This
is yet to gain common acceptance in the offshore pipeline industry for field-welds but is
often used for factory operations - such as the SAW method for pipe manufacture.
Common work 261
Flux coating
Slag layer
(to be removed)
Core wire
Weld metal
Parent metal or previous weld pass
Shielded metal arc welding is also known as stick welding or manual metal arc (MMA).
Heat is provided by an electric arc that melts a consumable electrode and also some of
the parent metal. When it cools, it hardens to form one pass of the weld.
The consumable electrode serves as one pole of the arc, the pipe steel being welded as
the other pole. Electrode, steel pipe and arc make up an electric circuit back to the
power source, which may be either DC or AC. A covered electrode has a solid metal
core and an outer layer of material that insulates the core from accidental contact with
the pipe wall. The core covering also provides gas to shield the weld from air and it
may also contain special elements to improve weld quality.
Manual methods using stick electrodes are limited in the amount of weld metal that can
be deposited in a single operation. This is due to the volume of metal contained within
the electrode. Before a new electrode is started, the weld metal needs to be exposed by
removal of the slag layer.
SMAW is mainly used on steels, including carbon steels, stainless steels and nickel alloys,
and can be applied over a wide range of thicknesses. Materials require cleaning
following welding, but because of the flux/slag, some minor contamination is
acceptable.
262 Overview of pipeline engineering
SMAW CROSS-SECTION
Cap pass
Filler passes
Hot pass
Root pass
The first two welds - the root and hot passes - may be completed by the line-up team,
with the bulk of the welding finished by follow-up welders. The thinner capping layer
aims for a smooth finish to eliminate stress concentration build-up. The root pass is
critical - it can “burn through” the wall and melt away the metal, dropping it into the
pipe. A removable copper ring is sometimes attached to the line-up clamp in order to
prevent this.
The aim is to deposit a similar amount of weld material on each pass. It is not desirable
to place too much in a single pass because of stresses that build up on cooling. Cracking
of the adjacent parent metal may then occur.
The root pass can be made from inside the pipe and subsequent passes from the outside
(though normally, all would be made from the outside). Slag needs removing before the
next weld pass or coating repair. Thin-walled pipe may only require one filler pass.
Limitations of this method are that it is not an easily controlled process, and can
therefore result in shape defects, slag inclusions, Hydrogen Induced Corrosion Cracking
(HICC) and arc strikes. The direction of welding (whether it is from above, or vertical
or even from beneath) must be taken into account. Access for the welder and the length
of the rod must also be considered, especially when working underneath the pipe (in the
overhead position).
Common work 263
SMAW METHODOLOGY
Consumable stick
electrode with covering
(usually cellulose)
Weld shielding by CO2
released from electrode
coating
Welder positions electrode and
compensates for electrode consumption
Welder has to stop when electrode fully
consumed
Filler wire
Weld metal
An inert gas shield is required when welding with tungsten electrodes using the gas-
tungsten arc welding (GTAW) process.
This process is particularly suited to welding thin material and to depositing the first
weld bead (root pass) because penetration can be controlled more easily than with other
welding processes. Good heat control is possible with this process and it is possible to
weld with or without filler metal.
264 Overview of pipeline engineering
The non-consumable electrodes are not deposited as part of the metal weld. The steel
being welded is melted, and the electrode serves only as one pole of the electrical circuit.
Usually with pipeline welding, however, a filler wire is fed into the weld joint, providing
additional material. The filler wire is supplied from the reel feed.
GTAW METHODOLOGY
GTAW can be used on all weldable materials including steels, stainless steel, nickels,
aluminium, magnesium, copper and reactive metals such as titanium. It can weld up to
around 6 mm (0.25in) joint thickness if done manually.
Automated GTAW methods can weld thicker sections. The materials must be very
clean both chemically and mechanically as there is no flux/slag as in SMA.
Reel feed
Gas
nozzle
Gas shield
Arc
Consumable
electrode
(filler wire)
Weld metal
This is similar to GTAW but the electrode is now consumed from the reel. It also
provides filler material for the weld.
This is the method used by the CRC-Evans automatic welding machine - a popular and
well-proven method dating from 1980s.
GMAW METHODOLOGY
Gas metal arc welding also uses heat from an electric arc. The arc is covered by an inert
gas, such as argon or helium. The inert gas shielded metal arc process uses a
consumable, continuous electrode. Since this process requires no flux, no slag is
produced on top of the weld. Gas for shielding is delivered to the weld area through a
266 Overview of pipeline engineering
It can weld similar metals to GTAW and weld joint thicknesses from thin to very thick
sections. Pre-cleaning of the parent materials is required as there is no flux/slag.
When compared with GTAW, it has been described as being fast and furious. Some
weld specifications require the root and hot pass to be undertaken in GTAW, with the
filler and capping passes in GMAW. However, other specifications reverse this; it
should be noted that either method can be used for the whole weld.
The newer process of surface tension transfer (STT) overcomes the lack of control with
conventional MIG, and yet provides rapid controlled welding with minimal weld spatter.
This is commonly used for oil and gas pipeline installation though comparatively
unknown in other industries. The voltage and current are continuously monitored and
adjusted throughout the welding operation: it detects when a ball of molten metal is
discharged from the end of the wire electrode altering the potential and throughput
accordingly.
Site welding
Welding procedures
Repair procedures
Welder tests
Weld tests
Non-destructive tests (NDT)
Destructive tests (sample coupon)
Tensile strength
Hardness
Toughness
Before any welding takes place on site, a full set of welding procedures are drawn up and
agreed. These will cover all standard welds to be used on the contract, agreement on
what defects can be allowed, what must be repaired, the method of repair for different
defects, and what will require a cut-out.
Welders will be tested to prove their individual competency on these procedures. These
welds will then be tested to prove the procedures are correct. Normally, non-destructive
testing is first carried out over the whole weld to identify defects, and then sections of
Common work 267
each test weld will be cut out to ensure that the tensile strength is greater than that of the
pipe wall, and that no problems exist with the weld hardness or toughness which might
give rise to brittle fracture.
JOINT PREPARATION
(0.312in)
7.9 mm
using line-up tool/clamp 1.0 mm 1.5 mm 1.6 mm
(0.060in)1.6 mm (1/16in)
(0.040in)
12.7 mm
(0.5in)
welding using GTAW or
GMAW
Applicable codes
(0.867in)
22.2 mm
UK - BS 4515, BS EN 288-9
USA - API 1104
Line pipe is usually manufactured and delivered with ends prepared at a standard 30°
bevel. To increase productivity with semi-automatic welding, this is modified to a J
shape resulting in a U shaped weld and reduced weld filler material. It is possible to
reduce the number of individual passes, saving both time and material.
The end of the pipe joint is prepared using a pipe facing machine which cuts a bevelled
edge. This operation normally takes between 2 and 5 minutes, depending on the pipe
wall thickness and skill of the operator.
The two bevelled pipe ends are then aligned using a line-up clamp. The root pass and
hot pass are made and the line-up clamp is removed. The filler passes are then made
using one or two automatic welding units.
268 Overview of pipeline engineering
JOINT PREPARATION
Proper joint preparation is the first step in preventing weld defects. The ends of the
pipes must be clean and, if bevelled, must have the proper angle and thickness of bevel.
The gap between the ends of the pipe, if specified, must be prescribed for the pipe size
and welding methods used, and two joints must be properly aligned before welding
begins. Other factors affecting weld quality include proper welding current and proper
electrode angle.
Line-up clamps should be internal to provide concentricity of pipe bore and must not
cause scoring or otherwise damage the pipe surfaces. Each joint of pipe should be
swabbed with a leather or canvas belt disc of the proper diameter or cleaned to remove
dirt, grease, loose mill scale, or other substances before line-up. Pipes should be kept
free of dirt when work is not in progress. Open ends of pipe should be closed with an
approved cap or plug, securely fixed to prevent unauthorised removal.
Before welding, joints should be cleaned free of all paint, grease, oxide, rust and other
contaminants. Cleaning should extend for at least 30 mm (1.2in) from the joint on both
internal and external faces. Burrs, score marks, indentations or other small
imperfections may require smoothing out by filling or grinding. If these are serious, then
the pipe end may require cutting back and the joint re-preparing. If moisture is present
then the pipe may require drying, so that joints are completely dry. Welding is then
weather dependant.
Common work 269
Semi-automatic
Fine positioning of electrode
controlled by welder
GTAW or GMAW
Automatic
Electrode controlled automatically
SAW, GTAW or GMAW Courtesy of CRC-Evans
Cap pass
Filler passes
Hot pass
Root pass
The manual method SMAW uses a fixed stick electrode that is consumed as the weld is
made. The welder controls the position of the electrode and arc, and compensates for
the consumption of the electrode end. Once the electrode is fully consumed, the welder
has to stop and replace the electrode. He then chips away to remove the slag in order to
restart the next welding rod on clean metal.
Manual welders often have to work in unpleasant conditions: the weld may need
protection to prevent the wind blowing in dirt and grit, moisture and cold - all of which
can have an important effect on weld quality. To some extent, semi and fully automated
welding techniques remove some of the restrictions. Use of continuous wire eliminates
the restrictions on the maximum volume of metal contained in stick electrodes, so fewer
passes are needed. Semi-automatic methods use a consumable wire electrode or filler
that is fed automatically to the welding head. The welder still manually controls the
position of the electrode and arc, but does not have to stop to replace consumed
electrodes.
Among the advantages of automated welding machines are an increased weld deposition
rate, reduced volume of weld metal, improved consistency of weld strength, toughness
and NDT quality, reduced vulnerability of weld quality to human error, reduced physical
strain on welder/operator, ease of training operations, reduced manpower and
equipment requirements for heavy wall and large diameter pipe.
270 Overview of pipeline engineering
SEMI-AUTOMATED WELDING
Prior to welding, the pipe is usually pre-heated using propane burners or induction units.
The induction type uses rapidly alternating electrical fields to induce eddy currents in the
pipe wall, which gives a uniform heat throughout the wall of the pipe. The pre-heating
causes the evaporation of any moisture near the weld site and allows a slower cool-down
rate after the welding. This reduces the problems associated with rapid cooling,
particularly hydrogen embrittlement.
Specialist line up clamps can be used to complete an internal bead run, which allows
greater tolerances on the joint fitting operations. Alternatively the bead (or root pass)
can be undertaken from the outside with just a simple clamp used to keep the two ends
together and aligned.
An external steel band is used as a rail to run the ‘bug’ or welding machine. The
operator needs to watch the bug ride along the band and make corrections using a
horizontal adjustment knob in order to correctly align the welding machine with the
centreline of the joint. The torch oscillates from side to side of the weld to ensure filling
of the gap.
The welds are made on one side of the pipeline from the top (12 o’clock position) down
to the bottom of the pipe (6 o’clock location). The weld on the other side of the pipe is
then completed, again in the downward direction. Immediately after the internal or
external root bead, the hot pass is completed. Then a number of fill passes are carried
out (dependent upon the thickness of pipe). Finally a cap weld is added in the same
manner. Typically, on large diameter lines, the whole operation from clamping to
completion of the root bead is a matter of a few minutes, with rates of 1 - 1½ m/min (3
to 5ft/min) for the filler runs. Multiple stations are used on laybarges to increase
productivity.
Common work 271
Useful specifications
BS 2633 Class 1 arc welding of pipework
BS 2971 Class 2 arc welding of pipework
BS 4677 arc welding of stainless steel pipework
BS 4515 welding of onshore steel pipelines
BS EN 288-9 welding procedures
ASME B 31.3 process piping
API Std 1104 welding of pipelines
Company procedures or national standards
Local conditions - low ambient temperatures
The above provides a list of common standards used worldwide for welding and NDT.
There may also be company or national standards specified for a particular contract,
which take into account the particular conditions - perhaps the local steel quality or
particularly low ambient temperatures.
WELDING - SUMMARY
Any questions?
Prior to welding, we need to prepare the joints to maximise weld integrity. Various
automated methods of welding are used in pipeline construction to increase efficiency.
Common work 273
Imperfections caused by
Poor welding technique
High residual stresses in component
Steels susceptible to
Porosity Axial crack
Transverse crack
Cracking
Solidification
Hydrogen
Reheat
Weld repair Slag inclusions Root crack
Lamination
in parent plate
initiates crack in weld
or lack of fusion
Full details and records should be kept on all welds and welders. Then if faults occur,
problems with a particular welder or his equipment can be identified. Strict controls on
weld quality means that testing must be done to ensure weld integrity. Comprehensive
inspection of all completed welds is also required. Weld defects must be identified and
prevented in future.
Cracking is related to the parent material composition, thickness, heat input, stresses and
the presence of hydrogen
If a weld does contain imperfections (other than cracks) they may be repaired, but a
repair should only be attempted once at each weld. All imperfections should be
removed by grinding to clean sound metal. Should laminations, split ends or
longitudinal seam defects be discovered in pipe, the whole joint should be removed from
the line.
274 Overview of pipeline engineering
NDT METHODS
Radiographic inspection
Ultrasonic inspection
Although useful, DPI and MPI are not the prime means of ensuring that pipeline butt
welds are free from defects. For this, we use radiography and ultrasonics.
RADIOGRAPHY
PD 8010 requires 100% radiographic inspection for all welds in areas where leakage is a
hazard (e.g. offshore, road, rail, and watercourse crossings) or where repair is difficult.
API 1111 requires at least 90% (and preferably 100%) of welds be inspected by
radiography, UT or another form of NDT.
276 Overview of pipeline engineering
ULTRASONIC TESTING
Until recently, pipeline weld inspection has been traditionally solely the domain of
radiography. With the advent of mechanised GMAW, ultrasonics as a method of
nondestructive examination has proven to be an effective option to detect non-fusion
defects orientated unfavourably for radiography. The mechanised UT of pipeline girth
welds is now readily available. However, the codes require the presence of a skilled
operator, able to undertake a manual review in order to confirm and verify the results of
the automatic UT.
With ultrasonic inspection, high frequency sound waves are introduced to material,
interfaces between materials of differing acoustic properties reflect or transmit sound,
the reflected sound is displayed on a monitor. Both manual and automatic techniques
are used - sometimes in conjunction with each other or with radiography. Although UT
can be used near the welders, the pipe does need to cool down before the couplant is
applied.
With mechanised UT inspection, the array of probes is moved around the girth weld by
a motorised carrier, which travels along the same track the welding apparatus uses.
Signals received by the ultrasonic instruments are monitored by electronic gates and both
amplitude of signal and its time of arrival can be collected. In evaluating the scan results,
the operator makes a decision as to weld acceptability based on the length of the signal
exceeding a threshold. Acceptability criteria for ultrasonic NDT is currently being
prepared.
NON-DESTRUCTIVE TESTING -
SUMMARY
Any questions?
After welding, the integrity of the weld needs to be confirmed, and several methods of
weld testing have been discussed along with the defects that they can find.
The two main methods are radiography and the more modern method of ultrasonics
which provides a 3D visualisation of the defects – giving confidence with smaller flaws.
278 Overview of pipeline engineering
The seabed generally requires some preparation prior to lay and a fixed point is needed
for initiation of the pipe lay.
The welding methods used for pipelay are covered. It is important to assure that every
weld is acceptable prior to laying because the pipeline experiences high stresses at
touchdown and repairs after laying are costly. Also, a flaw in the weld may result in
accelerated localised corrosion affecting the operating life of the pipeline.
Installation methods
Installation methods 281
EXPECTATION
EXPECTATION
By far the commonest method is S-lay. This can be used for all water depths and for
flowlines and export lines.
In deeper water, the slightly slower J-lay method is employed. This requires DP to
maintain station. There is less pipeline stress near touchdown.
With reel-lay, bundles and towed methods, the pipelines are assembled on land and
either loaded onto a reel or towed to the field. Lay rates are more rapid, but the
methods are limited to the smaller diameters (or lengths) used for flowlines. With reel-
lay the pipeline is yielded as it is loaded onto the reel and again when it is straightened.
However, once it leaves the barge, it is installed in a similar manner to that of the J-lay
with minimum stress at touchdown.
Flexible pipelines and umbilical cables are installed in a similar manner. However, the
stresses are kept lower still because of the relatively non-robust nature of these items.
282 Overview of pipeline engineering
S-LAY
WHAT IS S-LAY ?
Overbend Area
Sagbend Area
Tension
S-lay takes its name from the suspended shape of the pipe at the end of the barge, which
lays in a gentle ‘S’ from the stinger to the seabed. The crucial feature of this method is
that the pipe must be held under high tension to hold its shape.
Installation methods 283
This takes 12 m (40ft) lengths of pipe, which can be seen stacked on its deck. It places
these in a firing line, running down the centre of the vessel, and welds them up. The
pipe then runs out of the stern of the vessel down the stinger and into the water.
As the pipe is welded up, so the vessel is winched forward on an anchor system. It has
12 anchors, and 2 anchor tugs to position them, though only one anchor is moved at a
time.
The above picture shows the Lorelay in front of a platform. The stinger at the back of
the boat is lifted, showing that it is not yet in pipelay mode.
As with the previous barge, it assembles 12 m (40ft) joints into a welded pipeline and S-
lays them onto the seabed.
The main difference is that it is a ship-shaped vessel rather than a barge, and applies the
necessary tension through dynamic positioning thrusters. The thrusters make it easier to
manoeuvre close to platforms than for anchored laybarges, which have to carefully
position their anchor cables to avoid clashes with the jacket legs during barge movement.
SOLITAIRE
A further S-lay barge is the Solitaire, which is three times larger than the Lorelay and is
aimed at large diameter trunk lines. Welding and coating repair operations are divided
equally between seven workstations. The length of the vessel means that it is able to use
double-jointed pipes, so speeding up the lay rate.
On the Magnus EOR 610 mm (20in) line, it achieved an average lay rate of 8 km/day (5
mile/day) and a peak of 9.3 km/day (5.8 mile/day).
Installation methods 285
The pipe was laid by two semi-submersible laybarges, the Castoro Sei and the Semac-1
with a fleet of support vessels including pipe carriers, supply vessels, anchor handling
tugs, guard vessels and survey vessels.
The continuous (24 hour) pipelay process is fully explained, including line-pipe leaving
the pipe coating facility, double joint length production, passage through the firing line
and barge movement.
INSTALLATION ENGINEERING
The purpose of installation engineering is to work out how a particular vessel will install
a pipeline.
It is the domain of the vessel owners and has two key activities. The first is determining
the firing-line sequence to spread the time needed to make the weld evenly amongst the
welding stations. The second activity is to set the pipeline curve. This is addressed in
the next slide.
Normally, pipelines which run from land will be laid from beach to platform. Interfield
lines can be laid in either direction. The initial holdback wire tension anchoring may be
the decisive factor.
Anchor
Tension cables
The installation contractor will check the stresses in the lay curve, and from this will
determine the optimum stinger settings (these cannot easily be adjusted once pipelay has
commenced) and the tension to apply for a given water depth.
Inshore, the detailed anchor pattern locations will be worked out in order to avoid any
obstacles and yet provide the necessary tension at the sag bend. This needs knowledge
of the soil conditions on either side of the laying centreline.
Installation methods 287
Adjust
Stinger roller settings (radius of curvature)
Stinger angle
Find
Tension for
given water
depths
Operating
conditions
Hold station
A&R
The installation vessel controls the stresses in the pipeline by setting of the stinger angle
and roller positions, and by controlling the tension.
At each water depth, the necessary tension to maintain the pipeline within safe stresses is
determined.
Each barge will have a maximum sea state for laying operations and holding station.
There will also be more severe weather conditions when the pipeline needs to be
abandoned - and the improved seas in which it can be recovered (A&R procedures).
TENSIONERS
288 Overview of pipeline engineering
The above pictures show tensioner sets. These are pairs of caterpillar tracks that are
hydraulically brought together to grip the pipe and apply a back tension.
Dead band for pipe tensioners is between +25% and -10% of set level, so normally the
pipeline is still. If it moves, then the welding kit moves with it.
The firing line can be viewed as the factory assembly line for the pipeline. It runs down
the centre of the barge. The figure above shows the firing line for the Lorelay. In this,
new pipes are aligned and root-welded forward in the vessel (near the bow) and then
passed from right to left through the welding stations, having a filler welds and a cap
weld added.
As weld is added, the pipe passes through multiple sets of tensioners to the non-
destructive testing stations, where a radiograph is taken of the weld. From there, it
passes to the back of the ship where a field joint coating is applied, after which the pipe
passes down the stinger and into the water.
The key to the firing line is to make sure that the time taken to complete the entire
process is divided evenly amongst the stations. For example, if it takes 45 minutes to
complete the operation from alignment through to field joint coating and there are 9
stations, then the objective would be to spend 5 minutes at each station. If it were
necessary to spend, for example, 10 minutes at one station (and 4½ minutes at the
others), then this would slow the vessel speed to half and so would double the cost of
construction.
Installation methods 289
Solitaire:
8 km/day (5 mile/day) for single pipe
Depth limit about 2500 m (8200ft)
due to 400 tonne (kip) tensioner capacity
The above slide contains some ball-park information on pipelay speeds, limitations and
vessel costs. However, it should be noted that these vary considerably from vessel to
vessel.
The pipelay market is an opportunity rather than a commodity market. The prices do
not necessarily reflect the cost of building and running the vessels. Instead, they climb
in busy years and drop in quiet years.
Two points of comparison. Firstly, due to its length and number of welding stations, the
Solitaire goes twice as quickly. Its DP system avoids the 500 m (1640ft) depth limitation
of anchor mooring, meaning that its limit is due to tensioner capacity.
Secondly, pipe-in-pipe systems take about twice as long to lay because they require about
twice as much welding. Typical figures are a maximum of 2 km (6600ft) per day, average
1.6 km (5250ft) per day.
An interesting point to note regarding the anchoring depth limitation and the type of
opportunity market, is that an anchored laybarge is being used for a large contract in
1100 m (3600ft) of water because of the lack of availability of other vessels in the
contractor’s fleet. The slower operations due to anchor movement did not increase
costs prohibitively.
290 Overview of pipeline engineering
S-LAY - SUMMARY
Any questions?
The S-lay method derives its name from the shape of the lay curve. The ‘S’ shape arises
from having a horizontal assembly or ‘firing’ line on the vessel deck. The pipe is then
laid under tension down to the seabed.
The high forces required to keep the pipeline under tension means that the installation
vessels need to be substantial in size with strong anchors or Dynamic Positioning (DP)
thrusters to react the required tension.
S-lay vessels usually utilise around four weld stations, and the lay-rate can be optimised
by the correct distribution of weld passes as the pipe joints travel along the firing line
through the weld stations.
Installation methods 291
J-LAY
WHAT IS J-LAY?
J-lay takes its name from the shape of the suspended pipe, which forms a ‘J’ going from
the surface of the vessel to the seabed. This curve is similar to a catenary and develops
lower stress levels in the pipe than S-lay.
Its main limitation is that it has a single work station in which to assemble the pipe.
Consequently, most J-Lay systems make use of pre-assembled strings of 4 to 6 pipes.
The additional time spent making a joint at a single work station is compensated for by
attaching 4 to 6 pipe joints rather than just one.
The figure shows the ramp at a relatively shallow angle. This is needed for installing in
shallow water - perhaps near landfall. In deeper water, the angle becomes steeper -
almost vertical.
292 Overview of pipeline engineering
The deepwater section of the Bluestream project was laid using the Saipem 7000 J-
Laybarge. The 50 m (164ft) quad joints were offloaded from the pipe transport barge
and stored on deck. The corrosion coating of the quad joints was inspected and then
the ends were bevelled. A turning device rotated each quad joint by a quarter turn to
avoid alignment of the longitudinal seals in adjacent sections.
The quad joints were upended and hoisted to the top of the J-Lay tower, where a line-up
clamp aligned them with the previous section. Welding was performed using three
Presto twin-torch welding units mounted on a rotating carousel. After welding, the quad
joint was lowered a few metres to the NDT and field joint coating station on the floor
below, where 100% automated ultrasonic weld inspection took place. It is common
practice to separate the welding area from the coating area for cleanliness.
After the field joint coating was applied the tensioners were activated. The tensioners
have a lay capacity of 252 tonnes and contingency holding capacity of over 1000 tonnes.
The S7000 has a dynamic positioning system which allows the correct tension to be
maintained in the pipeline as it is lowered to the seabed. The system enables the
laybarge to remain stable in winds approaching 30 knots.
Installation methods 293
Performance
Lay speeds up to 2.3 km/day
(1.4 mile/day) - half of S-lay rate
Vessel cost up to $350,000 per day
Ideal for deep water Stationary Stationary
clamped clamped pipe
Consumable ring
rotated and
compressed radially
Acergy’s radial friction welding system
The above slide shows ball-park lay speeds and vessel costs.
This system is ideal for use in deep water, where the low lay stresses and low horizontal
tensions required lend themselves to installation from dynamically positioned vessels.
Although quicker one-shot welding methods have been developed, they have yet to be
used for a contract. Acergy’s radial friction welding system is shown.
One further way of improving the speed of assembly at a single work station is to use
mechanical connectors, similar to those used downhole.
Reluctance by operators to use what is perceived as novel technology means that neither
has been adopted to speed up J-lay installation.
294 Overview of pipeline engineering
J-LAY - SUMMARY
Any questions?
The J-lay method has a ‘J’ shaped lay curve due to the vertical assembly line located in a
tower that is fitted to the vessel deck. This has the advantage over the S-lay method that
lower horizontal tensions are required to maintain the required bend radius at the
bottom of the lay curve.
The lower tensions mean that the vessels do not require anchoring, so usually operate
with Dynamic Positioning (DP) thrusters. These will use less power than DP systems
for S-lay vessels. Because the vessels are dynamically positioned, they are able to operate
in deeper water.
The lay rate is approximately half that of the S-lay process because there is only a single
weld station on the assembly line. However, the cost of vessel deployment is about the
same. This is offset by the ability of J-lay vessels to operate in deep water.
The single weld station is usually the limiting factor in the speed of pipe installation.
Therefore, there has been a demand for research into the potential for connectors and
rapid welding techniques to improve the efficiency of this installation method.
Installation methods 295
REEL-LAY
REEL LAY
The picture above shows a reel of pipe on board the Technip Apache. The construction
site is at Technip’s Evanton facility loading pipe onto the Deep Blue.
Reeling is a technique where the pipe is assembled into long lengths onshore and is
wound onto a reel on the vessel by yielding the steel.
At the field it is then unwound, straightened and J-laid down to the seabed.
The dynamically positioned vessel is able to lay rapidly because there are no welds to
complete.
296 Overview of pipeline engineering
This video shows the capabilities of the ‘Apache’ rigid pipe reel-lay vessel, operated by
Technip. It discusses the following aspects of reel-lay from the Apache in more detail.
This and other vessels have now been used for deeper reel-lay operations.
The welding, testing and joint coating of pipe joints to form the pipeline section to be
reeled are undertaken at an onshore spoolbase. The onshore facility can provide a more
controlled environment for welding and testing and so joint integrity can be ensured at a
lower cost than if performing offshore welding of joints. Technip have three permanent
spoolbases in the world. One on the west coast of Scotland at Evanton, one in Norway
and another in Brazil. However, temporary spoolbases can be constructed around the
world as required.
In 1995, the Apache vessel underwent an upgrade that provided the vessel with a main
permanent single reel capable of carrying 2000 tonnes (2205 ton) of 406 mm (16 in)
diameter pipe. This is the equivalent of 10 km (6.2 mile) of 406 mm (16 in) pipe or 24
km (14.9 mile) of 254 mm (10 in) pipe. It also carries two smaller auxiliary reels for
smaller diameter pipe. The pipe on these smaller reels can be installed in parallel or on
“piggy-back” with the main pipeline being laid. The updated configuration has been
used to install pipe to a depth of 1400 m in offshore Brazil.
Installation methods 297
The Express shown above can accommodate reeled rigid steel or flexible pipeline. The
rigid line requires straightening prior to installing using a similar curve to that for J lay.
At the stern of the vessel, the straightener system can be seen on the adjustable angled
tower. Below them, there is a tensioner system which fixes the pipeline temporarily to
permit anodes to be attached.
Reeling has a set of performance characteristics and constraints which are quite different
to those of S-lay and J-lay.
298 Overview of pipeline engineering
Current vessels are limited to a maximum pipe diameter between 324 mm and 457 mm
(12in and 18in), because larger pipelines would buckle if one tried to reel them at the
radii of the present drums.
Once on site, the installation rate is very quick - 1000 m (0.6 mile) per hour, 24 km (15
mile) per day This compares to say 4 to 8 km/day (2.5 to 5 mile/day) for S-lay and J-lay.
Attaching a piggyback line will roughly halve the lay rate.
ACERGY FALCON
One further pipelay vessel is the Acergy Falcon (formerly the Stolt Seaway Falcon). It
uses a mix of all three methods.
It has a single welding station in the horizontal on the deck. The pipe is lifted and
yielded, runs over the top of the reel, is re-straightened on the ramp and is then J-laid
from there.
It can lay in areas where there is no convenient spool base at a rate comparable with S-
lay barges but with low residual tension.
Installation methods 299
REEL-LAY - SUMMARY
Any questions?
The reel-lay method has the advantage over the S-lay and J-lay methods in that the welds
can be made efficiently onshore and then the pre-welded pipeline can be quickly
unreeled from the vessel at a high lay-rate. The unreeling process involves straightening
the pipe after the plastic bending deformation induced during reeling of the pipe onto
the spool. Then the pipe is laid from the stern of the vessel through a J-lay type tower.
The disadvantage of this lay method is that a limited length of pipeline can be carried to
the installation site in one trip.
300 Overview of pipeline engineering
TOWING
As with the reeled pipe, an onshore facility is needed for pipeline assembly for towed
installation methods.
However, instead of the jetty and berth required for the reel-laybarge, a gently sloping
sheltered bay is needed for bundles. The bundles are trimmed for a buoyancy of around
-30 N/m (-2.1 lbf) prior to towing to site.
A number of methods have been used to tow flowlines to site. These are classified by
the buoyancy in the pipeline and hence the height in the water column at which the tow
takes place.
Single lines are sometimes installed by the near-bottom tow or surface tow methods.
Installation methods 301
Flow-lay Reusable PE
buoyancy pipe
Reusable PE pipe
Concreted flowline
Flowline
with coating
Surface tow systems use shore-based construction sites and then float the pipelines to
the offshore field. There they are flooded and laid in position.
The method is sometimes used for landfalls, where temporary buoyancy is attached to
the pipeline as it leaves the laybarge or construction site to make it easier to reach the
shore. The buoys are then disconnected to sink the pipeline in place.
Such a float-and-lower method is widely used throughout the world. In the sheltered,
shallow sea to the west of Trinidad, long lengths of pipelines are assembled on the
beach. They are then towed out to sea and the buoyancy tanks removed once the pipe
string has been lowered down to the seabed. There the individual strings are diver-
connected together using conventional bolted flanges. No expensive laybarge is needed,
only small floating plant.
Surface towing of bundles has not been widely used due to fears of bending fatigue, and
also the risk of collisions with vessels crossing the path of the bundle during tow.
The ‘Flow-lay™’ system minimises the fatigue problem by limiting the tow-out
operations to only a few days in good weather/seas whilst maintaining tension on the
trail tug. It was developed from bundle towing technology. Either the flowline or the
carrier can be flooded, depending on the relative weights and buoyancy of each, and the
on-bottom stability requirements. The PE pipe is then released to the surface where it is
recovered for future use. It promises considerable savings over other systems of
installation for single or double lines in remote areas of the world.
302 Overview of pipeline engineering
Gas
Oil Concrete
Water Insulation
Water
P-I-P flowline injection
Pioneer’s Oooguruk field development is in Harrison Bay of the Beaufort Sea, North
Slope, Alaska. Some 40 to 60 wells will be drilled (early 2007) from a 7 m (23ft) high
island standing in less than 1.5 m (5ft) of water some 9 km (5.6 miles) from shore. First
oil is scheduled for early 2008. The 2.4 ha (6 acre) island was constructed during the
coldest months by trucking gravel on an ice haul road build over the frozen sea.
The flatpack (or open) bundle takes the production fluids ashore and supplies water and
gas injection facilities plus diesel fuel to the island. The flowline is 323.8 mm by 406.4
mm (12in by 16in) pipe-in-pipe. This and the other lines are connected with 250 mm
(10in) wide spacers at 6 m (20ft) intervals. Pioneer will employ an annulus vacuum
monitor or pressure monitoring system for environmental protection. The inside of the
internal pipe operates at about 40 bar (580psi); hence if high pressure is detected in the
annulus then an internal leak has been detected. If low pressure is detected, this signifies
a potential external leak.
All lines are grade X52 or higher for compatibility with potentially high operational
strains.
The 0.6 m high by 1 m wide (2ft by 3ft) bundle is to be installed in a 2.7 m (9ft) deep
pre-excavated trench in the seabed, giving almost 2 m (7ft) of cover when backfilled in
order to prevent uplift buckling. Backfill to the trench also protects against ice gouging
and strudel scour (where river water flows offshore over the ice each summer, scouring a
hole through the floe and whirl-pooling down into the seabed beneath). The pipeline
will continue onshore for a further 3.7 km (2.3 miles), making the pipeline length a total
of 12.7 km (7.9 miles).
BUNDLES
Britannia Bundle
Test flowline
Methanol flowline
Heating flowline
Production flowline
Gullfaks Bundle
Bundles as depicted in the picture above are groups of flowlines encased within a carrier
pipe. The carrier pipe provides buoyancy, which allows the bundle to be completely
fabricated onshore, towed offshore and then the annulus flooded to sink it in place and
provide stability.
Transponders
Trailhead
Towhead
Ballast chains
Controlled-depth tow, as the name implies, is towing the bundle such that it stays in
mid-water between the seabed and the surface. When one considers that bundles may
be 5 to 7 km (3 to 4½ miles) long and the water depth may be 100 m (330ft), it is quite a
feat to keep the bundles straight and steady without perturbations, which could take it
either to the surface or the seabed.
304 Overview of pipeline engineering
PRINCIPLE OF CDT
Neutrally
buoyant bundle
Webbing
straps 2 m to 3 m
Ballast (6ft to 10ft)
Wire Chain above seabed
chains
For a controlled-depth tow, the carrier pipe is sized so that the bundle is slightly
positively buoyant and then chains are attached to the underside. The bundle is then
towed out into a sheltered bay. Being positively buoyant, the carrier pipe rises from the
seabed and lifts the chain until enough links are suspended to counteract buoyancy.
Divers then work their way along the bundle to see how many links are left on the
seabed and to trim these as necessary to give an even negative buoyancy.
Once trimmed, the whole bundle is tensioned between a leading and trailing tug and
towed to site. As the speed increases, the chains slope backwards. This generates lift as
well as drag as they pass through the water. This means that, at a certain speed, the
bundle will become neutrally buoyant and will rise from the seabed. The speed of the
tugs is adjusted to maintain the lowest point of the bundle about 10 m to 15 m (30ft to
50 ft) above the seabed and the tow and trailheads at a similar depth below the surface.
Installation methods 305
BOTTOM TOW
Chain ballast
Bottom tow, as the name implies, is where the bundle is dragged along the bottom.
However, the improvement shown above is near-bottom tow. The carrier and buoyancy
is sized to ensure that the bundle is just positively buoyant. Chains are then attached to
give a controlled amount of submerged weight.
This technique has been used successfully in the Gulf of Mexico, where bundles were
constructed along the beach, launched into the surf zone and then pulled along the
seabed to site. The tow route to the offshore field can be hundreds of kilometres (miles)
long, following a detailed pre-surveyed route avoiding such features as coral and rock
outcrops, and as many pipeline crossings as possible.
306 Overview of pipeline engineering
DEEPWATER BUNDLES
Girassol project
Deepest installation
of a pipeline bundle
at 1350 m (4430 ft)
‘Wet bundle’ system Girassol
Field layout
Established technology Courtesy: Elf Exploration Angola
Use of unpressurised carriers (which remain flooded) means that the insulation needs to
be able to resist the full water pressure at the field.
This means, however, that essentially any depth can be achieved - though the insulation
can be costly.
In deepwater, bundles can be installed using controlled depth or bottom tow methods to
transport them to location from the fabrication site.
Installation methods 307
There are safety concerns in pressurising gas above 25 bar (363 psi) in a thin-walled
carrier on the construction site. Plant may impact and rupture the pipe, causing an
explosion adjacent to personnel.
The picture shows the relative thinness of the carrier used for the Gannet development.
Although not a deepwater bundle, a similar thickness might be used for deep water. It
cannot be made thick enough to withstand hydrostatic collapse because its weight would
increase too much.
Normally, bundles counteract the hydrostatic pressures at the field by pressurising the
carrier pipe annulus with nitrogen. In deep water, the substantially higher pressures
cannot be provided prior to launch. Health and safety considerations require that the
differential pressure never exceeds around 25 bar (360 psi) at the construction site.
The total mass of the bundle needs to remain constant during all stages of the mid-depth
tow-out. Injecting additional nitrogen at an intermediate-depth holding station would
increase the weight, making the bundle too heavy. So the flowlines can be super-
pressurised for the initial loadout to the parking area in around 200 m (650 ft) water
depth. There, the pressure in the flowlines and carrier is equalised by venting the gas in
the flowlines into the carrier annulus. Thus the higher hydrostatic pressures at the field
can be counteracted. Alternatively, from the parking area, the carrier can be flooded and
a bottom tow method used.
Finally, the whole bundle can be towed out ‘wet’, as used for the Girassol Project. The
insulation was designed to resist the full hydrostatic pressure with no need for flooding
at the field.
WHY BUNDLES?
Pros Cons
Good for many parallel Only straight routes or
pipes – narrow corridor gentle curves
Use of pipe-in-pipe All eggs in one basket
Include manifold and pre-
Short lengths
commission
Good for heating and Difficulty of monitoring or
insulation repair of individual lines
Include umbilical Installation restricted to
Carrier offers protection fine weather (summer
No concrete needed for months)
stability
Land-based construction
costs are lower
Bundles have many advantages. They are economic for many parallel pipes. In some
cases, it is possible to install the manifold pipework in the tow head and to pre-
commission this and the control system. It is also possible to arrange for heating and/or
insulation of pipelines. This may be done by including pipe-in-pipe or re-circulating
heating lines.
The umbilical no longer requires armouring and can be pulled inside the carrier for
protection. The carrier pipe, once installed, is non-pressure containing and forms a good
structural barrier against fishing interaction and dropped objects, meaning that there is
no requirement to trench the bundle.
The drawbacks of bundles are that they are restricted to short routes and relatively short
lengths. The longest controlled depth towed bundle to date is 7.5 km (4.7 mile), whereas
the longest bottom towed bundle is about 20 km (12.4 mile).
Finally, ‘all your eggs are in one basket’ with a bundle. If, for any reason, there is a
problem, then all your flowlines and manifolds are out of commission until the problem
is sorted out. It may be difficult to monitor corrosion of the annulus with heating
systems.
Installation methods 309
TOWED SYSTEMS
Projects Contractors
Troika Subsea 7
Gulfaks Land and Marine
Skene RJ Brown
Britannia Acergy
Green Canyon
Girassol – wet bundle
Oooguruk – flat pack
Towed bundle and pipe-in-pipe systems have been installed in relatively deep waters.
Girassol is 1350 m (4430ft) deep but uses the ‘wet bundle’ method without a pressurised
annulus. This avoids the health and safety concerns during launch when there are high
differential pressures in the carrier. These are needed to counteract the hydrostatic
pressure at the field.
Because the only vessel requirements are two tugs for the short tow period, these can be
hired as needed on the open market. A number of contractors are able to offer this type
installation.
The 9 km (5.6 mile) long open (flatpack) Oooguruk bundle is currently being
constructed in Alaska for installation between an artificial island and the shoreline on
behalf of Pioneer Natural Resources.
310 Overview of pipeline engineering
BUNDLES - SUMMARY
Bundles
Allow low cost high quality onshore fabrication
Permits rapid offshore installation
Good for multiple parallel lines
Limited to flowline diameters and lengths
Any questions?
Bundles have the advantage over single rigid pipelines that they can contain several
individual flowlines within a single carrier pipe. The installation of a bundle then
becomes a very efficient method of installing multiple parallel lines along a single route.
However, the installation efficiency of S-lay and J-lay methods is heavily constrained by
the time required for welding the pipe joints together. The make-up of joints for
bundles requires the welding of the multiple flowlines of various lengths making bundle
installation by S-lay or J-lay methods unfeasible; and the only alternative is to lay
individual flowlines.
Bundles are fabricated at low cost onshore facilities and then towed out for installation
on the seabed.
Installation methods 311
WHAT IS A FLEXIBLE?
Armours
Pressure
vault
Armours
Pressure Pressure sheath Carcass
sheath
Carcass
A flexible pipe is one that is designed to bend to (relatively) small radii without damage.
Flexible pipe
loaded onto
vessel carousel
Quay adjacent to
fabrication yard
The flexible flowline is wound off its reels in the factory, over a conveyor belt or roller
system, onto the vessel and into the carousel, as shown in the picture above. This
means that the quayside needs to be adjacent to the fabrication yard.
The carousel is normally horizontal in the vessel hold, but modular spools can be located
on deck.
FLEX-INSTALL CAPABILITY
DP vessels
Fast lay
Low stress curve
Flowline rather than
trunkline market
Primary concerns
Gripping flexible
without damage
Where the lay tension (mainly due to self weight of the flexible) is high, the pipe is
routed through a vertical lay tower such as that shown above. It passes over the set of
Installation methods 313
curved rollers at the top, then vertically through the tensioners and down into the water
below.
The tensioners normally have 3 or 4 gripping points around the circumference of the
pipe. This minimises the ovalisation of the pipe. In addition, the tensioners need to
work over a long-enough length to avoid crushing the internal layers of the pipe.
Where lay tension is small (shallow water) the flexible may be laid over a curved chute,
or over the curved vessel stern ramp.
With water depths over 400 m (1300ft), it is normal to install over a guide as shown
above.
For shallower water, umbilical cables can be lowered using a horizontal tensioner and
chute system similar to that used for flexible pipelines. However, for deeper water, the
tension can put the cable at risk.
If a cable is wound five times around a drum, then there are enough friction losses to
hold any tension applied to the cable.
However, if the drum is a simple one, the cable will spool right off one edge.
This SMD (formerly Soil Machine Dynamics Ltd) cable engine keeps the position of the
five wraps constant relative to the edges of the drum enabling the whole length to be laid
without conventional tensioners.
Technip Helix
Sunrise 2000, Deep Blue Intrepid
Acergy
Condor, Falcon
Subsea 7
Kommandor 3000,
Seven Seas, Skandi Navica
Helix
Express, Intrepid
SapuraCrest
Sapura 3000
Most of the major contractors are able to install flexible pipelines or cables.
The photo is that of the Intrepid which can install cables and both flexible and rigid
reeled pipelines.
PERFORMANCE OF FLEX-INSTALL
Laying speed
12 km/day (7.5 mile/day)
Maximum diameter
480 mm (19in) - bore
Multiple line installation
Up to 3
Can be re-used (Petrobras)
The laying speed is comparable with that for the reel-lay method. There is no need to fit
anodes during the laying operations but care is needed in handling the flexible pipeline
or cable.
Installation methods 315
Remember, that flexible pipelines are specified by their internal diameter and this is set
by the manufacturing process rather than any limitation on laying.
Petrobras has recovered and refurbished a number of flexibles for reuse. These are long
flowlines and risers in deep water. However, in Australian fields, where there are
shallower water depths and shorter lengths of line, the risk assessment favours disposal
over reuse.
Any questions?
Flexibles are stored on carousels and unreeled to install them on the seabed.
For deepwater, they are laid vertically in a J-lay configuration to maintain the required
tension, similar to the reeling process. In shallow water, they can simply be laid
overboard using a chute and tensioner.
Deepwater cables can be laid using a drum winch rather than a tensioner system.
316 Overview of pipeline engineering
INSTALLATION METHODS -
SUMMARY
The main installation techniques for rigid pipelines, bundles and flexibles have been
presented. We have highlighted where modifications are needed to these methods for
deepwater lines.
Construction support
Construction support 319
EXPECTATION
EXPECTATION
Trunk pipelines generally bring oil or gas to shore. We will introduce the basic activities
required for landfall construction.
Smaller diameter pipelines are often buried. We look at the reasons and main methods
for the trenching and burial of pipelines on the seabed.
Finally, the main activities for pre-commissioning pipelines for product receipt are
introduced.
320 Overview of pipeline engineering
LANDFALLS
SCHEMATIC OF LANDFALL
Cofferdam
through tidal zone
Winch &
Cutter dredges trench
reelwinder
to laybarge depth
Laybarge
The landfall, as the name implies, is where a pipeline comes onshore. The construction
process is shown schematically above and is focussed on preparing the site for the
laybarge to install the pipe.
A typical trench depth is 3 m (10ft) to ensure that the pipeline stays buried well below
any future erosion of the beach. The trench is normally dredged out to about 12 m
(40ft) LAT (that is, 12 m water depth relative to the lowest astronomical tide). This
ensures that the remainder of the pipeline can be post-lay trenched using offshore
trenching equipment.
Construction support 321
The landfall was required for a 835 km (519 mile), 1067 mm (42in) high pressure
pipeline bringing natural gas from the Draupner E platform in the Norwegian North Sea
sector to the coast of France.
This landfall required the installation of a cofferdam and pipe pull-in equipment,
levelling of sandwaves at the shore approach, stabilisation and protection of the laid
pipeline with rockdumping and finally tie-in between the section of pipeline at the
landfall and the other section laid from the platform towards Dunkirk.
The wing walls to the cofferdam helped protect the area behind the beach from
flooding, should the dune protection be breached by storms. These are generally
constructed using land-based piling hammers and crane equipment.
The long cofferdam ensured that longshore drift of sand did not refill the trench
between high and low water marks. The jackup barge was floated in to shallow water at
high tide and the legs deployed. This meant that it could continue to pile throughout the
tidal cycle unaffected.
A spud-legged dredger used its cutter suction arm to open a trench in the nearshore
section.
322 Overview of pipeline engineering
U section (Larssen)
‘Clutch’
‘Pan’
Clutch details
Z section (Frodingham)
‘Clutch’
Clutch details
Arcelor-Mittel manufacture two styles of sheet steel piles: the U and Z sections. These
are also known as Larssen and Frodingham piles. See www.sheet-piling.arcelor.com for
available section sizes and design software. Elsewhere in the world other similar designs
are used. See www.pilespecs.com for a world-wide list of sheet pile specifications.
The difference between the two is the location of the clutches that link the steel piles
together. The Larssen has the joint near the neutral axis of the complete section. If the
clutch holds well, then there is no movement between the adjacent piles and a large
section modulus can be developed. The Frodingham does not rely on clutch friction to
develop its full section modulus because the pile spans between the extreme fibres in
tension and compression.
CUTTER DREDGER
The diagram shows a cutter dredger. The arm is lowered to the seabed, cuts the soil and
lifts it in a slurry to the vessel, thence to a floating hose leading from the stern. This
excavation occurs prior to the pipeline being brought ashore.
The cutter head moves from one side to the other and then back, as the dredger moves
forward along the line of the trench. This is accomplished by first lifting one of the spud
legs and swivelling the whole barge and cutter arm around the second leg by
pulling/releasing the forward anchor wires. At the end of each cut, one spud leg is
lowered and the other lifted, causing the barge to move forward along the line of the
trench: the anchor winch wires sweeping the arm back across the face of the excavation.
For a landfall, the slurry is typically pumped 100 m (330ft) from the vessel through a
floating pipe, and is placed in a spoil heap. Once the pipeline is in place, this spoil is
redredged and placed back over the pipe.
324 Overview of pipeline engineering
BEACH PULLS
The beach pull, as illustrated in the picture above, is where the pipe is assembled on
board the lay vessel and pulled into the pre-dredged trench using cables and a linear
winch. Temporary buoyancy has been attached to the pipeline to reduce seabed friction.
Once the shore pull is complete, the laybarge continues laying the pipeline towards its
offshore location. The pulling head is cut off and the section up to the pre-laid landline
is completed pipe-by-pipe. It is common to have an electrically-insulating flange just
before the shoreline emergency shutdown (ESD) valve. This maintains separation
between protection systems –sacrificial anodes are used offshore, whilst impressed
current is commonly used for the landline section.
An alternative (not shown) to pulling onshore from the laybarge is to pre-assemble the
pipe onshore and use a pull-barge to pull it offshore. As before, the end can be picked
up with a lay barge and laying continued offshore.
If the pipeline is laid from the offshore end towards the shore, and then laid down prior
to the installation of the landfall section, a tie-in will be necessary. This can be done
above water by the laybarge using derricks to lift the two ends above the sea level and
completing a weld alongside. The excess length of pipeline is then laid in a loop on the
seabed.
However, most pipelines would start from the landfall and go out to sea.
Construction support 325
The 100 km (60 mile) long Goldeneye pipeline and piggyback were installed during the
summer of 2003 at St Fergus on the north-east coast of Scotland. Because the dunes
were to be breached and the area is of sensitive environmental interest, the opportunity
was taken to install a second landfall line at the same time for future pipeline connection.
This is the Atlantic Cromerty pipeline.
At St Fergus, seven gas pipelines have their landfalls. These bring ashore most of the
UK supply and are connected to three adjacent gas treatment plants. Gaining approval
from the national security services to breach the dunes in this environmentally and
security-sensitive area was a major challenge.
Van Oord, the landfall contractor first constructed a cofferdam 130 m long and 25 m
wide (426ft x 82ft). An anchor wall was also piled to provide a deadman for the two 350
tonne (772 kip) linear winches.
The Goldeneye pipeline was trenched out to 1200 m (4000ft) from the beach to provide
cover of 2 m (6.7ft) nearshore and 1 m (3.3ft) offshore. This was undertaken by the
barge ‘Manta’ using a jetting machine (above), which excavated the soil and pumped it
out through a pair of eductor tubes into two windrows either side. High and low
pressure water was supplied through hoses using pumps on board the Manta. Some of
the anchor wires from the vessel required a mid-line buoy to ensure vertical separation
from the existing live pipelines.
A second vessel, the ‘Coastal Worker’ completed the shallowest sections of the trench
inshore using a suction pipe lowered from the side of the vessel and sidecasting the
material through a discharge pipe.
Finally, the dunes were carefully reinstated and stabilised using marram grass.
326 Overview of pipeline engineering
DIRECTIONALLY-DRILLED
LANDFALLS
Main benefits
Minimum disruption to environment
Minimal third party disturbance
Less risk of flooding than with open cut method
Pipeline installed at great depth
The overhead shows the drilling rig site and the reel barge in position at a landfall site in
Northern Holland (plus an artist’s impression of the method).
DRILLING RIG
Stitch drilling
Pilot hole drilled from shore from jack-up
The video shows how a landfall can be accomplished with minimum environmental
disruption by drilling first a pilot hole using a land-based rig out to a laybarge. Then the
pilot hole is widened using a reamer, allowing the laybarge to lay a section of the pipeline
onto the seabed which can be drawn back to shore.
The alternative (shown top right) is to drill from a jack-up barge and pull the pipeline
from shore. Using a development of this technique, sometimes known as ‘stitch
drilling’, it is possible to accomplish long distances in sections of around 1.7 km (1 mile).
During construction of the Hoover offshore crude oil pipeline system, it was necessary
to cross Quintana beach to reach Freeport Texas. To avoid disrupting the sensitive
ecosystem, it was deemed necessary to run the pipe underground. This was done by
drilling 1200 m (4000ft) from the mainland to the sea.
A land-based directional drilling rig with a 127 mm (5in) washpipe and 76 mm (3in)
drillstring opened the hole beneath the beach and out to a barge where successively
larger reamers were attached and pulled through the hole, opening it up to 914 mm
(36in) – around 25% larger than the pipeline. Meanwhile, the 508 mm (20in) pipeline
was laid on the seabed by the Horizon Lonestar S-lay barge.
After the final reamer pass, a diver attached it to the pipeline via a swivel and universal
joint. The pipeline was drawn through the hole using a force of 2.2 MN (500kip) in 17
hours.
328 Overview of pipeline engineering
LANDFALLS - SUMMARY
Initially a trench will be prepared through the surf zone, which may require the use of a
cofferdam to prevent the walls collapsing and the trench refilling.
Then the laybarge will be positioned as close to the shore as possible using either
anchors or DP. The pipe is then laid from the back of the lay vessel and pulled to the
beach by linear winches.
Once the pipeline is installed, the trench can then be backfilled to bury the pipeline in
the surf zone.
Finally the beach will be reinstated to remove evidence of the pipeline installation.
Trenching means removing the soil under the pipeline so that it falls below the natural
seabed level. It is normal to undertake trenching after the pipeline is laid on the seabed.
However, umbilical cables are often laid and buried in one operation and occasionally
pipelines are laid into a prepared trench - such as we have just seen at landfalls.
Backfilling means replacing the soil so that the pipeline becomes buried. Not all
trenched pipelines are backfilled because the shape of the trench itself can provide some
protection.
PLOUGH
Ploughing spread is
One DSV ($100 000 per day)
Two tugs ($30 000 per day per tug)
The picture above shows a plough. It has skids at the front (left hand side) and a
ploughshare at the back.
Offshore, the plough is lowered over the pipeline with the share open. (It splits in half
down a vertical plane and opens about a hinge at the top of the plough). The pipeline is
picked up by rollers at the back and the share is closed underneath. Tugs or an anchored
laybarge then pull the plough forward via a warp attachment at the front. The share digs
in and produces a triangular trench under the pipe into which it falls as the plough
moves forward.
The animation by CTC shows how their plough is lowered from the vessel on a wire and
located over the pipeline with its split shares open. Lights and cameras on the ROV
allow this to be accomplished safely using the plough’s onboard thruster units.
The pipeline is lifted into the forward and stern roller boxes and the shares closed using
the ram. By lowering the skids at the front, the depth of cut is adjusted as the plough is
pulled forward by the bridle chain.
It is necessary to check the stresses in the pipeline during the initiation and trenching
(with pipe resting at the base of trench to the stern).
Typical values for plough performance are given in the table above. The point to bring
out here is that it is capable of working on nearly all types of soil, including friable chalk
and rock.
The major difficulty that it encounters is very dense sand, where the permeability is low.
The reason for refusal in dense sand is that, as the plough tries to cut and lift a segment
of the sand, it requires water to fill the void created.
In low permeability sand, the water cannot reach the interstical voids between the grains
and a hydraulic lock results. Some ploughs pump water down to the share tip to prevent
this.
Ploughs can be employed in water depths down to about 400 m (1300ft), although
deeper water is possible using large DP tugs and careful control of the bollard pull to
within 5 tonnes (11 kip).
332 Overview of pipeline engineering
Jetter spread
Typically flat bottom barge
with water jet pumps
$70 000 per day
Also requires two anchor-
handling tugs
$20 000 per day each
The above picture shows the Jet Sled. A barge on the surface pumps seawater down to
the sled which discharges out through the jetting arms and blasts away the soil. The sled
is towed by the jetting barge.
This tool is used extremely effectively. There are two main points to consider. The first
is that the soil is whipped away and dispersed, so is not available as backfill. The second
is that the machine works best in consistent conditions. For example, if it is on full
pressure to excavate some stiff clay and moves into an area of soft sand, it could
excavate a large unwanted crater in seconds.
The above table gives some general characteristics which indicate that the jet sledge is
best used in sand or soft to firm clay.
Jet sledges work in depths down to about 200 m (650ft), the limitation being current
forces and the length of umbilical power cable or water hoses. In deeper waters, ROV
jetting or cutter machines can be employed.
As the name implies, the mechanical cutter is a device that drives along the pipeline with
mechanical teeth or buckets excavating a trench. Mechanical cutters are well suited to
hard seabed soil conditions. The above picture shows the Digging Donald - a tracked
vehicle with two chainsaw arms reaching under the pipe. The Digging Donald has the
advantage that it does not need to make contact with the pipe during the trenching
operation.
334 Overview of pipeline engineering
MECHANICAL CUTTER
This picture shows the Digging Donald being deployed from the Allseas Trenchsetter
support vessel.
CUTTER PERFORMANCE
Again cutters can be used in most types of soil. Their particular ‘bête noire’ is to cut
through chalk or soft clay, where boulders or flint embedded within the soil tend to
break or blunt the teeth on the cutters.
Cutter units are limited only by the means of deployment and length of umbilical cable
being acted upon by the ocean current.
Construction support 335
TALON TRENCHER
Swords on ROV
Cutter and jetter
options
Used for deep
water flowlines
Insulation of soil
‘Flies’ to location
In deepwater, it becomes difficult to plough due to the length and flexibility of the
towing warps. A conventional jetter also has problems following the line of a pipe when
being slung from a barge.
Devices such as the Talon Trencher, pictured above, have therefore been developed.
They have of a pair of ‘swords’ mounted under an ROV (remotely operated vehicle)
which can ‘fly’ down to the pipeline and commence burial. The swords can either be jet
arms or cutters, depending upon the soil conditions. They fit either side of the flowline
and lower it to depth.
The machine is usually used for deepwater lines, which may require burial for insulation
reasons rather than protection against trawler impact.
336 Overview of pipeline engineering
DEEPWATER TRENCHING
Challenges:
Soft soils
Equipment sinks in
Trench walls unstable
Plough tow rope catenary cannot give even pull
Plough tends to surge and damage pipe
ROV cut or jet methods required
Trenching may be used in deepwater for thermal insulation. It is not required for
stability in waves or currents because the effects of both are reduced in deep water. Nor
is there as much trawling effort in such depths.
However, we tend to find soft soils which prevent the use of tracked equipment.
Trench walls in such soil tend to collapse more readily.
Ploughing methods for pipelines cannot be used much below 400 m (1300ft). This is
because the catenary in the wire results in the plough surging forward and then stopping
until the tow vessel moves forward and reapplies the force. During the surges the
plough may deviate off line and damage the pipe.
This means that ROV cutting or jetting methods are preferred. The ROV uses the
pipeline as a ‘monorail’ guide and support.
Construction support 337
Towed sled
cable plough
Cutter wheel
for rock
The same three methods are used for burial of umbilicals and cables. Costs are lower
because less soil needs to be removed because of the smaller diameter of these
compared with pipelines.
Similar equipment is used for umbilicals and cables, so these will be examined together.
Sometimes, these terms are used interchangeably, but a cable usually provides power
through copper cables or data down optical fibre links. An umbilical usually has small
bore chemical injection or hydraulic lines as part of the bundle.
This tracked jetting vehicle is used to bury umbilicals and cables after laying as a separate
operation.
It needs a firm seafloor to operate but the cable is trenched and buried in one pass. The
cable is passed though a protective tube in the ploughshare. Jetting is ideal for silty and
sandy seabeds.
Where the ground is softer a towed sled plough system may be employed. This operates
best in coarse sand, silt and clay. The plough displaces a wedge of soil upwards and then
lets it drop back down burying the cable.
In harder ground or rock, a cutter wheel may be used to make a slot. Again the cable is
laid into the bottom of the trench.
338 Overview of pipeline engineering
The CTC tracked trencher can jet cut and disperse the seabed sediment lowering the
cable into a trench.
Where possible, a single pass lay and bury system should be used. This generally results
in a slower lay rate since the operation is dependent upon the speed of trenching.
However, a single operation means that total costs may be lower.
If this is not possible, the commonest practice is to lay the cable first and then trench
and backfill. If the umbilical follows the route of a pipeline, then it may be laid into the
Construction support 339
previously cut trench. That is, three operations - lay the pipeline, cut the trench, lay the
umbilical.
Whereas pipelines have some inherent strength, the smaller diameter of umbilicals and
cables inevitably means that there are additional risks of them parting due to high
tension. This is especially true when the trenching and burial is completed as a separate
operation and the alignment of the trench is not exactly that of the umbilical.
Single pass helps minimise the tension in the unit. However, a suitable design of
catenary from the vessel into the trencher must account for the wave and current
movement of the cable and the vessel.
In cut rock trenches, there may be the need for additional armouring to provide
protection against the rock rubble that backfills in on top of the cable.
When electricity cables were laid across the English Channel in 1986, a trench was pre-
cut in the chalk and a guide wire laid into the trench. The wire was removed in a
separate operation when the slot was cleaned out and power cables were then laid. The
trench then backfilled naturally with sand.
The CTC plough is located over the cable, which it lifts into the guide chutes before
being towed forward by the tug. Depth of trench is controlled using the forward skids.
It is different from a pipeline plough in that the ploughshare is very narrow, enabling it
to trench and bury the cable in a single operation.
340 Overview of pipeline engineering
PIPELINE BACKFILLING
Natural backfill
Backfill plough
Rockdump
Although umbilical cables are generally backfilled in the same operation as trenching,
this is not so for pipelines other than those lowered by sand fluidisation (jetting).
There are three main ways of doing this, which are presented here in order of escalating
cost:
■ Natural backfill means leaving the pipe in the trench and waiting for tide and waves
to wash the soil into the trench and to fill it over the pipe. This has the advantage of
being free and the disadvantage that it may take some time and is only feasible in
certain areas like the Southern North Sea which have sufficiently high sediment
transport. It would be very slow in the Central North Sea and negligible in the
Northern North Sea.
■ The next level up is to use a mechanical backfill plough to push the soil from the
sides of the trench back over the pipeline.
■ If there is no soil to pull back over the trench, then the third method is to rock
dump. This is shown in the picture above: a ship with gravel and a digger in the
hold. The digger shovels gravel onto a conveyor system and drops it down a fall
pipe. The fall pipe runs from the ship down to close to the seabed and can be seen
in the inset. It has thrusters and sensors on the end to position the rock over the
pipeline. Larger vessels are available to supply the quantities of rock needed for
trunk pipelines. They are typically fitted with longer fall pipes suitable for water
depths of 800 m (2600ft) or more.
Construction support 341
Any questions?
There are several methods used to trench/bury pipelines. The selection of the method is
dependant on the type of soil in which the pipeline must be buried. The ploughing
method works well in most soil types, except for very dense sands. The jetting method
will not work in stiff clays and chalk or rock. Cutters are suited to all soil types but are
particularly suitable for working in chalk and rock.
Similar methods can be employed for umbilicals and cables, but it is common for the
trenching and backfill to be undertaken in a single operation.
Where trenches need to be backfilled three methods are used depending upon whether
there is available spoil or natural backfill conditions. The final option of rockdump is
the most costly because of the need to import fill material.
342 Overview of pipeline engineering
PRE-COMMISSIONING
WHAT IS COMMISSIONING?
Commissioning
Operations for first product delivery through the line
PRE-COMMISSIONING OPERATIONS
Flooding
Flood the pipeline with treated water
Fresh water for flexibles with 316 SS
Send through gauging pig
Hydrotest
Pressurise to prove strength and leak tightness
Dewater
Pig out the water and dispose of it
Dry (gas lines)
Hygroscopic swab and air or vacuum dry
Intelligent pig run (baseline)
The pipeline is flooded with treated water in order to be able to strength-test it. (Water
is used rather than air in order to keep the pressurisation energy to a minimum, and so
too the consequences of any failure.) At the same time, a gauging pig is passed through
the line to prove that the bore is clear. This is more fully explained in the flow assurance
module.
Flexibles with a 316 stainless steel carcass will need fresh water since the material is
prone to chloride stress corrosion-cracking.
The sequence of events is normally to flood the line after trenching and burial.
However, in some cases the extra weight is beneficial, so the line is flooded prior to
trenching. This is particularly so of flexibles which are normally pressurised (to a low
pressure) prior to trenching. It is also true of pipelines with low relative density, where
there is a risk of flotation during backfilling.
Good practice would suggest the use of an intelligent pig to provide a baseline of defects
for the future integrity management operations. How can we be sure of wall thickness
loss without having the initial data to compare with?
344 Overview of pipeline engineering
PRE-COMMISSIONING AND
DOCUMENTATION
The pre-commissioning phase should also be used to check the integrity of the ancillary
equipment to the pipeline, which includes the equipment and the systems shown above.
The full set of manuals for operating the line through its life need to be handed over.
This should include proposals for decommissioning at the end of the pipeline life.
Construction support 345
DEFERRED COMMISSIONING
If this is case, the line should be filled with a temporary fluid to minimise internal
corrosion. Suitable fluids for deferral include dry inert gas, product gas and product, oil
or water to which biocides and fungicides are added. If using water, then care should be
taken to ensure that all the air is removed from the pipeline and that the water contains
no corrosive materials.
It is also advisable to leave the pipeline under a small positive pressure and check the line
periodically for leakage until commissioning commences.
HYDROTESTING PRESSURES
Strength test
1.5 times MAOP or 90% hoop stress for 24 hours
Gas lines may test to 105% SMYS
Pre-yielding helps with cyclic loading fatigue
Risers and other preformed bend sections
Separate strength test prior to installation
At a higher pressure for thicker wall
Leak test
Tie-in joints may be leak-tested at 1.1 times MAOP
for 3 to 6 hours to prove valves and fittings
346 Overview of pipeline engineering
Normally, the hydrotest pressure on the pipeline is set to 1.5 times maximum allowable
operating pressure or 90% of hoop stress, whichever is less.
The US codes have slightly reduced requirements at 125% or 140% of maximum design
pressure held for just 8 hours.
In the ‘Pipe Size and Route’ module, we mentioned that risers are often designed to a
lower design factor with thicker walls. This in turn means that they should be strength-
tested to a higher pressure. Therefore, they are typically strength-tested in a fabrication
yard prior to being assembled into a pipeline system.
Once the pipeline, the spoolpieces, the risers, the valves and the pig traps have all been
strength-tested individually, the pipeline is assembled and leak-tested to 1.1 times
MAOP for 3 to 6 hours, or as long as it takes to prove that all assembly joints are sealed.
When conducting hydrostatic tests on gas pipelines, it is may be necessary to take the
test pressure to 105% SMYS (dependant on national codes). The resulting yielding in
the pipeline serves to smooth out any stress concentration points that may have
developed from incomplete weld penetrations. This helps to improve fatigue properties
which is important in gas lines as they tend to undergo more cyclic loading than oil lines.
HYDROSTATIC TEST
Hydrostatic tests involve filling sections of the pipeline with water and then pressurising
them to check for possible leaks or defects. With landlines, the operation may be
required to be undertaken only once, after burial because it is possible to dig down and
repair leaks. However, this is difficult with offshore lines, so it is common to undertake
hydrotests at a number of additional stages such as after laying and after trenching. For
the main pipeline sections, the hydrostatic test should take also place after backfilling to
Construction support 347
identify any possible damage to the pipeline that has occurred during to the backfilling
process.
It is vital that all trapped air is removed prior to full test pressurisation. The air pockets
need to be removed as they can be compressed (which means the pipe takes longer to
reach the full test pressure) and would also become a hazard if the pipe were to rupture.
To prevent air becoming trapped, it is usual to install the water behind a pig. The air
being flushed out is then kept backpressured to prevent the pig running away from the
water. Also to be noted is that valve bodies, bypass pipework, etc. need to be vented
and sealed to relieve the air.
The water for use in a hydrostatic test needs to be clean and filtered. Filtering is
particularly important if the water is being taken from a natural source like the sea, rivers
or streams. If water is being taken from the sea then it may also require desalinating
when hydrotesting pipe containing 316 stainless steels (some clad pipe and flexibles).
When releasing the water back into the environment after the hydrotest, it is important
that the test water has been cleaned of any harmful corrosion inhibitors, bactericides or
other chemicals.
Safety precautions will also need to be adhered to and should include measures to
protect public and personnel, prevent pollution or damage to roads, waterways and
rivers, and obviously to ensure that no work is still being undertaken on sections being
tested.
With arctic landlines, it may be necessary to use heated water for the hydrotest to
prevent freezing. Here, quite unusually, the use of air for the pressure test may be used
since these lines are generally remote from personnel and any explosive rupture would
do little damage to third parties.
COMMISSIONING
Usually the final steps in pre-commissioning is to remove the water from the hydrotest
and dry the pipeline if necessary. For oil and petroleum based products, the drying and
introduction of the product is simpler than for hydrocarbon gas products. With
flammable or toxic products that are liquid at ambient temperature (e.g. oil and
petroleum), it is acceptable to displace the water with the product and use a series of pigs
348 Overview of pipeline engineering
If the pipeline is to convey products that are flammable and gases at ambient
temperature (e.g. LPG, natural gas, hydrogen, etc) then the pipeline will require the test
water to be removed independently of the product and for some products the line will
require drying. The choice of drying method depends on the degree of dryness required.
A common method for gas and LPG pipelines is to swab through with pigs to remove
the majority of water. Then methanol is conveyed between a series of pigs. After the
methanol, the pipeline is purged with dry nitrogen.
Where gas is being delivered to the end user, then vacuum drying or air drying is needed
as a final step.
When introducing products, precautions should be taken to ensure the mixtures of the
gases or liquids is not done in a way that may result in explosive combinations.
DEWATERING
Water &
Nitrogen Methanol Methanol mix Water
For gas trunk lines, dewatering would be done with a train of pigs, perhaps with gel or
methanol between, as shown in the above diagram. The line would then be vacuum-
dried to remove all traces of water before the introduction of export quality gas.
Such a procedure would not be necessary with a two-phase flowline or an oil trunk line,
where the likelihood is that the water would be displaced by a pig train driven by the
production fluid.
Construction support 349
AIR/NITROGEN DRYING OF
PIPELINE
Foam pig trains may initially be run to act as swabs, removing any condensed water from
the walls and push any liquid out in front of them.
Then warm dry gas is delivered to the inlet. Either air or nitrogen is used. The latter is
an inert gas so has the advantage for hydrocarbon lines in that we can safely introduce
gas without fear of explosion.
The picture shows BJ process air drier unit. This can deliver -73°C (-100°F) dewpoint
air which is used to achieve extremely low dewpoints during pipeline drying.
As the differential dew point readings reduce, the drying process is completed. It is
common to achieve a final dewpoint of -20°C (-4°F).
This is a rapid process, but which may be followed by additional vacuum drying.
350 Overview of pipeline engineering
VACUUM DRYING
A B C D
0
0 Drying Time 30
(days)
Vacuum drying means attaching vacuum pumps to one or both ends of the pipeline and
drawing a vacuum. It is only used for gas lines where water vapour would be a problem.
If you reduce the pressure above water, you also reduce its boiling point. An example of
this is that mountaineers find that water boils at less than 100°C (212°F) at altitude, and
consequently boiled eggs take longer to cook.
Inside the pipeline, the pumps reduce the pressure to the point where water will boil at
(say) 4°C (39°F), or whatever the ambient temperature is. The drawdown curve flattens
as the water vapour comes off.
The finishing process involves stopping the pumps and checking whether the pressure
rises. As the pipeline reaches that of the seawater, further vacuum will freeze ice crystals
on the inside of the wall. Thus the air will initially appear to be fully dried. However, by
releasing the vacuum slightly, these crystals will melt. Only when all the water is
converted to vapour and removed from the system will the graph stabilise.
It only works where the line has already been dried using other means. Puddles of water
take a very long time to clear. If necessary at pig traps, valve chambers etc, it may be
possible to enter the line and remove standing water using squeegees.
The process can last for 4-12 weeks, depending on the pipeline size and length.
For this reason and the costly delays, it is avoided wherever possible.
Construction support 351
PRE-COMMISSIONING - SUMMARY
Prepare documentation
Hydrotest
Flood
Pressurise
Dewater
Flush out with nitrogen or product
Dry – swabs and air dry
Vacuum dry for sour gas or consumer gas line
Any questions?
Then the pipeline will be hydrotested to ensure its integrity. The hydrotest procedure is
shown above. Initially the pipeline is flooded with water and then pressurised.
Then the hydrotest water is removed either using nitrogen or the product. If the
product is to be gas it may be necessary to dry the line using swabs or warm air. The
costly process of vacuum drying is needed for certain gas lines.
CONSTRUCTION SUPPORT -
SUMMARY
Any questions?
352 Overview of pipeline engineering
The basic aims for landfall construction are to protect the trench through the beach area
whilst avoiding flooding of the land. Once the pipeline is brought ashore, it is buried
deeply to protect it in the surf zone. It is one of the few times that a trench is normally
preformed prior to laying the pipeline.
The reasons and main methods for the trenching and burial of pipelines on the seabed
have been covered. The amount of seabed soil to be removed with post-lay trenching is
much less than for pre-lay because the position of the pipeline is known. The methods
to protect umbilicals are similar, though smaller plant is used.
Tie-ins, spools and risers
Tie-ins, spools and risers 355
EXPECTATION
EXPECTATION
Connecting in pipelines to
topsides jacket or floating host
Flanges and hub connectors
Spoolpieces and jumpers
Installation of rigid risers
Flexible risers
Spoolpieces and risers are needed to connect the pipeline to the platform or FPSO.
The usual method for linking between the pipeline and spoolpiece is using flanges.
However, other proprietary systems are available.
Spoolpieces are required to connect between the end of the pipeline and the riser or
wellhead.
Subsea pipelines are normally allowed to expand on the seafloor. This is in contrast with
buried onshore lines with thrust blocks to resist movement.
The length of the spoolpiece is kept as short as possible to enable it to be lowered into
position without damage yet long enough to take up the expansion in bending. For this
reason, it is common to use L, U or Z shaped thick-walled spools with formed 5D (or
gentler) bends.
When connecting the spool to the end of the pipeline, it is possible to use either
standard API weld-neck flanges mated with a swivel ring flange. The swivel permits the
bolt holes to be aligned without applying torque forces. The seal is made using a soft
iron ring (either oval or hexagonal in cross-section) fitted into a standard groove in the
flanges.
Tie-ins, spools and risers 357
Metrology
Measure spool length and four angles for flanges
Fabricate on deck and lower to seabed
Use of flanges or connectors
Commonest method
Flange leaks at make-up, testing or operation
Not too loose nor too tight – crushing of seal
Lifted and welded at barge
Shallow water only
Hyperbaric welding – dry habitat on seabed
Used in North Sea and Australia
Divers first need to measure the spoolpiece distance and the angles (vertical and
horizontal at both flanges) between the pipeline and riser ends.
This is then reproduced on the deck of the workbarge and pressure tested prior to being
carefully lowered the seabed.
Flanges or connectors are then made up by the divers. This is by far the commonest
method.
However, flanges can and do leak. The force on the bolts needed to draw the ends of
the spool up (accounting for any mis-measurement) and make the seal is undertaken
once. This then usually must serve for the hydrotest and operational conditions with no
further adjustment. The pressure at hydrotest can make the pipeline and spool move
and is greater than will be experienced in normal operation. For hot lines, the final
condition may mean further movement. It is important not to undertighten the bolts
nor to overtighten and crush the soft iron seal.
Jee Ltd was called in to investigate a problem with flange leakages during a spoolpiece
installation. Concern was raised by the client as to whether the seal obtained on
hydrotest would leak further when the higher temperature and lower operational
pressure were imposed.
There were many possible causes suggested, including the arrangement of the spool
lengths, the thickness of paint on the flange faces, the out-of-specification dimensions of
flanges and bolts, the material grade of the gasket and flanges, the sub-contractors’
experience and their actual tightening procedures (which differed slightly from those laid
down).
Subsea, it is common to tighten the bolts once at make-up. They should initially be
tightened to leave a residual tension of just under half their yield. This single operation
should then maintain the seal during the hydrotest and operational phase with no further
adjustment. During make-up, there is no internal pressure and ambient temperatures,
but there may be some mis-measurement (angular or axial) or fabrication tolerance of
the spoolpiece and flanges, which needs to be pulled in. At hydrotest, the internal
pressure is the highest it is likely to experience but there is no increase in temperature.
Spoolpieces may move from their initial position; flanges may rotate slightly and pull
apart. For the operational phase, temperatures may cause expansion of the pipeline and
further movement may occur.
The conclusion reached following analysis was that the cause was related to the method
of holding the gasket during tightening operations. The gaskets were located within
locally-made skillets to ensure they aligned with the flange grooves. The skillets’ inner
holes were not concentric within the rims. Because they did not hold the gaskets
centrally between the bolts, the gaskets were crushed during the initial make-up
operation. At this stage, the bolting up procedure using bolt tensioners caused over-
tightening and crushing of the soft iron.
Leaks were detected during the hydrotest and this then resulted in individual bolts being
‘flogged up’ further with no regard to equalling out the load in each. It is suspected that
this operation caused some of the bolts to yield, as well as further deforming the gasket
seal.
Tie-ins, spools and risers 359
The solution was to renew the gaskets, skillet and bolting, and to revisit procedures to
prevent a recurrence.
DIVERLESS CONNECTION
METHODS
Divers are often used to connect a rigid pipe spoolpiece from the bottom of the riser to
the end of the pipeline. However, divers cannot work in the deepest water.
Diving is at its absolute limit at 300 m (984ft) water depth using saturation methods.
Normal safe maximum operating depths are less at 200 m (656ft). This range covers
most of the fields in the waters around the UK and the North Sea.
Diverless systems originally developed for deep water are now also used in diving
depths.
360 Overview of pipeline engineering
WHY DEEPWATER
The world’s shallow water oil and gas reserves have been developed. The continuing
demand for oil is driving the need to develop more difficult reserves in deeper waters.
There are considerable deep water reserves in the Gulf of Mexico and other parts of the
world, and we are seeing rapid technical advances being made so that these reserves can
be exploited.
WEST AFRICA
Similar story
elsewhere
Offshore
West Africa
Girassol, Angola
Bonga, Nigeria
120·106 m³
(750 MMboe)
Courtesy of
Van Oord ACZ
Tie-ins, spools and risers 361
Offshore West Africa is another area of considerable deep water reserves and we are
seeing much activity in this region.
NWECS (UK)
Southern
Caspian Sea
Eastern
Southern CA Canada Egypt
GOM
Nigeria
Equatorial Indonesia
Guinea Angola-
Campos Congo
Gabon
Basin
Namibia
South Africa
The above map – produced by Offshore Magazine and Mustang Engineering – shows
where the major deepwater basins lie and where future developments may take place.
Current development areas are named in yellow with new and future regions indicated in
red. The white area offshore of California is now deemed a former area.
Where:
■ NWECS (UK) = Northwest European continental shelf (United Kingdom)
362 Overview of pipeline engineering
WHAT IS DEEP?
However, not everyone agrees with this arbitrary definition of deep at 1000 m (3300ft).
Flexible riser manufacturers, ROV buoyancy suppliers, fishermen, sport and commercial
divers all have different views. This also changes around the world.
DEEP PIPELINES
0 0
1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 Year
This figure illustrates the advance in deep water pipelines. The axes show difficulty, here
defined as water depth x diameter and plotted by the year. We can see that currently we
are going through a period of rapidly increasing difficulty.
Tie-ins, spools and risers 363
Along with deeper pipelines, we have correspondingly increased depths for platforms
and associated risers.
Principles: Alignment
Necessary methods:
requirements Flexible jumper
Reversible connection Rigid pipe spool
Retrievable seals
Straight pull-in
Often desirable
Deflect-to-connect
No hydraulics remaining
on seabed Example systems:
Preferably one ROV trip DMaC
Self-seal on opening
KOSCON
Pressure balanced
Testing of seal
MATIS & UTIS
BRUTUS
For diverless connection of spoolpieces to connect the end of the pipeline to the bottom
of the riser there are a number of principles common to all methods.
The two essential principles are that the connection can be reversed if something goes
wrong and that any seals can be retrieved and replaced if they become worn or damaged
during the installation or during subsequent operation.
It is also better if we leave as few hydraulic parts on the seabed as possible. After a
number of years, these will almost certainly cease to function and cannot be serviced. If
there are a number of connections to be made, then it is preferable that all go down to
the seabed at the start of operations. The ROV can pick up the necessary part when
needed. It takes a long time for an ROV to be recovered to the surface to have a new
tool or part added and then return down to the seabed. If possible, any hose fittings
should self-seal when the connection is opened and such items should be pressure
balanced to avoid large make-up forces. Many systems are able to test the seal prior to
the hydrotest.
There are four basic methods or configurations for making subsea connections, as listed
above.
Note that these methods apply to both diver and diverless connections and tie-ins. The
basic principles of connection (reversible connection and retrievable seals) again apply to
both diver and diverless connections. However, they are more technically challenging
and costly to achieve for a diverless system.
364 Overview of pipeline engineering
Flexible spool
Wire pull-in - flexible flowlines
Fly-to-place - umbilicals and cables
Direct pipe pull-in - no thermal expansion
Only at one end of the pipeline
Rigid flowline spool - accurate fabrication
Spool pull-in - joint made at seabed
Deflect-to-connect - joint made at seabed
J-tube pull-in - joint made at top
Rigid or flexible spool with vertical stab
Installed on guide posts
Where thermal expansion of the pipeline is not a consideration, the pipeline itself can be
pulled directly into the manifold structure either using diver or ROV intervention and
the topside vessel crane. This method can only be used at one end of the pipeline.
In contrast to flexibles, all rigid spools require accurate measurement and fabrication, in
combination with an alignment system that can apply considerable force to bring the
ends together.
Three methods can be used for the initial alignment of a rigid spool. A direct pull-in can
use wire (as for the flexible) or rams on the ROV tool. Deflect-to-connect makes use of
buoyancy on the line to reduce seabed friction and wires bring the ends together. We
will examine the J-tube method in the Risers module.
Rigid spools can also be made up using vertical stab-ins at either end. These spools are
an inverted U shape and are aligned using guide post systems.
Tie-ins, spools and risers 365
4 Remove
pullhead
The DMaC connector is extensively used in the West of Shetlands in the north of
Scotland. The procedure follows that shown on the previous slide. It is used for both
rigid and flexible pipeline spools.
Other proprietary designs exist that do not require as accurate a rotational alignment of
the end of the pipeline. However, they operate on similar principles.
The picture shows a DMaC manifold unit containing a number of connection ports.
366 Overview of pipeline engineering
DEFLECT-TO-CONNECT AND
VERTICAL STAB
Risers on
fixed platform
Vertical
stab lowered
Set down of Pull-in wire into place
rigid pipe end
within tolerance
Deflect-to-connect
rigid pipeline
with buoyancy and chains
Deflect-to-connect can be used with the ends of rigid pipelines. Even large diameters up
to 914 mm (36in) have been installed in this way.
Pipelay initiation must ensure that the end sits within a rigid target box. The weight of
the pipe is minimised using buoys and chains. A wire pulls the end of pipe over to the
riser. The ends are finally connected using collets or clamps.
Care must be exercised when recovering the buoyancy modules, since without the
weight of the pipe, they surface rapidly.
Vertical stab-in risers can be lowered down using barge or platform cranes. An ROV
helps guide the spool onto the ends of the riser and pipeline.
Tie-ins, spools and risers 367
Collet Clamp
For deepwater developments, dedicated remote pull-in systems have been designed.
They may utilise diverless technology such as collet connections or clamp and hub
systems combined with retrievable pull-in tools. Alternatively, lightweight or standard
flanges may be used. These require much larger equipment to install the bolts and
tighten the nuts.
In all cases, as much of the equipment as possible is recovered for use on the next
connection. Ideally, only the connectors themselves should remain.
Collet connector Collet connector Connector assembly hinges ROV makes hot-stab
assembly is lowered on assembly lands in over to make up and test
flexible or rigid flowline receiver pyramid during pipe lay-away connector assembly
It was originally perceived to be easier to use vertical stab-ins because these can be
lowered into place.
This slide illustrates the vertical stab and hinge-over system used for initiating and
connecting the first end of a flexible pipeline.
DIVERLESS INSTALLATION
DIVERLESS INSTALLATION
Vertical spool
1
Easier to lower and align
Both ends connected together
Minimises makeup forces and
moments at ends
Requires hinged PLET
2 3
This sequence illustrates the vertical stab subsea tie-in being made.
Vertical spools are the common method used in the Gulf of Mexico where trawling snag
risk is low.
It is much easier to lower the spool and connect up both ends in one operation.
Provided the metrology has been undertaken carefully, the make-up forces and moments
are almost eliminated. However, the pipeline must be laid with a vertical bend on a
hinged pipeline end manifold (PLET).
One problem associated with diverless rigid spool tie-ins is misalignment of the
connection hubs.
The Big Inch articulated connector illustrated above allows for up to 5° of misalignment.
Connection is first made using funnel and guide post, then the seal is made by drawing
the ends together using a clamping mechanism. The seal can be pressure tested prior to
commissioning.
FLANGE MAKE-UP
MATIS system
Lightweight or
standard
flanges
Minimum
equipment left
on seabed
The above slide shows the MATIS (Modular Advanced Tie In System) diverless make-
up system, which can effect subsea diverless connections utilising a variety of connection
systems.
The system operates by aligning the ends of the pipes using conventional remotely
operated pipe handling frames to bring the flanged ends within the flange alignment
frame.
Once final alignment has been achieved and a gasket has been inserted, the flange faces
are brought together and a cassette compatible with the flange type is lowered into the
frame. This cassette inserts the studs into the bolt holes in the flanges and then runs the
nuts onto the studs.
When each stud has a nut on it, the whole assembly is tensioned up to the particular
flange’s specific requirements.
One advantage of MATIS (or other similar systems such as BRUTUS) is that only
normal bolted flanges remain at the seabed.
Tie-ins, spools and risers 371
We have covered the main approaches to connecting the end of the pipeline to the riser.
These are usually connected with standard flange and a swivel ring flange.
However, there are certain times when the pipeline and spool are lifted and welded
above-water. In some parts of the world, hyperbaric welding is undertaken by divers.
In deep water, beyond the limits for divers, we have to use reliable systems. The main
principles for these were listed.
There are normally two stages in connecting spools: there is the initial alignment which
brings the end within the reach of the tool, and the final make-up when the seal is made
between the hubs or flanges. These stages are sometimes referred to as soft landing and
hard landing.
RIGID RISERS
Anchor flange
Design as for pipeline
Watch for:
Guide
Thicker wall
5D bends
Hang from top, free at base
ESDV and SSIV Guide
Splash zone corrosion protection Space to
Site for pig traps, facing out to sea flex down
The pipe wall thickness design for a riser is fundamentally similar to that for the pipeline
in terms of meeting pressure containment, bending, and hydrostatic collapse
requirements.
■ Splash zone corrosion can be problematic in that the area is wetted, exposed to
oxygen but not protected by the cathodic protection system. Elastomer cladding is a
typical solution.
■ Pig traps usually face out to sea to cater for the unlikely event that they eject a pig.
■ Riser fatigue is invariably a big issue, and we consider it in detail.
■ Subsea isolation valves (SSIVs) are not compulsory on non-gas lines but are often
installed up to 500 m (1640ft) from the jacket. They may be a ball valve for an
incoming line or a non-return clapper valve for an export line.
RETROFIT RISERS
When retrofitting risers to a jacket, there are additional issues to consider. The first is
whether there was any provision at the construction stage to put in spare risers, or J-
tubes, or conductor slots, or riser support brackets. If so, the retrofit riser can make use
of these.
One point to note is the slenderness of the riser, and the inherent difficulties in lifting
and upending without overbending it.
374 Overview of pipeline engineering
J-TUBE
A J-tube is typically a 508 mm to 762 mm (20in to 30in) tube with a 30D bend. Through
this a small diameter (102 mm to 324 mm or 4in to 12in) rigid steel (or flexible) riser may
be pulled up. In pulling up the J-tube, the rigid steel riser will be yielded round the bend
and then yielded straight again as it is pulled in.
Because the annulus between the J-tube and the riser itself cannot be easily inspected, it
is common to seal the bottom end with a plug and fill the annulus with inhibited water.
The photograph shows a typical sealing plug (black and yellow) slung on a lifting clamp.
The picture shows a finite element analysis of a J-tube installation undertaken by Jee on
the Nuggets Field Development. Not shown in the analysis is the bell mouthed orifice
at the bottom end, which aids location of the riser in the J-tube.
Tie-ins, spools and risers 375
Flex joint
Pipeline
High bending
≈ 20% at touchdown
Stress
Yield
Bending
(without
flex joint) Total
Stress Bending
Weight
The above diagram illustrates the shape of a steel catenary riser and the associated
stresses. The riser is simply a steel pipe hung from the vessel to the seabed. Compared
to the length of the span, the pipe stiffness is small and the behaviour of the pipe
approximates to that of a chain, hence the term “catenary”. However, in practice this
type of rigid riser is highly stressed/fatigued at the flex joint and at the touch down
point, yet lowly stressed over the majority of its length.
Firstly, let us look at the stress and fatigue characteristics of the riser. The stress pattern
is a function mainly of its self-weight and bending as shown in the graph above. For the
majority of the riser, the stress and fatigue levels are low. At the top, high bending
stresses would result if there were a rigid connection to the vessel. Therefore a flex joint
is introduced (see subsequent slide) which also serves to relieve the bending fatigue due
to wave loading.
At the touchdown there is a region of high bending and high fatigue. The fatigue is
caused by a magnification of the vessel motions at the touchdown; i.e. if the vessel
heaves a distance x, the touchdown point moves a distance many times x. Titanium pipe
is sometimes used in this area (see details below).
376 Overview of pipeline engineering
FLEX JOINT
With flexibles, bend stiffeners are used to avoid over-bending of the riser.
Steel pipes in themselves have a much greater rigidity than bend stiffeners and the length
of such stiffeners is limited, so they cannot provide enough protection to rigid steel
risers.
Instead, rigid steel risers are typically fitted with flex joints at the vessel. This permits
limited angular movement with a low bending moment.
Using flex joints avoids fatigue failure at the vessel, but checks are needed that the
remaining length of the riser is not over-bent.
Fatigue at the touchdown point tends to dominate the design life of such risers. Careful
modelling of the soil-pipe interaction is needed. In strong currents near the surface but
below the wave action, vortex-induced vibration (VIV) fatigue may also be an issue.
Tie-ins, spools and risers 377
TOUCHDOWN POINT
Laydown
Lift
At the touchdown point, the vessel motions are amplified due to the shape of the
catenary. Sending the touchdown point backwards and forwards over the seabed tends
to form a trench. This was replicated in the tests above, and the resultant increase in
force to lift the riser out of the mud is shown in the graph.
Rails running 10 m (33ft) along the harbour wall allowed the trials to include lateral
pullouts of the pipe. The graph shows the best technique for identifying the soil suction
effect. It relies on comparing a riser lift-up with a lay-down. The lift-up will feel the
suction forces, the lay-down will not. By reversing the lay-down data and placing it on
top of the lift-up, the suction effects can be estimated by the difference in the curves.
One particular point to watch for is the generation of compression waves in the riser if
the vessel heaves faster than the riser is able to freefall through the water. This can
cause buckling and/or a whiplash effect at the touchdown point.
378 Overview of pipeline engineering
Stakes or
fairings
A&R wire
Buoyant
section
Pull head
Recovery
wires
Pull head
Tie-ins, spools and risers 379
When the host vessel arrives and moors, it attaches a wire to the riser end, and winches
it under the turret.
The riser is pulled further into the FPSO and a dry connection made on the turret. (The
turret allows the vessel to weather vane without twisting up the moorings and risers).
Some FPSOs have the turret at the bow. In areas with a predominant current, wave and
wind direction, it is not necessary to have turrets. In this case, the SCR is brought along
the side.
SCR RECOVERY
SCR docking
off platform
FlexJoint
Monkeyface
Two pull wires
Two pullwires and a monkeyface are used to maintain sufficient touchdown tension to
prevent buckling.
380 Overview of pipeline engineering
TENSIONED (RIGID)
Tensioned risers are primarily used in conjunction with ‘floating’ facilities such as the
tension leg platform illustrated, semi-submersible drill rigs and production platforms
(e.g. Buchan) and drill ships. The riser response to wave and currents loads and to
vortex-induced vibration (VIV) is controlled by the application of tension.
Pros Cons
TLPs and spars More weather
Bigger diameters sensitive
Greater pressures Taper stress
and temperatures joint required
Can do localised Complex
repairs anchor base
Used for drilling, Host above
completion and well template
workover operations
Production and
export risers
Tie-ins, spools and risers 381
The above slide summarises some of the benefits and problems associated with vertical
tensioned steel risers. These are usually used on hosts such as TLPs and spars where the
well template is immediately below the vessel.
Because the riser is vertical and under high tension, the riser is essentially in a fixed
location so it is possible to undertake inspection and repairs.
The same configuration can accommodate all types of operation as well as production
and export.
The high tension needs to be resisted by additional fixity to the seabed through the
casing grouted to the upper layers of soil. Moments at the base demand a taper stress
joint and a complex base design.
MARS TLP
20 wells
Risers assembled using Well
pipes
drilling derrick
Tendons
Proprietary connectors
Lowered and fixed to 20 wells
template anchorage Piled
bases
The Mars tension leg platform is designed for deep water drilling. It is built to withstand
the winds and heavy seas of hurricanes. Mars drills wells and processes oil and gas from
its own 20 wells as well as flowlines from other well clusters.
In addition to the risers, there are 12 flexible tendons (3 at each corner) which move
with the sea but firmly anchor each pontoon of the rig. These tendons are linked to
piles in the seafloor some 900 m (2940ft) below.
The Derrick is used to assemble the risers which are made up from standard lengths
with proprietary connectors. Once at seabed, the taper joint is connected to the
anchorage and the tension is transferred to the floor.
382 Overview of pipeline engineering
Hybrid Risers
HYBRID RISERS
Buoyancy
Export lines
Flexible from
FPSO to SPM
risers
Rigid
riser
tower
Control
Girassol field umbilicals
with hybrid risers
and flowline bundles
Hybrid risers involve a combination of tensioned rigid and flexible pipe. The example
above shows the rigid pipe used for the (long) vertical portion and the flexibles attaching
from the top of that vertical portion in a catenary to a floating production vessel.
Hybrids are seen as a potential deep water solution, where the use of flexibles is limited
by the weight of the flexible being held at the top. The rigid part of the system is limited
to the lower depths where the hydrodynamic loadings are low.
The export monobuoy Single Point Mooring (SPM) enables visiting tankers to
‘weathervane’ around it, thus minimising wind and current forces acting on the vessel.
Tie-ins, spools and risers 383
Subsea swivels
Flexible
risers
Rigid
Articulated tower
joint
Girassol risers
Courtesy of
Acergy
An example for a more benign West African environment is the Girassol configuration
above. Here a cost-effective solution is obtained by spanning most of the 1400 m
(4600ft) water column with tensioned (by buoyancy) steel risers, and spanning a short
step from the top of the tower to the moving vessel with flexibles.
The floating production storage and offloading (FPSO) ship is used because it is more
economical than a fixed platform in deeper water.
Interlocking syntactic
foam blocks
The riser towers were assembled on the beach in the manner of the wet bundles used for
the flowlines to the wellhead manifolds. They were then towed out to the field.
384 Overview of pipeline engineering
There, they were pulled down to pre-prepared fixed bases. Connections at the seabed
were undertaken by ROV. The flexible sections between the flotation unit at the top of
the towers and the FPSO was completed using divers.
Any questions?
Traditionally, rigid steel pipe risers are slung from the platform topsides and held
between guides on the jacket legs. Small flowlines may be pulled directly into a J tube.
The end is sealed to prevent hidden corrosion.
Steel catenary risers to floating facilities usually have a flex joint at the top, but care is
needed at the touchdown point to avoid dragging the pipeline laterally out of the groove
in soft sediments.
Top tensioned risers are lowered from the vessel with connectors joining each section.
The bottom end is subjected to high bending stress, necessitating the use of a taper flex
joint at the seabed.
On the Girassol project, where due to the depth of the field, it was necessary to make
use of ROV connection systems at the seabed. A rigid bundle section was used from the
seabed to diving depths. This is able to move slightly, but currents and wave action
means that this section remains almost fixed. The riser pipes are insulated and buoyed
throughout their length but have a large buoyant unit at the top. From here to the
FPSO vessel, flexibles were used. They could be connected using divers and were better
able to resist the wave and current action near the surface.
Tie-ins, spools and risers 385
Flexibles of a given diameter contain more steel than the equivalent rigid line. Due to
their complexity of manufacture, they are inevitably more expensive to make than rigid
lines - so why use them?
As the slide indicates, the primary driver to develop flexibles was for dynamic risers
which connect a static pipeline to a vessel or some other facility that is moving on the
waves. Rigid lines are not capable of performing this function.
Other applications for which they prove cost effective are jumpers (spoolpieces between
wellheads and manifolds) or integral flowlines, where the flexible can run from the
production facility all the way to the manifold or wellhead without any joins. The latter
two are often cost effective due to their rapid installation.
A flexible may be ten to twenty times the price of a rigid steel line but the installation
vessels will be considerably cheaper. The purchase/installation cost ratio for rigid is
30%/70% whereas flexibles the ratio is reversed - 70%/30%.
386 Overview of pipeline engineering
Pressure (ksi)
600
Pressure (bar)
6
400
3
200
0
0 100 5 200 10 300 15 400 500 20
Internal diameter - bore mm (inch)
Flexibles also cover the complete range of requirements for deep water, and are being
evolved to address deeper and deeper applications as such fields are developed. The
largest flexibles to date are 483 mm (19in) inside diameter. One has been developed by
Technip for the Bonga export pipeline.
The picture shows Wellstream’s gas lift umbilicals (GLUs) riser flexible. This consist of
a number of individual bore, gas lift lines surrounded by the structural and protective
layers.
Where additional insulation is needed a foamed tape is wrapped helically around the
flexible prior to the outer protective seal layer.
Smooth bore flexibles can be used on non-gas services (such as oil or water injection).
Because they have a smooth plastic inner bore, they offer less resistance to flow.
However, should the product contain gas or dissolved gas, it will be necessary to have a
steel carcass on the inside of the plastic. Gas naturally permeates through the plastic at a
low flowrate due to diffusion. Should the bore be vented, the build up of gas outside the
plastic tube could have sufficient pressure to cause it to collapse, which would ruin the
pipe. The carcass acts to prevent such collapse and renders the flexible a ‘rough bore’.
The carcass is generally made of 316 stainless steel flat strip, which is bent and
interlocked to give a layer resistant to external pressure.
388 Overview of pipeline engineering
For high pressures (i.e. most in-pipeline applications) a separate pressure vault layer is
needed to withstand the pressure loads as shown in the left hand picture. For low
pressures, the tensile armours can be wound at the ‘magic angle’ of 55°, which is ideal
for the dual function of resisting tensile and hoop pressure loads without twisting. The
angle is a result of the hoop stresses being twice that of tensile stresses when resisting
internal pressures.
DYNAMIC OR STATIC
STATIC DYNAMIC
For risers, which are a dynamic application where the pipe is continually moving and
thus the layers are continually rubbing over each other, it is necessary to have anti-
friction layers as shown on the right. Note that it is not possible to change from one
Tie-ins, spools and risers 389
structure to another without an end fitting, so if a pipe is to form a static flowline and a
riser in one length, then it must all be made to a dynamic specification.
NORMAL DEEPWATER
Plastic sheath
Carcass
For normal water depths, the Zeta layer (or equivalent layer for other manufacturers) has
sufficient bending strength (EI value) to resist hydrostatic collapse.
For deep water, a greater EI (or stiffness) value is needed, as offered by the Teta design
(amongst others).
MYTHS DISPELLED
End fittings
Gas permeation
Hydrolysis
Damage
Integrity
monitoring
Gas released
and monitored
Phoenix Beattie
unflanged end
Installation Analysis
Having established the different riser configurations and cross-section designs, we will
now look at flexible riser analysis: the computer prediction of the response of risers to
wave and vessel motions. This will cover the following:
■ Static analysis to find mean configuration and response to currents and vessel drift
■ Dynamic analysis to find response to waves and vessel motions
■ Software to carry out the analysis
■ What to do if the riser is outside its capability
392 Overview of pipeline engineering
STATIC ANALYSIS
Inputs Excursion
Flow Ebb
Riser weight, stiffness Tide
The above slide lists the inputs, load cases and outputs for a riser static analysis.
It is normal to first determine the boundary envelope for the shape of the riser
considering the above input forces. Remember, that this will be in 3D rather than 2D
shown above.
At this stage minimum and maximum tensions, vessel and anchor loads may be found.
DYNAMIC ANALYSIS
It considers the full response of the vessel and riser to a regular wave train. If this
analysis proves acceptable, a simulated random wave set may be used for more detailed
work.
Either time or frequency domain analysis may be used depending upon the power (and
cost) of the computer.
We can now determine whether a pair of risers are likely to clash and cause impact
damage.
Compression waves can be a concern. This can be likened to a whip effect, where the
wave, initiated by the vessel dropping into a wave trough, travels down the flexible riser
until it reaches the seabed. At this point, the riser crushes and is damaged.
Fatigue of the wires in a riser can be a problem where there is an inadequate bend
stiffener at the surface or the curvature of the riser at the mid-water arch or the seabed.
This causes repeated bending in the wires and eventually fatigue of the riser.
SOFTWARE
The above software can be used for both static and dynamic riser analyses.
394 Overview of pipeline engineering
The above animation shows the motions of a flexible riser passing over a mid-water arch
and spanning up to a vessel. The waves not only put lateral loads on the riser, they also
make the vessel and arch move.
REMEDIES
What can be done if the riser is overbent, or clashes, or is in some other way deemed
unsuitable by the static or dynamic analysis?
■ Make the pipe denser, increasing its inertia to drag ratio. This generally improves
the dynamic response. If the riser is too light, it may not ‘fall’ through the water as
fast as the vessel, leading to compression waves as the vessel heaves.
■ Adjust the riser configuration to one more suited to the conditions (see previous and
following slides for descriptions of configurations).
■ If the problem is overbending at an end termination then add a bend stiffener. The
picture shows two bend stiffeners. Their purpose is to support the riser as it arcs,
such that it deflects over a longer length and does not lock-out or overstress at the
minimum bend radius. Bend stiffeners need to be analysed carefully.
CONFIGURATIONS
FPSO
Top stiffeners
prevent overbending
Protection needed
against wear
at touchdown
Bend stiffeners on catenary
risers beneath a platform
The free hanging catenary riser is the simplest flexible riser configuration. It is only
suitable for moderate environmental conditions or for set-ups with negligible heave
motions such as on a Tension Leg Platform (TLP).
Bend stiffeners are increasing in length. They may be up to 14 m (46 ft) long.
S RISER
FPSO Locating
clamp
Top stiffeners
Mid-water
arch
buoyancy
Arch units
Steep-S Lazy-S
Tethered Tether
clamp
Clump weights Clump
base
The S-configuration riser is good for satellite tie-backs, where vertical access from FPSO
to a drilling template is not necessary.
Tie-ins, spools and risers 397
The mid-water arch is produced by a single buoyancy unit anchored to the seabed. A
number of risers can pass over a single buoyancy unit, which fixes their separation
relative to each other. The configuration gives very good dynamic response but arch
behaviour may restrict its use in shallow waters; that is, less than 90 m (295 ft).
The steep-S configuration is particularly good for multiple riser situations where seabed
space becomes restricted.
The locating clamps hold the flexible centrally in the buoy. The two trumpets prevent
overbending of the pipe during installation. An appreciation of the size of the mid-water
arch is given by the photograph of the two men stood within the CRP unit (produced by
Trelleborg).
WAVE RISER
Top stiffeners
Distributed
buoyancy
modules
Steep Lazy
wave Bottom wave
stiffener Clamp sections for Titanium band
Clump weight fixing to flexible and bolts
CRP advanced fixing system
for distributed buoyancy
The lazy wave riser is good for deep water diverless installation. Dynamic response is
very sensitive to cross currents due to lack of any anchoring. This riser configuration is
not recommended if a large number of individual risers must be accommodated within a
single anchoring sector.
The steep wave configuration is good for congested seabed developments. However it
is limited to single or well separated lines. The steep wave gives a very good dynamic
response.
When fitting the buoyancy, it is now common practice to use a GRP-epoxy clamp with
Kevlar or titanium banding rather than steel clamps with long bolts (see the tethered
clamp on the compliant wave).
Titanium has a lower Young’s modulus and greater strength than stainless steels so
permits the flexible to expand during operation whilst keeping sufficient tension to hold
the clamp.
398 Overview of pipeline engineering
BUOYANCY
FPSO
Technip
development
Top stiffener Hybrid between lazy
wave and steep wave
Distributed
buoyancy Advantages of lazy
modules
wave
Dynamic
Pliant
behaviour
wave Tethered
of steep
clamp wave
Clump weight Bottom
tethered
clamp
Technip has developed the compliant wave riser. This was used at the Foinaven
development in the West of Shetland (WoS), north of Scotland.
Tie-ins, spools and risers 399
This hybrid combines the advantages of the lazy wave with the dynamic behaviour of
the steep wave. The position of the lower tethered clamp means that the length of the
flexible on the seabed can be laid in any direction.
MULTIPLE RISERS
SFPS vessel
Compliant wave
Footprint of risers
Compact at vessel
Fans out
Compact at wells
Easily installable
Non-clash
The figure shows a semi-floating production system (SFPS). It has catenary anchor
cables with multiple compliant lazy wave risers. The tails of the risers are brought
together on the seabed directly beneath the vessel.
By fanning out, the risers can be designed not to clash with each other or the vessel’s
anchor cables.
400 Overview of pipeline engineering
COMPLIANT-S RISER
FPSO
Technip development
Controls riser touch
Top stiffener down behaviour
Mid-water
Shallow waters and
arch harsh environmental
buoyancy
conditions
Bend
restrictor Tethers
Technip has also developed and patented the compliant S riser. This improves on the
lazy-S characteristics by controlling the behaviour of the riser at the touch down point.
It is very effective in shallow waters and harsh environmental conditions.
The photograph shows installation of a flexible fitted with a bend restrictor. In this
instance it is used to limit bending radii adjacent to an end manifold. Trelleborg
manufacture the Linksyn units used for bend restrictors. Restrictors do not permit the
flexible to be bent to a tighter radius than that specified.
The critical water depths where one option gives way to another will depend upon the
environmental loadings, the response of the vessel and the number of risers (their
dynamic envelopes must not clash with each other).
Any questions?
Flexible pipelines are unbonded layers of wire and plastics, each contributing to the
behaviour of the whole.
Different arrangements of these layers are required for the particular requirements or
usage of each flexible.
It is necessary to consider the total cost of supply and installation rather than just the
initial cost of purchase, which is much more than for a rigid steel pipe.
However, flexibles are usually limited to flowline sizes because of the strength of the
various layers.
We examined various problems with flexibles and how they have been solved.
Any questions?
Typical methods of installing tie-in spools and risers have been reviewed.
The options for connecting the pipeline to the spoolpiece will depend on the water
depth, but traditional flanges are commonly used.
The risers can be either made using rigid steel pipe or flexible pipe. The method of
manufacture of flexibles has been covered.
Introduction to integrity
Introduction to integrity 405
EXPECTATION
EXPECTATION
We aim to keep the number of incidents to a minimum and operate the pipeline safely
for as long as possible.
The best way of doing this is by setting up a pipeline integrity management system
(PIMS). We examine what it should include and how it should be operated.
406 Overview of pipeline engineering
BATHTUB CURVE
Design mistakes
Construction incidents
Inherent defects
Number of failures
Component replacement
Wear and tear effects
Pipelines are like any other mechanical or electrical component used in industry.
Initially, there is a high rate of failure. Some of these are due to mistakes made by the
designer or the interpretation by the supplier, fabricator or contractor. These inherent
defects with the pipeline system have not been detected by the assessment or inspection
regime.
Gradually, though, the rate of failure drops to near zero, and for most of the pipeline’s
life it remains reasonably stable. Events are often as a result of third party failures or
damage – perhaps adjacent equipment may suffer a failure and impact on the line or
fishing interaction with a pipeline.
Eventually, however, the equipment wears down or corrodes away through old age.
This even applies to us as our teeth fall out and joints creak.
Even when the defect is found, it may not be easy or convenient to repair. When a
component is replaced, unexpected changes may occur because the part is slightly
different from what it has replaced. The adage, “If it ain’t broke, don’t fix it” has some
truth to it.
Introduction to integrity 407
Below are just three incidents showing events at the three stages of the bathtub curve.
We include them to make people aware of some incidents that have happened – after all,
it is better to learn from others than suffer from our own mistakes.
Lead-lined pipeline
Second world war
Pressurised laying
Hydrostatic collapse
Low through-put
Increased pumping pressure (re-inflated line)
The PLUTO lines were laid during the second world war to supply petrol (gasoline) to
the allied forces for the re-occupation of France. Two types of different cross-sections
were used: codenamed the HAMEL and HAIS.
The former was rigid steel pipe, laid using floating drums, whilst the latter was the first
use of pipeline reel lay vessels. HAIS line was based on telegraph cable technology but
with the inner core replaced by continuously-cast lead pipe. Trials showed that it needed
to be laid whilst pressurised to offset hydrostatic collapse.
The final specification of the HAIS pipeline shown above was for a flexible pipe
comprising an inner lead pipe of 76 mm (3in) diameter, two layers of prepared paper
tape, 1 layer of bitumen prepared cotton tape, 4 layers of mild steel tape, jute bedding,
steel armour wires and an outermost layer of jute servings.
However, even with internal pressure, the external hydrostatic force caused these to
flatten slightly during installation. This may have been due to inadequate control of
tension, resulting in greater bending at touch-down compared with what could be
achieved today.
Because the through-put was not initially what was expected, the operators increased the
pressure trying to overcome what was thought to be more line friction than had been
estimated. However, this pressure increase fortuitously had the effect of ‘re-inflating’ the
lines over time and so fuel supplies were restored.
408 Overview of pipeline engineering
Chevron pipeline
Water depth 33.5 m (110ft)
Mudslide initiated by
Hurricane Georges
Pipeline parted 6.1 m (20ft)
below mudline Chandeleur Islands’ lighthouse
Restart procedure
not followed faithfully
Leak not identified
MMS investigation
OCS report 99-0053
The pictures show the Chandeleur Islands’ lighthouse before and after Hurricane
Georges hit at the end of September 1998. Substantial modification to the seafloor
sediments swept away the barrier islands.
A crude oil pipeline operated by the Chevron Pipe Line Company in the South Pass area,
Block 38 was hit by a mudslide set off by the same event.
It is normal in extraordinary events such as earthquakes, floods and high winds to close
down all operations. A previously planned restart incorporating inspections and tests is
then followed.
However, this procedure was not followed by the operators and they failed to detect that
the line had parted having been covered by 6 m of heavy mud. Some 1306 m³ (8212
bbl) leaked out during restart.
The Minerals Management Service (MMS) investigation concluded that the cause was a
combination of the hurricane and mudslide followed by human error. “The damage to
the pipeline occurred as a result of a natural hazard, specifically, a mudslide that was
precipitated by Hurricane Georges in the latter part of September 1998. The pipeline
was found completely parted 20 feet below the mudline. Deviations from established
other-than-normal startup operating procedures contributed to the failure to identify the
pipeline leak promptly.” Full details are contained in their OCS report 99-0053.
A list of incidents for the USA offshore oil and gas industry can be found at the MMS
website http://www.mms.gov/incidents. Other countries have similar information such
as the UK’s http://www.hse.gov.uk/offshore/index.htm. In Australia, the
www.workcover.vic.gov.au/vwa/home.nsf website is a good source of general
construction operational health and safety (OH&S) incidents and information. By
signing up to their ‘safety soapbox’, they email a weekly report on safety issues
worldwide.
Third party causes include many associated with shrimping nets snagging valves causing
leaks, over-dredging of navigation channels, and jackup legs being dropped onto
pipelines.
Introduction to integrity 409
Increased throughput
Operations over-pressured line
Major environmental damage
New zig-zag for expansion
Float and lowered into trench
Satellite image by
Canadian Centre
Details for Remote Sensing
11 km (6.8 miles) long
457.2 mm (18in) diameter
50 mm (2in) concrete
A pipeline leads from Campos Elisios at the north of Guanabara Bay near Rio de Janeiro
to the Ilha do Governador (Governor’s Island), on which the international airport is
sited.
The pipeline was not supplying the required throughput so the operators increased the
pressure causing a rupture near the water’s edge. Guanabara Bay is an enclosed shallow
water and the spill caused major environmental damage and loss of public support for
the operators.
The pressure had exceeded the capacity of the line towards the end of its life. The
report identified thermal and pressure cycling (ratchetting) resulting in loss of steel
strength capacity. This was combined with loss of wall thickness, towards the end of its
life.
The pipeline was decommissioned and a new one installed by the SuperPesa Group
(www.superpesa.com.br).
This was floated into position using pontoons and lowered into a pre-prepared trench.
However, the problem of expansion was overcome by forming induction bends in each
pipe-length prior to welding. Expansion buckling problems is thus avoided using this
zig-zag form – each pipe-length has a preferred point of bending avoiding a build-up of
moment at a single point along the pipeline.
The photograph shows the line being installed over the laybarge stinger with rectangular
pontoon floats.
410 Overview of pipeline engineering
CAUSES OF FAILURE
It is usual that failures are caused by mistakes, and in the vast majority of instances, they
can be prevented.
In a lot of cases, the original intent has not been passed on completely to others in the
team. With large undertakings and teams, it is not always possible for everyone to be
fully aware of all the hazards.
Other failures are caused by people making a conscious decision to save money or time.
Maintenance is omitted or let slide, operators or third-parties (shrimpers, dredgers,
jackup operators) deliberately ignore warnings or fail to carry out procedures in full.
PREVENTION
We need to ensure that all calculations and procedures are checked. This may be
internally and where appropriate external review by an independent consultant.
Computer software is becoming easier to use these days although we often have a
plethora of rarely used features (bloatware). However, this has two consequences:
engineers often become overconfident in its use and it is often applied to the wrong
problem. It is good practice when conducting an independent check to use a different
package (that you are familiar with).
Every decision on the design intent and purchasing should be traceable. A similar
approach should be made during construction where full records should be available of
linepipe, welding equipment, welders and consumables used at each butt. Full quality
control and testing (where appropriate) is required of every item on the job.
It is essential that everyone should be aware of their sphere of work. This applies from
designers through to operators. During the pipeline life, a maintenance regime should
be adhered to, with appropriate testing of gauges and equipment.
Finally, it is important that where we cannot control events, we provide protection. This
may be in the form of rock dump though shipping channels, dropped object or
overtrawlable covers to pipeline and valvework, or it might be providing information to
fishermen or shipping in the vicinity of the pipeline.
412 Overview of pipeline engineering
COST OF QUALITY
loss of image)
Total costs
Cost of inspection,
testing and evaluation
The above curve shows how as quality assurance (QA) improves the cost rises steeply as
the curve approaches 100% quality. QA costs include prevention of failures by
inspection and testing of material and equipment used. But it is also important to keep
to the supply programme time restraints to avoid equipment hire overruns or (in the last
instance) client-imposed financial penalties.
If failure does occur, then fines may be imposed by government bodies. The company
image will suffer a loss, which is difficult to quantify financially apart from a rise
insurance levels but it will have an effect on both future clients and the public. Shell’s
Brent Spar was a notorious example of when a poor public perception caused significant
financial losses to a company.
Although shown as a well-defined line on the above graph, it is difficult to fully assess
exact failure costs. For this reason, it is shown as a dotted line. This is in contrast to
QA and HSE costs, which can be reasonably accurately determined. Nevertheless, by
summing the two, we can get an appreciation of the total quality costs.
By aiming for the minimum point, we can optimise the benefit to the company and
client in terms of profits and customer satisfaction.
Introduction to integrity 413
It was fortunate that no ignition source caused a tragedy. Correct selection of electrical
and other equipment was the final back-up to avoid the fireball.
414 Overview of pipeline engineering
FAILURES - SUMMARY
Bathtub curve
Example incidents at three phases of life
Start of operation – design and construction flaws
Low level risks – often from third parties
End of life – equipment wear and tear
Causes and prevention of failure
Build-up of small changes causing failure
Any questions?
We have identified the different types of failure and the likelihood of them occurring
throughout a pipeline life.
PIMS
PIMS
Learn Do
Measure
A PIMS document codifies good pipeline operating practice. It ensures the three
objectives for safe operation to equipment, people and the environment.
By following the four principle steps of the integrity assurance cycle. The final step of
which is seen by some as the most important. This ensures that the loop is closed out in
a report stating how well a particular operation was undertaken and what should be
improved next time. A later slide expands on this cycle.
That is to say, we should not just follow prepared procedures without looking for better,
safer practices and noting where things could have gone wrong. Nevertheless,
modifications to procedures should only be made following set management change
procedures.
The four distinct activities listed above must be considered in a comprehensive integrity
management system.
These aspects should be addressed in parallel and are complementary to each other so
must not be treated in isolation.
The activities within the PIMS serve the primary purpose of managing risk. The risk
management process and assessments that have been carried out in the development of
the procedures, plans and reviews that form part of the PIMS are recorded and include
clear statements on the assumptions made, level of risk and actions needed to mitigate
the risk. The assessments address both the threats and the consequences.
The risk assessment process includes periodic reviews and updates as the risk profile
changes with time and experience.
Records are kept of the reviews carried out, the actions taken and how the risks have
been mitigated in design, construction and operation.
Introduction to integrity 417
Pipeline operation
Kept within designed operating envelope
Safety systems
Inspected, maintained and tested
Ensure safe operation
Optimise performance
The operations and safety systems are concerned with ensuring the pipeline is operating
within the designed operating envelope and that safety systems – for example,
emergency shutdown valves (ESDVs) – are inspected maintained and tested to ensure
safe operation and optimum performance.
The photographs show a 323.8 mm (12in) class 900 ESDV used on an Indian gas
project supplied by Hawa Valves (India) pvt ltd (www.hawavalves.com/spv.htm); and a
cutaway and testing of a pressure relief valve.
STRUCTURAL INTEGRITY
This area includes the major activities of pipeline inspection and corrosion assessment.
Integrity can best be assured by taking a pro-active, risk-based approach to find and
assess potential threats.
Pipeline inspection is focused on monitoring and control of the external condition of the
pipeline and the associated protections systems such as coatings and cathodic protection
(CP). Potential threats include low CP, damaged coatings, dents and failure of joints.
Corrosion is the most significant internal degradation mechanism for pipelines and
needs to be assessed, monitored and controlled throughout service life.
The following modules will examine how the structural integrity of the pipeline can be
ensured.
MODIFICATION MANAGEMENT
Major modifications and rectification work on the pipeline systems can pose a significant
threat to the ongoing integrity of the pipeline systems if not managed and controlled in
the context of the whole system.
These include replacement parts or changes to throughput when these drift out of the
original specification envelope. The reservoir may not behave as originally envisaged
during the design. For example, a higher water cut at the end of life may result in higher
than expected temperatures. These can increase problems with slugging or pipeline
expansion, resulting in the risk of lateral/upheaval buckling of the pipeline or an increase
in forces acting on the riser guides.
When changes are made to the operational procedures, these should be carefully
scrutinised by a change committee to ensure there is no increase in risk.
Modifications and additions to the pipeline system have to be integrated into the PIMS.
Introduction to integrity 419
The picture shows coating loss from a riser at the lower end of the splash zone. The
thick neoprene corrosion coating has been scraped away by a wire. This may have been
as a result of some unidentified construction activity.
FLOW ASSURANCE
The purpose of flow assurance is to provide the optimum operating process parameters
(flow velocities, pressures, temperatures, product composition). It should also identify
critical process/ flow upset conditions that may threaten integrity.
420 Overview of pipeline engineering
The flow conditions have a significant influence on corrosion rates and forces produced
within the pipeline, such as water cut, slugging flow, changes in temperature. These may
change over the service life of the pipeline.
An understanding is needed of past and present history and how conditions may change
in the future.
2001
Exposure
2002
Short span
2003
Longer
2004
Excessive
2005
Rock dump
An example integrity analysis package is Prism. The above typical screen dump shows
output for an anonymous pipeline currently being managed by Jee Ltd. [Currently, Jee
Ltd is the ‘Pipeline Competent Person’ for 600 km (373 miles) of North Sea pipelines
(39 subsea lines, one umbilical and 4 landlines), defining the requirements and frequency
of inspection for the PIMS.]
The slide shows how a pipeline span increased in length through the years 2001 to 2004.
The final picture shows the pipeline having been rock dumped.
The blue line at top of each year shows lengths of exposed pipeline. Red bars just below
show sections that have started to span. By clicking on the grey bars, a pictorial
representation of the side scan image can be brought up. Cyan indicates sections that
have been stabilised using rock dump.
Other information on the plots are the distances along the pipeline (KP or chainages),
red numbers above the grey bars anomaly report references, the yellow triangle (left
hand side of grey bar in 2004) shows where the anomaly has exceeded the maximum
allowable value, requiring remedial action.
Introduction to integrity 421
PLAN-DO-MEASURE-LEARN CYCLE
Plan
Develop operating procedures and inspection plans
Hazard identification and assessment (HAZID/HAZOP)
Set reporting criteria and performance standards
Do
Operation and inspection examples coming up
Measure
Inspect and test equipment biennially
Valve closure speed and leak (bypass) rate
Defect analysis and database
Learn
Inspection experience and need for remedial works
Successful operation – refine inspection plan
We must set standards also for what criteria are deemed out of range and how such
conditions should be reported if they arise.
Standards of performance for each item of equipment must be set. These may be how
quickly a valve closes in normal operation and in an emergency; what amount of bypass
flow is deemed to be acceptable, etc.
Each item of plant and every operation (regular or one-off) in the procedures and plans
developed earlier needs to be compared with the performance standards set down.
Perhaps we need to take a valve out every two years for servicing and performance
testing.
Defects to the pipeline system must all be recorded in the database for future reference.
This must provide an easy and rapid means of comparing how these defects have
developed over time.
The learn phase means that the PIMS procedures can and should be kept up to date with
information whether the operation or inspection proved successful or not. It should
also flag-up when remedial action is needed. If whilst undertaking the work, operators
can identify ways of improving inspections or procedures then this phase may indicate
the need for refinements to make the operation safer or more robust.
For example, in the 2006 survey of the spanning pipeline on the previous slide, it will be
possible to see whether the rock dump succeeded in eliminating the scour and exposure
of the pipeline at the ends of the span.
422 Overview of pipeline engineering
PERSONNEL
Those operating the PIMS should be SQEP personnel with competence in their own
particular field.
It is necessary to identify the different specialists for support, operations and projects –
as shown in the suggested groupings, above.
PIMS - SUMMARY
A PIMS is required to ensure nothing goes wrong whilst operating the pipeline network.
We need to balance the four activities which must be run together. This can be done
using the integrity assurance cycle and providing clear responsibilities for each member
of the team.
INTEGRITY MANAGEMENT -
SUMMARY
Any questions?
Different types of failures occur throughout the life of a pipeline. We have seen how the
frequency of failure and the reasons for them can be seen using the bathtub curve.
424 Overview of pipeline engineering
By setting up a PIMS, it is possible to limit incidents thus ensuring safe operation of the
pipeline. The system should also aim to extend the bottom of the bathtub curve for as
many years as possible.
Flow assurance
Flow assurance 427
EXPECTATION
EXPECTATION
Flow assurance is the skill of optimising the throughput of oil and gas through the
pipeline, whilst reducing as much as possible the loss of wall thickness through corrosion
and erosion.
This is done by injecting additives and pigging on a very frequent regular basis to remove
unwanted deposits in the line. Controlling the flow in a pipeline within the safe working
design envelope also helps prevent internal damage to the pipe walls.
We will introduce the activities required for the safe operation of subsea pipelines. By
this, we mean, work carried out on a frequent regular basis (rather than annual
inspections).
Some of these regular operations will involve additives to the product in order to
enhance the flow. This may be done as a continuous process or in a batch.
A description is given for the various types of pigs and their functions.
OPERATIONAL CONTROLS
These are particularly associated with the flow conditions and rates. As discussed later,
problems can arise in the pipeline if the flow conditions are not carefully controlled.
The resulting problems that may arise are due to wax or hydrates. These can block the
line. If temperatures fall, the fluid may be too viscous to pump efficiently or the product
mix may form inseparable emulsions.
Corrosion and erosion are also controlled by the way the pipeline is operated.
Flow assurance 429
HYDRATES
Hydrates
80
1.0
60
40
0.5
No Hydrates
20
0 0
32 41 50 59 68
0 5 10 15 20
Temperature °C (°F)
Hydrates are a particular problem in multi-phase flow and wet gas flow, where water is
present. They are formed under conditions of low temperature and high pressure.
They are subject to hysteresis, which means that their formation depends upon the
conditions they have been subjected to upstream. Hydrates have a tendency to form
downstream of valves because of the Joule-Thomson cooling effect at a pressure
reduction.
A hydrate plug can block the line. This presents both an operational and a safety
problem. The pressure differential across that plug will increase. It may then shift at
high pressure and travel along the line at high velocity. It can therefore cause damage
when it reaches a bend or some equipment.
Control of hydrate formation is by the control of the operating pressure and temperature
of the pipeline, and by injection of a hydrate inhibitor.
The graph shows the safe operating zone to the right of the dotted line for the Hyde gas
line in the Southern North Sea. The solid line shows the temperature of formation but it
will take a higher temperature (dotted) for the hydrates to melt.
430 Overview of pipeline engineering
WAX
Long-chain
paraffins
Condenses on
pipeline wall
and restricts
flow
Keep up flow
rate
Wax deposition can be a problem for oil lines. As the oil cools the long-chain paraffins
in the oil can form a waxy deposit on the pipeline walls. This restricts the flow, increases
the pressure drop down the line and can be very costly. Wax formation is restricted by
maintaining a higher fluid temperature, which can be assisted by keeping up the flow-
rate.
CORROSION
Corrosion inhibition
Corrosion inhibitor carried in liquid phase
Stratified flow - only bottom of pipe is protected
Pitting corrosion in upper part of pipe becomes a problem
Water phase drop-out
Low flow velocity - water drops out
Water can be highly acidic Gas
Increased corrosion at
bottom of pipe - tramlines Oil
As corrosion inhibitor is carried in the liquid phase, we may not get adequate protection
in stratified flow.
Flow assurance 431
Water drop out in stratified flow can cause localised corrosion. The water can be highly
acidic, leading to rapid corrosion. At the interface between oil and the water, selective
attack can lead to the formation of tramline grooves in the wall.
EROSION
Multiphase flowlines
Fluid contains sand and water
Erosion at bends and valves - sandblasting
Oil trunk lines
Cavitation collapse
Flow
Weld Corrosion
bead Erosion pit Erosion
It is perhaps easy to understand that flowlines containing multiphase fluids direct from
the well may contain sand and water, in addition to the oil and gas. This can result in a
sandblasting effect on the pipe wall, causing erosion of the steel as the flow changes
direction at bends.
However, erosion can also occur in oil trunk lines to shore, where there are no abrasive
elements in the flow. If the velocity of oil itself is too great, then any small bump or
cavity in the wall may cause cavitation bubbles to form. When the bubbles collapse or
implode, the resulting shockwaves can also erode the wall.
This effect is often seen downstream of field weld, where the bead or root protrudes out
of the boundary layer of fluid attached to the wall, causing disruption to the flow.
The photograph shows the effect of a field weld root bead and the lines of erosion it
causes downstream.
API RP 14E gives the above formula for the velocity at which erosion may start to
occur.
Where:
■ Ve = erosional velocity
■ ρ = density of fluid
Different formula are needed for SI and metric because of the units in the numerator
constant.
Where corrosion has left a pit, then this can also disrupt the flow and erode the wall on
the downstream side, increasing the length of the defect.
432 Overview of pipeline engineering
TURN-DOWN – OPERATIONAL
ENVELOPE
Because we are abstracting oil and gas from the reservoir, the flow parameters through
the pipeline will alter throughout life.
With a gas field, the amount of water may increase. This water is often hot, and as these
slugs pass through the pipeline, the expansion along the pipeline may increase – this
could cause uplift or lateral buckling problems where there was no risk of this before.
In oil lines, the temperatures tend to decrease over time causing waxing which may
require more frequent pigging.
In general, flow rates will decrease causing additional cooling along the length of the
pipeline.
For mixed lines, the ratio of gas to oil may alter. This is dependent on the depth of the
oil well within the reservoir.
Operationally, the chemicals added to the line may alter or the method of assisting
recovery by injection of water or gas.
It is necessary to account for all of these changes whilst maintaining the line within the
operational envelope.
Flow assurance 433
OPERATIONAL CONTROLS -
SUMMARY
They are the means of ensuring that the flow is maintained within the design envelope.
This generally means controlling the temperature and pressure in the line.
If the product strays out of this, then some of the effects may be the formation of slugs
or pressure surges.
We have looked at some of the effects when temperatures fall - such as the formation of
wax and hydrates, the increase in friction due to high viscosity or formation of
emulsions, which cannot be separated.
ADDITIVES
ADDITIVE APPLICATION
Continuous Batching
Hydrate inhibitor Corrosion inhibitor
Corrosion inhibitor Periodic coating of pipe wall
(say 3 monthly)
Erosion/corrosion
Used in wet gas lines or from
control unmanned minimum facilities
Wax suppressants Gives good covering over all
Drag reducing of wall
agents Methods
Biocide Introduce slug of additive
between pigs
Spray pig
A range of chemicals can be added to the flow as part of the pipeline operation. There
are two main methods of introducing additives to the pipeline - continuous injection and
batching.
Logistics
Inhibitor and carrier fluid
Pigs, launchers, storage tanks and pumps
Personnel
Supply of carrier fluid (diesel)
Disrupt normal operations
Receiving slug
Ensure large enough separator and slug catcher
Leading pig Slug of carrier fluid and corrosion inhibitor Trail pig
These include the pigs to contain the slug of inhibitor, the pumps and personnel to carry
out the work. The supply of the carrier fluid to the end of the pipeline must be
considered.
This contrasts sharply with the automatic continuous injection method where only the
inhibitor itself is needed.
Normal product delivery operations must be disrupted during the batch treatment
process.
The slug must be caught at the far end of the pipeline and the carrier fluid decanted out
from the product.
436 Overview of pipeline engineering
The alternative method of batch inhibiting is the use of the inhibitor spray pig. This is a
proprietary product and would have to be designed and built for a specific application.
ADDITIVES - SUMMARY
Any questions?
We can introduce additives into the pipeline to improve the flow characteristics and
reduce the possibility of corrosion. To improve flow, additives can reduce drag and
suppress wax formation. To reduce corrosion, there are inhibiting chemicals.
PIGGING
Bypass
Flow
Pipe wall
Suspension rubber cups
Pigs are devices driven through the pipeline by the pipeline fluid. They come in all
shapes and sizes and perform a number of functions, as explained below.
In essence, they contain the components shown in the diagram above. There are cups to
seal against the pipeline wall, giving the device its driving force, and a body upon which
the cups are mounted, which contains brushes, gauge plates or other devices that give
the pig its function.
Only a small pressure differential is usually needed to propel a simple pig, around 0.5 bar
(0.75 psi), depending on the diameter and condition of the line.
Normally there is some bleeding of the line contents past the rubber disks in either
direction as they deform to follow the contours of the wall.
In gas lines, pigs will tend to repeatedly surge forward and stop if not carefully
controlled.
Some pigs are built with a bypass tube to slow them down and flush debris out within
the upstream product.
438 Overview of pipeline engineering
PIG LAUNCHER
Vent valve D
Mainline trap
and gauge
Door valve B Pig signaller
Pig
Launch Flow
Trap Mainline
tray kicker bypass
valve C valve A
Flow
Under normal operation, valves A, B and C are left open and the pig launcher door is
kept closed. When a pig is to be launched, the valves B and C are closed and the vent
valve D is used to release gas pressure. The door is opened and the pig pushed into the
trap. Valve D is shut again. The door resealed and valve C cracked open again until the
trap pressure equalises with that of the pipeline. Valve C is closed and valve B opened.
The pig can be launched by opening valve C again and then gradually closing valve A. A
pig signaller indicates passage of the pig. Once the pig is in the main pipeline, valves A,
B and C are fully opened again for normal operation.
For pig receipt, a similar unit is used except that the pig signaller is on the other side of
valve B to indicate that the pig has been caught.
The photographs show a typical landline pig launcher and a subsea unit supplied by
Pipeline Engineering (www.pipelineengineering.co.uk) to installation contractor Subsea
7. This operates at a depth of 130 m (426ft) in Esso’s Jotun field in the North Sea
(Norwegian sector).
It is a 150 mm by 250 mm (6in by 10in) subsea class 1500 vertical pig launcher with
receiver facilities. The unit can launch or receive both conventional and intelligent pigs.
It has full subsea capabilities including a soft landing system and ROV operations
compatibility.
The unit consists of three sections: a manifold interface, the protection head and pig
launcher. The manifold section is bolted to the subsea manifold and includes three
pedestals for the Soft Landing System. When the launcher/receiver is not in use, the
protection head is used to protect the manifold from damage and corrosion. It is fitted
with hydraulic quick connect/disconnect collett connectors and a control panel to allow
removal and connection of the head by ROV.
The pig launcher assembly, which is kept either onshore or on the barge until required, is
fitted with three pig release fingers and three baskets capable of launching and receiving
three conventional pigs or one intelligent pig respectively. The pig launcher and receiver
is designed in accordance with PD 5500, permanent pipework to Det Norske Veritas
(DNV), and the launcher/receiver structure to DNV and NORSOK.
Flow assurance 439
Most pipelines are pigged at least occasionally, if not routinely, for the reasons listed on
the slide above.
■ Cleaning out waxes and solids may be necessary on an oil pipeline where wax is
deposited on the wall. Deposition of wax can dramatically increase the pressure
drop necessary to get the flow through the pipeline. Where it is not possible to
insulate the pipeline sufficiently to avoid wax deposition, regular pigging to remove
the wax is often the solution. This would apply particularly to oil trunk lines.
■ Sweeping out liquids tends to be done by spheres. These are usually polyurethane
balls pressurised with glycol to a diameter a few percent above the pipeline internal
diameter. Taking a gas trunk line as an example, it might accumulate condensates
that would need to be swept out on a regular basis. This would keep the level of
liquids in the line under control and would avoid the occasional arrival of a very
large slug of liquids at the terminal, an event that might cause process problems.
■ Corrosion inhibitor pigs can be used to introduce a slug of inhibitor into a line with
the objective of coating the entire pipeline inside wall with corrosion inhibitor.
■ Proving the bore is clear is carried out during hydrotesting at the pre-commissioning
stage. It may also be used when a dent is suspected.
440 Overview of pipeline engineering
SPHERES
Spheres are frequently used in wet gas and multi-phase lines on a regular basis. This
might even be more frequent than once a day.
They are used to sweep liquids from lines to prevent build up of slugs. They can spread
a corrosion inhibitor around the full circumference of the wall to prevent it collecting at
the bottom of the pipe.
Some platforms have an automatic launch system with a cartridge containing half a
dozen spheres. These can be individually launched with little or no manual input.
They are usually slightly oversized (2%) to give good seal with inside bore of pipe.
Flow assurance 441
FOAM PIGS
Foam pigs are generally bullet-shaped, moulded from open cell polyurethane foam and
usually with an external PU coating. They come in a variety of shapes, sizes and colours.
They have no independent sealing elements but are compressed axially by the pressure
differential, which gives sufficient radial expansion to form a seal between the pig body
and pipe wall.
FOAM PIGS
Foam pigs are a general-purpose but lightweight pig suitable for sweeping liquids and
solids from a pipeline. Specific applications can be ‘built-in’ at the moulding stage where
442 Overview of pipeline engineering
gritted bands, brushes, jetting holes, magnet inserts (for tracking) or studs (for fixing of
gauge plates or scrapers) can be added.
They have the advantage of being tolerant of tight bends and bore restrictions. They will
also break-up if they become stuck. This makes them useful for an initial pig run prior
to a more robust brush or scraper pig being used.
Their disadvantage is that they wear out quickly, although heavy duty versions exist for
single pass usage on long lines.
BATCH PIGS
Metal bodied pigs utilise polyurethane or rubber seal discs or cups. The material
selection is dependent on the specific application. Metal bodied pigs offer the ability to
add a range of attachments that may be used to perform a range of functions.
They are commonly used for removal of liquids and inserting a batch slug of corrosion
inhibitor.
If smaller diameter spheres or pigs have been used to clean a smaller diameter branch
pipeline, once it enters the main line the larger bore means that there is no differential
pressure to move it. A batch pig can be sent down the main line to sweep it up.
Gel pigging may be carried out to de-sand a multiphase line. The gel picks up solid
debris and removes it from the line. The gel also lubricates the pig and gives improved
drive.
Flow assurance 443
BRUSH PIGS
Removal of solid
debris and wax
Bypass ports
Jet of fluid
Debris suspended
in front
Swept out
Slows pig
By-pass ports are used to produce flow in front of the pig. This flow helps prevent the
build-up of debris or wax in-front of the pig. By-pass ports are typically threaded holes
with plugs.
The operator can therefore adjust how much by-pass occurs prior to entry.
SCRAPER PIGS
Polyurethane or steel
blades or ploughs
Wax removal
Scraper pigs are used for the removal of wax deposits from the pipe wall.
444 Overview of pipeline engineering
The spring joint at the middle of this example helps it negotiate tight bends.
SPECIALIST PIGS
Pin-wheel pig
Magnetic cleaning pig
In addition to the basic cleaning and sweeping operations, pig bodies can be configured
for specialist functions.
The picture above shows a magnetic cleaning pig in use in Germany, where magnets
have been mounted on the body of the pig and have pulled a veritable bird’s nest of
welding rods from the pipeline. Note also the bi-directional sealing discs on the pig and
a gauging disc, which can just be seen behind the welding rods.
Approximately 3000 rods were extracted on the first passage of the pig. This dropped to
1000 rods at the next pass and down to zero after five runs.
These are only two examples of specialist pigs. You can imagine the myriad of shapes,
sizes and functions that have been adapted over the years.
Flow assurance 445
A CAUTIONARY TALE
Trevor Jee was approached to resolve a problem with an infield line that was normally
pigged on a regular monthly basis. A pig had become stuck in the launcher and it was
decided to suspend pigging for a number of months.
In the meantime, the pressure needed to maintain flow rose more than tenfold. The
reason for this was traced to the undulating nature of the pipeline: the high pressure loss
was due to slugs of product which needed to be forced uphill. On the downhill slope,
the liquid dribbled over the crests of the hills and very little pressure head was recovered.
The system pressure was brought down and the stuck pig removed from the launcher.
When the operations were resumed, it was decided to use a smaller than normal pig for
the first run. This got lost in the system as the gas flowed past the pig.
The full size pig which followed had the effect of removing some of the slugs, but
puddles of condensate overlying water had formed in a hollow. As the pig hit these, a
spray of water and condensate splashed out and formed a hydrate plug. This effectively
blocked the passage of the pig about three-quarters of the way down the length of the
pipeline.
The pressure behind the pig was increased to 90 bar (1300 psi) and that in front of the
pig was gradually reduced by bleeding off. When the differential reached 50 bar (725
psi), the hydrates became unstable and melted.
This occurred just as Trevor arrived on site. The pig surged forward and backward like a
spring until the pressures equalised on either side.
When their calculations were checked, even though the volume of the pig catcher had
been forgotten, there was just enough distance to prevent the pig hitting the end of the
line.
446 Overview of pipeline engineering
PIGGING - SUMMARY
Any questions?
Pigs are small components that are driven through the pipeline by the flow of the fluid.
They can perform a wide range of activities to ensure the correct operation of the
pipeline, these activities are summarised above.
Operations
Maintain temperature and pressure within envelope
Chemical injection
Wax, hydrate and corrosion control
Improved flow rate
Continuous or batch
Pigging
Any questions?
We have introduced routine operations to maintain the pipeline flow within the designed
envelope.
Flow assurance 447
EXPECTATION
EXPECTATION
We will introduce the activities required for the operation of subsea pipelines. The first
requirement is to understand the inspections that are carried out. Why do we do them
and how do we decide what to look for?
An overview is given for the methods of assessing the various different anomalies and
finally the methods of correcting those anomalies are discussed.
452 Overview of pipeline engineering
Damage
Debris
Anode removal or
early wastage
Exposure
Spans
Leaks
Rock cover
Under ‘Installation’, we mentioned that surveys were carried out to characterise the
seabed, and that further surveys were required during operation. These typically look for
anything that may have gone wrong with the pipeline:
■ Damage – impact from trawler activity or objects dropped from platforms or supply
boats
■ Debris – near to or draped over the pipeline (large boulders are dragged and lifted
by trawlers)
■ Anode wastage – usually anodes are knocked off by fishing but they can be ablated
away following coating damage
■ Exposure of a previously buried line
■ Spans – scour of soil from beneath the pipeline
■ Leaks – usually from flanges
■ Loss of rock cover
Pipeline inspection 453
There is a variety of techniques to survey the pipeline, and the operator is also presented
with a choice of when it is necessary to survey. In the prescriptive regime of the 1980s,
an annual survey of the entire length of the pipe was required. In the goal-setting regime
of today, in UK waters, it is the responsibility of the operator to determine a safe
inspection interval as part of his inspection plan. The result of this is that most
inspections in the early part of the pipeline life are carried out annually, and they are then
spaced further apart if the results are benign.
INSPECTION PLAN
Identify risks
Write an
inspection plan
Inspect pipeline
and report
Interpret results
The flowchart above shows the processes involved in pipeline integrity management. It
is an iterative process in which the results of inspections are fed back in to the inspection
plan and future inspections modified accordingly.
RISK-BASED INSPECTIONS
Hazards identified
Inspections targeted according to
risk (probability x consequence)
value of inspection
Highest value
of inspection
Consequence
of failure
n
c tio y
e l it
Not worth
n sp i ca
I it
inspecting cr
Probability of failure
for
Any questions?
A subsea pipeline faces many hazards during its lifetime. Inspections must be done to
ensure that the pipeline continues to operate safely. Several tools are available to
externally inspect the pipeline. The external inspection strategy will be driven by an
assessment of the risks due to the anomalies and the usefulness of the chosen inspection
technique in countering those risks. The inspection plan will evolve over the life of the
pipeline using feedback from the results of the inspections.
456 Overview of pipeline engineering
EXTERNAL SURVEY
The initial surveys may be carried out by ROV (as shown in the picture), especially if
detailed information is needed. However, side scan sonar is far more common for the
routine survey of pipelines.
AUVs are more suitable for inspection of long lengths of major trunk lines
Modern side scan sonar is quite capable of picking up any physical objects of concern to
the pipeline and of estimating span heights and lengths. Being considerably faster
(perhaps by as much as a factor of 10), and therefore lower cost, it is in widespread use.
Pipeline inspection 457
Divers are limited to shallow water investigation work where ROVs are unable to
operate due to cavitation of their thrusters.
SIDESCAN SONAR
Pipeline span
Sidescan sonar techniques use a towed fish such as that shown in the picture above.
They are based on sonar, whereby the device emits a sound pulse and listens for the
echo. It interprets the strength, time and direction of the echo to give a picture of the
pipeline and seabed in sufficient detail to gauge pipeline features such as embedment and
spans. Seabed features can be distinguished such as sand waves, debris, trawl scars, etc.
The sonar printout is from an integrity management contract currently being undertaken
at Jee Ltd. The seabed mega-ripples are indicative of a mobile sandy bottom and the
exposed section of pipeline is clearly visible together with the region either side of the
span where the mega-ripple pattern has been disrupted by scour. The shadow at the
centre shows where scour has developed sufficiently to cause an unsupported length of
pipeline to span freely. This may be further investigated by ROV to determine the
support end points.
458 Overview of pipeline engineering
Typical screen shots from an ROV survey show disrupted weight coating at an anode
beneath substantial marine growth. The second view is of a spanning pipeline at a field
joint.
Both screens show the date and position (Eastings and Northings) and chainage along
the pipeline with essential other ROV camera view data.
Any questions?
Pipeline inspection 459
The external inspection of the pipeline can be carried out using the following
technologies:
■ Side-scan sonar
■ ROTV
■ AUV
■ ROV
■ Diver
Side-scan sonar using fish or ROTV is the cheapest and fastest method but cannot pick
up fine details – especially those beneath the pipe.
ROV is a more flexible method than side scan sonar, and the ROV can carry a range of
extra instrumentation.
AUVs are a relatively new technology but much development is going on. They are
potentially the most flexible method of all.
460 Overview of pipeline engineering
INTERNAL INSPECTION
In addition to external inspection, there are internal inspection techniques available for
pipelines. These range from the simple gauge plate check for dents and debris, through
to sophisticated pig checks for cracks and corrosion.
In this section, we will look at three types of intelligent pigs - the magnetic flux,
ultrasonic and eddy current pigs, describing their function and their uses.
Before an intelligent pig is sent down the line, a full pig cleaning operation would
normally be carried out to ensure the intelligent pig remains undamaged and that the
data obtained from the pig run is the highest quality possible.
Pipeline inspection 461
INSPECTION TECHNOLOGIES
Magnetic flux
leakage
Ultrasonic
thickness
Eddy current for
flexibles
There are two main technologies: magnetic flux leakage (MFL) and ultrasonic thickness
measurement (UT). Each has started by finding wall thickness loss (general corrosion
defects, both inside and outside), and has then been rotated into the hoop direction to
find axial cracks.
A final technology, that of eddy current, is being developed for the inspection of
flexibles.
MAGPIE - VIDEO
462 Overview of pipeline engineering
The Magpie tool is inserted into the pipeline using pigtrap launchers and is propelled
along the inspection route by the pressurised oil or gas. The tool uses magnetic flux
leakage (MFL) to detect defects in the pipe wall and a digital signal processing data
logger to record up to 1000 pieces of data per second.
Above-ground sensors use Bluetooth to track the position of the tool before logging the
information using GPS. On retrieval from the pipeline, the data is uploaded from the
tool and then sent to the lab for processing and interpretation.
The picture above shows the PII magnetic flux pig. In the picture you can see the
magnetic brushes and the finger-like arrays of magnetic flux detectors. The rest of the
pig contains power and data storage facilities. It is used to detect internal and external
corrosion defects in oil and gas pipelines. Variants are available to detect both axially-
oriented and hoopwise-oriented cracks.
Typical speeds of intelligent pigs are from 0.3 to 5 m/s (1ft/s to 16 ft/s). If the product
flow is faster than this, it is normal to include a bypass system to permit the pig to travel
slower than the oil. Head losses for pigs are typically less than 1 bar (15 psi).
Pipeline inspection 463
No defect present
Brush Brush
Sensor
N Magnet Magnet S
PIPEWALL
DEFECT Defect present SECTION
Brush Brush
Sensor
N Magnet Magnet S
LEAKAGE FIELD
The above diagram illustrates how the pig detects corrosion defects. In the non-
corroded condition, the two brushes form a magnetic circuit and the flux passes through
the pipeline wall with little passing either side. However, in the lower diagram with the
defect present, there is less metal through which the flux can pass, and some of it leaks
outside the pipe wall and is detected by the sensor.
PRESENTATION OF DATA
ASSESSMENT
4 8 12 16 20 24 28 32
The above diagram shows an example of results obtained from an MFL pig. It shows
over 450 000 internal metal loss features, and there were also over 3500 external metal
loss features identified. This analysis looks for any defects where the dimensions exceed
those tolerable at 1.5 x MAOP, or where the peak depth exceeds 80%.
464 Overview of pipeline engineering
In this case there were 19 defects identified as possibly needing repair. A detailed
assessment was also carried out in each case, measuring the effective depth and length of
the defect, which reduced the number of defects requiring repair down to just one.
ULTRASONIC PIG
The ultrasonic pig is used to detect corrosion defects in liquid lines. The liquid is crucial
in acting as a couplant for the sound emitted by the ultrasonic probes. For these pigs to
function in a gas line, they must be run within a slug of liquid. Alternatively pigs are
available that use wheels running along the pipe wall to transmit the ultrasonic vibrations
into the pipe wall.
More modern ultrasonic pigs are also able to detect cracks of may different orientations
in the pipe wall, including longitudinal cracks.
Pipeline inspection 465
PRINCIPLE OF OPERATION
Transmitter
The probes on the ultrasonic pig work in exactly the same way as hand held ultrasonic
thickness probes. They emit a sound wave and detect the front and back pulses
reflected from the specimen. By calibrating the speed of sound in the pipe steel (using a
sample of known thickness), it is possible to interpret the sound time delay in terms of
metal thickness. It is also possible to interpret, from the time of the first reflection,
whether the corrosion defect is on the inside or the outside of the pipe wall.
Corrosion at
helical weld
Acid attack pitting
The output from the ultrasonic pig is a pixellated scan of the entire internal surface of
the pipe.
466 Overview of pipeline engineering
In the picture above, any normal reading has been colour-coded white and corrosion
defects given a colour code depending on their depth. One can see on the left-hand side
a spiral weld with preferential corrosion. Across the middle of the scan, there are some
corrosion pits characteristic of acid attack and one can also see some red inclusions
running parallel to the plate-rolling direction.
The output of the ultrasonic pig is far more intuitive than the magnetic flux pig and a
general picture of the state of the pipeline can be obtained rapidly at the end of the pig
run.
OTHER PIGS
Gyroscopic pig
Leak detection pig
Neutron scatter pig
Camera and tethered inspection
Crawlers
Wax and scale assessment
A variety of other pigs have been developed for pipeline inspections. Gyroscopic pigs
can be used to survey a pipelines shape and can also detect spans by the vibration of the
pipeline as the pig passes through the pipeline span.
Leaks can be detected by mounting sound detectors on a pig and listening for
characteristic sounds of fluid leaking.
Neutron scatter pigs were developed to detect whether the pipeline was buried or
spanning and have largely been superseded by side scan sonar surveys.
It is possible to survey the sections of pipeline close to the pig trap using tethered pigs.
Crawler pigs use on-board power to propel themselves against the fluid flow. Their
range is limited by the availability of on-board power. There is also a range of crawler
pigs that can be introduced at the landfall end of a subsea pipeline and crawl up to 12
km (7½mile) inside the line, towing an umbilical to give an on-site evaluation of the
line’s condition.
Pigs have also been developed to measure the wax and scale coating the inside of a
pipeline.
Pipeline inspection 467
Flexible pipes present a different set of inspection requirements. The primary mode of
failure for which it is necessary to inspect is that of cracks in the hoop and armour
windings (rather than corrosion defects). The eddy current pig, pictured above, is being
developed to detect such cracks. It functions by inducing an eddy current in the
windings and detecting the difference in the resulting electromagnetic field caused by a
crack.
The above picture is an output from the device showing a crack in one of the armour
wires.
468 Overview of pipeline engineering
Flexibles can be externally inspected but the scope for internal inspection is limited. The
integrity of the flexible riser liner can be monitored using coupons or vent gas
monitoring. Coupons are small samples of liner sitting within the flow of oil or gas that
can be removed during inspections for testing.
The condition of the polymer liners in flexibles can be assessed by monitoring of the gas
that diffuses into the windings layers. This photograph illustrates the vent gas
monitoring system.
The flexible pipe manufacturers are developing fibre optic cable systems that are laid
into the armour windings. These can monitor any potentially damaging stretching of the
armour wires.
Pipeline inspection 469
Any questions?
Intelligent pigs enable comprehensive internal inspections of the pipeline to check for
corrosion or cracks in the pipe wall. There are two main technologies used by intelligent
pigs for internal inspections, these are magnetic flux leakage (MFL)and ultrasonic
thickness (UT). A third technology of eddy currents is under development to enable the
inspection of flexibles.
470 Overview of pipeline engineering
ANOMALY ASSESSMENT
Spans
SPANS
A pipeline span is simply a section of the line that is not in contact with the seabed. This
can be due to a variety of reasons, the most common of which is an uneven seabed on
the selected route. Pipelines submerged in seawater form quite efficient beams, resulting
in a relatively high bending stiffness and a tendency to span over seabed undulations.
Rock dump can cause spans, in that the rock berm is designed to be stable and resist
dissipation due to environmental loads. The seabed around the rockdump may not be as
stable, and scour of the seabed may result in a pipeline suspended between periodic
mounds of rockdump.
Sandwaves are a feature of many soft seabeds, including the southern North Sea. The
sandwaves tend to propagate, resulting in continuously moving pipeline spans unless the
pipeline is lowered to below the trough level.
Seabed scour can be regional or localised. Regional scour is the general lowering of the
seabed, which tends to destroy pipeline trenches and create spans. Localised scour is
Pipeline inspection 471
caused by the presence of the pipeline. This can be caused by seabed currents, fish
digging themselves in under the pipe, or variations in seabed sediment.
10000 Frequency
100
100
Frequency
1
0 50 100 150 200
1 S p a n L e n g th (m )
Spans are very common. In the North Sea UK Sector alone there are in excess of 33
000 spans in 7800 km (4900miles) of pipelines. That is an average of one every 230 m
(750ft). Of these, most are short and low, maybe only a few inches high at most. Only a
few hundred are of any concern, either due to the integrity of the span or for their
potential to cause hooking of fishing gear. First-pass span analysis is principally about
identifying which spans present a problem and require further evaluation.
Typical spans have been described statistically. The distribution of span height is log-
log; while the distribution of span length is log-linear. There is no significant correlation
between span height and length.
472 Overview of pipeline engineering
SPAN ASSESSMENT
There are a number of approaches to span assessment, which vary depending on when
they are carried out in the life of a pipeline.
During design, a first pass spanning assessment will often be performed. The purpose
of this assessment is to determine limits on allowable span length for the installation
contractor to work to. The assessment of these span limits is normally based on
conservative criteria, which ensure that no short or long term damage of the pipe will
result.
Also during design, an assessment of the seabed profile along the proposed route may be
performed to identify whether pipeline spans are expected to occur, and if so where and
how long. This assessment of the route would be based on survey data and would use
finite element analysis (using a general FEA package such as ABAQUS, or a specialist
pipeline package such as Orcaflex or Sage Profile) to ‘lay’ the pipeline over the
anticipated seabed profile. This analysis would give predictions of the numbers and sizes
of expected spans and therefore allow an assessment of the route preparation or span
remedial work that will be required. This is obviously important to allow assessments of
cost to be made.
Subsequent span analysis is performed during operation of the pipeline to address any
anomalous spans identified. The analysis is therefore to determine the acceptability of a
known span length, and would entail a detailed assessment of stresses and fatigue.
Pipeline inspection 473
PROBLEM
bending
&
fatigue
End
Current & supports
Axial tension &
wave action
compression
The section of a pipeline that spans is subject to its own self-weight, fluid loading and
potentially third-party loads from fishing gear. This could cause it to yield and to fail in
bending with plastic hinges. If this mechanism could occur, then it is necessary to
stabilise the span and give it additional support.
A second mode of failure for spans is a fatigue failure due to vortex-induced vibrations
(VIV). These are vibrations induced in the span due to the passage of currents (and
waves) perpendicular to the pipe. These cause the pipe to oscillate at its natural
frequency which, over a period of time, can lead to fatigue failure. Again, should fatigue
failure due to VIV be predicted for a particular span, it would need to be supported to
prevent this happening.
Major span lengths can prevent internal pipeline inspections because of the risk of
overstressing failure when the weight of an intelligent pig is passed through.
474 Overview of pipeline engineering
SPAN CONCERNS
These aspects are considered during both the pre-construction analysis and the
operational analysis.
Any questions?
Pipeline inspection 475
Pipeline spans are a common occurrence where the seabed terrain is uneven. The main
problem with assessing ‘real’ spans is determining the actual length and height of the
span. The difficulties in determining accurately the span height and length arise from
■ The variable end conditions for different seabed soil types
■ The potential for any mid-span touchdown
■ The spans may move and change shape over time.
For the design of a pipeline, it is important to assess the maximum allowable span
length. This should be done for both the installation and operational cases. For
maximum allowable span lengths, it will be necessary to establish the peak stresses in the
pipeline for both static and dynamic loading of the span, consider the potential for
pipeline buckling due to the combined axial and bending loads within the span. Also,
possible fatigue due to VIV and interference with trawl gear may need to be assessed.
The DNV approach makes use of finite element methods to assess interplay between
adjacent spans.
Having found a defect during the internal survey, the next step is to decide whether it is
safe to continue operation or whether it is necessary to make a repair. We will consider
the approaches taken in evaluating the internal corrosion and dents.
Internal corrosion is rarely so simple as an isolated pit. The picture above shows some
general corrosion, some erosion, some preferential attack of the weld and some isolated
pits. The issue is how do we evaluate whether the pipe is safe?
476 Overview of pipeline engineering
ASSESSMENT OF CORROSION
Using finite element analysis and burst tests, corrosion defects have been assessed and
formulae developed to predict the safe operating pressure for a given defect or set of
combined defects. The assessment method is based primarily on the axial length of the
defect (or its equivalent axial length if there are a number of defects together) and the
remaining wall thickness.
A long defect will fail as a rupture while a short defect will fail as a leak. It is therefore
crucial to distinguish whether groups of pits are close enough to act as a single defect or
whether they will all act as isolated pits.
Cookbook formulae are given for the above analysis in ASME B31.G and more recently
(and more comprehensively) in DNV RP-F101 ‘Corroded Pipelines’, 1999 (note: not to
be confused with DNV OS-F101).
Pipeline inspection 477
The assessment of dented pipelines is usually based on the unpressurised dent depths. It
is crucially dependant on whether there are any localised defects such as gouges, cracks
or sharp folds within the dent. Essentially plain dents (without gouges, cracks or sharp
folds) fail at the same pressure as undented pipe. Consequently the problems that they
cause are centred on fatigue and the obstruction of pigs. The latter is due to the fact that
the dent reduces the diameter of the pipeline locally and could cause the pig to jam. The
fatigue aspect is due to the fact that there are stress concentrations at the dent, which
will flex as the internal pressure varies. This is covered in the next slide.
Should there be any gouges or cracks, then the dent could fail rapidly and
catastrophically due to a time-dependant creep in the material. To avoid this, the
pressure must be held below 85% of what it was when the dent was formed.
478 Overview of pipeline engineering
FATIGUE IN DENTS
Dent size
160
(% of diameter)
1%
120
2%
100 100 3%
4%
Δσ/ΔPP
80 5%
6%
60 7%
8%
40
9%
20 10%
10
0
15 20 25 30 35 40 45 50 3
3⎛ 100 ⎞ 3
D/t ratio Fatigue ∝ σ = ⎜ ⎟ = 10
⎝ 10 ⎠
The above chart shows stress concentration factor (in this case the stress divided by the
internal pressure) versus D/t ratio. For offshore pipelines we are typically in the D/t
ratios of 15 to 25. The experimental results in the graphs show that the deeper the dent,
the higher the stress concentration factor.
It can be seen that a 7% dent in a pipe with a D/t ratio of 25 induces a stress 10 times
higher than that for a plain undented pipe. Given that fatigue is proportional to stress
cubed, this dent therefore reduces the fatigue life by a factor of 10³ or 1 000.
In summary, known defects may be acceptable provided that they are are not too severe.
Pipeline inspection 479
Internal corrosion
Determine risk of rupture or leakage
Assess corrosion length, remaining wall thickness
and proximity of other defects
Dents
Determine risk of rupture, interference with pigging
Reduced fatigue life on gas lines
Assess dent depth and presence of other defects
Any questions?
For the assessment of internal corrosion defects, the objective will be to determine the
risk of pipeline rupture or leakage. The assessment should consider the length of the
defect, the remaining pipe wall thickness and the proximity of other defects to establish
if they are significant.
Exposure
PIPELINE EXPOSURE
Pipelines are often buried for reasons of protection, thermal insulation or stability. If a
section of pipeline that was previously buried is found to be exposed on the surface then
480 Overview of pipeline engineering
this needs to be assessed. Depending on the reasons why it was originally buried, it may
be acceptable for a short section of line to be left exposed.
Note that rock dump cannot be used to restore thermal insulation because of the free
flow of water between the rock so mattresses or trench and burial are needed.
EXPOSURE ANOMALY
ASSESSMENT
Exposed sections of pipeline may still be acceptable, particularly for short lengths.
However, assessment is required.
Where cover was provided to prevent pipe movement, the line may be at risk of
upheaval or lateral buckling. In shallower waters, winter storms may move the pipeline
and initiate buckling or damage coating.
Trawler gear may impact the pipeline and remove coating or anodes.
Where the cover was needed to maintain the temperature of the pipeline, the arrival
properties of the product may become out of specification.
For the assessment of spans, the potential problems are bending, buckling and vortex-
induced vibrations.
Pipeline inspection 481
Whilst normally, scour is a problem for mobile sandy or silty seabeds exposed to strong
currents, Jee Ltd was involved with an exposure of a rock-dumped pipeline.
The summer survey of 2006 of a natural gas export pipeline for a major operator
revealed that the armour layer had been lost in the shallows of the shore approach – in
water depths of 7 m to 9 m (23ft to 30ft). The survey showed some 100 m (330ft) of
exposed pipeline and a short 9 m (30ft) spanning section. This deterioration had been
worsening over the last three surveys, despite the pipeline protection having been stable
for the previous 17 years. An adjacent pipeline had been rock dumped at about this time
and may have modified the current and wave regime.
However, there are a number of other possibilities. The original size of armour stone
may have been too small. It is common to design for 1:100 year return wave and
currents. Such a severe storm may not have occurred until just before the adjacent
pipeline needed additional protection (both lines were affected at the same time). Recent
developments in rock sizing recommend adding algebraically the shear due to waves and
the shear on the rock slope due to current : earlier analysis methods added their
velocities algebraically and then applied them to the slope. The natural seabed used as a
foundation may have settled or scoured away. The armour rock may have been
damaged and broken in storms over the years, leaving a stone size insufficient to provide
stability – many shore protection works fail gradually in this way.
A study of the recent storm data and last five year’s of annual video and side-scan
surveys is likely to indicate why the armour stone has been lost.
However, due to the length of exposed pipeline and the proximity of winter storms, it is
necessary to order more rock dump immediately to restore the protection for the final
10 to 15 years of the pipeline’s life, and avoid further spans forming.
482 Overview of pipeline engineering
EXPOSURE ASSESSMENT -
SUMMARY
Exposure caused by
Scour of sand or silty seabed
Damage to rock dump
Cover needed for
Protection – impact from trawler or dropped object
Stability – uplift or lateral buckling
Insulation – flow assurance (wax / hydrate formation)
Assessment may show no action to be taken
Monitor in following surveys
Any questions?
Exposed lengths of pipeline can be due to scour of sand or soft sediments or by damage
to rock armour layers.
The assessment needs to consider why the pipeline was covered in the first place.
It may show that no action need be taken immediately, but that the situation requires
monitoring.
ANOMALY ASSESSMENT -
SUMMARY
Pipeline span
Assess risk and consequences of buckling and VIV
Internal corrosion and dent
Determine risk of rupture or leakage, interference
with pigging and reduced fatigue life
Exposure
Cover needed for thermal or impact protection
Risk of further deterioration, buckling or damage
Could be precursor to span
Any questions?
Spans are not necessarily a cause for concern. There are many short spans on pipelines.
However, in the case of spans higher than 0.7 m (2ft), these become a risk to trawler
Pipeline inspection 483
men. Yielding damage can also occur by buckling or bending under self weight. Fatigue
damage may be caused by VIV in strong currents.
For the assessment of internal corrosion defects, the objective will be to determine the
risk of pipeline rupture or leakage. The assessment should consider the length of the
defect, the remaining pipe wall thickness and the proximity of other defects to establish
if they are significant.
For the assessment of dents in the pipe wall, the objective will be to determine the risk
of pipeline rupture, reduced fatigue life or if the dent depth is sufficient enough to
prevent the passage of pigs. The assessment should consider the unpressurised dent
depth and the presence of other defects, such as gouges, cracks or sharp folds.
Sections of pipelines that become exposed may be acceptable, but the situation must be
assessed and monitored because scour can develop into spans.
484 Overview of pipeline engineering
REMEDIAL WORKS
REMEDIAL WORKS
Retrofit anodes
Span correction
Pipeline stabilisation
Anti-scour fronds
Grout bags
Mattresses
Rock dump
Clamp
Sealant application
Having conducted a survey, it may be necessary to carry out some maintenance tasks
(remedial works). These are detailed in the following slides.
Retrofit anodes tend to be a sled full of zinc placed next to the depleted anode and
electrically connected to the pipe. Before fitting, it would be normal and wise to
establish the cause of the anode depletion.
Span correction is applied where the span is too long and may be prone to overstress or
fatigue due to vortex-induced vibration. The correction takes a number of forms. It
could be the placement of sand or grout bags at mid-span to provide support.
Alternatively mattresses could be placed below and above the span, or the span could be
rockdumped.
If the pipeline has been dented or there is a corrosion defect then a clamp may be placed
around the pipe - either to seal any leaks or to support the dent and prevent fatigue.
Clamps are dealt with below, but other options are covered in the Modifications and
Repairs module.
Pipeline inspection 485
STABILISATION
Grout bags
Anti-scour fronds
Mattresses
Rock dump
Where the pipeline has deburied and is unstable and moving around on the seabed, pipe
stabilisation is necessary. Were it not corrected, this could lead to a fatigue failure of the
pipe. A number of techniques are available. These include
■ anti-scour fronds, as shown in the picture. When placed over the pipeline, these will
trap sediment from the water and build a sand berm which stabilises the pipeline.
■ concrete or bitumen mattresses laid over the pipe.
■ grout bags placed over the pipe.
■ rock dumped onto the pipe
STABILISATION MATTRESSES
486 Overview of pipeline engineering
Dense mattresses are placed over the pipeline to stabilise it. These mattresses may be of
bitumen and rope construction, or of concrete blocks on a rope matrix (shown above).
Both, when placed over the pipeline, will conform to the shape of the pipeline and
seabed.
First we will consider clamp repairs, using a landline clamp to show the principles. The
picture shows the clamp being installed around a pipe. Its flanges will be bolted together
on both sides. There are elastomeric seals around each end and down both sides so that
if any fluid does leak out into the annulus, it is contained by the clamp.
Sturdy
Rated up to
≈200 bar
(≈3000 psi)
Hinges open
for installation
Pipe must be
able to take
weight
Pipeline inspection 487
When the pipeline clamp is scaled up to accommodate large diameter and high-pressure
lines, it can become a very heavy and robust device. The clamp shown above weighs 40
tonnes and has a steel thickness of 406 mm (16in). There are hydraulic clamps on the
top to hinge it open and closed. Each bolt is three inches in diameter, is over a metre
long and needs buoyancy attached to help the diver lift it into place.
From the viewpoint of the pipeline engineer, one crucial calculation to carry out is to
check that the damaged pipeline still has sufficient strength to withstand the self-weight
of the clamp being attached.
Seal
There are two ways to use pipeline repair clamps: as pressure vessels or as structural
supports.
The pressure vessel mode is shown in the diagram above. The clamp forms a sealing
chamber around a leaking pipe. In this mode the clamp is truly pressure containing and
forms part of the pipeline system.
488 Overview of pipeline engineering
The clamp is attached to the outside of a dented (but non-leaking) pipe. The annulus
between the clamp and pipe is filled with grout and this is allowed to set. When the
pipeline is repressurised, the hoop stresses from the pipe are transmitted out to the
clamp. The clamp thereby gives structural support and stops the dent flexing, hence
returning the fatigue life of the damaged section back to that of the undamaged pipe.
The clamp is therefore a permanent structural repair but is not pressure containing.
LEAK REPAIR
www.Seal-Tite.com
Pressure-activated sealant for small leaks
Can be delivered using a batch pig train
Pipeline inspection 489
One company, Seal-Tite, provides a new leak repair concept without the need for
external intervention. It is claimed that Seal-Tite is able to cure leaks with only a brief
off-line period.
The leak repair sealant is deployed inside the pipeline: for subsea pipeline applications it
can be delivered to the leak site in a train of pigs.
The pressure differential across the leak polymerises the liquid sealant and plugs the leak.
This system has been used successfully offshore and in a wide range of other
applications.
1. Fluid escaping through leak site 2. Sealant bridging across leak site
Safety valve
Sealant
flexible
Seal Element polymer seal
at leak site
3. Leak sealed
The pictures above illustrate the process of sealing a leak adjacent to a safety valve.
Initially the fluid escapes through the hole. The pressure differential across the leak
starts the polymerisation process. The sealant starts to solidify at the edges of the leak
and the hole is gradually plugged.
490 Overview of pipeline engineering
Any questions?
In cases of severe damage the affected section of pipeline will need to be replaced. This
is covered in the Repair module.
Any questions?
Pipeline inspection 491
We have introduced the main concepts for the integrity management of subsea pipelines.
Inspections are necessary to ensure the continued safe operation of the pipeline.
Anomalies are identified and corrected before they are severe enough to cause problems.
The nature and frequency of inspections is determined by a risk-based inspection plan.
External inspections can be done using ROV, side scan sonar or AUV. Internal
inspections are done using intelligent pigs.
Following an inspection, any anomalies are first identified and then assessed. Those that
are judged to be unacceptable are corrected.
492 Overview of pipeline engineering
Modification and repair
Modification and repair 495
EXPECTATION
EXPECTATION
We may wish to add a new branch to the network. This involves a tie-in with a tee or
wye (shaped like a T or Y) to existing pipe. Where this is not a hot tap, it is necessary to
first isolate the section to be cut open.
An overview is given for the methods that can be used for pipeline isolation and tie-ins.
The ‘Integrity Management’ module covered minor remedial works intended to stabilise
the damaged section. Where a deep dent or major damage has occurred, it may be
necessary to replace a section of the line or even the whole pipeline or riser. We will
look at methods to carry these out.
Finally, the considerations for planning the decommissioning of pipelines are discussed.
496 Overview of pipeline engineering
ISOLATION
ISOLATION
One way of doing this might be to shut down, depressurise and water-flush the entire
pipeline.
In most cases, this is undesirable from an operational point of view. For example, in a
gas trunk line, the depressurisation would involve flaring a lot of gas (lost inventory), and
flooding would lead to a requirement to dewater and vacuum dry, which could put the
pipeline out of service for many months.
Modification and repair 497
LOCAL ISOLATION
Work site
Hydrocarbon
Inert fluid/gas
Isolation plug
The alternative to depressurising and flooding the entire line is to perform a local
isolation. This introduces an internal barrier between the product and the worksite.
Therefore, only a short section of the pipeline is flooded and the time taken to flood,
dewater and dry is greatly reduced.
Depending on the isolation system used, pipeline pressure may also be resisted, avoiding
the need to depressurise the system.
ISOLATION METHODS
There are a range of isolation techniques. The main ones are listed above and are
described in the following slides.
498 Overview of pipeline engineering
Differential
pressure
Friction force
Friction Wall force
Wall force
High friction pigs are bi-directional pigs with oversized polymeric discs giving a high seal
with the pipewall. They are available from a range of pig manufacturers.
The principle they use is that increasing the differential pressure acting over the pig seal
will result in an increase in the force applied on the wall. This increased wall force then
causes an increase in the frictional force resisting the pigs movement. Increases in
frictional force result in an increase in the differential pressure. The point at which in
the pig becomes trapped in the pipeline is determined by controlling the differential
pressure applied over the pig.
They can generally hold differential pressures of about 3 bar (44 psi) and are therefore
used for isolation where the pipeline is depressurised. The use of trains enables a greater
total differential to be held. They are pigged into place. Because the high seal discs will
wear during this placement operation, they are generally limited to use within about 2 km
(1.2 mile) of the pig trap.
The design of high friction pigs is critical to their functioning. Consideration should be
made to ensuring the flanges are capable of holding the seals against the high drag forces
and ensuring they do not pull out. Care should be taken to ensure the seals will not
buckle. Compression set may become a problem, where the seal material relaxes and
does not provide the necessary sealing resistance.
Modification and repair 499
ISOLATION PLUGS
Isolation plugs are pigged to the required location, have brake shoes which set against
the pipe wall and hold them in position even against full-line pressure, and elastomeric
seals which are inflated to effect a complete seal against the pipe wall.
Tethered isolation plugs are suitable for use near to a platform and have been used
extensively for functions such as change-out of platform emergency shutdown valves.
The plug is pigged into position and receives power and control through an umbilical
which is run down the inside of the line. There is a limit to how far the plug can be
pigged from the platform because the plug has to tow the umbilical behind it. Tethered
plugs are capable of withstanding 150 bar (2180 psi) differential pressure.
Remote set isolation pigs are similar in principle to the tether plugs, but do not utilise an
umbilical. Power and control is provided onboard and is remotely operated. This
means that there is no limit to where in the line the isolation pig can be used. Remote
set plugs are capable of withstanding of the order of 80 bar (1160 psi) differential
pressure.
500 Overview of pipeline engineering
ISOLATION PLUG
This is another manufacturer’s isolation plug showing the details of the slightly different
locking mechanism.
The figure above illustrates the method of remotely activating a SmartPlug isolator.
The vessel sends extreme low frequency (ELF) signals to a seabed array. As the plugs
arrive, the ELF communication link (ECL) activates the remote activation system (RAS)
which locks the plugs in place.
Modification and repair 501
PIPE FREEZING
Gel
Insulation
Product Gas
Cut-out area
Pipe freezing produces a plug by freezing a slug of water or gel within the pipeline. The
gel or water is introduced within a train of high seal pigs.
Liquid nitrogen is used to chill the coolant on the vessel. This coolant is then pumped
through a freeze jacket installed around the pipe. The pipe is maintained at a
temperature of -20°C to -40°C (-4°F to 40°F).
PIPE FREEZING
Pipe freezing involves the controlled formation of a solid frozen plug inside the pipeline
using specialist equipment and techniques. Once formed, the plugs provide isolation of
the line while pipework modifications are carried out.
The pictures show the process on a landline. However, the technique has frequently
been successfully used subsea.
ISOLATION - SUMMARY
Any questions?
The simplest method of isolation is to insert a high friction pig to block the line. The
use of this is limited by both pressure differential and distance from pig inserter.
Isolation plugs lock against the side of the pipe wall, forming a barrier to prevent
product flow in the isolated section. These plugs can be either remotely operated or
tethered, depending on the location of the isolated section.
504 Overview of pipeline engineering
Pipe freezing is another method of isolating a section of the pipeline, involving the
formation of solid frozen plugs capable of withstanding high pressures.
Line stopping involves hot tapping the pipeline, to insert a block head, which prevents
flow of product through a section.
Modification and repair 505
TIE-INS
TIE-INS
Repairing damage is not the only reason for needing to work on the pipeline.
Other common reasons are expansion of the network as new fields are brought on
stream or the requirement to tie in a third party pipeline. Because of decommissioning
of some unmanned platforms, a new bypass diversion was inserted into the Frigg line
(2004 and 2005 seasons).
Where facilities such as a tee or wye have not already been provided, it is necessary to
add them whilst the pipeline is in service.
An alternative solution is to use a single hot tap (without the stopple). This can be
installed with hyperbaric welding or clamp as before, and provides a valved flange to the
new branch.
For a cold tie in, following isolation using one of the methods already described, a
section of the line is purged with inert gas.
506 Overview of pipeline engineering
1168.4 mm by
609.6 mm
(46in x 24in) Tee
Contingency
bolted clamp
144 bar
(2.1 ksi)
MAOP trunk
pipeline
The photograph shows a hot tap Tee repair clamp supplied by Stats Group.
TIE-IN PROCEDURE
The procedure for a tie-in follows the flow diagram to the left.
Once the coating is removed, full inspection is required prior to ensure the area is
acceptable prior to cutting into the pipe itself.
Modification and repair 507
A new tee can be added to the pipeline without the need to shut down the existing
pipeline, using the hot tap procedure described previously.
The horizontal T is installed with the cutter unit and clamp bolts attached. In the Gulf
of Mexico, it is more common to use a vertical Tee, so the slinging arrangement is
different.
For smaller lower pressure lines, grouted tees may be used. This avoids welding.
508 Overview of pipeline engineering
The grouting sleeve can be dimensioned to allow for any pipe ovality and provides an
electrical insulation between the new and existing lines.
This video illustrates the hot tapping process used to perform a repair to a 12” flowline
in the Yellow sea off the coast of northern China. This flowline supplied 40million
cubic meters of gas daily to Tianjing. Due to the vital importance of the pipeline to
Tianjing city, the repair work has to be carried out without interruption to normal supply
of gas to Tianjing and especially to the main power plant in the area.
CNOOC had developed the fields in the west of Gulf of Bo Hai, Yellow Sea in northern
China. In the late spring of 2000 the pipeline was damaged, possibly due to impact from
a sunken ship. The damaged pipeline has a dent of 11” x 5” x 0.5” and a rupture of 2.5”
long. Initially, CNOOC installed a make-shift sleeve pipe for the damaged pipe section.
However, due to the severity of the damage, it was unlikely that the pipeline could be
pigged in the future and therefore a permanent repair was required.
Armed with the hot-tapping technology from TWD and Oil States Hydro-Tech, repair
work to the pipeline was carried out in October 2001. CNOOC were in charge of the
project, while COOEC carried out the repair work. The hot tapping operation allowed a
bypass to be installed, enabling the continuous supply of gas to Tianjing while the
damaged pipe was replaced by a pre-fabricated section.
Modification and repair 509
Tappable flange
A recent innovation is the tappable blank flange, which provides a location at which a
valve can be installed and hot-tapped into should it be required at a later time.
This avoids the need for fitting a pipe clamp or hyperbaric welding. Compared with
these alternatives, the tappable blank flange is relatively inexpensive.
However, the possible tie-in locations need to be foreseen. Future damage locations
cannot be determined. How many of these flanges should be added to pipelines and
where is a matter of judgement. The added cost must be allowed for - especially if it is
for a third-party.
Good practice dictates the use of double block valves with a bleed system between. This
means that safe operation can be guaranteed.
510 Overview of pipeline engineering
VALVING
To achieve isolation, a double block and bleed valve arrangement is required. This
means that two valves are used with a bleed-tapping between. This provides redundancy
and a means of monitoring for leakage.
In piping, provision of drains and vents will enable dewatering and drying of pipework.
PIGGING FACILITIES
Pig trap
Branch line flow
New
Existing
Once the mainline tee has been fitted with double block and bleed valves, the branch
flow can be attached. It too has a double block and bleed termination.
The valve arrangement provides full isolation both from the main line and the branch
line ensuring a safe working environment for divers or future operators of the lines.
This illustrates how pigging facilities can then be provided. Temporary or permanent
pigging facilities can be attached.
If the pig trap were then removed, this arrangement could be used for provision of
future additional tie-ins. Again, an extra double block and bleed valve set arrangement
would provide the means of isolating the two-branch lines independently.
Wye piece
Same diameter as the existing
Allows pigging of the new line into the existing
Longer pigs
Different size lines
Dual diameter pig Main
pipeline Pigged in
this direction
Branch line
Where the new branch is of the same diameter as the existing line, the use of wyes rather
than tees means that both the lines are piggable.
Longer pigs are normally used to ensure that they pass the junction. In gas lines, the
pressure on the branch should be adjusted to ensure easy passage. If the pressure is too
high, the pig will stop before the wye. If it is too low, as the pig passes, the flow will
divert back up the branch.
Where the branch line is smaller than the main line, a dual diameter pig is used. If the
branch is not to be pigged, then bars are sometimes provided at the opening of the wye
to ensure easy passage of the pig.
Although normally pigs are sent in only one direction, an arrangement like railway points
is available that ensures pigs can be sent in the reverse direction to either branch.
512 Overview of pipeline engineering
NEW WYE
Shut down
existing pipeline
Isolate and
cut-out section
Install new wye
Abaqus FE stress model
entrant
New
Existing pipeline
The new valves, pipework and wye piece would normally be mounted onto a skid with a
protection structure over.
Valves are normally added to enable shut down of either branch. Again, double block
and bleed system would be provided.
The pipeline would be shut down and the section isolated as before. The new wye
would be connected up using bends.
The FE model of a reinforced wye piece recently carried out by Jee shows the high
stresses (yellow) during hydrotesting in the ‘crotch’ area. The wye can be manufactured
from sections of a 30° bend and a straight pup piece. The three stiffener plates help to
prevent the widest section from bellying out.
Modification and repair 513
TIE-INS - SUMMARY
Any questions?
Tie-ins can also be used to bypass sections of pipe that require replacement.
We have looked at the steps in undertaking a tie-in with careful inspection of the existing
line to ensure that it is in a suitable condition.
A number of methods have been described including bolted or grouted clamps and a
pre-fitted blank flange - useful when the need had been foreseen.
The main principles of valving and fitting of pig traps has been described.
REPAIRS
REPLACEMENT SPOOL
Two options:
Hyperbaric weld
Mechanical connector
In cases where the pipeline damage is too extensive to be repaired by a clamp, it will be
necessary to cut a section out and insert a new replacement spool.
The techniques for doing this are initially to isolate the pipe and then to insert the new
section with either a hyperbaric weld or a repair connector. These issues are addressed
in the following slides.
Modification and repair 515
SPOOL REPLACEMENT
WELD OR CONNECT?
Once the location of a leak or damage has been detected, the pipeline on either side is
isolated using one of the methods described earlier.
The seabed beneath the site needs excavating to gain access for the equipment needed.
The damaged pipework is cut out and a new section of spool inserted.
HYPERBARIC WELD
During the initial development of the North Sea oil and gas fields in the late 60s and
early 70s, it became apparent that the wet welding techniques used in salvage and civil
engineering applications would not be adequate for these deeper water conditions. This
lead to the development of hyperbaric welding techniques which have been utilised for
the tie-in and repair of subsea pipelines.
A hyperbaric weld is carried out in a dry chamber, known as a habitat, which is placed
over the pipeline and the seawater is expelled with a helium/oxygen breathing gas.
Diver-welders enter the habitat and perform the welding operation in a dry environment,
working at the ambient seabed pressure. Prior to the installation of the habitat, the pipe
ends are aligned using pipe handling frames located on the pipeline.
Hyperbaric welding was initially developed using manual procedures, such as Gas
Tungsten Arc Welding (GTAW) and Shielded Metal Arc Welding (SMAW). GTAW
(due to its high quality but slow deposition rate) has been used mainly for the root and
hot pass, and SMAW, which is a quicker but a less controlled process, used for the weld
cap.
The quality of manual welding is directly related to the performance of the welder, which
can vary from welder to welder, and is also be dependant on the water depth, as human
performance can be impaired due to the effects of hydrostatic pressure.
In recent years, mechanised welding systems have been developed which have improved
the overall quality and repeatability of hyperbaric welding, and also allow welding to be
carried out at greater depths. Special welding procedures need to be prepared to account
for the different pressure at depth.
However, the operator needs to maintain full qualifications in diving, end preparation,
welding of a number of possible diameters, wall thicknesses and pipes material as well as
many types of NDT operations.
HYPERBARIC SPREAD
These figures show a welding habitat and associated pipe alignment frame.
Modification and repair 517
Subsea 7 have undertaken a number of hyperbaric welds for Total on the Frigg lines’
TP1 / MCP-01 bypasses as part of an EPIC contract.
This required hyperbaric welding on 813 mm and 610 mm (32in and 24in) pipelines to
re-route them around two platforms in 90 m to 110 m (300 to 360 m) of water.
Hyperbaric welding was selected because they are large diameter with a relatively thin
wall, 19 mm (¾in).
In the first season 4 pups (8 welds) were welded with a further 4 welds during the
second season.
Once the Frigg diversions were completed, the steel platforms will be removed in their
entirety (similar to the procedure at Maureen) but only the topsides will be removed
from the gravity concrete base structures.
This contract follows Subsea 7’s successful completion of hyperbaric welding work in
Australia.
A hyperbaric weld will generally take considerably longer than is required to make up a
mechanical connection. There are water depth limitations for hyperbaric welds,
although welds are generally feasible within diver depths.
The advantage of a hyperbaric weld is that the pipeline is returned to its original
condition with no subsea equipment remaining.
It is also possible to avoid hydrotesting of the repair by use of the ‘Golden Weld’.
518 Overview of pipeline engineering
GOLDEN WELD
A ‘Golden Weld’ will undergo a thorough testing with a number of different non-
destructive testing (NDT) methods. The results are used to verify the acceptability of
the weld.
This then eliminates the need to conduct a full hydrotest of the entire pipeline
containing the repaired section.
Note that new sections or pups being used to replace defective sections will have already
undergone a full hydrotest in the yard or on the vessel prior to their incorporation into
the existing system
MECHANICAL CONNECTORS
The alternative to a hyperbaric weld is the use of a mechanical connector. There are a
variety of connectors available, but all make a seal with the outside of the pipe, which
first needs to be cleaned of all coatings.
The diver in the picture is inserting the Flexiforge tool into the connector. See next
slide.
FLEXIFORGE CONNECTOR
The system involves an end fitting incorporating a standard flange, which slips onto the
cut pipe end and is swaged. This is a cold-forging process performed using an internal
expansion tool. The pipe is plastically expanded into the connector. The connector
incorporates a system of rings and grooves that ensure a metal-to-metal seal.
Because the thicker-walled Flexiforge fitting is elastically expanded whilst the pipe is
plastically expanded, the fitting becomes pretensioned in the hoop direction once the
forging tool is removed. This ensures a high axial load capacity.
520 Overview of pipeline engineering
MORGRIP CONNECTOR
The connector is slid on to the cut pipe, positioned and then activated by tensioning
longitudinal bolts. The Morgrip contains graphite activated metal sealing rings (shown in
black in the picture).
It has an attachment mechanism, based on ball bearings, which indent the external
surface of pipe. These act to wedge the connector onto the pipe, so that the harder the
pressure tries to push it off, the more the ball bearings dig in.
Two sets of seals are incorporated to allow a leak test to be performed between them.
Modification and repair 521
MORGRIP
Generally
diver-installed
ROV version
available
Tensioning
bolts
Activates
gripping
system and
metal seals
Both diver and ROV installable versions are available. The Morgrip connector has been
used for both repairs and new-build tie-in applications.
The main advantages of mechanical connector systems are the fast make-up time and,
because diverless systems are available, no depth limitation.
Mechanical connectors do need to be leak tested which, for some connectors, requires a
full system hydrotest.
522 Overview of pipeline engineering
This full system test can be avoided if the connector includes a seal test port, as does
Morgrip. This tests as a back pressure between the seals.
Some types of connectors are not made for larger diameter pipelines, and specials may
be difficult to procure in time for emergency repair operations.
Depending upon the risk assessment, it is normal to have either standby connectors or a
fully trained hyperbaric welding team.
In shallow water,
‘Cursor’
use a direct umbilical Strong umbilicals launch
supplying control, system
power and support
Workclass Tether
or eyeball ROV management
system (TMS)
Sea current
or ‘Top Hat’
Secondary
eyeball ROV
The figure shows three procedures for operating ROVs, two of which are specifically
designed for deepwater applications. When operating in deepwater environments, one
of the main concerns is the time taken to lower the ROV to the seabed (this can be
several hours). As the ROV requires a power supply cable there is a problem in that the
umbilicals become both heavy (due to their length and strength requirements) and are
subjected to large loads due to sea currents. Operators have developed two main
systems where a powered unit with separate thrusters carries the workclass ROV down
to the work site. This unit can be sized to withstand the loads from the main umbilical.
When in position, it then releases the ROV on a lightweight umbilical or tether. This is
normally up to a few hundred metres long, but can be made up to 1 km (3280 ft).
The figure shows two different methods of deepwater ROV installation. One involves
lowering the ROV in a steerable garage. Any heavy equipment or selections of tooling
can then be lowered to the seabed on a separate frame. This method may also include a
secondary eyeball class ROV slung beneath, which can be used to oversee the operations
of the workclass ROV or other tasks.
The second method involves lowering the ROV on a device known as a TMS (tether
management system) or Top Hat which releases the ROV at the worksite. The ROV in
this case grasps a separate tool unit beneath. This may be a trencher, burial device,
flowline connection module, suction anchor installation, mining or military.
Launch using a ‘Cursor’ enables the almost neutrally buoyant ROV to be pushed safely
through the surface zone (where the thrusters have difficulty operating) into the deeper
Modification and repair 523
water beneath the vessel. The cursor can run down a set of rails or wires, and it holds
the TMS or garage.
Typically, workclass ROVs locate themselves by the left arm grasper, and manipulate
using the right arm. When following a pipeline, the ROV may fly above the route, run
on tracks or grip the line using wheels.
DIVERLESS REPAIRS
ROV-operated systems have been developed for pipeline repair in deepwater. That is,
below diver depth.
During installation, the buckled section may be cut off and removed, and a temporary
pulling head fixed onto the end of the undamaged section to enable the line to be
dewatered, thus restoring its buoyancy. The recovery wire is then pulled up to the
laybarge and laying resumes.
Alternatively, the buckled line may be used as a recovery system to pull the undamaged
section back in order to effect a repair on the barge.
We have just seen how a pipe can be repaired with mechanical connectors once in
operation.
Flexible risers are normally replaced. However, some repairs of impact damage to the
outer layer may be effected using clamps. The annulus is then filled with inhibited water.
In practice, most deepwater systems are built to perform a specific repair as part of a risk
reduction plan. Fortunately, they are rarely used.
524 Overview of pipeline engineering
Sonsub-Saipem
Bluestream wet buckle repair system
Diamond
cutter unit
This cutter can be used to repair a wet buckle at depths of up to 2200 m (7220ft). It was
developed for use on the Bluestream Project in the Black Sea.
The intention is to cut the pipe below the buckle and insert a recovery head. The
evacuated pipe can then be brought back to the surface and laying continued.
BLUESTREAM HEAD
Pressurised
volume
The second tool designed to be used by the ROV sealed the end of the pipe, enabling
water to be removed and allowing the more buoyant pipe to be lifted.
Modification and repair 525
A thin-walled can was inserted inside the pipe and expanded. This plastically deformed
the end of the pipe onto an anvil. The latter deformed elastically.
When the pressure was released, the anvil recovered (elastically) and held the
permanently deformed pipe wall using friction.
Valves (not shown) permitted the pipe to be purged. This reduced the weight enabling
the pipeline to be recovered onto the laybarge, where the unit could be cut off.
Fortunately, it was a contingency item only. Although proven technology, it was not
used in anger.
Loading facility
Crude sent from shore storage tanks to ‘sea island’
Ballast water line discharge from ship to shore
914.4 mm (36in) by 1200 m (3937ft)
Inspection using RTD tethered crawler
Ultrasonic pipeline
inspection technology
Detector stand-off at
nominal bore 75 mm (3in)
Transmission medium
Water or oil
Zig-zag coverage of wall
Spider PIT
The ballast water line is used to transfer contaminated water from the tankers moored at
the terminal when they are receiving crude oil from the onshore storage tanks. The site
applied internal lining at the field joints failed due to quality control (QC) problems
during construction, resulting in severe internal corrosion.
A single pipeline was used to transport oil offloaded from tankers at a sea island
structure to the tank-farm onshore. Because it was a single line, it was not possible to
regularly pig the line after each discharge.
CORROSION OF SEALINE -
BAHAMAS
The RTD crawler proved that severe corrosion had occurred, particularly to the bottom
of the line. The nature of the corrosion took the form of deep pits: in places the wall
had been reduced from 12.7 mm down to just 3 mm; in some areas, the corrosion
affected over 500 mm length mainly at the 6 o’clock position (bottom of pipeline). In
three pits, there was just 2 mm of wall left.
It was suspected that the intermittent discharge of oil (every few days or so) allowed the
small amount of water to drop out and collect at the and then travel back down to the
lower offshore end of the pipeline.
The photographs show sections of the line that were subsequently removed during the
repair operations. The first shows the corroded wall with a core sample removed for
testing (at lower right) and the pits covered with corrosion product (rust). The second
shows a cleaned surface prior to repair, demonstrating the depth of the pits encountered.
528 Overview of pipeline engineering
Land and Marine Engineering relined the sealine using a glass reinforced plastic (GRP)
liner. This was purchased in 15 m (49.2ft) lengths and assembled into 200 m (656ft)
strings using simple GRP overwrapping of the square-butt ends.
The strings were pushed down into the damaged steel line using winches on the beach
attached to a beam at the rear of the string. Sets of rollers on top, bottom and sides of
the pipe were required to avoid strut buckling of each string. These had to be released
as the beam moved forward.
The photograph shows the pressure testing of the liner. Once this was completed, the
annulus was filled with grout to provide fixity to the liner within the pipe during
operation. This commenced at the offshore end with displaced water being released
from ports drilled into the damaged steel line every 300 m (1000ft). The ports were
monitored for arrival of the grout so that operations could move to the next section
towards the shore.
Modification and repair 529
REPAIR - SUMMARY
In the Integrity Management module, we looked at repair clamps that can be used as a
reinforcement for minor defects such as dents.
However, when a section of the pipeline has become significantly damaged, then it may
be necessary to replace that section of the line with a replacement spool.
Two types of connection can be made to tie-in the spool. One is to perform a
hyperbaric weld, this will be relatively expensive. A ‘golden weld’ means that the system
does not require a pressure test.
The other tie-in method is to fit mechanical connectors to the ends of the spool and the
existing pipeline. A range of mechanical connectors are available. The advantage is they
do not all require a diver to make the tie-in and allow remote operation in deepwater.
In deep water, we must use diverless techniques to connect the pipelines to the risers or
well heads. We also need diverless methods for repair to lines should damage occur.
The tools used for undertaking such work usually are attached to ROVs. We have
examined how these tools are operated.
Methods of pipeline and flexible riser repair have been shown, both during installation
and operation.
Repair systems must be fully tested and available for emergency operations. Fortunately,
they are rarely needed.
Where a leak has not yet occurred on a short length of sealine, it is possible to provide
strength using a GRP lining.
530 Overview of pipeline engineering
DECOMMISSIONING
DECOMMISSIONING
What to do in order to decommission pipelines and platforms has been debated for
decades. The focus of the debate has been platforms, and pipelines have received little
attention.
The centre for the discussions has been the OSPAR (Oslo/Paris) Convention. This met
in Portugal in 1999 and agreed that in the North Sea, platforms under 10 000 tonnes
should be removed. Platforms over that weight, along with pipelines, should be
considered on a case-by-case basis.
The Maureen platform has already been removed from the Northern North Sea.
The plans to remove the topsides to the Frigg platforms have been drawn up. The
tubular steel support structure will also be removed but those with a concrete gravity
base are to stay. The alternative to totally removing tubular supports is to cut them off
at a level safe for shipping. This might be preferred when they are fixed to the seabed
with difficult-to-detach piles. The Frigg removal work is to be completed by the end of
2012.
Modification and repair 531
We should not be complacent about decommissioning. The public storm over the deep-
sea disposal of Brent Spar is a case in point. No matter what the carefully evaluated
scientific and environmental solution might be, a lot of damage can be done to a
company’s reputation and sales if the public relations are not handled correctly.
DECOMMISSIONING TO DATE
Although a common practice in GoM, there have been relatively few pipelines
abandoned to date in the North Sea.
Most of them are cleaned and then sealed, so a decision on their long-term future can be
made at a later date. They might be reused for development of smaller reserves or for
injection of CO2 back into reservoirs. This helps with extraction and may gain carbon
credits in the future.
By deferring the decommissioning, it has the advantage of not setting a precedent. The
costs of the work can be postponed into some future year’s accounts.
However, the trend elsewhere appears to be towards leaving buried pipelines in place
and removing unburied lines.
Flexibles have a good record for re-use, particularly in Brazil where they are routinely
retrieved, refurbished and re-laid. This is not so in Australian waters where flexibles
tend to be recovered to the shore for disposal.
Incidentally, the Brazilians have also recently placed a disused structure in a fish
spawning ground to act as an artificial reef. This has been done with the backing of
government fisheries scientists and has been shown to be successful in terms of
providing a safe haven in which fish can breed.
This lead might be followed elsewhere in the world. It raises the question of whether
pipelines on the seabed are beneficial to fish (and even to fishermen) in acting as
breeding sites.
532 Overview of pipeline engineering
DECOMMISSIONING - SUMMARY
Any questions?
Decommissioning involves the removal of subsea equipment and components at the end
of the service life.
In the North Sea, there has been limited decommissioning of pipelines. Many are
mothballed or abandoned in a state of protected storage after the subsea manifolds,
wellheads or similar structures have been removed .
Platform topsides often require removal due to their visible nature, but how they are
ultimately disposed of will be determined on a case-by-case basis.
The supporting structure may be removed entirely or cut-off at a level safe for shipping.
Modification and repair 533
Any questions?
An overview was given for the methods of isolation, tie-ins and repairs that may be
needed during the life of a pipeline.
Finally, the considerations for planning the decommissioning of pipelines have been
described.
534 Overview of pipeline engineering
Profiles
536 Overview of pipeline engineering
Profiles 537
TREVOR JEE
MANAGING DIRECTOR
MA CEng FIMechE
Training courses
Trevor has been responsible for the production of the Jee Limited training courses and
presents the following:
■ Overview of Pipeline Engineering
■ Offshore Pipeline Construction course
■ Pipeline Operations and Integrity Management
■ Subsea Pipeline Design
■ Offshore Installation Calculations
MIKE HAWKINS
TECHNICAL DIRECTOR
BTech (Hons) CEng MIMechE
Training courses
Mike presents the following training courses on pipeline engineering:
■ Overview of Pipeline Engineering
■ Offshore Pipeline Construction
■ Pipeline Operations and Integrity Management
■ Subsea Pipeline Design
MARTIN EAST
OPERATIONS MANAGER
BSc (Hons) MSc CEng MIMechE
Training courses
Martin is responsible for the development of the Subsea Pipeline Design course and
presents the following training courses on pipeline engineering:
■ Overview of Pipeline Engineering
■ Pipeline Operations and Integrity Management
■ Subsea Pipeline Design
ALAN KNOWLES
SENIOR ENGINEER
Eur Ing BSc(Hons) CEng MICE
Training courses
Alan has authored a number of Jee Limited courses and presented them on four
continents, both to the public and for companies in-house. These courses include:
■ Overview of Pipeline Engineering
■ Offshore Pipeline Construction
■ Offshore Installation Calculations
■ Subsea Pipeline Design
■ Army depots and landlines
■ Smit Land & Marine Engineering, 1974 – 1988, Design Engineer/Site Engineer
□ Site investigation, structural design and report; then the subsequent
supervision for reconstruction of an historic listed stone jetty at Plas
Newydd. Rip-rap stone apron design around the jetty in strong tidal
currents of the Menai Straits and associated cathodic protection of
structures
□ Analysis of single buoy mooring (SBM) cable support to allow the
exceptional tidal differences in Bay of Fundy
552 Overview of pipeline engineering
PHIL MEDLICOTT
Training courses
Phil presents the following training courses on pipeline engineering:
■ Overview of Pipeline Engineering
■ Pipeline Operations and Integrity Management
■ Subsea Pipeline Design
■ Pipeline stability and use of PRCI pipeline stability software
■ Overview of properties and implementation of polymer composite materials in
offshore applications
Parallel activities
In 1994 Phil Medlicott established his own engineering consultancy business which
specialises in the use of polymer/composite materials technology to meet oil industry
and transport requirements. He still continues to operate this business and has provided
the following services:
■ Project manager of a £280,000 Joint Industry Project to develop the qualification
methodology for FRP lined downhole tubing and flowlines. This work was
completed at the end of 2003 and included the successful testing of FRP lined
steel tubing systems in 160°C and 5000 psi production service environments over
4000 hrs
■ Preparation of ISO 14692:2002 GRP piping Standard for use within the oil and
natural gas industries
Profiles 555
STUART JOYNSON
SENIOR ENGINEER
BSc (Hons) PEng
Nationality: British
Education: Salford University
Academic Qualifications: Degree in Civil Engineering
Professional Qualifications: Professional Engineer
Member of the Institution of Civil Engineers
■ Land and Marine Engineering Limited and associated companies (over 30 years)
□ Production line manager, June 1999 to December 2000. Responsible for
obtaining offshore construction work associated with flowline bundles,
pipeline trenching, tanker terminals, decommissioning and relining. This
involved marketing, preparation of prequalifications and tenders and
negotiations with prospective clients.
□ Operations manager, May 1992 to May 1999. Responsible for the
following:
□ Marketing of the flowline bundle technique including the submission
of budgetary proposals.
□ Co-ordination of tender preparation and the submission of bids for
major offshore pipeline bundle projects.
□ Liaison with alliance partners.
□ Management of the company’s pipeline assembly area at Tain
including liaison with landowners and environmental organisations.
This included the preparation of the annual environmental
monitoring reports with input from environmental consultants and
various specialists
□ Project manager for the Gannet pipeline bundle installation contract, May
1990 to May 1992. This £46 million E.P.I.C. contract included the
fabrication and installation in Shell Expro’s Gannet Field of four pipeline
bundles with lengths up to 3.6km. These bundles were assembled at Tain
where up to 120 staff were employed. The project office staff were located
in Middlesex where the engineering, procurement, and contract
administration duties were undertaken. As Project Manager, was
responsible for all aspects of the contract including liaison with the Client
and J.V. partners, cost control, engineering design, safety, Q.A. and
environmental management and approval of all phases of the work.
□ January 1990 to May 1990, Responsible for establishing the Company’s
pipeline assembly area at Tain in Scotland. This £1.5 million development
was undertaken in 16 weeks and included the erection of fabrication
buildings, formation of access roads over tidal areas, precasting and
positioning concrete pipe supports, setting up permanent offices and
installation of all services. Was based in Tain during this period and
negotiated all sub-contracts and liaised directly with the local council on all
planning matters. Established a working relationship with the various
environmental groups concerned about the site development and addressed
meetings with local business and similar associations.
□ Operations manager, 1988 to 1990. Responsible for the following:
□ The company’s activities in North and South America.
□ Projects involving the relining of underwater pipelines.
□ Operation of the company’s offshore survey department.
□ The management of the company’s pipeline assembly site in
Scotland including finalisation of the leases with the landowners,
negotiations with the planning authority and preparation of baseline
environmental studies.
Some particular activities and projects undertaken included:
□ The supervision on behalf of the client of the installation of two
pipelines to an offshore terminal in the Dominican Republic. Both
of these lines were installed by the off-bottom towing technique.
Profiles 559
BRUCE STOWELL
SENIOR ENGINEER
Eur Ing BEng(Hons) NDip CEng
MIMechE MIGEM
JONATHAN FRANKLIN
Training courses
Jonathan is currently developing a number of new courses for deepwater flowlines and
risers.
568 Overview of pipeline engineering
PIPELINE ENGINEER
Phd
Training courses
Nick is currently writing material for a number of new courses for deepwater flowlines
and risers.
PAUL JOB
PIPELINE ENGINEER
MEng CEng MIMechE
FEED studies
Paul has been involved in a number of FEED studies, which included the steady-state
modelling of multiphase pipelines using Pipesim, and finite element analysis for upheaval
buckling and overtrawling of pipelines.
Finite Element Analysis
Paul has worked on a number of FEA jobs since joining Jee, using both ABAQUS and
ANSYS. These include analyses as follows:
■ Riser analysis - investigating operational and earthquake loads of the risers
supported inside a concrete gravity base structure, to be used on the Sakhalin
project. This included a two-week placement based at Aker Kvaerner’s offices in
Oslo, Norway.
■ Parametric flexible pipeline analysis, to determine the effect of trenching on the
interaction of trawl gear in the North Sea.
■ Analysis of pipe pull, installing a pipeline in a pre-dredged trench using the
bottom-tow method
■ Parametric upheaval analysis on a flexible pipeline, to determine an installation
methodology to ensure the pipeline does not upheave during hydrotest or
operation.
■ Analysis of a hot-tap tie-in to a spoolpiece, to determine the stresses during
operation and the allowable hydrotest pressure
■ Analysis to prove a fabricated wye piece fit-for-purpose
■ Parametric thermal analysis of an insulated flexible pipeline
Other analysis software
Paul has recently been involved in a number of stability analyses using the PRCI/AGA
pipeline stability software package, including both flexible and rigid pipelines. He has
also completed verification analyses using the marine dynamics program Orcaflex for
static and dynamic analysis of flexible pipeline and cable systems in an offshore / marine
environment, and also the computational fluid dynamics package CFX.
Pipeline training courses
Paul has been presenting training courses since September 2003, both in-company and
to the public, including Subsea pipeline design, Offshore pipeline construction and
Subsea pipeline installation calculations (3 days). These courses have been in various
locations around Europe and USA.
Paul wrote a one-day overview course on umbilical design, installation and operation
towards the end of 2004. Since then he has co-presented the in-house course to Saipem,
and it has now been added to the regular courses offered by Jee.
Clamp Connector Tool Design
Paul has worked on this project for the last three years, developing a tool to install
mechanical connectors on subsea pipelines using an ROV. This has included developing
the design from concept to a detailed design with fabrication drawings. The tool has
now been fabricated and is awaiting final testing.
QA System
Paul has upgraded Jee’s Quality Assurance System, to ensure it is in compliance with the
requirements of ISO 9001:2000.
DAVID APPLEFORD
GRADUATE ENGINEER
MEng (Hons) AMIMechE
He has also attended an LRQA Internal QMS Auditor Course and is involved in
performing internal audits for Jee limited. He was also involved with developing the
new Jee Limited website www.jee.co.uk.
Engineering Studies
David has undertaken a series of fishing interaction studies for clients. These have
involved:
■ Scale model testing of subsea protective structures
■ Investigating ways to improve fishermen’s awareness of subsea obstacles and the
consequences of their interaction
■ Gathering fishing data from a number of sources across Europe, Africa and the
Middle East
■ Calculating fishing gear pullover loads, impact energies and dent assessment
■ FEA of pipeline pullover response and trawl door hooking
During his time at Jee Limited, David has also worked on the development of a
Microsoft Excel and Visual Basic spreadsheet to analyse deepwater pipe-lay capabilities
of pipelay vessels and has also been involved in writing various MathCAD calculation
sheets.
Pipeline stability
David has been involved in a number of stability analyses using the PRCI/AGA stability
software package, including both flexible and rigid pipelines. In addition he has done
calculations on vortex-induced-vibrations and has performed a study on the
effectiveness of self-burial-spoilers in the Southern North Sea.
Training courses
Since joining Jee Limited David has attended the following pipeline engineering training
courses:
He has also been trained in using the finite element analysis package ABAQUS and in
using the marine dynamics program Orcaflex for static and dynamic analysis of flexible
pipeline and cable systems in an offshore / marine environment.
Recently David was involved in writing a half-day training course on the use of BP’s
pipeline related Engineering Technical Practices.
GRAHAM WILSON
GRADUATE ENGINEER
MEng AMIMechE
Fishing interaction
■ Graham has undertaken a series of fishing interaction studies for clients, which
have involved:
■ Gathering fishing data from a number of sources across Europe, Africa and the
Middle East
■ The calculation of fishing gear pullover loads, impact energies and dent
assessment
■ FEA of pipeline pullover response and trawl door hooking
He has also been involved in a number of scale model flume tank trials, assessing the
overtrawlability of a range of subsea protection structures.
Training courses
Since joining Jee Limited, Graham has attended the following Jee pipeline engineering
training courses:
■ Overview of Pipeline Engineering
■ Offshore Pipeline Construction
■ Subsea Pipeline Design
■ Installation Calculations
■ Pipeline Operations and Integrity Management
Graham has also been involved in the development of the Subsea Pipeline Design
course exercises. He has also written modules and material for a Technip in-company
course.
Graham has also received training in the use of PRISM integrity management software.
Acronyms &
abbreviations
582 Overview of pipeline engineering
Acronyms & abbreviations 583
+ve positive
-ve negative
°C degree Celsius
°F degree Fahrenheit
30D bend radius of 30 times the pipe diameter
3D three-dimensional
3rd Third
AC Alternating Current
AGA American Gas Association
AGI Above-Ground Installation
Al Aluminium
ALARP As Low As Reasonably Possible
ALS Accidental Limit State
ANSI American National Standards Institute
API American Petroleum Institute
approx. approximate
ASB Above SeaBed
ASD Allowable Stress Design
ASME American Society of Mechanical Engineers
AUV Autonomous Underwater Vehicle
AVTUR Aviation Turbine (fuel)
Bar g Bar gauge (1 bar = 100 kN/m²)
BAT Best Available Technology
bbl US oil barrel (1 bbl = 0.159 m³)
BHP Brake Horse Power (1 BHP = 745.7 W)
BLEVE Boiling Liquid, Expanding Vapour, Explosion
BMP Best Management Practice
BOP Blow-Out Preventer
BP British Petroleum Ltd
bpd barrels per day
BPEO Best Practical Environmental Option
BS British Standard
C2H4 Ethene (Ethylene)
C2H6 Ethane
C3H6 Propene (Propylene)
C3H8 Propane
C4H10 Butane or Isobutane
C5H12 Pentane or Isopentane
C6H5CH3 Toluene
C6H6 Benzene
C6H14 n-Hexane
C10H8 Napthalene
CA Corrosion Allowance
CALM Catenary Anchor Leg Mooring
CAPS Cranfield Automated Pipe-welding System
CBM Conventional Buoy Mooring
CDT Controlled Depth Tow
CDTM Controlled Depth Tow Method
CDUs Crude oil Distillation Units
CFD Computational Fluid Dynamics
CH4 Methane
CHP Combined Heating and Power
584 Overview of pipeline engineering
The following companies have kindly provided images, videos or help with this course.
Their help is gratefully acknowledged.
BRITISH GAS
(Walney Channel crossing Case Study)
See Transco
R J BROWN
See Technip-Coflexip
Acknowledgements and references 593
CORROSION CONTROL
PRODUCTS COMPANY
See CCP
594 Overview of pipeline engineering
MORGRIP PETROBRAS
(Underwater connector) Maracal Adhemar de Queiroz
See Hydratight Sweeney EDISE
Avenida Republica do Chile 65
NKT FLEXIBLES I/S Centro
(Flexible subsea pipelines) Rio de Janeiro RJ
Priorparken 510 Brasil
DK-2605 Broendby Tel: +55 (21) 2534 4477
Denmark Fax: +55 (21) 2534 2288
Tel: +45 43 48 30 00 www.petrobras.com.br
Fax: +45 43 48 30 10
E-mail: nkt.flexibles@nkt.dk PII PIPELINE SOLUTIONS
www.nktflexibles.com Atley Way
North Nelson Industrial Estate
NORFRA A/S Cramlington
(Dunkirk landfall) Northumberland NE23 1WW
Strandveien 106 Tel: +44 191 247 3486
N-9292 Tromsø Fax: +44 191 247 3419
Norway www.piigroup.com
Tel: +47 77 60 24 00
Fax: +47 77 60 24 25 PIPE INDUCTION HEAT LTD
E-mail: postmaster@norfra.no (PIH)
www.norfra.no See CRC-Evans
Acknowledgements and references 599
Additional Help
Additional help was provided by individuals:
Cyril Bishop
(Pipe freezing and hot tapping)
Herman Duff
(Malaysian pipeline)
Mike Mosedale
(Cartoonist)
Frank Gibbons
(Marsh and wetlands)
References
“Corrosion Costs and Preventive Strategies in the United States”, G.H. Koch, M.P.H.
Brongers, N.G. Thompson, Y.P. Virmani, and J.H. Payer, Study by CC Technologies,
Report FHWA-RD-01-156, September 2001.
Web Sites
The following web contact addresses may also be of use:
API
American Petroleum Institute
www.api.org
ASME
American Society of Mechanical Engineers
www.amse.org
ANSI
American National Standards Institute
www.ansi.org
BS
British Standards Institute
www.bsi-global.com
DTI
Department of Trade and Industry
www.dti.gov.uk
DNV
Det Norske Veritas
www.dnv.com
604 Overview of pipeline engineering
GIS RESOURCE
University of Edinburgh
(Geographic Information System)
www.geo.ed.ac.uk/home/giswww.html
HSE
UK Health and Safety Executive
(Offshore Safety Reports and
Contact Research Reports)
www.hse.gov.uk
WORKSAFE VICTORIA
Australian State of Victoria
Health and Safety Accident Prevention Arm
(Good international contacts worldwide)
www.workcover.vic.gov.au
IP
Institute of Petroleum
www.petroleum.co.uk
ISO
International Organisation for Standardization
www.iso.org
OS
Ordnance Survey (of Great Britain)
www.ordsvy.gov.uk