Bellary Nala Irrigation Project: Sl. No. Description Unit Quantity Rate Amount BOQ Canal 10-17 KM
Bellary Nala Irrigation Project: Sl. No. Description Unit Quantity Rate Amount BOQ Canal 10-17 KM
3 Cum
(SR Item No.3.5, page 54-55 of WRD, for 2016-17)
10-11 Km 8425.00 177.68 1496954.00
11-12 Km 11937.00 177.68 2120966.16
12-13 Km 6702.00 177.68 1190811.36
13-14 Km 8754.00 177.68 1555410.72
14-15 Km 11963.00 177.68 2125585.84
15-16 Km 5940.00 177.68 1055419.20
16-17 Km 17866.00 177.68 3174430.88
Providing impervious hearting embankment with selected soil
from Approved borrow areas in layers of 250 to 300 mm
before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out,
transporting, spreading in layer of specified thickness,
breaking clods, sectioning, watering, compacting each layer to
density control of not less than 95 percent or as stipulated by
power roller etc., complete including De-watering & Desilting,
with all lead and lift and as directed by the Engineer - in -
Charge of the work.
4 cum
(SR Item No.3.7, page 55 of WRD, for 2016-17)
10-11 Km 24.00 355.03 8520.74
12-13 Km 1.00 355.03 355.03
13-14 Km 5.00 355.03 1775.16
14-15 Km 31.00 355.03 11005.96
15-16 Km 3073.00 355.03 1091010.39
6 Cum
(SR Item No.3.12, page 56-57 of WRD, for 2016-17)
10-11 Km 2308.00 168.64 389221.12
11-12 Km 2370.00 168.64 399676.80
12-13 Km 2350.00 168.64 396304.00
13-14 Km 2360.00 168.64 397990.40
14-15 Km 2392.00 168.64 403386.88
15-16 Km 5215.00 168.64 879457.60
16-17 Km 2370.00 168.64 399676.80
8 cum
(SR Item No.3.32.1.a, page 61 of WRD, for 2016-17)
10-11 Km 406.51 7336.03 2982168.08
11-12 Km 406.51 7323.55 2977094.45
12-13 Km 406.51 7321.44 2976239.35
13-14 Km 406.51 7319.34 2975384.26
14-15 Km 406.51 7317.23 2974529.16
15-16 Km 437.07 7315.13 3197224.48
Providing and laying insitu vibrated M-15 (Cement content:
270 kg/cum with use of super plasticiser, 28 days cube
compressive strength not less than 15 N/sqmm) grade cement
concrete using 20 mm downsize approved, clean, hard,
graded coarse aggregates for bed lining of canal including
cost of all materials, machinery, labour, formwork including
supports, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with all lead
and lift and as directed by the Engineer - in - Charge of the
work.
9 cum
(SR Item No.3.34, page 61 of WRD, for 2016-17)
10-11 Km 200.65 6260.67 1256202.71
11-12 Km 200.65 6248.19 1253698.41
12-13 Km 200.65 6246.08 1253276.34
13-14 Km 200.65 6243.98 1252854.27
14-15 Km 200.65 6241.87 1252432.20
15-16 Km 187.37 6239.77 1169145.97
Providing, fabricating and placing in position reinforcement
steel bars for RCC works including cleaning, straightening,
cutting, bending, hooking,lapping, welding wherever required,
tying with 1.25 mm dia soft annealed steel wire including cost
of all materials, machinery, labour etc., complete with all lead
and lift and as directed by the Engineer - in - Charge of the
work.
10 Kg
(SR Item No.6, page 84 of WRD, for 2011-12)
10-11 Km 439.00 53.29 23395.99
12-13 Km 124.00 53.30 6609.19
13-14 Km 124.00 53.31 6609.94
14-15 Km 297.00 53.31 15833.68
15-16 Km 1506.00 53.32 80297.10
Providing and fixing 20 mm thick 100 mm depth tarfelt
expansion joint filler board for cement concrete lining of canal
including cost of all materials, labour etc., complete with all
lead and lift and as directed by the Engineer - in - Charge of
the work.
11 Rmt
(SR Item No.49, page 70 of WRD, for 2011-12)
10-11 Km 354.00 94.64 33502.56
11-12 Km 354.00 94.64 33502.56
12-13 Km 354.00 94.64 33502.56
13-14 Km 354.00 94.64 33502.56
14-15 Km 354.00 94.64 33502.56
15-16 Km 372.20 94.64 35225.01
Providing and fixing one line dressed 650 x 150 x 100 mm
thick IRC standard hectometre stone in cement concrete M-
10 grade with 40 mm downsize aggregates including
excavating pit of size 500 x 450 x 400 mm embedding the
stone by 300 mm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed
surfaces and lettering as directed, cost of all materials, labour,
finishing, curing etc., complete with all lead and lift and as
directed by the Engineer - in - Charge of the work.
12 Nos
(SR Item No.4.56, page 92 of WRD, for 2016-17)
10-11 Km 9.00 1134.78 10213.01
11-12 Km 9.00 1133.50 10201.51
12-13 Km 9.00 1133.22 10199.01
13-14 Km 9.00 1132.95 10196.51
14-15 Km 9.00 1132.67 10194.01
15-16 Km 9.00 1132.39 10191.51
14 Nos
(SR Item No.8.12, page 153 of WRD, for2016-17)
10-11 Km 103.00 155.41 16007.69
11-12 Km 103.00 155.41 16007.69
12-13 Km 103.00 155.71 16038.54
13-14 Km 103.00 156.01 16069.39
14-15 Km 103.00 156.31 16100.24
15-16 Km 103.00 156.61 16131.09
Providing and fixing one line dressed 1110 x 350 x 250 mm
thick IRC standard kilometre stone in cement concrete M-10
grade with 40 mm downsize aggregates including excavating
pit of size 750 x 450 x 400 mm and embedding the stone by
300 mm in concrete,providing 2 coats synthetic enamel paint
of approved quality and colour to exposed surfaces and
lettering as directed etc., cost of all materials, labour, finishing,
curing etc., complete with all lead and lift and as directed by
the Engineer - in - Charge of the work.
15 Nos
(SR Item No.4.55, page 92 of WRD, for2016-17)
10-11 Km 1.00 1678.85 1678.85
11-12 Km 1.00 1677.57 1677.57
12-13 Km 1.00 1678.19 1678.19
13-14 Km 1.00 1678.81 1678.81
14-15 Km 1.00 1679.43 1679.43
15-16 Km 1.00 1680.05 1680.05
Total 48412661.57
Say 48412660/-