Problem of The Week: Do Your Best!
Problem of The Week: Do Your Best!
Problem of The Week: Do Your Best!
The Project Triangle In the project triangle, also called the iron triangle (Barnes 1969), there
are three key constraints (triple constraint):
In the project triangle, also called the iron triangle, there are three key constraints
(triple constraint):
Scenario # 1:
Impact of changes:
Building a wall:
Bricklayer Labor injured after two days’ work due to accidently dropped from Height of 10-
feet.
Question: What will be the options available for Project Manager in order to Execute the task
within Scope, Time, Cost, and Quality? Please elaborate in the form of Iron triangle in case of
options available with Project Manager? (Marks-2.5)
Scenario # 2:
Impact of changes:
Building a wall:
Scope: 2m (h) by 5m (l)
Question: What will be Impact on Cost and Scope? Draw an Iron Triangle to Show all
Constraints (Marks-2.5)
Scenario # 3:
Impact of changes:
13 Crashes
426 Fatalities
Question: Why? Please Explain with Reason in terms of Project Management Constraints.
Which Constraint impacted much more than others? (Marks-2.5)
Final Answer Box: Put your final answer here. Describe or explain it in one complete
sentence. (Do not just write a number.)
Scenario # 1
In scenario 1 we have 2 options. Either project manager can wait for the
recovery of the labor as we have no time restriction. In this case PM would be compromising
on Time. Or PM can hire another resource for this purpose as it is not considered good to stop
a running project. So, in this case Pm would be compromising on cost.
Cost
Cost
Cost
Time Scope
Scenario # 3
De Havilland's Comet is pioneer in jet industry. They were investing a lot in this
field in the very initial stages. Their research and development cost were in billions so there
was no compromise on the Cost constraint. It was a dilemma they overlook some Quality
Assurance protocols. They don’t go for proper prototyping and not followed Six Sigma
techniques. They also skipped some testing protocols which resulted into 13 crashes and 426
fatalities.
So, De Havilland’s Comet compromised on quality rather than cost or time.
Cost
Time Quality