Professional Documents
Culture Documents
Report Geo
Report Geo
UET, Lahore.
The Geotechnical Investigation Report prepared for the design of foundation for the subject
building. The report includes information about sub-soil stratigraphy, in laboratory determination
of soil characteristics and foundation design recommendations.
We hope that the investigation results presented in this report will provide all the necessary
information for the design of foundation of the building.
2016-Civ-01
2016-Civ-04
2016-Civ-07
2016-Civ-10
2016-Civ-16
2016-Civ-53
INTRODUCTION:
1.1-General:
The building will be a multi storey frame (beam-column) structure .The total covered area
of site is 18,473 ft2, 7159 ft2 being for each floor.The construction site is extension of Administration
Block near Gate No.2 UET Lahore. This report deals with the geotechnical investigations conducted
on the proposed site.
CONTRACTOR:PROCESS DYNAMICS
DESIGNER: NEW VISION ENGINEERING CONSULTANTS
CLIENT:UNIVERSITY OF ENGINEERING AND TECHNOLOGY,LAHORE
START DATE:13-AUGUST-2018
DURATION OF COMPLETION:8 MONTHS
ESTIMATED COST:Rs. 56.717 M
All the group members,Dr. Hassan Mujtaba(Director Geotechnical Laboratory),Mr. M
Sadiq(Supervisor Geotechnical Laboratory),Mr. Shoaib (Lecturer Assistant Geotechnical
Laboratory),Mr. M. Ansar and Mr. M Imran(Laboratory Assistant,Geotechnical Laboratory) were
engaged by Engineer Ehtesham Mehmood to carry out geotechnical investigation of the proposed
site.
The geotechnical investigation was conducted through three(3) boreholes down to 35 feet
depth below existing NSL.The field work on the site was performed on 8 th-January,2018.
Termite Proofing:
The purpose of anti-termite treatment is to provide
the building with a chemical barrier against the sub-
terrain termites. Termite proof spray of 1:40 (1 liter
anti-termite chemical and 40. liters of water) is used
all over the Engineers Fill and Compacted Earth.
COMPACTION:
Soil compaction is the process in which a stress applied to
a soil causes densification as air is displaced from the pores
between the soil grains. Earth was compacted using
smooth wheeled rollers.The relative compaction of
the soil was achieved up to 95%.
Engineering Fill:
As referred by the Geotechnical investigation
report, soil has less bearing capacity to withstand
load of structure, Engineers Fill is provided in 2
layers which are compacted from 15in to 1ft. It
consists of 50% sand and 50% coarse aggregate.
Layers are compacted by water as the water
percolates through the fill it settles down up to 3in.
These two layers raise the level of excavation and
they will avoid the differential settlement of
foundation. The layers are compacted and 95%
relative density is achieved. (ASTM-1557).
Lean Concrete:
A 6in thick layer of P.C.C (1:4:8) is placed over Engineers Fill to provide to a horizontal surface for
foundation. Concrete is batched by volume and mixed by mixer.
LAYOUT OF COLUMNS:
Red lines are marked over dried P.C.C layer for the layout of
columns.
STEEL FIXING:
Grade 60 ribbed Steel bars are
used for reinforcement of Raft
foundation. #6 steel is used in
bottom #5 is used at top and for
columns.
CURING
The curing was done for 7 days. In one part curing was done and in
other part simultaneously the steel fixing was being done.
CASTING OF COLUMNS
A concrete mix of 1:1.5:3 was used for casting of columns up to plinth level. #5 steel is used in
columns.
BACKFILLING:
The back filling behind the foundation will increase the bearing capacity. It can be used in tasks such
as protecting foundations, landscaping, or filling in voids that would weaken underground
structures. In order to provide the foundation more support, Backfilling is done using Ravi sand.
CASTING OF PLINTH BEAMS:
As the structure is Frame-Structure, Beams are provided at plinth level with a concrete mix of 1:2:4
and reinforcement of #5 bar. While #3 bar is used in rings.
MATERIAL STORAGE:
Following materials were used in extension of
administration block:
Lawrencepur Sand
Pioneer Cement
Grade 40 and grade 60 steel bars
Ravi Sand
TESTING OF SOIL SAMPLE:
We carried out following tests for determination of characteristics of soil that we obtained from the
site:
Can No
90 56 82
Weight Of Container + Wet Soil (gm):
W2 46 42.02 40.97
Weight Of Container + Dry Soil (gm):
W3 43.48 40.15 39.04
2.SPECIFIC GRAVITY
TEST NO. 1 2 3
VOLUME OF FLASK 50 50 50
TEMPRATURE 22 21 22
PLASTIC
LQUID LIMIT LIMIT
Can No 65 41 91 27
PI=LL-PL=6.8
FLOW CURVE
35
30
MOISTURE CONTENT (%)
25
25, 21.5
20
15
10
5
10 15 20 25 30 35 40 45
Log N (NO. OF BLOWS)
RESULTS
LIQUID LIMIT (LL) = 21.5 PLASTIC LIMIT=14.7 PLASTICITY INDEX (PI)=6.8
FLOW INDEX (IF) = 42 TOUGHNESS INDEX (TI) = 0.16 LIQUIDITY INDEX (Li) = -0.98 (semi-solid)
4.sieve analysis Date: November 27, 2018
Table 4: Table for the observations and calculations of Sieve Analysis of soil
As percentage of sand passing Seive#200 is more than 12%, we need to perform Hydrometer Test
5.HYDROMETER TEST
Hydrometer no: 152 H Gs of solids=2.7 Correction Factor for Unit Weight of solids= α=1
Dispersing Agent: Sodium Oxalate Amount: 5gm Wt. of soil. Ws. =50gm Ct=0.40
%age finer
Temp (˚C)
D(mm)
L (cm)
L/t
R
K
1 22 45 39.4 78.8 46 8.8 8.8 0.0131 0.03886 58.61538
GRADATION CURVE
100
90
80
70
PERCENTAGE FINER (%)
60
50
40
30
20
10
0
10 1 0.1 0.01 0.001
PARTICLE SIZE (mm)
RESULTS
Percentage of gravels = 4.5 %
COMMENTS
For well graded sand, 1≤Cc ≤3 and Cu≥6. If soil fails any one or both of these criteria it is considered to be poorly
graded.
Blows per layer = 25 No. of layers = 3 Weight of hammer = 2.5 Kg/5 lb. Height of drop=1ft
Weight of mold = 2.529 Kg = 2529g Diameter (d) = 4 inch/10.16 cm Height (h) = 4.5inch/11.43 cm
γw = 9.8 kN/m3
S = 100%
Gs = 2.7
11.4821324 20.42973462
18.75802998 17.46335118
Table 5. Table for zero air void line
Date: November 29, 2018
COMPACTION CURVE
23
22
DRY DENSITY OF SOIL (kN/m3 )
21
20
O.M.C
19
18
17
0 2 4 6 8 10 12 14 16 18 20
MOISTURE CONTENT (%)
Fig 2. Graph for determination of maximum dry density and Optimum Moisture Content of soil
RESULTS
Diameter = d = 1.5 in
Area = Ao = πd2/4 = 1.77 in2
Height = Lo = 3.2 in
Volume=V= Ao(Lo) = 5.65 in3
Weight of Soil Sample=W= 188.11 gm
Least Count of DDG = L.C = 0.005 in
Proving Ring Constant = P.R.C = 0.82 lb./in
Deformat Load Dial Horizont Unit Area Corrected Total Stress Remarks
ion Dial Gauge al Strain Correctio Area Load on
Gauge Reading Displace n Factor Sample
Reading ment
∆L/L = ε 1-ε A = A o/1-ε σ= F/A
∆L=DDG F=LDGxP
x (L.C of RC
DDG)
12
10
STRESS (kPa)
0
0 0.05 0.1 0.15 0.2 0.25
STRAIN (%)
Figure 3
16
MOHR'S CIRCLE
14
12
SHEAR STRESS τ (kPa)
10
8
C=6.85 kPa
2
q u=13.76 kPa
0
0 2 4 6 8 10 12 14 16
NORMAL STRESS σ (kPa)
Figure 4
8. Direct Shear Test Date: November 30, 2018
Size of Shear Box = 6cm x 6cm x 2cm Area of Shear Box = A= 36 cm2/0.0036m2
Dry Density of Specimen = γd = 1.59 g/cm3 PRC (Proving Ring Constant) = 0.82 lb./div
Least Count of DDR = L.C. = 0.01mm/0.00001m Weight of Hanger = 8lb 15 oz / 8.94 lb.
Normal Load For Specimen No.2 = N = 20 lb.+ 8.94 lb. = 28.94 lb./128.72 N
30
τMAX=28.3 kPa
25
SHEAR STRESS (kPa)
20 τMAX=21.3 kPa
15 τMAX=16.24 kPa
10
0
0 0.0005 0.001 0.0015 0.002 0.0025
STRAIN ΔH (% )
Figure 5
29
27 28.3
25
Max. Shear Stress (kPa)
23 21.3
y = 0.4719x + 4.5434
21
19
17
16.24
15
13
0 10 20 30 40 50 60
Normal Stress (kPa)
Figure 6
Date: November 30, 2018
Horizontal Shear
Horizontal D/R
Corrected Area
Displacement
Specimen No.
Shear Stress
Horizontal
Remarks
Force
1 2 3 4 5 6 8 9 10
Col. 8/Col. 5
Col.6*P.R.C
ΔH= Col. 3
A'=A-bΔH
*L.C
kPa
RESULT
Shear Strength parameters of given soil sample are as follows