Productivit
Productivit
Productivit
Multifactor productivity:
Labor-Machine productivity: Productivity= output/input
720/(4*8)+2=720/32+2=21.17 square yards of carpeting/hour
5. Multifactor productivity
Labor-material=7040*1.1/ 1000+520= 7744/1520=5.09 units /taka input
Labor-overhead=7744/1000+2000=2.58 units /taka input
Material-overhead= 7744/520+2000=3.08 units /taka input
6. Total productivity:
Output/input= 7744/(labor+machine+ overhead)=7744/(1000+520+2000)=2.2 units /taka input