BOBOT FISIK GUDANG PT.

BERKAH PETANI JAYA


Pekerjaan Pembangunan Gudang Konstruksi Baja
Dimensi Gudang : L 15 M x P 22 M = 330 M2
Lokasi : Jl. AJUNG, Jember - Jawa Timur

SAT. HRG-SATUAN JML-HARGA FISIK % FISIK % FISIK % FISIK % FISIK %


NO. URAIAN PEKERJAAN VOLUME
( Rp. ) ( Rp. ) RAB

I. PEKERJAAN SIPIL
a. Pekerjaan Persiapan & Prasarana penunjang
1 Mobilisasi,bouplank, pemb. Bedeng Ls Ls 2.500.000,00 0,55% 0,55% 0,55% 0,55% 0,55%

b. Pekerjaan Galian & urugan


1 Galian tanah pondasi setempat 120 x 120 8,00 ttk 300.000,00 2.400.000,00 0,53% 0,53% 0,53% 0,53% 0,53%
2 Galian tanah pondasi menerus 1 x 1 89,00 m3 50.000,00 4.450.000,00 0,99% 0,99% 0,99% 0,99% 0,99%
3 Urug pasir bawah pondasi 10 cm 8,90 m3 125.000,00 1.112.500,00 0,25% 0,25% 0,25% 0,25% 0,25%
4 Urug pasir bawah lantai gudang 5 cm 16,50 m3 125.000,00 2.062.500,00 0,46% 0,46% 0,46%

c. Pekerjaan Pasangan
1 Pasangan pondasi batu + anstampeng 57,00 m3 350.000,00 19.950.000,00 4,42% 4,42% 4,42% 4,42% 4,42%
2 Pasang dinding bata merah 80,10 m3 550.000,00 44.055.000,00 9,76% 9,76% 9,76% 9,76% 9,76%
3 Plesteran + acian dinding bata merah 1.015,00 m2 35.000,00 35.525.000,00 7,87% 7,87% 7,87%
4 Plesteran cor kolom pedestel 8,00 ttk 350.000,00 2.800.000,00 0,62% 0,62%
5 Benangan dinding, pedestel & sloop 210,00 m1 20.000,00 4.200.000,00 0,93% 0,93%

d. Pekerjaan Cor beton


1 Cor rabat lantai gudang 10 cm ,besi wiremesh M8 single 33,00 m3 1.750.000,00 57.750.000,00 12,80% 12,80%
2 Cor lantai kerja fooplat 1.20 x 1.20 M - tebal 5 cm 0,90 m3 1.250.000,00 1.125.000,00 0,25% 0,25% 0,25% 0,25% 0,25%
3 Cor Foot plat 2,50 m3 3.250.000,00 8.125.000,00 1,80% 1,80% 1,80% 1,80% 1,80%
4 Cor beton kolom pedestal 20/25 2,10 m3 3.250.000,00 6.825.000,00 1,51% 1,51% 1,51% 1,51% 1,51%
5 Cor beton kolom 20/20 0,90 m3 2.750.000,00 2.475.000,00 0,55% 0,55% 0,55% 0,55% 0,55%
6 Cor beton sloof 20/20 3,60 m3 2.750.000,00 9.900.000,00 2,19% 2,19% 2,19% 2,19% 2,19%
7 Cor kolom praktis & ring 15/15 6,50 m3 2.750.000,00 17.875.000,00 3,96% 3,96% 3,96% 3,96% 3,96%
8 Plastik cor 330,00 m2 5.000,00 1.650.000,00 0,37% 0,37%
9 floor hardener lantai gudang 330,00 m2 20.000,00 6.600.000,00 1,46% 1,46%

e. Pekerjaan Finishing
1 Cat laburan dinding ex.kapur+lem 1.015,00 m2 6.000,00 6.090.000,00 1,35% 1,35%

II. PEKERJAAN KONSTRUKSI BAJA & ATAP GALVALUM


1 Rafter kuda-kuda besi WF 150 1.680,00 Kg 17.500,00 29.400.000,00 6,51% 6,51% 6,51% 6,51%
2 Tiang rafter WF 150 672,00 Kg 17.500,00 11.760.000,00 2,61% 2,61% 2,61% 2,61%
3 Clading zincalum 0,30 ,rangka hollow 5x5 dan hollow 4x4 255,00 m2 200.000,00 51.000.000,00 11,30% 11,30% 11,30%
4 Gording besi CNP 125 2.032,50 Kg 17.500,00 35.568.750,00 7,88% 7,88% 7,88% 7,88%
5 Regel besi CNP - tangkup 6,00 set 750.000,00 4.500.000,00 1,00% 1,00% 1,00% 1,00%
6 Besi plat 10mm, 8 mm & 6 mm 420,30 Kg 17.500,00 7.355.250,00 1,63% 1,63% 1,63% 1,63%
7 Ikatan angin & gording besi beton O 12 mm 256,80 Kg 17.500,00 4.494.000,00 1,00% 1,00% 1,00% 1,00%
8 Finishing : zincromate 5.322,60 Kg 1.000,00 5.322.600,00 1,18% 1,18% 1,18% 1,18%
9 Mur baut + angker + jarum keras, dll. 330,00 m2 5.000,00 1.650.000,00 0,37% 0,37% 0,37% 0,37%
10 Penutup atap gudang galvalum 0.30 695,00 m1 45.000,00 31.275.000,00 6,93% 6,93% 6,93%
11 Wuwung galvalum 0.30 21,00 m1 45.000,00 945.000,00 0,21% 0,21% 0,21% 0,21%
12 Flashing Galvalum 0.30 60,00 m1 35.000,00 2.100.000,00 0,47% 0,47% 0,47% 0,47%
13 Drilling screw 5 cm 1.740,00 biji 750,00 1.305.000,00 0,29% 0,29% 0,29% 0,29%
14 Pintu besi sliding uk.450 x 450 = 2 unit 40,50 m2 600.000,00 24.300.000,00 5,38% 5,38%
15 Pintu besi sliding uk.120 x 240 = 1 unit 2,88 m2 600.000,00 1.728.000,00 0,38% 0,38%
16 Pintu besi sliding uk.80 x 80 = 3 unit 1,92 m2 600.000,00 1.152.000,00 0,26% 0,26%

TOTAL 100% 27% 50% 76% 100%


Dibulatkan
TERBILANG : *** Empat Ratus Lima Puluh Satu Juta Tiga Ratus Ribu Rupiah***