XXXX Project Configuration Management Strategy
XXXX Project Configuration Management Strategy
Name
XXXX Project
Document
Name
Configuration Management
Strategy
501447054.docx Page 2 of 14
XXXX Project Configuration Management Strategy
1 Introduction
Tis strategy defines the project’s approach to configuration management and
change control. The Executive owns this strategy.
Identify. As Stage Plans are built, Product Descriptions will be created for
each of the Stage’s products. Each of these products will be registered in
the Product Register and given a unique identifier. The key planned dates
for each product will also be recorded.
All management and specialist products of the project will be recorded in the
Product Register. A description of the Product Register is provided in section Error:
Reference source not found. No team or team member is permitted to work on a
product that is not registered in the Product Register.
The role of the Configuration Librarian in supporting Project Board control of the
project’s products using the Product Register is illustrated in the following diagram.
501447054.docx Page 3 of 14
XXXX Project Configuration Management Strategy
The steps in the above diagram are described in the following table.
1 Project Board Approve the next Stage Plan and the attached Product
Descriptions
6 Team Member(s) Check the quality of the completed product against its
Product Description. The Review Chair is to update the
Quality Log with the results of the quality check.
501447054.docx Page 4 of 14
XXXX Project Configuration Management Strategy
7 Team Member The Review Chair is to check that the Quality Log has
been updated, update the Product Checklist to show that
the product has been completed, then advise the Team
Manager that the product has been completed.
9 Configuration Check the Product Repository, and if OK, update the CIR
Librarian for the completed product(s), then update the Product
Checklist with the actual date of completion.
13 Project Manager Use the Checkpoint Reports (and Product Status Account,
if requested) to compile the Highlight Report
15 Team Manager When all products within the allocated Work Package
have been advised as being completed, check the hand-
over requirements in the WP, and if satisfied, advise the
Project Manager of WP completion.
17 Configuration For the products in the WP, check that the details in the
Librarian Product Checklist and Quality Log are correct. Check the
Product Repository (if in SharePoint) for the correct
versions of all products referenced in the WP.
501447054.docx Page 5 of 14
XXXX Project Configuration Management Strategy
19 Project Manager Create an ‘End Stage Report’ to advise the Project Board
that all products in the Stage have been completed.
Attach the Product Status Account as evidence.
20 Project Board Check that all products have been completed and
returned to Project Board control. Engage Project
Assurance if necessary.
21 Project Board As part of its other Stage boundary activities, the Project
Board will confirm the completion of the current Stage.
This may involve Project Assurance conducting a
Configuration Verification Audit, a physical audit of the
status of products in the Product Repository against the
information held in the Product Register (CIRs, Product
Checklists and Quality Logs).
This project has been allocated a unique identifier in the corporate project register:
PR009. All products created will be allocated a filename commencing with
‘PR009_’.
Each Project level management product will be allocated a filename commencing
with ‘PR009_PR_’.
Each Stage-level management product will be allocated a filename commencing
with ‘PR009_STN_’, where N is the specialist Stage number.
Each Quality product will be allocated a filename commencing with ‘PR009_QL_’.
Each specialist product will be allocated a unique product identifier in the form
SPNN, where NN is the next available specialist product identifier in the Product
Register spreadsheet. Each specialist product will be allocated a filename
commencing with ‘PR009_SPNN_XXXXX_’ where XXXXX is the short title of the
product.
Product versioning will depend on the type of product. Versioning may be in the
form of a version number or a date.
For products where a version number makes sense, such as products released at a
particular time but which may be updated after review before being approved, the
product filename will conclude with ‘_VNN_MM’ where NN is the release number and
MM is the revision number. MM starts at 01 and is increased by one each time the
product is updated and released for internal review. NN starts at 00, moves to 01
for the first external release of the product, and increments by 1 for each
subsequent external release. Each time the release number increments, the
revision number is reset to 00.
For products where a date makes more sense than a version number, such as
products updated and released on a daily or weekly basis, the product filename will
501447054.docx Page 6 of 14
XXXX Project Configuration Management Strategy
conclude with ‘_CCYYMMDD’ being a date of relevance such as the date a status
report was last updated and released.
Examples of valid specialist product filenames using each type of versioning are
PR009_ST5_SP10_InitialRolloutEvaluationReport_V00_01
and
PR009_ST5_SP08_SummaryImplementationActionsMatrix_20081112.
501447054.docx Page 7 of 14
XXXX Project Configuration Management Strategy
The steps in the above diagram are described in the following table.
3 Configuration Log the Change Request in the Change Log and allocate
Librarian it the next available Change Request Number
501447054.docx Page 8 of 14
XXXX Project Configuration Management Strategy
Stakeholders
7 Project Board If the Project Board’s view is that the nature of the
change does not need full Board consideration, it may
appoint a Change Authority to act on its behalf.
8 Change Authority Provide advice and direction to the Project Manager when
finalising the scope of the proposed change
13 Change Authority Review the change and approve, reject or escalate. The
Change Authority will also indicate the priority to be
allocated to this Change Order with respect to other work
of the project teams. On approval, the Change Request
becomes a Change Order.
501447054.docx Page 9 of 14
XXXX Project Configuration Management Strategy
15 Project Manager The Project Manager will advise the originator of the
Change Request of the Board’s decision.
CIRs. This sheet consists of one Configuration Item Record (CIR) for each
product in the Product Hierarchy. As each Stage Plan is approved, a CIR will
be created for each new product. As the Stage progresses, the CIRs will be
updated to reflect the status of each product through its development
lifecycle.
Product Checklist. A template to be populated on a Stage-by-Stage basis as
each Stage Plan is approved. It will contain an entry for each product of the
Stage.
501447054.docx Page 10 of 14
XXXX Project Configuration Management Strategy
LAN. All instances of products where the product is not seen as a key
product of the project will be stored in subdirectories within the project’s
directory.
PVCS. All software components of the Unify product will be stored in PVCS.
HP Quality Centre. All tests cases, test scripts and test summaries will be
stored in HP QC.
LoadRunner. All load test scripts and load test results will be stored in
LoadRunner.
Paper. All paper-based products where it does not make sense to scan and
destroy the original, such as instances of Site Implementation products (one
instance per site).
The Product Repository within SharePoint acts as the repository of all approved
documents of the project. The Project Repository is the project’s primary document
filing system. As a document is approved, a copy will be provided to the
Configuration Librarian who will enter it into the Project Repository. Access to the
Project Repository in SharePoint is restricted. No product in the Project Repository
may be updated; products must be checked out, updated and approved before
being checked back in to the Project Repository as a new version of the product.
The Project Board will determine which of the project’s products should be available
to stakeholders outside the project management team. Read-only copies of these
selected documents will be made available from other areas in SharePoint. As one
of these documents is checked back in SharePoint after being updated, the
Configuration Librarian will ensure that any previous version is withdrawn and the
latest approved version made available in its place. A number of pages will be
made available in SharePoint for this purpose:
A homepage will be created for the project in SharePoint. Project-level
products will be available from this project homepage. Project-level
documents may be entered into SharePoint by the Project Manager or the
Configuration Librarian. The Project Manager will determine who may
access or retrieve project-level documents.
There will be a link from the project homepage to a stage homepage for
each stage. Stage-level products will be available from the relevant stage
homepage. Stage-level documents may be entered into SharePoint by the
501447054.docx Page 11 of 14
XXXX Project Configuration Management Strategy
5 Records
The composition and format of the Issue Register and Configuration Item Records
are defined in the respective Product Descriptions.
6 Reporting
The composition and format of the Issue Report and Product Status Account Report
are defined in the respective Product Descriptions.
7 Timing of Activities
The Project Manager will request a Product Status Account Report at the end of
every stage.
The Project Board will require a configuration audit at the end of the project.
9 Scales
9.1 Priority of Issues
These values are to be used in the Priority field in the Issue Register.
Value Interpretation
501447054.docx Page 12 of 14
XXXX Project Configuration Management Strategy
Value Interpretation
Impact:
Value Interpretation
Low Impact:
Medium Impact:
High Impact: People are being prevented from completing their jobs
A change that will simplify the project?
501447054.docx Page 13 of 14
XXXX Project Configuration Management Strategy
Document History
Document This document is only valid on the day it was printed.
Location
The source of the document will be found in the XXXXX directory.
Revision
History
Version Revision
Number date Summary of Changes
Date of
Name Signature Title Issue Version
01Jul2010 01_00
Date of
Name Title Issue Version
01Jul2010 01_00