Professional Documents
Culture Documents
Ce 431 - Concrete Technology Project: Milwaukee Art Museum
Ce 431 - Concrete Technology Project: Milwaukee Art Museum
Ce 431 - Concrete Technology Project: Milwaukee Art Museum
TECHNOLOGY PROJECT
- D. Sri Ramya
CE02B013
Milwaukee Art Museum (MAM)
• It is located in the downtown of
Milwaukee on the west shore of the
Lake Michigan.
• A $100-million project was taken up
to expand the existing museum from
160,000 sq feet to over 285,000 sq
feet to accommodate more art works.
• The Project Started in 1997
• It was completed in mid 2001
• It is the First Calatrava designed
structure in the US.
• Length: 134.0 m
• Width: 37.0 m
• Roof Height: 11.3 m
• Soleil Mast Height: 44.0 m
• The addition, named as the Quadracci Pavilion is made up of
three major components:
• a central building
• a movable, wing-like sunscreen-the Burke Brise-Soleil-
composed of 72 steel fins and resting atop a vaulted 90 ft.
high glass-enclosed reception hall
• a cable-stayed suspended pedestrian bridge
• Central building (made up of reinforced concrete) consists of
• Parking garage
• Gallery space
• Pavilion (the ring beam)
• South terrace
• Technically, the job was full of high demands with curved
walls, with changing radii as well as different floor heights and
steps in the slabs to be constructed to the highest quality.
• Some jobs are about brute strength, but this job was all in the
delicate nature of the building.
Requisites:
• Aesthetics was the most important point in the building of the structure.
• Because the building was exposed concrete, the fit and the finish were
very important. Success depends almost entirely on the ultra-smooth
finished surface which is not normally expected from concrete.
• Because the parking garage was built below the level of the Lake
Michigan, pumps were required for continuous dewatering to keep the
place dry enough for construction.
• The structure had to be durable and should last long.
Design details of the structure:
Foundation Details:
• The first task in the construction of the foundation was to drive
sheet piles to enclose the project site, because of the proximity
to Lake Michigan.
• The next step was to dewater the site and prepare for the
foundation work.
• The building foundation is of the mat type and it spans from
the foundation walls to a mildly reinforced concrete center
foundation beam. The mat foundation is a 0.6 m thick mildly
reinforced concrete slab spanning approximately 18 m.
• A mud slab was placed right below the mat slab. Between
them was an active-clay-based water proofing membrane to
keep the building water tight. This membrane was also
extended vertically to waterproof the foundation walls.
• On top of the mat slab, gravel was placed which served as
dead load against the buoyancy force, as the base course for
the topping slab and housed the plumbing lines.
Parking Garage:
• The parking garage was below the lake water level.
• The parking garage has a 152 mm thick mildly reinforced
concrete floor slab.
• Most of the garage level elements are mildly reinforced semi arches.
• Post-tensioned reinforcement is introduced in the element to resist the
lateral thrust force produced by the arching action.
• The arches have a hexagonal cross section.
• Above the semi arches is the galleria floor’s 203 mm thick
concrete slab.
Gallery Space:
• The new gallery space is a low-slung mildly reinforced concrete arched
structure.
• The arches are variable-depth hexagons, narrow at the base and deeper near
the crown.
• Few arch segments have a trapezoidal cross section of variable width and
depth.
• All the arches have a pin joint at the bottom to allow small amounts of
shifting which would otherwise lead to cracking.
• Pin joints are just massive steel hinges, each cast into the concrete while it is
formed.
• One half of the pin joint is cast into the base of each arch, with the
corresponding other half cast into the top of the basement wall.
Pavilion (the ring beam):
• Towards the south end of the gallery space is the unique
towering pavilion.
• The pavilion is the support for the frames that in turn
support the movable Burke Brise-Soleil.
• The pavilion also supports the back stay beam and the
cable-stayed east pier for the pedestrian crossing.
• There is an oval shaped
ring beam made of post
tensioned reinforced
concrete, 600 feet in
circumference, cantilevered
90 feet over the lake, resting
on just four support points.
South Terrace:
• The terrace, south of the pavilion is constructed of two
mildly reinforced concrete elements which form a radial
grid.
• One element is a two storey high frame composed of wide
upper and lower beams of variable depth that are
supported by a leaning column and a concrete truss at the
south and east ends, respectively.
• The other element consists of semi arch T-shaped segments
of variable lengths and depths of rectangular cross section.
Concrete Arches
Selection of concrete type:
• Medium Strength High Performance concrete
• Characteristic compressive strength of 50MPa.
(This is a value that I have assumed because the structure does not have to take
any high loads and is a building with just 3 floors of reinforced concrete)