"LS XXIVTH & PART BILL"

Name of Work : Construction of Bridge across Uppanar in Vedaranyam Municipal Area in the Following Location
.(i) Between Manianthievu and (ii) At km 1/2 of Sannathi street (iii) At km 1/6 of Thopputhurai -
A.cattuthurai road (iv) Between Arukkattuthurai and Ayyanar Kovil Vasal at km 2/8 of Arukkattuthurai
road (v) Between Arukkattuthurai and Kollithevu at 3/4 of Aruttuthurai road .

Estimate Amount : 1125.00 Lakhs. CE'S .No: /2010 -11


Name of Contractor : Thiru.R. Devarajan.
C.R AGT.No: /10-11 Date:13.10.2010

Bill Measurement P. Bill Abstract P: 58-87/9550


QUANTITY AMOUNT
upto Since Description of Work Rate Upto Since
Date Last Date Last
1 Providing and driving in position permanent M.S
liner including cost and conveyance to the site and
fabrication charges and tools and plants and
driving M.S 6mm thick liner to be left permenently
with the pile shift as per the requirements and as
per the specification and plcing from the bottom
with all leads and lifts using 6mm M.S sheet etc.,
Complete

163.305 MT 0.000 MT as per Vide Page 30000.00 M2 4899150.00 0.00


2 Providing RCC cast in situ bored piles of 1200mm
diameter M35 grade Design Mix using ISS size
graded HBG metal including cost and conveyance
cost and fabrication of steel including placing of
reinforcement in position, concreting including all
labour charges for driving or boring mobilisation
of pilling equipment and other accessories
required for driving the pile, cost of Bentonite
solution and the temporary liners chiselling and
providing casing for the excavated spoils to a
distance of 200mm including forming of working
platform over the river for accommodating piling
equipments including working platform, cost of
test piles both initial and routine test for vertical
loads and horizontal load forming aapproaches to
the working platform missing concrete filling it in
position, compacting, cutting of pile head to cut off
level for the casting the pile caps, including
diversion of water course in necessary and all
other incidental charges etc., complete as per
standard specifications etc.,

1945.20 0.00 RM as per Vide Page 12100.00 M3 23536920.00 0.00


3 Supply and fabrication of Fe - 415 steel requireid
for all Rcc items of works involved in the schedule
cost of steel at site fabrication labour charges for
cleaning the roads straightening cutting bending
typing grills including overlapping to the required
length whenever necessary and placing the
reinforcement in position as specified in the
drawings including cost of binding wire, provision
of spacer bars cover blocks and all other incidental
charges etc., complete up to 16mm dia

103.164 MT 3.594 S as per Vide Page 50000.00 M3 5158200.00 179700.00


above 16 mm dia
260.399 MT 0.000 MT as per Vide Page 56/9250 50000.00 M3 13019950.00 0.00
C/O 46614220.00 179700.00
// : 2 : //
B/F 46614220.00 179700.00
4 Earth Work excavation in all classes of soils except
hard rock requiring blasting and depositting on
bank with all leads and lifts as per SS 20 B
including cost of all labour, materials, tools,
equipments and all incidental charges and
sheeting, shoring and bracing and their
subsequent removal, removal of all logs, stumps
and other deletrious matter and obstructions,
trimming bottom of excavation back filling,
clearing up the site and disposal of all surplus
materials etc., complete as per standard
specifications for FOUNDATIONS PLE CAPS
UNDER ABUTMENTS

1330.04 M3 0.00 M3 as per Vide Page 13/9545 150.00 M3 199506.00 0.00


5 Vibrated reinforced cement concrete M30 (Design
mix) using graded metal 20mm and below ISS size
graded hard broken granite crushed metal including
cost and conveyance of all materials to site but
including cost and labour charges for formwork and
centering labour charges for laying, compacting,
curing, including all incidental charges etc., complete
for PILE CAPS UNDER ABUTMENTS AND PIERS

1163.52 M3 0.00 M3 as per Vide Page 18/9545 5745.00 M3 6684422.40 0.00


6 Vibrated cement concrete M10 ( Mominal mix 1 :
3:6)using 40mm ISS size hard broken granite
metal including cost and conveyance of all
materials to site cost and labour charges for
formwork centering, labour charges for laying,
compacting curing, all incidental charges etc.,
complete for base course below pile cap under
abutments and piers.

46.09 M3 0.000 M3 as per Vide Page 21/9545 3500.00 M3 161315.00 0.00


7

Earth work excavation in all classes of soils except


hard rock requiring blasting and depositing on
bank with all leads and lifts as per SS20B including
cost of all labour, materials, tools, equipments and
all incidental charges and sheeting, shoring and
bracing and their subsequent removal,removal of
all logs,stumps and other deletrious matter and
obstructions, trimming bottom of excavation back
filling, clearing up the site and disposal of all
surplus materials etc., complete as per standard
specificatin for FOUNDATION of Toe walls of
revetment

118.81 M3 17.05 M3 as per Vide Page 27/9545 110.00 M3 13069.10 1875.50


8

Vibrated cement concrete M15 (Nominal Mix


1:2:4) grade using 40mm ISS HBG metal including
cost and conveyance of allmaterials to site
including form work and centering, labour charges,
transporting and placing in position, compacting,
finishing and curing, working at depths, tools and
plants and incidental charges such as sheeting,
shoring and bracing and their subsequent removal
etc., Complete as kper standard specifications FOR
TOE WALLS OF THE REVETMENTS.

55.623 M3 17.05 M3 as per Vide Page 31/9545 4900.00 M3 272552.70 83545.00


C/O 53945085.20 265120.50
// : 3 : //
B/F 53945085.20 265120.50
9 Vibrated Cement Concrete M20(Nominal Mix
1:1:5:3) using 40mm ISS HBG metal including cost
and conveyance of all materials to site., complying
to the required standard and specifications
including cost of formwork, mixing, laying,
compacting using vibrator including hire and fuel
charges for all toolsand plants engaged in curing
and all other incidental charges such as baling out
water wherever necessary forming baling out
water wherever necessary forming protective
bunds coffer dams etc., complete for ABUTMENTS,
PIERS AND WING WALLS

1297.74 M3 0.00 M3
as per Vide Page 30/9545 4900.00 M3 6358926.00 0.00
10

Providing and fixing 100mm dia PVC SEEPAGE


PIPES of required length for abutment and wing,
retaining wall including costand conveyance of all
materials to worksite, cost and labour for semi-
spherical backfill arrangements with 100mm size
broken granite stones at the periphery and labour
charges for fixing etc., complete to drain the
backfill as per standard specification

44.00 M3 0.00 M3
as per Vide Page 150.00 M3 6600.00 0.00
11

Vibrated reinforced cement concrete design mix


M30 grade using ISS size HBG graded metal
crushed stone including cost and conveyance of all
materials to site but excluding cost and fabrication
of steel but including cost and labour charges for
forwork and centering, labour charges,
compacting, finishing and curing including all
incidental charges etc., complete for BED BLOCK
CUM DIRT WALL OVER ABUTMENTS.

45.231 M3 M3
as per Vide Page 42/9250 6800.00 M3 307570.80 0.00
12
Providing and fixing PVC expansion joints
including cost and conveyance of expansion joints,
shalimar pad an joint sealants and fixing them in
position etc., complete.

10.00 nos 2.00 Nos as per Vide Page 59/9250 3800.00 M3 38000.00 7600.00
13

Vibrated reinforced cement concrete M30 (Design


mix) using crushed ISS, hard broken granite
graded metal 20mm and below including cost and
conveyance of all mateials to site but excluding
cost and fabrication of steel but including cost and
labour charges for forwork and centering labour
charges for laying, compacting curing, including all
incidental charges etc., complete for DECK SLAB
and KERB.

1101.03 M3 114.89 M3 as per Vide Page 60/9250 6100.00 M3 6716283.00 700829.00


14
Providing and fixing Kraft pape for full width of
seating of deck slab including cost and conveyance
to worksite labour fo fixing the same in correct
position and all other incidental charges etc.,
complete.

158.04 M3 0.00 M3 as per Vide Page 58/9250 35.00 M3 5531.40 0.00


C/O 67377996.40 973549.50
// : 4 : //
B/F 67377996.40 973549.50
15 Providing FILTER MEDIA behind abutments and
wings with clean graded material 53mm to
5.60mm 600mm thick and well compacted in
layers with smaller sized towards the soild and
bigger size towards the wall including cost and
conveyance of all materials to site including all
labour charges and all other incidental charges
etc., complete

as per Vide Page 71/9230


158.80 M3 0.00 M3 1250.00 M3 198500.00 0.00
16

GRAVEL FILLING BEHIND THE ABUTMENTS with


clean good gritty gravel including cost and
conveyance to site including labour charges for
filling in layers, watering tamping under optimum
moisture content to get the maximum density all
incidental charges etc., complete.

as per Vide Page 75/9230


645.73 M3 0.00 M3 700.00 M3 452011.00 0.00
17 Vibrated reinforced cement concrete M40
design mix using 20mm ISS HBG metal including
cost and conveyance of all materials to site.,
complying to the required standard and
specifications including labour for formwork,
laying, watering, curing and compacting vibrator
charges and all other incidental charges etc.,
complete for RCC CRASH BARRIERS OVER DECK
SLAB

44.01 M3 14.67 M3
as per Vide Page 86/9230 6200.00 M3 272862.00 90954.00
18 vibrated cement concrete M15 (Nominal mix
1:2:4) using 40mm ISS size hard broken granite
metal including cost and conveyance of all
materials to site, cost and labour charges for
formwork centering, labour charges for laying,
compacting curing, all incidental charges etc
complete for base course below approach slab.

37.40 M3 0.00 M3 as per Vide Page 78/9230 3900.00 M3 145860.00 0.00


19 Providing PVC ducts using 150mm dia (6Kg) PVC
pipes for service utility in the specified RCC
construction as per the instructions of the
departmental officers including cost and
conveyance and all labour charges and other
incidental chaarges etc., complete for poriving
utility service in foothpaths.

591.60 M3 169.20 M3
as per Vide Page 77/9230 300.00 M3 177480.00 50760.00
20 Vibrated reinforced cement concrete M30
(Design mix) using crusher ISS, HBG graded
metal of 20mm and below including cost and
conveyance of all materials to site but
excluding cost and fabrication of steel but
including cost and labour charges for
formwork centering, labour charges for laying
compacting curing, including all incidental
charges etc., complete for APPROACH SLAB.

39.38 M3 0.00 M3 as per Vide Page 81/9230 6000.00 M3 236280.00 0.00


C/O
68860989.40 1115263.50
// : 5 : //

B/F 68860989.40 1115263.50


21 Vibrated cement concrete M30 (Design Mix)
using 25mm, 12mm and 6mm IRC sized hard
granite metal including cost and conveyance of all
materials to site cost of premoulded expansion
joints and fixing the same in position including
cost and labour charges for formwork, labour
charges for laying compacting curing, including all
incidental charges etc., complete for WEARING
COAT 75MM uniform thickness OVER DECK
SLAB AND APPROACH SLAB.

528.00 M3 0.00 M3 as per Vide Page 400.00 M3 211200.00 0.00


22 Vibrated reinforced cement concrete M30
(Design mix) using HBG graded metal of 20mm an
below ISS size including cost and conveyance of all
materials to worksite but excluding cost,
conveyance and fabrication of steel but including
cost and charges for formwork and centering
labour charges for compacting curing, including all
incidental charges etc., complete for HAND RAILS
AND POSTS OVER DECK SLABS

56.40 M3 0.00 M3 as per Vide Page 800.00 M3 45120.00 0.00


23 Vibrated reinforced cement concrete M15
(nominal mix) 1:2:4 using 40mm ISS HBG graded
metal including cost and conveyance of all
materials to site including cement to be procured
and supplied by the contractor at site incluidng
formwork and centering, soft water, labour
charges for mixing, transporting and palcing in
position ;vibrating, compacting, finishing and
curing hire charges for tools and plants including
all other incidental charges etc., complete as per
standard specification for crash barrier type
parapet over Approaches

7.00 M3 M3 as per Vide Page 83/9255 5500.00 M3 38500.00 0.00


24 Excavation including removal and satisfactory
disposal of all materials necessary for the
construction of roadway and side drains in
accordance with the specifications and the lines,
grades and cross sections shown in the drawings
or as indicated by the engineer using carted earth
with in average lead of 1.00 Km for formation of
approach road.

5218.75 M3 3011.88 M3 as per Vide Page 60.00 M3 313125.00 180712.80


97 % compaction
5443.07 M3 1083.07 M3 as per Vide Page 60.00 M3 326584.20 64984.20
100 % compaction
25 Providing laying and compacting well graded
material on prepared sub-grade in accordance
with the requirements of the specifications. The
material shall be laid in one or more layers as sub-
base or lower sub-base and upper sub-base as
necessary according to lines, grades and cross
sections shown in the drawings or as directed by
the Engineer for sand gravel mix

268.64 M3 121.61 M3 as per Vide Page 900.00 M3 241776.00 109449.00


C/O
70037294.60 1470409.50
// : 6 : //

B/F 70037294.60 1470409.50


26 Providing laying water bound macadam
Grading-2 consisting of clean, crushed aggregates
mechanically interlocked by rolling and bonding
together with screening binding material and
finished in accordance with the requirements of
the specifications and thickness as per approved
plans or as directed by the Engineer.

423.90 M3 146.92 M3 as per Vide Page 2000.00 M3 847800.00 293840.00


27 Providing laying water bound macadam
Grading-3 consisting of clean, crushed aggregates
mechanically interlocked by rolling and bonding
together with screening binding material and
finished in accordance with the requirements of
the specifications and thickness as per approved
plans or as directed by the Engineer.

211.98 73.48 as per Vide Page 2100.00 M3 445158.00 154308.00


28 GRAVEL BACKNG TO ROUGH STONE DRY
PACKING 150MM thick for revetment ncluding
cost and conveyance of gravel to worksite and
stacking the same to departmental officers
including labour charges for filling in layers,
tamping working in all heights and all other
incidental charges etc., complete

34.73 M3 34.73 s as per Vide Page 800.00 M3 27784.00 27784.00


29 Manufacturing and fixing cement concrete blocks
of size 250x250x300mm in cement concrete M15
(Nominal mix 1:2:4) using 20mm ISS HBG metal
inclusing cost and conveyance and handling
charges for the same at both ends including all
other labour and incidental charges etc., complete
for revetments - 1 sqm

231.40 M3 231.40 s as per Vide Page 1200.00 M3 277680.00 277680.00


Total Value of work done 71635716.60 2224021.50
Price Escalation for the period from March - 5941256.67
2011 to July 2012.
Add L.s.XXInd & part bill vide page. 75352951.77
Total value of work Done 77576973.27 77576973.27
(OR)
77576973.00
Certified that the measurements were taken by me and recorded in P Dated on:
Check Measurement on: