OI/SI Reference :

Client : BBCI
Title of Project : LINE 5 Silo & Packhouse RC Foundation Additional Works (Road Chipping & Cyclopean Revision)
Location : LINE 5

1. 0 Scope of Work:

I. CIVIL/STRUCTURAL

Road Chipping Works, Prior Foundation Works


1 Purchase of materials and consumables.
2 Preparation of power tools (Jackhammer & Diamond Cutter)
3 Chipping/Demolition Works of Existing Road Network (4,000 psi)
4 Restoration and Rectification Works, on Chipped Road Network
5 Conduct quality inspection

Construction of Revised Cyclopean


1 Purchase of materials and consumables.
2 Preparation of tools and equipment.
3 Cutting and fabrication of B.I Pipe (1 1/2" Diameter), for formworks horizontal support
4 Cutting and fabrication of formworks & wood support
5 Stablishment of Layout/Coordinates Plan
6 Installation of permanent formworks (deadform) w/ strong support, prior sand & stone backfilling works
7 Back filling works (Sand & Stone Only), usage of backhoe equipment
8 Manual arrangement of stones on middle portion, filled with sand on voids.
9 Surface Compaction & Perimeter Trimming of Sand & Stone - 4 Layer/Process
10 Application of 20mil Vapor Barrier ( 0.75meter x 40meter ) Polyethylene Sheet
11 Concrete Pouring of Lean Concrete (100mm thick).
12 Conduct inspection with Client & C.M.
13 Turnover and Acceptance.
14 BBCI to issue and release the Certificate of Completion and acceptance of Works.

II. MECHANICAL

III. ELECTRICAL/INSTRUMENTATION
(N/A)

IV. ARCHITECTURAL
(N/A)

Prepared by: Checked by:

Rene Jay R. Matuloy / Clark Gagui Rommel Tumacder


Site QS / Structural Engineer Civil/Structural In-charge
JAZY Inc. JAZY Inc.

Noted by:

Ron Jayson A. Arciaga


Project Manager
JAZY Inc.

Approved by:
Emmanuel Flores
OIC Plant Director
BBCI
kfilling works
TRUST INTERNATIONAL PAPER CORPORATION
ENGINEERING AND GENERAL SERVICES NOTE:
MECHANICAL SECTION FOR 3 LADDERS AS IDENTIFIED ACTUAL
(SEE ATTACHED PHOTO FYR)
In House Cost Estimate

MWC Reference :
Department : MPPVI
Title of Project : Provision of Ladder (Stairway type) on Dryer section Basement catwalks
Location : PM

1. 0 Scope of Work:

I. MECHANICAL

1. Survey of Area and assesment


2. Pre fabrication of LADDER assembly and supports.
3. Installation of LADDER assembly and supports.
4. Testing and dry run.
5. Housekeeping upon completion of work.
II. CIVIL

III. ELECTRICAL

IV. INSTRUMENTATION

412/02/202010:17:10501618657.xlsx
Engineering section
In House Cost Estimate

2.0 DETAILED MECHANICAL COST ESTIMATE AND MATERIAL TAKE-OFF

Item No. Qty. Units Remarks Item Code Item Description Unit Cost Total Cost
1 10 LHT FOR PURCHASE PLU-PIP-0341 PIPE,CS,1 1/4"BWE x 20',SCH20,ASTM A53, ERW 390.00 3,900.00
2 7 LHT FOR PURCHASE CON-CHA-0051 CHANNEL, C6 X 8.2 #/FT, MS, 20FT 2,600.00 18,200.00
3 13 PCS FOR PURCHASE PLU-ELB-0090 ELBOW, CS, 1 1/4" BWE, 45 DEG, SCH 20, ERW 20.00 260.00
4 7 PCS FOR PURCHASE PLU-ELB-0087 ELBOW, CS, 1 1/4" BWE, 90 DEG, SCH 20, ERW 30.00 210.00
5 1 LOT FOR PURCHASE CONSUMABLES AND PAINT MATLS 5,000.00 5,000.00
10% contingency (actual cost variation) 2,757.00
Total Material Cost 30,327.00

3.0 COST SUMMARY

Item No. Qty. Units Remarks Item Code Item Description Unit Cost Total Cost
I. MECHANICAL

1 supv, 2 welder/helper in Supply of labor,tools,equipment consumables and supervision for the


1 1 lot 1 days
MSERVICE46 9,000.00 9,000.00
fabrication and installation of piping assembly and supports.

II. CIVIL
Supply of labor,tools,equipment consumables and supervision for the
1 lot -
fabrication and installation of piping assembly and supports.
III. ELECTRICAL
Supply of labor,tools,equipment consumables and supervision for the
1 lot -
fabrication and installation of piping assembly and supports.
IV. INSTRUMENTATION
Supply of labor,tools,equipment consumables and supervision for the
1 lot -
fabrication and installation of piping assembly and supports.
Total Porject Cost 39,327.00

4.0 Note
1) Cost Estimate includes the supply of Labor , consumables ,material and supervision.
2) Improvement Projects more than Php 50,000.00 needs an AFE before any project can be implemented
the requesistioner shall provide an AFE if this exceeds the project cost limit.
3) If the Project should be implemented please advice ENGINEERING to provide the approved for construction drawings.
4) 12% VAT is NOT included on material price unless otherwise indicated on the quotation
5.) Prices of the material is based on LS10 last purchased price

For Evaluation of the requesitioner upon notice.

Prepared by: Checked by:

Junior Mechanical Design Engineer Senior Mechanical Design Engineer

Approved by:

Operations Manager