Resources and Material Delay Monitoring Books

Project No :- P18318 Planning Actual


Project :- Reliance rabale Work Start 03 Jun 2019 Work Start 10 Jun 2019
Systems :- PW/WFI/PS Work End 08 Jul 2019 Work End 15 Jul 2019

Available No of days
Sr No Description Required Date Date Delay Reason

1 Consumable material requirement 10 Jun 2019 10 Jun 2019


2 Cutting Machine. 25 Jun 2019 25 Jun 2019
3 Facing Machine. 25 Jun 2019 25 Jun 2019
4 Mechanical team requirement 10 Jun 2019 10 Jun 2019
5 Work order no. for I card 10 Jun 2019 20 days required urgently
6 Aluminum Ladder 10 Jun 2019 10 Jun 2019
7 Aluminum Scaffolding NA NA
8 Fire Blanket 4*4 MTR. 10 Apr 2019 10 Jun 2019
9 Insert Machine 25 Jun 2019 25 Jun 2019
10 Power board along with meter 10 Jun 2019 10 Jun 2019
11 Argon cylinder trolley with chain 10 Jun 2019 10 Jun 2019
12 Argon Cylinder 10 Jun 2019 10 Jun 2019
13 Safety belt double rope. 10 Jun 2019 10 Jun 2019
14 Supporting Material Required in site. 10 Jun 2019 10 Jun 2019
15 Tube and fittings. 10 Jun 2019 10 Jun 2019
16 Tank and Skid required in site. 23 Jun 2019 17 Jun 2019
17 Fire extinguisher 10 Jun 2019 25 Jun 2019 14 days
18 Safety Helmet & Shouse. 10 Jun 2019 10 Jun 2019
19 Tools and M/c ( Contractor) 10 Jun 2019 10 Jun 2019
20 Orbital welder 28 Jun 2019 29 Jun 2019 1 days
21 Boroscopy person . 28 Jun 2019
22 weld joint approval 01 Jun 2019
23 Documets required from PM(if) 10 Jun 2019 10 Jun 2019
24 Clearance from Client 10 Jun 2019 13 Jun 2019 3 days
25 Cut out from Client 24 Jun 2019 27 Jun 2019
26 Fabrication Room electrical supply need from client 10 Jun 2019 14 Jun 2019 4 day
27 Isometric approval from client 11 Jun 2019 14 Jun 2019
28 Interconnection Material 26 Jun 2019
29 Mechanical Team B 24 Jun 2019 28 Jun 2019 4 days
30 Hydro Pump. 12 Jul 2019
31 POU cooler -5 Nos 11 Jun 2019 10 Jun 2019
32 Engraving tool 01 Jul 2019
33 Clearance and cutout Media Area 01 Jul 2019
34 Tank and skid positioning 24 Jun 2019
35

Due to resources work delay:- NA


Due to material work delay : NA
Remarks :-